Apqp
Apqp
Apqp
8/04
Delphi Global Supply Management
Feasibility Considerations
Our product quality planning team has considered the following questions, not intended to be all-inclusive in performing a
feasibility evaluation. The drawings and/or specifications provided have been used as s basis for analyzing the ability to meet
all specified requirements. All "no" answers are supported with attached comments identifying our concerns and/or proposed
changes to enable us to meet the specified requirements.
Yes No Consideration
Conclusion
Not Feasible Design revision required to produce product within the specified requirements.
Sign-Off
Revised:
08/11/04
Delphi Global Supply Management
RFQ/AP Number:
QUALITY ASSURANCE-SUPPLIER
The supplier shall adhere to the Supplier Quality expectations contained in the quality section of the Delphi Global Supply
Management supplier guidelines and any other divisional or program specific requirements referenced in the RFQ.
FEASIBILITY REVIEW
Please complete the attached 'Team Feasibility Commitment' form. Attach the form and any comments you may have regarding
the design of this part/system (e.g. Specs missing or not understood, Design alternatives or assumptions, etc.) If no remarks,
please state so!!
Company: DUNS#
* Part Specific Quality requirements: Engineering or other Delphi Statements of Requirements that may be
included along with the design records in the RFQ package. Also may include unique Delphi or Delphi
Customer specific quality requirements.
Revised:
08/11/04
APQP Open Issues
Supplier/Mfg
Location: Part Number(s):
Supplier Contact: Program(s):
Delphi SQE Contact: Part Name:
2.
3.
4.
5.
Progress Key:
Issue Identified Action Plan Proposed Action Plan Implemented Issue Resolved Revised
8/11/2004
APQP Timing Plan
Supplier Duns: Part Number(s):
Supplier/Mfg Location: (CL) (CL) (CL)
PPAP Date:
Supplier Name
Contacts Name and Title Mailing Address and E-Mail Address Contact Numbers
Sales Contact
Product Engineer
Quality Resident
Program Manager
in Sales Office
Program Manager
in Manufacturing Facility
APQP Contact
Quality Manager
Quality Engineer
PRR Response
Responsibility
Delphi Engineering
Delphi Buyer
Delphi SQE
Revised
08/11/04
A-1 DESIGN FMEA CHECKLIST
Prepared By:
Revised
08/11/04
A-2 DESIGN INFORMATION CHECKLIST
Revision Date:
Pg. 1 of 4
Revised
08/11/04
A-2 DESIGN INFORMATION CHECKLIST - CONTINUED
Revision Date:
Pg. 2 of 4
Revised
08/11/04
A-2 DESIGN INFORMATION CHECKLIST - CONTINUED
Revision Date:
Pg. 3 of 4
Revised
08/11/04
A-2 DESIGN INFORMATION CHECKLIST - CONTINUED
Revision Date:
Pg. 4 of 4
Prepared By:
Revised
08/11/04
A-3 NEW EQUIPMENT, TOOLING, AND TEST EQUIPMENT CHECKLIST
Revision Date:
Pg. 1 of 2
Revised
08/11/04
A-3 NEW EQUIPMENT, TOOLING, AND TEST EQUIPMENT CHECKLIST CONTINUED
Revision Date:
Pg. 2 of 2
Prepared By:
Revised
08/11/04
A-4 PRODUCT/PROCESS QUALITY CHECKLIST
Revision Date:
Pg. 1 of 4
Revised
08/11/04
A-4 PRODUCT/PROCESS QUALITY CHECKLIST CONTINUED
Revision Date:
Pg. 2 of 4
Revised
08/11/04
A-4 PRODUCT/PROCESS QUALITY CHECKLIST CONTINUED
Revision Date:
Pg. 3 of 4
Revised
08/11/04
A-4 PRODUCT/PROCESS QUALITY CHECKLIST CONTINUED
Revision Date:
Pg. 4 of 4
Prepared By:
Revised
08/11/04
A-5 FLOOR PLAN CHECKLIST
Revision Date:
Pg. 1 of 2
Revised
08/11/04
A-5 FLOOR PLAN CHECKLIST - CONTINUED
Revision Date:
Pg. 2 of 2
Prepared By:
Revised
08/11/04
A-6 PROCESS FLOW CHART CHECKLIST
Prepared By:
Revised
08/11/04
A-7 PROCESS FMEA CHECKLIST
Revision Date:
Pg. 1 of 1
Prepared By:
Revised
08/11/04
A-8 CONTROL PLAN CHECKLIST
Revision Date:
Pg. 1 of 1
Prepared By:
Revised
08/11/04
SUPPLIER PROGRAM REVIEW MEETING SUMMARY PAGE
SUPPLIER: LOCATION:
PART NUMBER DESCRIPTION MODEL DELPHI DELPHI START PLATFORM HIGH VOLUME
YEAR START OF OF SCENARIO
PILOT PRODUCTION
1
2
3
4
5
6
PART SUMMARIES:
ADDITIONAL NOTES:
23 08/11/04
Program Review Checklist - Review #1
The purpose of this meeting is to develop a common understanding between our companies concerning the
total requirements of the part/material.
Program Kickoff
1. Does the supplier understand the immediate application and intended end use of the part/material?
Yes No Specify
.
2. Does the supplier have the latest print and specifications? Yes No
Specify plans to obtain: .
Latest Change Number: .
3. Does the supplier have the Quality Expectations, AIAG Manuals, or other Delphi required quality
documentation?
Yes No If no, Explain the Quality Expectations and the Boise Cascade and AIAG
ordering procedures and specify dates to receive:
4. Design
(DR) Was a Design Failure Mode & Effect Analysis (DFMEA) initiated by the design responsible party?
Yes No Supplier not DR (Design Responsible)
If Yes, was Design FMEA Checklist A-1 completed? Yes No
If No, specify plans to complete: .
(DR) Has the DELPHI PDT reviewed the design responsible party's DFMEA?
Yes No Supplier not DR Target date to review:
(DR) Are DFMEA open items addressed on an action plan and communicated to the DELPHI PDT?
Yes No Supplier Not DR Target date to complete:
6. Have appropriate Key Product Characteristics (KPCs), Key Control Characteristics (KCCs), and Critical
Quality Characteristics (CQCs) been identified by Engineering? Yes No
Explain:
.
7.
a. Does the supplier understand Key Product Characteristics (KPCs), Key Control Characteristics
(KCCs), and Critical Quality Characteristics (CQCs) dimensions with respect to DELPHI's mating parts,
function, and manufacturing processes? Yes No
Specify plans to gain understanding:
.
24 08/11/04
Program Kickoff (cont.)
b. Does the supplier understand the critical nature of dimensions that interface with the customer's
application of their mating parts? List any known interfaces with the customer's parts:
c. All customer interface features and/or dimensions must be monitored through the Process
Control Plan and should be reviewed for the application of Error Proofing techniques. Has DELPHI
Engineering reviewed these interface dimensions for the application of KCCs?
Yes No
d. Have the right KCCs and CQCs been identified to control KPCs in order to prevent future
quality problems (PR&R's)? Yes No
b. Explain any quality concerns found during the prototype experience with the part or manufacturing process:
.
Does the supplier understand the prototype requirements per Delphi prototype procedure.
Yes No Specify plans to gain understanding:
.
c. Has a prototype Process Control Plan to control KPCs, KCCs and other features been developed?
Yes No If no, define the critical features and the plan to develop a Prototype
Process Control Plan:
.
25 08/11/04
Program Kickoff (cont.)
9. A tooling build/refurbishment status report and timing chart are required, fax to
on the day(s) of each month at fax number
- - . Person responsible for sending:
.
a. What process does the supplier have to assure that PPAP requirements are met (including timing) and
to track PPAP approval status of their component parts?
b. Does the supplier understand that a tool build should not be halted unless the buyer agrees to do so?
Yes
c. Does the supplier understand that tooling invoices will not be honored until full PPAP approval has
been documented? Yes
Note: Measurement Systems Analysis (i.e., R & R, Isoplot, etc.) studies are required per the PPAP
manual and as explained in the AIAG Measurement Systems Analysis Manual
11. Does the supplier understand their responsibility to control their suppliers (eg; platers, heat treaters,
coaters, etc), including part approval process and quality control? Yes
Explain how this requirement will be met:
.
12.
a. Does the supplier have on-line capability, on-site Internet capability and a valid login identification
to handle the Problem Reporting and Resolution (PR/R) Procedure? Yes No
Note: the supplier is considered "late" if the initial response to a PR/R is received after 24 hours and the
final response is received after 15 days. If No, explain:
.
b. Does the supplier understand schedule non-compliance or over-shipments will result in a PR/R
rejection? Yes
c. Does the supplier understand Delphi's expectation for a thorough and detailed response to all
PR/Rs? Yes No
What problem solving tool does the supplier use to determine root cause? (e.g., 5-phase, 8-D, etc.)
.
13. In line with Delphi's Problem Reporting and Resolution (PR/R) Procedure, all suppliers must provide
material disposition and containment within 24 hours of non-conformance notification.
Does the supplier understand this policy? Yes No Explain:
.
26 08/11/04
Program Kickoff (cont.)
b. What is the planned Tooled Capacity at SOP? . Does it support the high
volume scenario? Yes No If No, specify action plans:
.
2.
3.
27 08/11/04
Program Review Checklist- Review #2
The purpose of this meeting is to develop a common understanding between our companies concerning the
total requirements of the part/material.
2. Is a Value Engineering, Error-Proofing, Design For Manufacturing & Assembly (DFMA), or other
workshops applicable? Yes No
Explain opportunity and possible dates:
.
3. Does the supplier understand the Key Characteristic Designation System including distinction
between Fit & Function and Safety Compliance KPCs?
Yes No Specify plans to gain understanding:
.
4. Has New Equipment, Tooling, and Test Equipment Checklist A-3 been completed?
Yes No Specify plans to review:
.
5. Has a concept pack per the Delphi packaging specification DAS-GSPM been developed?
Yes No If Yes, specify: .
If No, specify plans for completion: .
Is the concept of returnable containers appropriate for this application?
Yes No (M.E.) and
(buyer) will assist the suppliers in defining the program.
Specify any special packaging concepts:
6. DELPHI requires a DAS-GSPM Supplier Packaging Information form to be completed. Record who
will complete the form and the completion date:
. Send to
at .
28 08/11/04
Mid Program Review (cont.)
7. Has the floor plan been completed, considering Floor Plan Checklist A-5?
Yes No Explain: .
9. Written certification of raw materials used is required. Are raw material samples required as part of
the component PPAP submission? Yes No
10. Does the supplier understand that the only authorization for suppliers to implement Delphi engineering
changes (including marked prints) is the applicable design record change notice issued by the appropriate
Delphi Buyer? Yes No
11. No change, of any kind, shall be made in material content, processing methods, testing methods, or
location of manufacture without the prior written approval of Delphi Purchasing. Does the supplier
understand the Delphi Change Request Form and applicable procedure? Yes
12. Delphi Automotive requires the use of accredited laboratories for PPAP submission of data for
specified characteristics.
(A2LA can be contacted for a list of accredited labs at: 301-670-1337; FAX: 301-869-1495.)
13. Delphi Automotive requires 1.67 Ppk minimum (short-term) process capability and 1.33 Cpk
minimum (long-term) process performance on critical characteristics (i.e. CQCs, KPCs and
KCCs. (Refer to the AIAG SPC and PPAP manuals.) All characteristics must conform
100% to specifications for the life of the part/material.
Are there any print, material specifications or Process Control Plan changes needed to meet
these requirements? Yes No Explain:
.
14. Does the supplier understand the progressive nature of the 100% screening requirements of the
Level I and Level II Controlled Shipping procedures? Yes No
Specify plans to gain understanding:
.
29 08/11/04
Mid Program Review (cont.)
2.
3.
30 08/11/04
Program Review Checklist - Review #3
The purpose of this meeting is to develop a common understanding between our companies concerning the
total requirements of the part/material.
PPAP Preparation
1. Does the supplier have the latest print and specifications? Yes No
Specify plans to obtain: .
Latest Change Number: .
3. Does the supplier understand that PPAP approval status is Engineering Change Level specific, cavity
specific, and process specific?
Yes
4. The default level for PPAP submissions is Level 3. The default for Raw Material PPAP submissions
is Level 4. Consult the AIAG PPAP manual for details. Additionally, DELPHI requires a copy of the
Hazardous Material and Restricted and Reportable Chemicals Form with the appropriate pre-approval
signatures to be attached to all PPAP submissions.
5. Does the supplier completely understand the requirements of the PPAP submission, resubmission
procedures in the event submission is not given full approval, and the shipping of PPAP submission
and parts/material? Yes
PPAP shipping location:
.
6. Does the supplier understand that it is their responsibility to resubmit any Interim approved parts prior
to the expiration date (preferably 2 weeks prior to allow our plants time to process)?
Yes No
7. Production Part Approval is always required prior to the first production shipment. Does the supplier
understand the situations where PPAP submissions are required due to future product or process
changes? (See the AIAG Manual)
Yes No
31 08/11/04
PPAP Preparation (cont.)
8.
a. Does the receiving plant need a trial run for approval? Yes No
Specify the program with assignments and dates. Designate persons for follow-up to assure
completion:
.
Due date:
Quantity Needed:
Supplier Promised Delivery Date:
Instructions for trial run delivery:
b. The most common problems with any parts are: 1) missed operations, 2) mixed parts, 3) surface
imperfections, and 4) other visual non-conformances. Explain the procedures the supplier will use to
prevent these potential quality problems:
10. The Hazardous Material and Declaration of Conformance to Delphi A 10949001 Form pre-approval
and submission is required for all parts. (Refer to the "Delphi Substance of Concern and Recycled
Content" procedure #10949001.)
Are any restricted and reportable chemicals present in the part?
Yes No
Document who will complete the form for pre-approval, to whom it is to be sent,
and the due date: .
11. HAZARDOUS MATERIAL - Is a Material Safety Data Sheet required? Examples of materials
requiring MSDS include but are not limited to: oils, lubricants, cleaners, adhesives, aerosol sprays, etc.
Yes No
Does the supplier understand this requirement? Yes No
Document below who will complete the form, to whom it is to be sent, and the due date.
12. Is the Process Flow Diagram acceptable per standard guidelines? Yes No
If Yes, was Process Flow Chart Checklist A-6 completed? Yes If No, specify plans to
revise: .
Approval will be given prior to or in conjunction with Full PPAP Approval.
32 08/11/04
PPAP Preparation (cont.)
14. Are operator training plans and job instructions adequate? Yes No
When will they be available for review?
15. Is the Production Process Control Plan for normal production runs acceptable per standard
guidelines? Yes No
If no, define critical features and level of control required (complete Control Plan Checklist A-8):
.
Approval will be given prior to or in conjunction with Full PPAP Approval.
c. Does the supplier understand the Early Production Containment exit criteria?
Yes No Specify plans to gain understanding:
.
17. Upon successful completion of Early Production Containment, all suppliers are required to
measure their quality performance and work for continuous improvement of all processes and parts.
Does the supplier fully understand the requirements of Continuous Improvement?
Yes No Explain action to comply:
.
18. Under what authority does the supplier need to ship production parts to the DELPHI facility?
Default is PPAP Full Approval .
If not under full PPAP approval, state Interim Level and reasons for Interim.
PPAP Interim Approval , Expiration Date: .
Other , Expiration Date: Specify action plans:
.
19. A "Run At Rate" study will be required to assure all systems are in place and adequate.
(Complete Floor Plan Checklist A-5 prior to run at rate.) Does the supplier understand that they must
be able to run at Tooled Capacity at the time of the Run At Rate? Yes No
33 08/11/04
PPAP Preparation (cont.)
21. Have Run at Rate studies and capacity issues been reviewed with sub-suppliers?
Yes No It is strongly recommended that the supplier review these issues with
their suppliers prior to start of production.
22. Are there tooling, material, equipment, etc., problems that would jeopardize the estimated production
quantities? Yes No Specify: .
2.
3.
34 08/11/04
Program Review Checklist- Review #2 or #3
PC&L Issues
1. a. Does the supplier understand their responsibility to have a delivery system with the capability
and design to be able to provide 100% on-time delivery? Yes No
Specify plans to gain understanding:
.
b. Does the supplier understand their responsibility for all premium transportation costs that are
created by the supplier's inability to deliver? Note: this includes premium transportation costs between the
supplier and the DELPHI plant and between the DELPHI plant and the affected assembly plants,
if necessary. Yes No
Specify plan to gain understanding:
.
Note: All premium transportation shipments must be arranged and approved by the appropriate expeditor
2. Does the supplier understand that DELPHI is not responsible for any materials over and beyond that
covered by our commitment document? Yes No
Specify plan to gain understanding:
.
3. Does the supplier understand that shipments to DELPHI are to be carried by the mode of
transportation and carrier selected by DELPHI? Yes No
Normal mode: Carrier: .
35 08/11/04
SUPPLIER PROGRAM REVIEW MEETING
SUPPLIER: THIS IS THE ELECTRONIC VERSION LOCATION:
PART NUMBER DESCRIPTION MODEL DELPHI DELPHI START PLATFORM HIGH VOLUME
YEAR START OF SCENARIO
OF PILOT PRODUCTION
1
2
3
4
5
6
PART SUMMARIES:
ADDITIONAL NOTES:
36 08/11/04
Program Review Checklist - Review #1
The purpose of this meeting is to develop a common understanding between our companies concerning the total
requirements of the part/material.
Program Kickoff
1. Does the supplier understand the immediate application and intended end use of the part/material?
Yes No Specify
2. Does the supplier have the latest print and specifications? Yes No
Specify plans to obtain: Latest Change Number:
3. Does the supplier have the Quality Expectations, AIAG Manuals, or other Delphi required quality documentation?
Yes No If no, Explain the Quality Expectations and the Boise Cascade and AIAG ordering
procedures and specify dates to receive:
4. Design
(DR) Was a Design Failure Mode & Effect Analysis (DFMEA) initiated by the design responsible party?
Yes No Supplier not DR (Design Responsible)
If Yes, was Design FMEA Checklist A-1 completed? Yes No If No, specify plans to
complete: .
(DR) Has the DELPHI PDT reviewed the design responsible party's DFMEA? Yes No
Supplier not DR Target date to review:
(DR) Are DFMEA open items addressed on an action plan and communicated to the DELPHI PDT?
Yes No Supplier Not DR Target date to complete: Yes No
6. Have appropriate Key Product Characteristics (KPCs), Key Control Characteristics (KCCs), and Critical
Quality Characteristics (CQCs) been identified by Engineering? Yes No
Explain:
7. a. Does the supplier understand Key Product Characteristics (KPCs), Key Control Characteristics
(KCCs), and Critical Quality Characteristics (CQCs) dimensions with respect to DELPHI's mating parts,
function, and manufacturing processes? Yes No Specify plans to gain understanding:
b. Does the supplier understand the critical nature of dimensions that interface with the customer's
application of their mating parts? List any known interfaces with the customer's parts:
c. All customer interface features and/or dimensions must be monitored through the Process
Control Plan and should be reviewed for the application of Error Proofing techniques. Has DELPHI
Engineering reviewed these interface dimensions for the application of KCCs? Yes No
d. Have the right KCCs and CQCs been identified to control KPCs in order to prevent future
quality problems (PR&R's)? Yes No
37 08/11/04
If no, define the critical features and the plan to develop a Prototype Process Control Plan:
38 08/11/04
d. Are there pre-production requirements (other than PPAP Requirements). Yes No
Reason Date Quantity Needed Supplier Promise Date
9. A tooling build/refurbishment status report and timing chart are required, fax to
on the day(s) of each month at fax number
Person responsible for sending:
a. What process does the supplier have to assure that PPAP requirements are met (including timing)
and to track PPAP approval status of their component parts?
b. Does the supplier understand that a tool build should not be halted unless the buyer agrees to do so?
Yes
c. Does the supplier understand that tooling invoices will not be honored until full PPAP approval has
been documented? Yes
11. Does the supplier understand their responsibility to control their suppliers (eg; platers, heat treaters,
coaters, etc), including part approval process and quality control? Yes
Explain how this requirement will be met:
12. a. Does the supplier have on-line capability, on-site Internet capability and a valid login identification
to handle the Problem Reporting and Resolution (PR/R) Procedure? Yes No
Note: the supplier is considered "late" if the initial response to a PR/R is received after 24 hours and
the final response is received after 15 days. If No, explain:
b. Does the supplier understand schedule non-compliance or over-shipments will result in a PR/R
rejection? Yes
c. Does the supplier understand Delphi's expectation for a thorough and detailed response to all
PR/Rs? Yes No
What problem solving tool does the supplier use to determine root cause? (e.g., 5-phase, 8-D, etc.)
13. In line with Delphi's Problem Reporting and Resolution (PR/R) Procedure, all suppliers must provide
material disposition and containment within 24 hours of non-conformance notification. Does the supplier
understand this policy? Yes No Explain:
b. What is the planned Tooled Capacity at SOP? Does it support the high volume
scenario? Yes No If No, specify action plans:
39 08/11/04
2.
3.
40 08/11/04
Program Review Checklist- Review #2
The purpose of this meeting is to develop a common understanding between our companies concerning the total
requirements of the part/material.
1. Does the supplier have the latest print and specifications? Yes No Specify plans to obtain:
Latest Change Number:
2. Is a Value Engineering, Error-Proofing, Design For Manufacturing & Assembly (DFMA), or other
workshops applicable? Yes No Explain opportunity and possible dates:
3. Does the supplier understand the Key Characteristic Designation System including distinction between
Fit & Function and Safety Compliance KPCs? Yes No Specify plans to gain understanding:
4. Has New Equipment, Tooling, and Test Equipment Checklist A-3 been completed?
Yes No Specify plans to review:
5. Has a concept pack per the Delphi packaging specification DAS-GSPM been developed?
Yes No If Yes, specify:
If No, specify plans for completion:
Is the concept of returnable containers appropriate for this application? Yes No
(M.E.) and (buyer) will assist the suppliers in defining the
program. Specify any special packaging concepts:
6. DELPHI requires a DAS-GSPM Supplier Packaging Information form to be completed. Record who
will complete the form and the completion date:
Send to at
7. Has the floor plan been completed, considering Floor Plan Checklist A-5? Yes No
Explain:
8. Has the supplier completed Product/Process Quality Checklist A-4? Yes No Specify plans
to review:
9. Written certification of raw materials used is required. Are raw material samples required as part of
the component PPAP submission? Yes No
10. Does the supplier understand that the only authorization for suppliers to implement Delphi engineering
changes (including marked prints) is the applicable design record change notice issued by the appropriate
Delphi Buy Yes No
11. No change, of any kind, shall be made in material content, processing methods, testing methods, or
location of manufacture without the prior written approval of Delphi Purchasing. Does the supplier
understand the Delphi Change Request Form and applicable procedure? Yes
12. Delphi Automotive requires the use of accredited laboratories for PPAP submission of data for specified
characteristics. (A2LA can be contacted for a list of accredited labs at: 301-670-1337; FAX: 301-869-1495.)
Which characteristics will require accredited laboratory documentation? Specify:
*Note: Third party registration to QS-9000 or ISO Guideline 025 is acceptable in lieu of GP-10 or
A2LA accreditation.
41 08/11/04
Does the supplier understand that the Laboratory's "Scope of Accreditation" must be included with the
PPAP submission? Yes
42 08/11/04
13. Delphi Automotive requires 1.67 Ppk minimum (short-term) process capability and 1.33 Cpk minimum
(long-term) process performance on critical characteristics (i.e. CQCs, KPCs and KCCs. (Refer
to the AIAG SPC and PPAP manuals.) All characteristics must conform 100% to specifications
for the life of the part/material.
Are there any print, material specifications or Process Control Plan changes needed to meet
these requirements? Yes No Explain:
14. Does the supplier understand the progressive nature of the 100% screening requirements of the
Level I and Level II Controlled Shipping procedures? Yes No
Specify plans to gain understanding:
.
43 08/11/04
Program Review Checklist - Review #3
The purpose of this meeting is to develop a common understanding between our companies concerning the total
requirements of the part/material.
PPAP Preparation
1. Does the supplier have the latest print and specifications? Yes No Specify plans to
obtain: Latest Change Number:
3. Does the supplier understand that PPAP approval status is Engineering Change Level specific, cavity
specific, and process specific? Yes
4. The default level for PPAP submissions is Level 3. The default for Raw Material PPAP submissions
is Level 4. Consult the AIAG PPAP manual for details. Additionally, DELPHI requires a copy of the
Hazardous Material and Restricted and Reportable Chemicals Form with the appropriate pre-approval
signatures to be attached to all PPAP submissions.
PPAP Submission Level (if other than default):
5. Does the supplier completely understand the requirements of the PPAP submission, resubmission
procedures in the event submission is not given full approval, and the shipping of PPAP submission
and parts/material? Yes PPAP shipping location:
6. Does the supplier understand that it is their responsibility to resubmit any Interim approved parts prior
to the expiration date (preferably 2 weeks prior to allow our plants time to process)?
Yes No
7. Production Part Approval is always required prior to the first production shipment. Does the supplier
understand the situations where PPAP submissions are required due to future product or process
changes? (See the AIAG Manual) Yes No
8. a. Does the receiving plant need a trial run for approval? Yes No Specify the program
with assignments and dates. Designate persons for follow-up to assure completion:
Due date:
Quantity Needed:
Supplier Promised Delivery Date:
Instructions for trial run delivery:
b. The most common problems with any parts are: 1) missed operations, 2) mixed parts, 3) surface
imperfections, and 4) other visual non-conformances. Explain the procedures the supplier will use to
prevent these potential quality problems:
9. (DR)* Has the supplier completed Design Information Checklist A-2? Yes No N/A
Specify plans to complete:
* DR stands for "Design Responsible". This question applies to a Design Responsible supplier only.
10. The Hazardous Material and Declaration of Conformance to Delphi A 10949001 Form pre-approval and
submission is required for all parts. (Refer to the "Delphi Substance of Concern and Recycled Content"
procedure #10949001.) Are any restricted and reportable chemicals present in the part?
Yes No Document who will complete the form for pre-approval, to whom it is to be sent,
44 08/11/04
and the due date:
45 08/11/04
11. HAZARDOUS MATERIAL - Is a Material Safety Data Sheet required? Examples of materials requiring
MSDS include but are not limited to: oils, lubricants, cleaners, adhesives, aerosol sprays, etc.
Yes No Does the supplier understand this requirement? Yes No
Document below who will complete the form, to whom it is to be sent, and the due date.
12. Is the Process Flow Diagram acceptable per standard guidelines? Yes No If Yes, was
Process Flow Chart Checklist A-6 completed? Yes If No, specify plans to revise:
13. a. Is the PFMEA acceptable per standard guidelines? Yes No If Yes, has Process FMEA
Checklist A-7 been completed? Yes If No, specify plans to revise:
b. Has label error-proofing been considered during PFMEA creation? Yes No If no,
specify plans to complete:
14. Are operator training plans and job instructions adequate? Yes No
When will they be available for review?
15. Is the Production Process Control Plan for normal production runs acceptable per standard guidelines?
Yes No If no, define critical features and level of control required (complete Control Plan
Checklist A-8):
Approval will be given prior to or in conjunction with Full PPAP Approval.
c. Does the supplier understand the Early Production Containment exit criteria?
Yes No Specify plans to gain understanding:
17. Upon successful completion of Early Production Containment, all suppliers are required to measure their
quality performance and work for continuous improvement of all processes and parts. Does the supplier
fully understand the requirements of Continuous Improvement? Yes No Explain action to
comply:
18. Under what authority does the supplier need to ship production parts to the DELPHI facility? Default is
PPAP Full Approval
If not under full PPAP approval, state Interim Level and reasons for Interim.
PPAP Interim Approval Expiration Date:
Other Expiration Date: Specify action plans:
19. A "Run At Rate" study will be required to assure all systems are in place and adequate. (Complete
Floor Plan Checklist A-5 prior to run at rate.) Does the supplier understand that they must be able to run
at Tooled Capacity at the time of the Run At Rate? Yes No
20. Will the Run At Rate study be a customer monitored R @ R? Yes No If Yes, specify date
the supplier can accommodate such study: If No, specify date the supplier will fax the
Self-Monitored Run at Rate study form:
46 08/11/04
21. Have Run at Rate studies and capacity issues been reviewed with sub-suppliers? Yes No
It is strongly recommended that the supplier review these issues with their suppliers prior to start of production.
47 08/11/04
22. Are there tooling, material, equipment, etc., problems that would jeopardize the estimated production
quantities? Yes No Specify:
48 08/11/04
Program Review Checklist- Review #2 or #3
PC&L Issues
1. a. Does the supplier understand their responsibility to have a delivery system with the capability and
design to be able to provide 100% on-time delivery? Yes No Specify plans to gain
understanding:
b. Does the supplier understand their responsibility for all premium transportation costs that are
created by the supplier's inability to deliver? Note: this includes premium transportation costs
between the supplier and the DELPHI plant and between the DELPHI plant and the affected assembly
plants, if necessary. Yes No Specify plan to gain understanding:
Note: All premium transportation shipments must be arranged and approved by the appropriate
expeditor
2. Does the supplier understand that DELPHI is not responsible for any materials over and beyond that
covered by our commitment document? Yes No Specify plan to gain understanding:
3. Does the supplier understand that shipments to DELPHI are to be carried by the mode of transportation
and carrier selected by DELPHI? Yes No Normal mode:
Carrier:
49 08/11/04
Run at Rate Plan
Supplier/Mfg Location: Supplier Run @ Rate Contact: Supplier R @ R Contact Phone #:
Customer or Supplier Monitored: PPAP Promise Date: Run @ Rate Promise Date:
8. Production Control/Logistics
Readiness
Progress Key:
No plan identified Open issues with plan Plan on schedule Plan Complete
Progress
Revised
Aug-04
Run @ Rate Summary Sheet
Delphi Monitored
Type of Run @ Rate:
Delphi Part Number:
Supplier Monitored
Date of Run@Rate:
G. Duration of Run@Rate [hrs]:
H. Downtime during Run@Rate period minutes hours minutes hours
1. breaks 0.00 0.00
2. lunch 0.00 0.00
The data calculated in these fields
3. maintenance 0.00 0.00 are not used in the Actual TC
tabulations but are very important
4. changeover / setup time 0.00 0.00 for process improvement and
corrective action activities. The
5. unplanned 0.00 0.00 downtime is already comprehended
in the Part Quantities produced (J)
6. Total [1 through 5] 0 0.00 0 0.00 results.
2. Rejected [# of ]
Supplier Representative
Delphi SQE
Delphi Buyer
Run at Rate Summary Worksheet Definitions
1. Green Cells These cells contain formulas used to calculate the user input cells. They
are not for user input.
2. White These cells are intended for user input as the respective column and
row heading indicates.
Supplier Duns Code Record the DUNS code of the manufacturing location responsible for the
parts.
Supplier Contact Name The name of the lead supplier representative who will serve as the
communication contact for the representative Engineer.
Manufacturing Address Address of the manufacturing location responsible for the parts.
Delphi Part Number Customer part number. Engineering released part number for which the Part
Certification is being submitted.
Rev. Level The revision level (or engineering change level) of the design record (or print
drawing) that is used during the R@R study. This should also be the same rev
level that is documented on the warrant from the PPAP package.
Delphi Part Name Use the finished part name (e.g. Resistor Array Module) appearing on the
product drawing typically found in the title block.
Delphi Program The program that the specific part number is being used for (e.g.. GMT-360,
Saturn LS).
Max Schedule Volume (MSV) Maximum scheduled volume based on PC & L’s or other functional area’s
documented customer requirements. This quantity should be the yearly
amount.
Work days of Delphi plant (s) The number of planned work days for the year of the Delphi user location(s).
Daily volume [quantity / day] The daily volume calculated from the Delphi MSV/ workdays.
A. Quoted Tool Capacity This should be net good parts, factoring in all downtime, scrap, & planned
machine loading. The capacity quoted on the contract.
B. Production Days The actual number of days per year that production is scheduled to run.
Revised
08/11/04
Run at Rate Summary Worksheet Definitions
D. Gross Hours/Day (total shift The total shift time in hours per day planned for production.
time)
E. Planned Machine Loading The planned run schedules identifying Delphi's availability on the machine or
tool. Cell is formatted in %. Enter actual value. (e.g. 100 for 100%)
F. Gross Hours/Day Allocated to Hours allocated for this part. Calculated Gross hrs/day * Planned Machine
the Part Loading.
Supplier Tooling Information Supplier tooling information such as quantity of tools, tooling description, and
other. Not used in calculations.
G. Duration of Run@Rate The actual number of hours the Run@Rate was conducted.
Comments This text box is available for the individual completing the Summary Sheet to
provide information pertinent to the Run @ Rate that does not have its own
cell in the Summary Sheet.
H. Downtime during Run@Rate This section represents the actual downtime minutes observed during the
period Run@Rate. Enter the downtime in minutes in the five categories and the
related time in hours for each category is automatically calculated. The
downtime should be based on the total shifts included in the duration of the
Run@Rate.
Total [1 through 5] The total amount of downtime in hours observed during the Run@Rate.
Calculated from the sum of the downtime categories in hours.
I. Net Productive Time Net Productive Time= Gross hours/day allocated * Uptime. Uptime = 1-%
downtime. This is a calculated field. This calculation is used for information
and continuous improvement. It is not used in the final results calculation.
Rejected Total # rejected during the Run@Rate. Rejects include both scrapped and
reworked parts.
Net Good Total # produced - total # rejected during the Run @ Rate. Calculated field.
Net Parts / Hr {=J3 / G} Net good parts / Duration of the Run@Rate (# / hour). Calculated field.
K. Net Daily Capacity {F*J4} Planning: This number relates to the Supplier's planned production during
preliminary R@Rs. Should normally meet or exceed QTC rate. Allows the
supplier to perform preliminary studies prior to the actual Run@Rate.
Actual TC: TC from the actual Run@Rate. Data that will be used to
determine the Run @ Rate status.
QTC: Capacity quoted by supplier as per a documented contract. Carry-over
from the QTC cell above.
Revised
08/11/04
Run at Rate Summary Worksheet Definitions
MSV: The Maximum Scheduled Volume required by Delphi. Carry-over from
the MSV cell above.
L. Net Yearly Capacity The Planning Net Daily Capacity value multiplied by the supplier's yearly
production days.
The Actual TC Net Daily Capacity value multiplied by the supplier's yearly
production days.
QTC: Capacity quoted by supplier as per a documented contract. Carry-over
from the QTC cell above.
MSV: The Maximum Scheduled Volume required by Delphi. Carry-over from
the MSV cell above.
Run @ Rate Summary The Run @ Rate status shall be based on both the Capacity and Quality
results. The status of the Run@Rate for capacity is based on the Actual TC
results in comparison with the QTC & MSV. The Actual TC must meet both the
daily and yearly requirements. The status of the Run@Rate for quality is
based on the results of the attached quality review worksheet. The
appropriate improvement plans are required for all open issues or
nonconformities. The Final Status will be derived from the Capacity and
Quality Results. The Final Status shall be the lower of the Capacity and
Quality statuses. (If either Capacity or Quality = Fail, Final = Fail. If Capacity
or Quality = Open, Final = Open. If no Fail or Open exists, the Final Status =
Pass) The Open/Fail MSV category exists for situations where the supplier
meets QTC requirements but does not meet MSV. In case of the Open/Fail
MSV result, the SQE should consult with the buyer to develop appropriate
action plans.
Rerun Date The date agreed upon by Delphi and the supplier if a rerun is required.
Responsibility This section authenticates the Run @ Rate Summary Sheet as an officially
documented summary of the Run @ Rate. The section should include the
Name, Signature, Mailing Address, and Contact Number of the Supplier Run
@ Rate Coordinator and Delphi SQE. The Delphi Buyer name, address, and
number should be documented.
R@R C1- Supplementary Form A form that can be used for documenting steps in an assembly process with
multiple operations within the production process.
Revised
08/11/04
DELPHI SYSTEMS
Run @ Rate C1 - Supplementary Form
CAPACITY PIECES PER HOUR UPTIME FTQ Gross DAILY CAPACITY CALCULATIONS Observation
Hours Planned Planned Actual Worst Excess Period
QTC MSV Mach. Cycle / Hr. Pieces # Total Hrs. Machine Capacity1 Equivalent2 Case or Net Good
Operation (per day) (per day) Planned Actual / Cycle Planned Actual Planned Actual Sh Day Useage (EGHJMN) (FGIKMN) Equivalent3 Shortage4 Time Pieces
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
A B C D E F G H5 I5 J5 K5 L M N5 O P Q R S T
5.) Percentages: All percentages (H,I,J,K,N) are input as they should appear (I.e.: 94.7% should be input as 94.7); NOT as a decimal (e.g.: 0.947).
7.1. Documentation
At the time of the Run @ Rate, the following support documentation should be available for
review:
Available YES/NO
7.1.1. Appropriate PPAP package information
7.1.2. Quoted tool capacity and planned machine loading
information
7.1.3. Operator/inspection instructions
7.1.4. Prototype/pilot concerns
7.1.5. Sub-contractor control/capacity planning process
7.1.6. Sub-contractor material schedules and transportation plan
for production
7.1.7. Packaging/labeling plan for production
7.1.8. Acceleration plan
7.2.2. Does the actual process flow agree with the process flow diagram,
as documented in PPAP? (Review the facility plan and layout. Walk
the process with the flow diagram.)
Comments:
Page 57 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
Comments:
Page 58 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
7.2.4. Is all in-process documentation, such as process control charts, in
place at the time of the Run @ Rate? Is the documentation utilized
to drive a defined reaction plan and corrective action process?
Comments:
7.2.6. Are maintenance plans in place? Are repair and maintenance parts
available? Is there planned downtime for preventative
maintenance?
Comments:
Page 59 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
YES/NO
7.3.2. During the Run @ Rate, did the tooling meet the quoted up time
requirements (net vs. gross quoted output)? Make note of any
unexpected downtime and corrective action plans required.
Comments:
7.3.3. Can all line changeovers, if any, be performed within the quoted tool
capacity requirements?
Comments:
7.3.4. Does the net throughput of good pieces (scrap taken out, any
allowable rework) meet daily quoted tool capacity?
Comments:
Comments:
7.4.2. Are all in process gaging and controls complete, functional and in
place?
Comments:
7.4.3. Do the process control plans (production and pre-launch) agree with
the actual process? Do production part checks and statistical
monitoring take place as outlined on the process control plan?
Comments:
Page 60 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
7.4.4. Are potential failure modes, as identified in the PFMEA, addressed
through error proofing or the control plan?
Page 61 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
Comments:
7.4.5. Do the process control plan's reaction plan and the supplier's
process for containment and corrective action ensure effective
containment and correction?
Comments:
Comments:
7.6.2. Are controls in place to isolate incoming material until it has been
approved?
Comments:
Page 62 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
7.7.2. Does the supplier's method for in process and final shipping
packaging and handling effectively eliminate the potential for
process errors or mixed stock?
Comments:
Comments:
Page 63 08/11/04
Supplier Performance Development Process
Delphi Global Supply Management
Run @ Rate Review Worksheet
Supplier Name: Part Number(s):
Additional COMMENTS:
Completed
By: Phone: Date:
Pass
- The manufacturing process agrees with the manufacturing & quality plan as
documented in PPAP.
- The quality system was documented and practiced.
- An effective & documented FTQ plan is in place.
- No open issues.
Open
- Minor nonconformity(s) exist but will not likely result in the shipment of nonconforming
material.
- One or more 'No' answers in the Review Worksheet.
- FTQ plan not documented.
- Open issues exist.
Fail
- Major nonconformities exist that may result in the shipment of nonconforming products.
- The manufacturing process does not agree with the manufacturing & quality plan as
documented in PPAP.
- The absence or total breakdown of a quality system.
Page 64 08/11/04
Page 65 08/11/04
SUPPLIER MONITORED - RUN @ RATE FOLLOW-UP FORM
To: Fax:
Attention: Phone:
Part Number:
I have reviewed the Run @ Rate data provided and determined the result as checked below:
PASS: Based on your documentation, you have met all applicable requirements of Run at Rate for
this part and have documented an ability to produce quality parts at an acceptable rate.
OPEN: I have identified some minor non-conformances to the Run @ Rate requirements in your
documentation as follows:
Please submit an action plan within the next 2 business days documenting your corrective action
plans to resolve these non-conformances.
FAIL: I have identified serious deficiencies in the documentation you provided for the Run @ Rate
results as follows:
As described in the Delphi Run @ Rate procedure, you are required to develop a written corrective
action plan to resolve these non-conformances. Please submit within the next few business days
your plan to resolve these non-conformances. The Run @ Rate study will need to be repeated when
corrective actions have been implemented.
Note: Keep a complete copy of this Run @ Rate on file for future reference.
Sincerely,
08/11/04
DELPHI Supplier Quality FMEA SEVERITY RANKINGS
Note #1: Any Failure Mode affecting the Vehicle Assembly Plant MUST be ranked an “8” or higher.
Note #2: Any Failure Mode affecting a Delphi Plant MUST be ranked “5” or higher.
Rev. Date: 5/02
Select from the categories below, using the highest applicable ranking.
Ranking Effect End Customer Vehicle Assembly Plant Delphi Plant Supplier Plant
10 Hazardous- Potential failure mode affects Potential failure mode may Potential failure mode may Potential failure mode may
without warning safe vehicle operation and/or cause unsafe condition for cause unsafe condition for cause unsafe condition for
involves noncompliance with plant personnel without plant personnel without plant personnel without
government regulation without warning. warning. warning.
warning.
9 Hazardous-with Potential failure mode affects Potential failure mode may Potential failure mode may Potential failure mode may
warning safe vehicle operation and/or cause unsafe condition for cause unsafe condition for cause unsafe condition for
involves noncompliance with plant personnel with warning. plant personnel with warning. plant personnel with warning.
government regulation with
warning.
8 Very High Vehicle/item inoperable (loss Potential failure mode may Potential failure mode may
of primary function); failure cause a spill/major disruption, cause a spill/major disruption
mode may cause customer repair, assembly difficulty, at a Delphi Plant.
walk home, field return, or rework, or sorting at the
durability issue. Vehicle Assembly Plant
7 High Vehicle/item operable but at a Potential failure mode may
reduced level of performance. cause repair, assembly
Customer very dissatisfied. difficulty, rework, sorting at a
Failure mode may cause See Note #1 Delphi plant.
vehicle repairs at Dealer.
Includes Noise issues
(squeak/rattle).
6 Moderate Vehicle/item operable but Potential failure mode may
comfort/convenience item(s)) cause special handling of
inoperable/not performing to See Note #1 components at Delphi-S.
customer expectation (e.g..
Noise)
5 Low Vehicle/item operable but Potential failure mode may
comfort/convenience item(s) See Note #1 cause inconvenience to Delphi
operable at a reduced level of prior to assembly.
performance.
4 Very Low Fit and finish item does not See Note #2
conform. Defect noticed by See Note #1
most customers.
3 Minor Fit and finish item does not See Note #2
conform. Defect noticed by See Note #1
average customers.
2 Very Minor Fit and finish item does not See Note #2
conform. Defect noticed by See Note #1
discriminating customers.
1 None No effect. See Note #1 See Note #2
: 5/02
ode may
ndition for
thout
ode may
ndition for
th warning.
DELPHI Supplier Quality FMEA OCCURRENCE EVALUATION RANKINGS
Sample calculation to determine Ppk value from a likely failure rate of 5 per thousand pieces (see FMEA third Appendix I).
Note: Identical to Manual except for Ranking of 1. Manual allows for .01 per thousand (10 PPM) Rev. Date:
08/11/04
DELPHI Supplier Quality FMEA Detection Rankings
Ranking Effect PFMEA
1 Almost Certain Discrepant parts cannot be made because item has been
error-proofed by process/product design.
* Note: Identical to Manual except for Rankings of 6 and 4. Words “OR gauging performed on setup and first piece check”
moved from a detection of 4 to a detection of 6 08/11/04
check”