Hindalco
Hindalco
Hindalco
HYDERABAD REV.NO : 00
HYDERABAD REV.NO : 00
CONTENTS
1.0 INTRODUCTION
2.0 PHILOSOPHY
REFERENCE P&IDs.
TO
INSTRUMENT AIR SCHEME DRG.NO. 2-131-00-90329
HYDERABAD REV.NO : 00
1.0 INTRODUCTION:
With the increase in unit capacity associated with increased capital costs and the steep
rise in fuel cost. It is necessary to maintain the availability of thermal power sets at as
various parameters of steam turbine demand quick decisions and numerous operations
from the operating personnel. In order to reduce the arduous task of monitoring
various parameters and effect sequential start up, minimise the possible human errors
and to achieve start up in minimum time in the optimum way Automatic Turbine Runup
System (ATRS) is introduced. The operation of ATRS is from Man Machine Interface
(MMI) of TG DCS. The operation of critical drives is also available from Backup console
2.0 PHILOSOPHY:
2.1 The ATRS is based on functional group philosophy i.e. the main plant is divided into
clearly defined sections called sub group controls SGC such as oil system, condensate
and evacuation, Turbine system. Each SGC is organised and rearranged in sub loop
defined state and contains the start up and shut down programme of the respective
group. S.G.C. issues commands either to control interface level or switches on SLC.
Desired number of criteria act as pre conditions before S.G.C. can take off to execute
its defined programme comprises of steps. For each step there is provision for
HYDERABAD REV.NO : 00
“monitoring time” and “waiting time”. Waiting time implies that the subsequent step
could not be executed unless the specified time elapsed. The time between command
signal and appearance of check back signal is known as monitoring time and when it is
being executed alarm is initiated and the programme will not be proceeding further. In
addition, execution of any step is also permitted only if the conditions specified for that
particular step are completely fulfilled. Bypass conditions are included to enable
switching ON after S.G.C. at any stage after completing certain task manually if so
desired. In addition to normal sequential start up, the following modes are possible.
In this mode data is received from the plant but no commands are issued to the control
Step mode:
This mode enables the programme to be executed one step at a time, even if step
criteria are absent and the automatic mode is malfunctioning. This is useful when
system criteria have been met and cannot be preceded due to transmitter
malfunctioning.
The control interface forms the link between the individual commands and the power
plant. Each remote controlled drive has a control interface. It consists of command
section, monitoring section, power supply and alarm section. The command section
provides the control commands according to the priority and validity and passes
actuation signals to the interposing relays in the switch gear. It monitors status
HYDERABAD REV.NO : 00
discrepancies, running time between command output and check back actuation and
When SLC is switched ON, it actuates the connected mechanical process condition.
through SGC.
Automatic Turbine Run up System consists of three sub group controls viz. Oil
supply system, condensate and evacuation system and turbine system. These
groups in conjunction with electro-hydraulic speed control and turbine stress evaluator
achieves the task of synchronising and block loading of the machine or orderly shut
down as required.
The sub-group control for oil system performs its tasks comprising starting relevant oil
pumps. Ensuring turning of turbine as and when demanded by the process and
4.1.0 OPERATION:
If the operator switches “ON” SGC and presses the manual push button for “operation”,
the programme would proceed to execute various steps, provided the release criterion:
STEP 1 & 2
“SLC Main Oil pumps (MAV21EE001)” and “SLC oil vapour exhaust fans
(MAV82EE001)” are switched “ON”. Within the 10s one of the Main oil pumps
HYDERABAD REV.NO : 00
STEP 3
This is a control step where the generator criterion is checked (if applicable).
STEP 4
SLC emergency oil pump (MAV24EE001) are switched ON and the solenoid valve of
turning gear (MAV51AA012) is switched off. With this measure, the availability of
emergency oil pump is ensured and turning gear is ready to rotate the turbine.
STEP 5
SLC Jacking oil pumps (lifting oil pumps) (MAV31EE001, MAV32EE001) are switched
ON and the turbine begins to rotate driven by hydro motor which is admitted with high
STEP 6
This is a waiting step to check the operation of lifting oil pumps and the minimum
turbine speed.
STEP 7 & 8
As soon as the turbine speed is 9 S-1 (i.e. 540 RPM) the lifting oil pumps
(MAV31AP001, MAV32AP001) are switched OFF and are checked. With this the start
up programme of lube oil system is completed. However in case, the turbine speed is
less than 8.5 S-1 (i.e. 510 RPM), the programme goes back to step 1 for recycling.
The shut down program essentially switches OFF all the equipments in the oil system.
The shut down program would be started if the SGC is ON and operator presses the
button for “shut down”. The release criterion for shut down program is “HP mean shaft
HYDERABAD REV.NO : 00
than 100°C”.
STEP 51
Solenoid valve of turning gear is (MAV51AA501) switched ON. This means turning
device is switched OFF so that turbine can coast down to stand still.
STEP 52 & 53
Step 52 is a waiting step, so that the turbine speed decreases. If the turbine speed is
less than 0.15 S-1 (i.e. 9 RPM) the program goes to step 53 where it waits for 20 min
STEP 54
STEP 55
SLC main oil pump (MAV21EE001), SLC emergency oil pumps (MAV24EE001), SLC
STEP 56
From the SGC steps, the SLC is switched ON or OFF. If SLC-is switched ON,
whenever the oil pump discharge header pressure (MAV21CP001) or lube oil header
pressure (MAV42CP019) falls below the set value, the standby pump is automatically
switched ON.
HYDERABAD REV.NO : 00
If SLC is ON, the emergency oil pump (MAV24AP001) is switched “ON” automatically
whenever lube oil pressure falls below set value. Additionally as a safety measure an
of emergency oil pump (MAV24AP001). This feature has been built to guard against
If SLC is ON, the lifting oil pump-1 (LOP) (MAV32AP001) is switched ON, if speed falls
below 510 RPM and switched OFF if speed raises above 540 RPM automatically.
If SLC is ON, the lifting oil pump-2 (LOP) (MAV31AP001) is switched ON, if speed
remains below 8.5 S-1 (i.e. 510 RPM) for more than 5s and lifting oil pressure
If SLC is ON, the preselected fan would be switched ON automatically and also the
stand by fan would be switched ON automatically if oil vapour exhaust flow is less than
set value.
This accomplishes the task of ensuring one condensate pump in operation, evacuating
the condenser, maintaining the condenser pressure and breaking the vacuum when
required by process.
HYDERABAD REV.NO : 00
If the operator switches ON SGC and press the manual push button for operation of the
program, it would proceed to execute various steps, provided the “Release criteria” as
2. Air isolation valves of both the main ejectors open (MAJ12AA301, MAJ13AA001).
STEP 1:
STEP 2:
In this step program issues command to switch ON ‘SLC drains (MAL00EE001)’. This
SLC is primarily hooked up with the “SGC turbine” program, but “SGC condensate and
evacuation system” also controls the same. Before executing step No. 02 the program
ON.
STEP 3:
3. Gland steam control valve close. Vacuum breaker valve is closed as a first step for
HYDERABAD REV.NO : 00
STEP 4:
In this step the command is issued for opening the steam-isolating valve to “Starting
Ejector-1 (LBG36AA001)”. This step itself gets bypassed if the system is already
KG/CM2(abs). Before execution of this step, the program checks availability of the
following criteria:
minimum value.
STEP 5:
In this step the command is issued for opening the air-isolating valve connected to
starting ejector. This step itself gets bypassed if the absolute pressure in the condenser
is less than 0.26 KG/CM2(abs). Before executing this step the program checks back
the availability of the criterion that the command of Step No. 4 has been executed.
STEP 6:
In this step the command is issued for opening the isolating valves supplying steam to
the main ejectors (LBG37AA301, LBG38AA301). However, before executing the step
the program checks back the commands issued in Step No. 5 are executed. This step
KG/CM2 (abs).
STEP 7:
HYDERABAD REV.NO : 00
No specific command is issued from this step and it acts as an ‘AND’ gate to check
STEP 8:
(MAW20DP001). Before executing the command the program checks that the turbine
is operating on Turning gear i.e. the speed of the turbine is more than 0.25S-1 (i.e. 15
KG/CM2(abs).
STEP 9:
In this step no specific command is issued in this step and acts as a ‘GATE’ to check
back that the command of Step No. 8 has been executed and the pressure of steam in
the gland steam header (MAW20CP001) is between 1.04 and 1.06 KG/CM2. The
monitoring time is blocked as all the ejectors are evacuating in entire system, and
process is in progress.
STEP 10:
In this step the valve in the air extraction line to the staring ejector-1 (MAJ11AA301) is
closed as a prelude to stop the starting ejector since the starting ejector is not effective
for evacuating the system after the condenser pressure (MAG01CP003,004,005) has
fallen below 0.26 KG/CM2 (abs). Before executing the command for Step No. 10, the
STEP 11:
HYDERABAD REV.NO : 00
In this step command is issued to stop the supply of steam to starting ejector-1 by
closing the steam isolation valve (LBG36AA301). This command is initiated after
STEP 12:
No command is issued from this step. The main ejectors continue the task of pulling
below the 0.12 KG/CM2 (ABS) and generator load is more than 5%. Monitoring time is
STEP 13:
In this step command is issued for closing one of the two main ejectors. Only one main
ejector shall be sufficient to maintain the vacuum after the turbine has taken block load.
A manual selection switch has been envisaged through which any of the main ejectors
can be selected. For stopping the ejector the command of Step No. 13 closes the
steam supply to the ejector, which has not been selected. Before issuing the command
of Step No. 13, the program checks back that the absolute pressure in condenser
(MAG01CP003,004,005) is less than the 0.12 KG/CM2 (ABS) and turbine has been
STEP 14:
In this step command is issued for switching ON SLC main steam ejectors
(MAJ20EE001).
STEP 15:
HYDERABAD REV.NO : 00
The shutdown programme can also be initiated by the operator provided the following
(i) The speed of turbine is less than 4S-1(i.e. 240 rpm); and
STEP 51:
In this step command is issued to close the supply of steam to both the ejectors and
STEP 52:
In this step command is issued for opening the vacuum breaking valve (MAG10AA051)
and air isolation valve of starting ejector (MAJ11AA301). Before initiating command
the program shall check back the execution of command of Step No. 51.
STEP 53:
1. Force closing the gland steam pressure control valve without manual intervention;
and
Before executing this step, the programme shall check back the execution of
STEP 54:
In this step commands are issued to switch OFF both the condensate pumps
HYDERABAD REV.NO : 00
Before executing this step the programme checks back the execution of commands of
STEP 55:
No specific command is issued from this step. This programme remains stay-put in
This SLC is switched ON from Step No. 01 and switched OFF from Step No. 54 of
SGC condensate and evacuation system. A manual push button is also provided in the
MMI to – switch ON or OFF this SLC. Selection of service pump shall be manual. The
other pump shall serve as reserve pump. If SLC is ON it shall perform the following
tasks:
service pump.
5.3.4 Switch ON condensate pump-1 (LCB10AP001) after 0 – 100 sec, in case pump-2
value, i.e. in case preselected pump-2 is not able to build up its discharge pressure
5.3.5 Switch ON condensate pump-2 (LCB20AP002) after 0 – 100 sec, in case pump-1
HYDERABAD REV.NO : 00
value, i.e. in case preselected pump-1 is not able to build up its discharge pressure
5.3.6 Switch ON reserve condensate pump if condensate pumps discharge header pressure
5.3.7 Open the discharge valve of both the pumps if pressure in any of the pumps is of more
5.3.8 Switch OFF condensate pump-1 (LCB10AP001) if pump-1 was selected but the pump
is not able to build its discharge pressure after 0 – 100 sec, of switching ON the SLC.
This action and the action mentioned in 5.3.5 shall take place simultaneously.
5.3.9 Switch OFF condensate pump-2 (LCB20AP002) if pump-2 was selected but the pump
is not able to build its discharge pressure after 0 – 100 sec, of switching ON the SLC.
This action and the action mentioned in 5.3.4 shall take place simultaneously.
The sub group control turbine, during start-up executes the tasks, which comprises of
loading. This subgroup also shuts down the turbine, which comprises of unloading,
closure of steam supply to turbine, isolation from grid and bringing the turbine drains to
desired position. The start-up and shut down are accomplished in a number of
6.1.0 OPERATION:
If the operator switches ON SGC and presses manual PB for operation i.e. start-up the
program would proceed to execute the steps in a sequential order after seeking the
STEP 1:
HYDERABAD REV.NO : 00
The SGC EHA oil supply is switched ON and its readiness is checked before
proceeding to step 2.
STEP 2:
Here the operation readiness for bypass operation is checked. Readiness means:
STEP 3:
LP bypass control and automatic set point matching (ASM) are switched ON. This
ensures opening of LP bypass control valves and the spray water injection valve.
STEP 4:
Command is issued for switching ON SLC drains (MAL00EE001); SLC warm-up drains
STEP 5:
Before warming up operation all valves and NRV positions are checked during this
step, it checks for closing of all turbine stop valves and control valves, Closing of CRH
NRV’s, Closing of all Extraction NRV’s. (Which is over ridden if generator load > 10%).
STEP 6:
Essential secondary systems are checked before commencing the warming operation
in this step.
HYDERABAD REV.NO : 00
STEP 7:
SLC warming control is switched OFF and drains before HP control valves are closed.
STEP 8:
In this step it waits for the following parameters to be satisfied before opening the
- All the above conditions are bypassed for cold start i.e. of wall temperature HP
STEP 9:
Emergency stop valves are opened by raising the starting device (Turbine startup and
The TSLLE can be operated from the main control room. The turbine startup and
limiting device (TSLLE) has the following tasks:
a) Holding and triggering of central tripping system.
b) Providing an analogous position value for each control valve for limiting the
valve position.
c) Providing blocking signals for the actuator unit HP/IP control for the opening and
closing of stop-valves.
STEP 10:
HYDERABAD REV.NO : 00
STEP 11:
Gland pressure control on Auto is checked. Also whether one of the oil vapour exhaust
STEP 12:
STEP 13:
SLC warm up control is switched ON. It is essentially a waiting step for suitable
parameters for opening the governing valve to be satisfied. The suitable parameters
are
temperature)
temperature).
HYDERABAD REV.NO : 00
STEP 13:
STEP 14:
STEP 15:
waiting time is 180 sec. It checks for the following conditions to be satisfied.
- X7 criterion satisfied
STEP 16:
Turbine speed set point raised upto 3030 rpm and drains before HP control valves are
closed.
STEP 17:
Actual turbine speed is checked to have reached 2940 rpm. (It can be bypassed if gen.
Brk. is closed)
STEP 18:
STEP 19:
STEP 20:
This is a waiting step for suitable warming of the turbine to take a minimum load. It
- Criterion X 8 checked.
HYDERABAD REV.NO : 00
STEP 21:
STEP 22:
STEP 23:
Power set point is raised and checked for the generator is carrying a load greater than
STEP 24:
6.1.1 SHUTDOWN:
protection.
STEP 51:
STEP 52:
In this step power set point is lowered upto 0% value, so that speed controller takes
STEP 53:
STEP 54:
HYDERABAD REV.NO : 00
Turbine trip channel is actuated, synchronizer is put OFF AVR is put on Auto, drain
STEP 55:
Starting device is lowered upto 0% and SGC control oil supply shutdown is initiated.
STEP 56:
The programme logic ends here and the programme would remain stay put in this step.
SLC drains is switched ON from step No.1 and 51 of SGC turbine (MAA00EC001) and
SLC opens the drain valves after HP control valve 1 and 2. If the following criterion are
satisfied.
a) Differential temperature between HPCV & wet steam is less than 20 deg K and
If the command for opening the drain valves exist and these drain valves do not open,
an alarm signal is generated and also used as SLC drain fault signal. Drain valves
after HP control valve 1 & 2 closed by SLC if the criteria are available.
a) Differential temperature between HPCV and wet steam is greater than 50 deg K
and
HYDERABAD REV.NO : 00
b) Differential temperature of IP stop valves and wet steam is less than 20 deg K.
by 50 deg K.
6.1.4 DRAIN VALVES NRV IN COLD REHEAT LINES LEFT AND RIGHT HAND:
Drain valves are given a command to open by the SLC if any of the NRV is closed or
not fully open. These drain valves are closed by the SLC if both the NRV’s are open.
This drain valve is given a command to open if one of the two-gland steam temperature
Gland steam drain valve is closed by SLC if temperature of gland steam measured by
SLC issues a command to, open this drain valve under the condition that generator
load is less than 2% or respective extraction valve is less than 5% open. For closing
this drain valve SLC checks that both generator load is more than 10% and respective
SLC issues command to open the drain valve under condition that extraction valve A4
is open by less than 5% or differential pressure across extraction valve A4 is less than
HYDERABAD REV.NO : 00
10m bar. As extraction valve A4 is connected to deaerator this criteria will be present
Similarly to close this valve program seeks that extraction valve A4 is more than 15%
open and differential pressure across extraction valve A4 is more than 32m bar.
more than 50 deg K than saturation steam temperature and opens when the
The drain is closed when the casing Top, bottom temperatures are more than 320 deg
C and opened when these temperatures are less than 300 deg C.
It is opened if the difference between temperature ahead of seal steam supply valve
and set point is smaller than a adjustable value. The set point is generated from
maximum value selection of saturated steam temperature and a variable set point
It is closed when the steam temperature ahead of seal steam supply valve is more than
adjustable value above set point and pressure ahead seal steam supply valve exceeds
minimum pressure.
If SLC commands a drain valve to open but actually it does not open within 200
The vacuum breaker valve in the condenser has the task of essentially reducing the
coast down time of turbo generator set in case of turbine trip due to :
HYDERABAD REV.NO : 00
By reducing the coast down time the extent of possible consequential failures can be
kept low in emergency. The ingress of air through the opening the vacuum breaker
valve as well as the steam which is led into the condenser through the LP bypass
In order to protect the end stages of LP turbine the condenser pressure is restricted by
open/ close of the valve as a function of speed. This action takes place automatically.
With vacuum breaker valve open/close as a function of speed the coasting down time
The opening and/or closing of the vacuum breaker takes place with the help of solenoid
manually. The vacuum breaker valve can be manually opened/closed from the control
room. The switch open by hand is stored and released with the enabling signal.
Non-return valves can be controlled by auxiliary means or may swing freely. A solenoid
Solenoid valve open (energize) – means to release the NRV in the direction of opening.
Solenoid valve close (de-energize) – means to apply closing force to the NRV.
The closing action of the NRV is taken for the following criteria:
HYDERABAD REV.NO : 00
controlled by limit signal of position set point of live steam control valve,
control valve.
Opening of NRV can be done manually or automatically when position set point of
IP control valve) is greater than 15% provided the release criteria of corresponding
In case of condensation turbine, the temperature in the exhaust steam nozzle should
Water injection is controlled by means of solenoid valve. The solenoid valve is opened
when
Two NRV’s are provided in the steam pipe between HP-turbine stage and reheater.
The control is executed depending upon the position set point of the live steam control
valve through two solenoid valves arranged in 1 of 2 arrangements. The NRV’s are
HYDERABAD REV.NO : 00
closed when the position set point live steam control valve is < 17% and opened when
the position set point live steam control valve is > 22%.
For verification of operability, a push button “Testing release of CRH NRV” is available
in the control room for each NRV. The actuation of the PB is stored. The release signal
enables ATT to test the CRH NRVs. The ATT signal controls both solenoid valves (1-
of-2) in closing direction. The monitoring of actuation time is activated while the 100%
position, if the NRV does not reach a certain intermediate position in the reset time
In the event of fire, to reduce hazards the Fire protection has to be actuated manually.
This has two channels. Each channel is operated in duplicated command channel as
well as duplicated logic circuits for redundancy. The fire protection is initiated from
On operation of any of the push buttons citied above commands are issued to do the
following:
Main oil pumps, lifting oil pump1, SLC lifting oil pumps, SLC AC EOP.
- DC Emergency oil pump and DC lifting oil pump2 and sol. VIV from
HYDERABAD REV.NO : 00
X – CRITERIA
HYDERABAD REV.NO : 00
RECORDS OF REVISION