Guidelines On Water Proofing
Guidelines On Water Proofing
Guidelines On Water Proofing
Hkkjr ljdkj
MINISTRY OF RAILWAYS
Guidelines
jsy ea=ky;
on
Waterproofing
in
New/Old Construction
Report no. RDSO/WKS/2015/1 Revision -2
October – 2019
Works Directorate
dk;Z funs’kky;
Preface
INDEX
This report covers water proofing methods in new as well as old building constructions,
roads and new construction chemicals. This report supersedes Guidelines on
Waterproofing on New /old construction (Guideline No. RDSO/WKS/2015/1 Rev.1:
January 2019). Repair of damaged structure due to seeping water is a very costly affair.
Hence proper waterproofing of building at construction stage is essential. This report
also covers the system of roof overhangs and extending part of roof as parapet wall.
Besides this modern water proofing methods including the use of nano technology and
construction chemicals has also been incorporated in the report. This guideline aims to
bring together various water proofing practices available in scattered forms in various
text books, handbooks, codes & manuals and Industries for the benefit of field
engineers. It is hoped that engineers in the field will find it a useful source of knowledge
and guidance. If there is any suggestion for improving or if any error/ discrepancy is
noticed in its contents, kindly suggest.
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Basic concept behind various methods used for water proofing, is use of
material such as admixtures, impregnation, film forming membranes,
surfacing, joint seal and grouting.
Page 1 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Sealants : Joints are the necessary important parts of the structures as it acts
as a link between parts of structures as column-beam joint , column-slab joint,
slab-slab joint , beam-beam joint, floor-floor joint etc. all these shall be sealed
with proper sealants.
2.2 It is absolutely essential that roofs are provided with adequate slope to ensure
effective drainage. The slope of roof should be such that the water gets drained
off quickly by achieving adequate velocity under influence of gravity. Even
areas with light rainfall will require adequate slope as continuous light drizzling
without dry spell will induce roof leakage problem badly. For the guidance of
the field Staff, each building plan must also incorporate a roof plan, showing the
position of drainage Pipes and direction and extent of slope on the roof.
Drainage slope should not be flatter than 1 in 80 and should preferably be 1 in
40. There should be no undulations in the roof surface, which may result in
accumulation of rain water. Extra care is necessary for construction of golas,
coping and joints.
Page 2 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
2.5 Any impermeable layer/coating should never be applied on both faces of the
wall as the wall must be allowed to “breathe”. A non-permeable finish or
waterproof finish should not be applied on a wet wall, as it takes a long time to
lose water used during construction.
2.6 Dense and low permeability of concrete also ensures relief-from dampness and
comes by adequate cement content and low water cement ratio in concrete
apart from required level of compaction and adequate curing. Use of Mineral
and chemical admixtures are widely used for specific purpose. These all help
to reduce the water content of the mix and make concrete dense and compact,
crack free and durable. Compatibility of Chemical admixtures with the concrete
mix ingredients, should be checked before going for casting of Slab or any
concreting activity, as RMC plants readily supply concrete mixes. Use of
Integral waterproofing compounds for cement mortar and concrete shall comply
IS 2645-2003.
2.7 Area surrounding plinth of the building should be filled with good earth and
rammed with slope away from the building, preferably with plinth protection
apron.
2.8 Proper drip course should invariably be provided on parapet wall copings, sun-
shades, chajjas etc. Particular care to be taken to seal architectural façade with
Main structure of building so that these joints, which may open during its
designed life, do not become a source of water ingress locations.
2.9 Sunken floors are a constant source, of leakage and dampness. These floors
are provided for accommodating the toilet seats. Sunken floors must invariably
be coated with suitable epoxy or polyurethane compound or polymer
cementitious waterproofing compound.
2.10 Joints of the W.C. pans and the trap should not be sealed with cement mortar,
as it has poor adhesion to ceramic surfaces. Also shrinkage cracks develop in
Page 3 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
the cement mortar. Such joints should be sealed with epoxy putty, which has
good adhesion to ceramic surface and is not affected by acids and chemicals.
2.11 Joints in tiles provided in floors of toilets and bath rooms are a source of
leakage. A specially formulated solvent based polymer sealant is commercially
available for sealing these joints. It is a clear transparent compound, having low
viscosity and excellent adhesion to ceramic surfaces.
2.12 Floors of bath rooms should be constructed of materials which do not readily
absorb moisture. Entire floor to be sunk 25 mm from adjoining floor. Slope
towards outlet 1 in 60 is recommended.
2.13 Bath room walls to a height of at least 1 M from floor (2 M where shower is
provided) should be made of impervious material such as cement plaster
(smooth finish) with water proofing compound, Mosaic, Ceramic tiles or stone
lining.
2.14 Any Concealed water supply (Hot and Cold) pipeline network needs to be
checked thoroughly at the time of installation and checked personally by SSE,
particularly joints, to ensure it does not leak, after tiles are placed on walls. The
same applies to drainage pipelines of Wash Basins which may be encased in
flooring tiles. A sketch showing concealed pipe network and distribution layout
of bathroom shall be fixed on the back of bathroom door for reference in future.
2.15 Specifications laid down by the manufacturers of the water proofing products
should be followed to ensure that no air bubbles are left between the under
lying surface and the water proofing layer. Adequate overlaps should be
provided for the water proofing layers, including cover up to the parapet wall.
There are a large number of relevant Indian Standards and Code of practice
available. Their provisions regarding material & execution may be followed.
2.16 Adequacy of drainage must be ensured. As a general guide line for every 40
M2 of roof area, one 100 mm diameter rain water pipe must be provided.
Drainage will also depend upon the intensity of rain fall in the area. As per
provisions of IRWM-2000, The size of rain water pipes, depending upon the
average rate of rain fall and roof area, should be as given in Table, for its
adequacy.
Page 4 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Diameter of 2
Average rate of Rainfall in mm/hr (Roof area, m )
pipes in mm
2 2 2 2 2 2
50 m 75 m 100m 125m 150m 200m
50 13.4 8.7 6.6 5.3 4.4 3.3
65 24.1 16.0 12.0 9.6 8.0 6.0
75 40.8 27.0 20.4 16.3 13.6 10.2
100 85.4 57.0 42.7 34.2 28.5 21.3
125 - - 80.5 64.3 53.5 40.0
150 - - - - 83.6 62.7
3.0 Integral cement based treatment for water proofing on horizontal surface
of under-ground structure/Basement: (CPWD DSR 2018 : Item No. 22.1 &
Specification 2009 Vol.-2 Item No. 22.1)
3.1.1 Preparation of Surface: The Water Proofing Treatment over the lean
concrete/levelling course surface should adhere to the surface firmly; the
surface of levelling course should be roughened properly when the concrete is
green. In case the surface is not made rough before the concrete is set, the
work of water proofing should not be executed till proper key is provided for
the base layer of Cement Mortar.
3.1.2 Blending Cement/Water with Water Proofing Compound: The required
quantity of cement bags to be used for a particular portion of work should be
emptied on a dry platform. Water proofing compound conforming to IS 2645
should then be mixed properly with the cement. The quantity of water proofing
compound to be mixed should be as prescribed by the manufacturer but not
exceeding 3% by weight of cement. The quantity of cement and water proofing
compound thus mixed should be thoroughly blended and the blended cement
should again be packed in bags. For the water proofing compound in liquid
form, the blending is to be done with water. This can be done by taking the just
required quantity of water to be mixed in the particular batch of dry cement
mortar. The required quantity of dry cement mortar to be prepared should be
mixed with liquid water proofing compound from sealed tins with ISI mark. The
water mixed with water proofing compound shall be thoroughly stirred so that
the water is blended with water proofing compound properly.
Page 5 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
‘Liquid Membranes’ are also available in the market and are extensively used.
Examples of sheet membranes are Multilayer bituminous paper system with
gravel topping, Butyl rubber sheeting, Bitumen/polyethylene sheets, Neoprene
rubber sheets and modified polypropylene bitumen sheets. Examples of liquid
membrane are Mastic asphalt, modified polyurethane tar, Flexible epoxy
resins, Acrylic co-polymers and epoxy based paints.
3.1.5 Preparation of Cement Mortar for base course: Cement mortar 1:3
(1 blended cement: 3 coarse sand) shall be prepared with cement/ water duly
blended as explained in clause 3.1.2 with water proofing compound. Only that
much quantity of cement mortar which can be consumed within half an hour,
shall be prepared. Any cement mortar that is prepared and remains unused for
more than half an hour shall not be used in the work and shall be rejected.
Before laying the base course of cement mortar, the lean concrete surface
shall be cleaned neatly with water.
Cement slurry prepared as per clause 3.1.4, shall be applied only on the area
of the concrete surface, that can be covered with the cement mortar (1:3) base
course within half an hour.
The cement slurry should cover every spot of the surface and no place shall
remain uncovered. Just after the application of cement slurry on the surface,
the cement mortar prepared as per clause 3.1.5 should be used for laying the
base course.
Base Course should be laid to a perfect level with wooden / aluminium straight
edge of at least 2 m long.
The top surface of cement mortar should be finished neatly and later scratched
when green with a suitable instrument before the base course dries and gets
hard that is just before the base course takes up initial set.
When the 25 mm thick base course is just getting set, the cement slurry
prepared as per clause 3.1.4 should be spread over the base course upto the
area that shall be covered with just two to three stone slabs.
The cement slurry shall be spread in such a way that the area of base course
to be covered immediately shall be covered with slurry without any gap or dry
spots. Then immediately on applying cement slurry on the base course, the
rough Kota Stone slabs (or other material as specified in clause 3.1.3) may be
laid over the base course and pressed gently so that the air gap can be
removed.
The slurry applied on the surface which gets spread when the stone slab is
pressed shall get accumulated in the joints of adjacent stone slabs and if any
Page 6 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
gap still remains between the stone slabs the same should also be filled with
additional quantity of cement slurry.
Cement mortar 1: 3 prepared as per clause 3.1.5 shall be used for laying the
next course.
For laying this course 25 mm high wooden strips shall be used and the top
surface shall be finished smooth without using additional cement or slurry.
After laying 3rd course and before the mortar layer takes the initial set, Stone
aggregate of 10mm to 12 mm nominal size shall be uniformly spread and
lightly pressed into the finished surface @.008cubic meter/sqm (approx.1/2
Bag).
The aggregates shall not be embedded totally inside the mortar and shall be
visible on the top surface.
In cases where slope is to be provided for the water proofing layer, grading
with additional cement concrete/cement mortar shall be provided and then the
water proofing layer shall be laid on the graded surface.
3.1.7 Curing: Immediately after completing the fourth layer, arrangements shall be
made for the top RCC slab as quickly as possible and in the mean time till the
top slab is casted the water proofing treatment shall be kept wet continuously.
In case the concreting of slab gets delayed for more than 2 weeks the curing
can be stopped after 14 days.
Fig.1
4.0 Integral cement based water proofing treatment on the vertical surface of
underground structures (CPWD DSR 2018: Item No. 22.2 & Specification
2009 Vol.-2 Item No. 22.2)
4.1 Preparing the Surface: The surface of the structure to be treated shall be
roughed either by raking of joints in case of brick/ stone masonry or by hacking
the cement concrete surface with a specifically made hacking tool just after
removing shuttering. Alternately, the surface should be roughened by providing
spatter dash key as explained under clause 3.1.1. While doing water proofing
to vertical faces from inside, it shall be ensured that water proofing treatment
of floor slab is not damaged. Preferably, water proofing of vertical surface shall
be done before that of horizontal surface.
Page 7 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Fig.2
5.1 Before the Water Proofing Treatment: Before the water proofing treatment,
the internal plaster of ceiling and walls of WC block leaving the portion for
dado/skirting should be completed. Grooving / chasing for doing the concealed
work of GI/CI pipes/Electrical conduits should be completed. Clean the
depressed/sunken portion of WC of all debris, extra mortar sticking to the
vertical and horizontal surface etc. Necessary holes for ‘P’ trap /Nhani
trap/Water escape pipe etc should be completed.
5.2 Preparing Surface and Fixing Pipes and Fittings: Before the water proofing
treatment work, proper key in the concrete surface should be provided. The
depressed/sunken portion should be hacked by a hacking tool, after the
Page 8 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
concrete slab is cast and when this concrete is still green. The vertical surfaces
of the depressed /sunken portion should be hacked with a hacking tool just
after the shuttering is removed. In case of old work, the water proofing
treatment on such surfaces shall be permitted after making proper spatter dash
key. Fixing the ‘P’ trap in position and all other pipes work including the water
escape pipe shall be fixed properly and the holes should be plugged carefully
before taking up the water proofing work.
5.3 1st Course: Cement duly blended with water proofing compound as explained
in clause 3.1.2 shall be used for preparing the cement slurry. The consistency
of the slurry should be such that 4.4 kg of blended cement with water proofing
compound is used per sq. metre area of surface to be treated. The slurry
should be started from the vertical faces towards the bottom of the floor as
shown in Fig. 3 below. Particular care should be taken to see that the slurry is
applied to corners without leaving any gap.
5.4 2nd Course: Immediately on applying the blended cement slurry on the surface
to be treated cement plaster 20mm thick in cement mortar 1:3 (1 blended
cement: 3 coarse sand) shall be applied both on vertical and horizontal
surfaces taking particular care to complete the entire depressed/ sunken
portion of WC within a day so that the plaster can be done without any joint.
Junctions shall be properly rounded. The surfaces of the plaster shall be left
rough but finished in one plain and cured for a week. On completion of the
curing period both horizontal and vertical surfaces shall be cleaned properly
and gently and allowed to dry.
5.5 3rd Course: Only after the surface is completely dried the blown or residual
bitumen shall be applied @ 1.7 kg of bitumen per sqm area.
5.6 4th Course: 400 micron thick PVC sheet shall be spread evenly without any
kink immediately, so that the PVC sheet sticks to the surface firmly. PVC sheet
shall be continued to be laid over the main slab upto 100mm. Overlapping of
PVC sheet should be done with a minimum overlap of 100 mm, duly pasting
the overlapped sheet with an application of bitumen @ 1.7 kg./ sqm. The
projections of pipes and ‘P’ trap outlet etc. inside the depressed/sunken portion
of WC shall also be cladded with water proofing treatment layer upto a height
of 150 mm, using a coat of bitumen with PVC sheet complete. The surfaces of
depressed/sunken portion of WC shall not be left without covering with
specified filling material and base concrete, otherwise the PVC sheet layer may
be tampered by the labour working in the vicinity. Fixing up of WC pan, filling
specified material and the top base concrete should be done as early as
possible and the top horizontal layer of water proofing may be taken up later
i.e. just before laying the floor tiles.
Page 9 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Fig.3
Page 10 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
proofing compound + y litres of water per sqm. area and the required quantity
of slurry thus prepared should only be used for second application. The
application of 2nd layer of slurry is same as for first layer as detailed in clause
6.3. The applied surface shall be allowed to air cure for 4 hours and thereafter
water curing shall be done for full 48 hours. In case no further work as
described above is to be taken up immediately on completion of water proofing
treatment due to any reason it is recommended to protect the treated portion
with cement plaster 1:4 as a protective layer .
Junction of roof with parapet wall is a vulnerable location for leakage. Hence
detailing at the junction of roof and vertical face of parapet wall is a necessary
and complicated issue requiring careful planning.
Providing sufficient roof overhangs of about 0.50m and extending part of roof
as parapet wall can address this issue to large extent as it avoids the junction
points of roof with parapet wall. It also provides shade from rains and solar
heat and help in saving energy, providing some spill over space and increase
the life span of the building.
i) The fillet (angular or concave, not convex) of adequate size should be provided
all along the junction of parapet wall with roof.
ii) Coping on top of the parapet wall should also be provided with adequate slope
along with the provision of drip course on either side.
iii) Water proofing system should be extended from roof to parapet wall for a
minimum height of 150 mm with a chase.
iv) Typical details of junction arrangement of rain water pipe with roof are indicated
in Fig. 5. Invert level of rain water pipe should be approx. 25 mm below the
level of top of adjacent tiles/water proofing work. Grating should be fixed at the
mouth of rain water pipe to prevent entry of leaves/other waste material from
roof. Unless, specified otherwise, rain water pipe and fittings should be
properly secured to the walls.
Page 11 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Fig. 4
Fig. 5
Page 12 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
water tight sealants so that no leakage occurs through joint. Joint filers should
confirm to IS: 3414-Code of Practice for Design & Installation of Joints in
Buildings or IS:1838 (Pt.I and Pt.II)-Specification for Preformed Fillers for
Expansion Joint in Concrete Pavement and Structures. Sealing compound
should confirm to IS:1834-Specification for Hot Applied Sealing Compounds
for Joints in Concrete. General Arrangements for an expansion joint are shown
in Fig. 6.
Page 13 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
9.1 Water proofing methods can be broadly classified into the following types:
1. Polymerized Bitumen.
2. Water proofing by APP(Atactic Polypropylene Polymeric ) Membrane
3. Water Proofing By Crystallization (Cement and Liquid Polymer)
Page 14 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Before taking up the water proofing work, the construction of parapet walls
including finishing should be completed. Similarly, the ancillary items like
haunches, khurras, grooves to tack the fibre cloth layer, fixing up of all down
take pipes, water pipes and electric conduits etc. should be completed and no
such work should be allowed on the area to be treated during the progress of
water proofing treatment or even later.
Page 15 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 16 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 17 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.2.1 Materials - The bitumen primer shall conform to the requirements laid down in
IS 3384.
10.2.2 Bonding Material: This shall consist of blown type bitumen conforming to IS
702 or residual bitumen 85/25 conforming to IS 73 heated to the correct
working temperature of 180°C. The penetration of the bitumen shall not be
more than 40 when tested in accordance with IS 1203, unless otherwise
specified each coat of bonding material shall be of blown type bitumen of grade
Page 18 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.2.3 Surface Finish: Surface finish shall be with brick tiles of class designation 100
grouted with cement mortar 1:3 (1 cement : 3 fine sand ) with 2% integral water
proofing compound by weight of cement over a 12 mm thick layer of cement
mortar 1:3 (1 cement: 3 fine sand) and finished neat.
Page 19 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Where the height is 45 cm. or less, no groove will be required as the water
proofing treatment will be carried over the top of the parapet wall to its full
thickness.
In the case of low dividing walls of height 30 cm. or less, outlets therein shall
be cut open for full height and the bottom and sides shall be rendered smooth
and corners rounded and such treatment shall not be measured and paid for
separately.
Where expansion joints are left in the slab the provision of dwarf walls and/or
RCC slabs for covering them and finishing the surface smooth shall be the
responsibility of the construction agency, which had laid the roof slab and will
not be included in the operation of water proofing.
The graded surface of the roof and concrete fillets and the faces of walls shall
be thoroughly cleaned with wire brushed and all loose scales etc. removed.
The surface shall then be dusted off.
Any crack in the roof shall be cut to V section, cleaned and filled up flush with
cement mortar slurry 1:4 (1 cement : 4 coarse sand) or blown type petroleum
bitumen of IS grade 85/25, or approved quality conforming to IS 702. Such
cleaning of the surface or treating the cracks shall not be paid for separately.
10.2.5 Treatment: The water treatment shall be of five or seven course as specified.
In seven course treatment, the first four courses shall be the same as for five
course treatment. The fifth course shall be a layer of APP modified polymeric
membrane. The sixth course shall be a coat of bonding material and the top
most seventh course shall be of specified surface finish.
10.2.6 Laying:
(a) First course shall be a coat of bitumen primer @ 0.40 kg per sq mt followed
by subsequent course as per treatment required.
(b) Drain outlets shall be given a four or six course treatment as specified for the
roof in the description of the item in the manner specified for the flat roof
surface. Water proofing treatment shall be carried into the drain pipe or outlets
by at least 10 cm. The water proofing treatment laid on the roof surface shall
overlap the upper edge of the water proofing treatment in the drain outlets by
at least 10 cm.
(c) The APP modified polymeric membrane shall be cut to the required length,
brushed clean of dusting material and laid out flat on the roof to eliminate curls
and subsequent stretching. The membrane shall normally be laid in length in
the direction of the slope and laying shall be commenced at the lowest level
and worked up to crest. The membrane shall not be laid in single piece of very
long lengths as they are likely to shrink; 6 to 8 m are suitable lengths. The roof
surface shall be cleaned and dry before starting the membrane treatment.
Each length of membrane shall be laid in position and rolled up for a distance
of half its length. The hot bonding material shall be poured on the roof across
the full width of the rolled membrane as the latter is steadily rolled out and
pressed down. The pouring shall be so regulated that the correct weight of
Page 20 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
bonding material per unit area is spread uniformly over the surface. Excess
bonding material that gets squeezed out at the ends shall be levelled up as
laying proceeds. When the first half of the strip of felt has been bonded to the
roof, the other half shall be rolled up and then unrolled on the hot bonding
material in the same way. Subsequent strips shall also be laid in the same
manner.
Each strip shall overlap the preceding one by at least 7.5 cm. at the longitudinal
edges and 10 cm. at the ends. All overlaps shall be firmly bonded with a blow
lamp and levelling down unevenness. The fourth layer of bonding material in
the five course treatment shall be carried out in a similar manner after the
flashing has been completed.
(d) In a seven course treatment the fifth layers of membrane shall be laid in the
manner already described, taking care that laps in the membrane are
staggered from those in the earlier layer. The sixth layer of bonding material
shall be carried out after the flashing is done.
(e) High Parapet Walls, Chimney Stacks etc.: Membrane shall be laid as flashing
wherever junctions of vertical and horizontal surfaces occur. Longitudinal laps
shall be 10 cm. The lower layer of flashing membrane in a six course treatment
shall overlap the roof water proofing by not less than 20 cm. while the upper
layer shall overlap the roofing felt by 10 cm. The minimum overlap of the
flashing membrane in five course treatment over the roofing membrane shall
be 10 cm.
The flashing shall consist of the same five or seven course treatment as for the
roof except that the final course shall be replaced by an application of 12 mm
thick cement plaster 1:3 on the vertical and sloping faces only, of the flashing.
The overlap along the length of flashing shall stagger with those in the second
layer of flashing membrane (in a seven course treatment and with the joints in
the roof membrane).
The upper edge of the finishing membrane shall be well tucked into the flashing
grooves in the parapet, chimney stacks etc. to a depth of not less than 6.5 cm.
Corresponding applications of bonding material shall also be made. The
flashing treatment shall be firmly held in place in the grooves with wood edges
at intervals and the grooves shall be filled up with cement mortar 1:4 (1
cement: 4 coarse sand) or cement concrete 1:2:4 (1 cement: 2 coarse sand :
4 graded stone aggregate 6 mm nominal size) and surface finished smooth
with the rest of the wall. The cement work shall be cured for 7 days. When dry,
the exposed plaster joints of grooves shall be painted with bitumen and two
coats of bituminous solution shall be applied on the vertical and sloping surface
of flashing.
After the top flashing membrane layer has been fixed, the penultimate layer of
bonding material shall be applied over the roofing membrane and the
horizontal overlaps and vertical and sloping surfaces of the flashing at the
specified rate.
Page 21 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
(f) Low Parapet Walls: Where parapet walls are of height 45 cm. or less,
membrane flashings shall be provided in the same manner as for flashings in
the case of high parapet walls except that the upper edge shall be carried upto
the full height of the wall and taken right across the top of the parapet and
down on the external vertical faces to a minimum distance of 5 cm.
(g) Low Dividing Walls: Where low dividing walls or inverted beams are met with,
the same shall be covered with a four or six layer treatment as for the main
roof, the latter bearing carried down both sides of the wall and overlapping the
roofing treatment as in the case of flashing of high parapet walls.
Drain outlets where formed in the low dividing walls, shall be given water
proofing treatment of the same number of courses as specified for the flat roof
surface. The bottom and sides shall be so treated that all overlaps are in the
direction of flow of drainage.
(h) Expansion Joints: Where the expansion joints are provided in the slabs, the
joints and their cover slabs shall be suitably treated with water proofing. A
typical sketch of an expansion joint with the RCC slabs on either side of the
joint turned vertically up and dwarf walls by not less than 7.5 cm. and are
provided with throatings on their underside along their length. The water
proofing treatment shall be taken up the sloping junction fillets and the vertical
faces of the walls to the underside of the cover slabs. The cover slabs are
given the water proofing treatment like the roofs slabs, after the cross joints
between adjacent cover slabs are first sealed with 15 cm width of roofing felt
struck to them with bitumen. The water proofing treatment shall be carried
down the sides of the cover slabs to their full thickness. Care shall be taken to
see that overlaps if any in the roofing over the cover slabs stagger with the
joints between cover slabs. The formation of the expansion joints and provision
of the cover slabs shall be the responsibility of the construction agency. The
formation of the junction fillets and the water proofing treatment of the joint and
cover slabs shall be carried out by the water proofing agency. Nothing agency
extra shall be paid for the sealing of the cross joints in the cover slab with 15
cm. width of bitumen strips.
(i) Pipes: Where vertical pipe outlets are met with, 7.5 x 7.5 cm fillets of lime or
cement concrete of the type shall be provided and flashing of four or six course
treatment, same as for the roofing treatment shall be laid. The upper edge of
the flashing shall be laid sloping down forward and butted against the pipe and
annular depression so formed shall be filled with hot bitumen. A circular metal
collar in the shape of an inverted truncated cone shall be fixed on the pipe to
throw off the rain water clear of the flashing and this shall be paid for
separately.
Page 22 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Fig. 7
10.3.1 Materials:
Bitumen primer for bitumen membrane shall have density at 25°C in the
range of 0.87 - 0.89 kg./litre and viscosity of 70-160 CPS primer shall be
applied @ of 0.40 litre/sqm.
Page 23 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
SI. No. of Layers Thickness Elongation Joint Tear strength Softening Cold
No. at 23° C strength in in longitudinal Point flexibility
in longitudinal Transverse
longitudinal and direction
transverse Transverse
direction direction
1 2 3 4 5 6 7 8
1 Five Layered 2 mm 3 N/5 cm. 350/300 60/80 N 150° -2°C
reinforced with N/5 cm.
fibre glass
2 Five layered 3 mm 3.3 N/5 cm. 350 / 3000 60/80 N 150° -3°C
reinforced with N/ 5 cm.
fibre glass
3 Five layered 3 mm 40/50 N/5 650 N/450 300/250 N 150° -2°C
reinforced with cm. N/5 cm.
non-woven
polyester matt.
10.3.2 Preparation of Surface: The surface to be treated shall have a minimum slope
of 1 in 120 or as specified, provision specified in clause 10.2.4 shall apply for
preparation of surface except for pitched roof where surface shall be cleaned
off any loose material dust etc. To ensure good adhesion between the surface
and water proofing treatment suitable method to dry the surface shall be
adopted. All hair line cracks in the surface should be filled with approved
sealant.
10.3.3 Treatment: The water proofing shall consist of prefabricated five layered 2 mm
/ 3 mm membrane as shown in Fig.8 . The choice of 2 mm or 3 mm membrane
will depend on the type of roof i.e. pitched or flat and importance of building,
durability, cost and rainfall etc.
10.3.4 Laying:
Bitumen primer @ 0.40 lts/sqm shall be applied to the prepared roof, drain and
all other surfaces where polymer modified membrane is to be laid.
Page 24 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
The five layered water proofing membrane shall be laid using Butane torch and
sealing all joints and preparing the surface complete.
Drain outlets shall be given same treatment as specified for the roof in the
description of the item in the manner specified for the flat roof surface.
Water proofing treatment shall be carried into the drain pipe or outlets by at
least 10 cm.
The water proofing treatment laid on the roof surface shall overlap the upper
edge of the water proofing treatment in the drain outsets by at least 10 cm.
The APP polymer modified prefabricated water proofing membrane shall be
cut to the required length.
Water proofing membrane shall normally be laid in length in the direction of the
slope and laying shall be commenced at the lowest level and worked upto
crest.
APP water proofing membrane shall be laid in 6 to 8 m lengths.
The roof surface shall be cleaned and bitumen primer shall be applied in the
correct quantity, over this specified water proofing membrane shall be laid with
butane torch after allowing 24 hours for primer to dry.
Each strip shall overlap the preceding one by at least 10 cm. at the longitudinal
edges and 15 cm. at the ends.
All overlaps shall be firmly bonded with bitumen primer and levelled by heating
the overlap with butane torch.
If the roof is accessible the treatment is protected by brick tiles laid over 12 mm
thick cement mortar of specified grade bedding and joints sealed with cement
mortar of which shall be measured and paid for separately.
APP water proofing membrane shall be laid as flashing wherever junction of
vertical and horizontal surfaces occur.
Longitudinal laps shall be 10 cm.
The upper edge of flashing membrane shall be well tucked into the flashing
grooves in the parapets, chimney stack etc. to a depth of not less than 6.5 cm;
corresponding applications of primer coat shall also be made.
The flashing treatment shall be firmly held in the grooves and it shall be sealed
with the approved sealant after terminating the membrane.
Where parapet walls are of height 45 cm or less AP water proofing membrane
flashing shall be provided in the same manner as for splashing in the core of
high parapet walls except that upper edge shall be carried out the full height of
the wall and taken right across the top of the parapet and down on the external
vertical faces to a minimum distance of 5 cm.
Where low dividing walls or inverted beams are met with, the same treatment
shall be provided as for the main roof, the lateral bearing carried down both
sides of the wall and overlapping the roof treatment.
Drain outlets where formed in the low dividing walls, shall be given water
proofing treatment same as for the main roof.
Where the expansion joints are provided in the slabs, the joints and their cover
slabs shall be suitably treated with water proofing treatment.
The cover slabs shall cover the vertical turned up dwarf walls by not less than
7.5 cm and are provided with throatings on their underside along their length.
The water proofing treatment shall be taken up the slopping junction fillets and
the vertical faces of the walls to the underside of the cover slabs are given the
Page 25 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
water proofing treatment like the roof slabs, after the cross joints between
adjacent cover slabs are first sealed with 15 cm. width of roofing felt struck to
them with bitumen.
The water proofing treatment shall be carried down the sides of the cover slabs
to their full thickness.
Care shall be taken to see that overlaps if any in the roofing over the cover
slabs stagger with the joints between cover slabs.
The formation of the expansion joints and provision of cover slabs shall be the
responsibility of construction agency.
The formation of the junctions fillets and the water proofing treatment of the
joint and cover slabs shall be carried out by the water proofing agency.
No extra shall be paid for the junction fillets or for the sealing of the cross joints
in the cover slab with 15 cm. width of bitumen strips.
Fig.8
Page 26 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Once the concrete has cured, the crystalline chemicals sit dormant until
another dose of water (such as through a new crack) causes the chemical
reaction to begin again. The ability to reactivate in the presence of water gives
crystalline-treated concrete the ability to “self-seal”. When cracks form due to
curing shrinkage, settling, seismic activity, etc., water entering through them
causes new crystals to form and grow, blocking and filling the cracks. Its ability
to self-seal cracks is one of crystalline technology’s most unique and useful
features, and can help to dramatically reduce the long-term maintenance and
repair costs of a concrete structure.
10.5 Water proofing treatment with integral crystalline admixture: (CPWD DSR
2018: Item No. 22.22)
10.5.1 General: One method that can simplify the protective process is to make
concrete with Integral Crystalline Admixtures that reduce its permeability in
effect to make the concrete itself waterproof. Apart from the regular workability
admixtures, Integral Crystalline Durability admixtures shall be added to all
concrete, structural and otherwise, to waterproof & enhance the Concrete
Durability. The Crystalline Admixture shall be added either at the time of
Page 27 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
batching at the batching plant or in the drum of the transit mixer, when the
concrete arrives the point of pouring.
The concrete water proofing industry redefined their terminology a short time
ago. American Concrete differentiates between those suitable for concrete
exposed to Non Hydrostatic Conditions (PRAN) and other beneficial
characteristics such as reduced drying shrinkage, reduced chloride-ion
penetration, and improved freeze thaw resistance and enhanced autogenously
sealing.
Page 28 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
1048 Part 5 by carrying out 4 cycles each of 5 bar hydrostatic pressure for 72
hours and drying for 48 hours between the cycles & co-efficient of permeability
calculated as per Darcy’ formula/ Valenta equation by incorporating
penetration values obtained at the end of fourth cycle pressure.
4. It shall possess CE mark approval as per EN934-2 and shall be procured from
CE mark approved manufacturing unit. It shall also possess approval
certificate from any national apex institution mandated to issue design codes.
The product has no corrosion effect on reinforcement steel according to test
norm DINV18998. The maximum chloride content lies less than 0.1% and
maximum alkali content less than 9.3%.
Page 29 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
9. Product must possess third party assurance, confirming that the product, when
used in the concrete, will have no detrimental side effects in terms of Alkali
Silica Reaction (ASR), corrosion of steel re-enforcement etc.
10. The product performance shall not be affected by wear abrasion of the treated
concrete surface and crystalline treated concrete shall not require protection
layer.
11. The crystalline admixture shall be non-toxic and shall confirm to NSF-61 USA.
10.5.5 Dosage: 0.8% (minimum) to the weight of cement content per cubic meter of
concrete or higher dosage as recommended by manufacturer’s specification
10.5.6 Mixing: The integral crystalline admixture shall be used @ 0.8% (minimum)
to the weight of cement content per cum of concrete or higher as
recommended by manufacturer’s specification desired to meet water proofing
and durability criteria. Integral crystalline Admixture must be added to the
Page 30 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
concrete at the time of batching at the batching plant or in the drum of the
transit mixer, when the concrete arrives the point of pouring.
The sequence of procedures for addition will vary according to the type of
batch plant operation and equipment. The mixing shall be followed as below
unless & until specified otherwise. For any detailing and mixing guidelines
recommended by manufacturer’s specification should be followed.
10.5.7 Ready mix plant- Dry batch operation: Add integral crystalline admixture in
power form to the drum of the ready-mix truck under the batch plant and add
60%- 70% of the required water, along with required aggregate. Mix the
materials for 2-3 minutes to ensure that the integral crystalline admixture is
distributed evenly throughout the mix water. Add the balance of materials to
the ready-mix truck in accordance with standard batching practices.
10.5.8 Ready mix plant- Central mix operation: Mix integral crystalline admixture
with water to form a very thin slurry (e.g. 18kg of powder mixed with 22.7 litre
of water). Pour the required amount of material into the drum of the ready-mix
truck. The aggregate, cement, sand and water should be batched and mixed
in the plant in accordance with standard practices (taking into account the
quality of water that has already been placed in the ready-mix truck). Pour the
concrete into the truck and mix for at least 5 minutes to ensure even distribution
of integral crystalline admixture throughout the concrete.
10.5.9 Precast batch plant: Add integral crystalline admixture to the aggregate and
sand, then mix thoroughly for 2-3 minutes before adding the cement and water.
The total concrete mass should be blended using standard practices.
10.5.10 Setting time and strength: The setting time of concrete mix is directly
affected by the chemical and physical composition of ingredients, temperature
of the concrete and prevailing climatic conditions. Retardation of set may occur
when using integral crystalline admixture. The amount of retardation will
depend upon the concrete mix design and the dosage rate of integral
crystalline admixture. However, under normal conditions, integral crystalline
admixture will provide a normal set concrete. Concrete containing integral
crystalline admixture may develop higher ultimate strengths than plain
concrete. Trial mixes of the concrete should be carried out under project
conditions to determine setting time and strength of the concrete.
Page 31 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.5.13 Storage / Shelf Life: Integral Crystalline Admixture must be stored dry at a
minimum temperature of 7º C and its shelf life is one year when stored under
proper conditions.
10.6 Water proofing treatment with integral crystalline water proofing coating
/ slurry: (CPWD DSR 2018: Item No. 22.23)
10.6.1 General: This Integral crystalline water proofing coating / slurry of hydrophilic
in nature is applied to surface of the concrete to water proof and protect the
concrete in-depth. It consists of Portland cement, specially treated quartz sand
and a compound of active chemicals. Integral crystalline water proofing coating
material needs only to be mixed with water prior to application.
10.6.2 Material: This Integral crystalline water proofing material consists of Portland
cement, specially treated quartz sand and a compound of active chemicals.
Page 32 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
as specified in concerned relevant codes etc. and the same shall be got tested
and get approved from the Engineer-in-charge before its use.
8. Potable Water Compatibility: Nontoxic & suitable for use in potable water
facilities- NSF listed as per ANSI 61 listing.
Total quantity of the Integral Crystalline water proofing slurry material required
shall be arranged only after obtaining the prior approval of the Engineer-in-
Charge in writing. Materials shall be kept under double lock and key and proper
account of water proofing compound used in the work shall be maintained. It
shall be ensured that the consumption of the compound is as per specified
requirements. Contractor shall associate himself with anyone of the specialist
Page 33 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
firms mentioned in approved list of specialized agencies for the work relating
to the Water Proofing Treatment.
10.6.6 Mixing: Integral crystalline water proofing slurry / coating material should be
mechanically mixed with clean water to a creamy consistency resembling to
thick oil. Only that much material should be mix as can be used within 20
minutes and mixture should be stirred frequently. The mixture should not be
allowed to set, it if happens, simply re-stir to restore workability but no more
water should be added to it. The ratio of integral crystalline water proofing
material with water should be as below
i) Vertical surface: - For applying with brush the ratio should be 5 parts of integral
crystalline water proofing material to 2 parts of water.
For applying with spray the ratio should be 5 parts of Integral Crystalline water
proofing coating material to 2.75 - 3.25 parts of water.
ii) Horizontal surface: - The ratio should be 3 parts of Integral Crystalline water
proofing coating material to 1 part of water. This should be applied by brush
only.
10.6.7 Application Procedure: The slurry mix of the Integral Crystalline water
proofing slurry material shall be applied in one or two coats as specified/
required according to work situation in the item. After preparation of surface as
described in para 9.6.4, and making the surface saturated with water before
application of Crystalline Slurry, then first coat of the slurry mix shall be applied
Page 34 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
The other method of application known as Dry powder consistency can also
be applied on horizontal surfaces only. The specified amount of integral
crystalline water proofing material is distributed in powder form through a sieve
or a semi mechanical barrow spreader and troweled into the freshly placed
concrete as this reaches the initial set.
ii. Horizontal surface: - One coat of integral crystalline water proofing material
slurry coat shall be applied @ of 1.10 kg per sqm or as specified by the
manufacturer to harden concrete. Alternatively integral crystalline water
proofing material mix can be dry sprinkled @ of 1.00 kg per sqm and trowel
applied to fresh concrete when it has reached initial set.
iii. Construction joint: - Integral crystalline water proofing material mix shall be
applied either as slurry coat or dry powder consistency immediately prior to
placing the next lift/ bay of concrete @ 1.60 kg per sqm. or as specified.
iv. Binding concrete: - Integral crystalline water proofing material mix shall be
applied either as slurry coat or dry powder consistency immediately prior to
placing the overlying concrete slab.
10.6.8 Curing: The treated surfaces should be kept damp for a period of five days
and must be protected against direct sun, wind and frost, by covering with
polyethylene sheeting, damp burlap or similar material.
10.6.10 Storage / Shelf Life: When properly stored in a dry place in unopened and
undamaged original packaging its shelf life is 12 months.
Page 35 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.7 Water proofing treatment with integral crystalline water proofing dry-
shake: (CPWD DSR 2018: Item No. 22.24)
10.7.2 Material: Integral Crystalline water proofing dry-shake (dry powder) compound
consists of Portland cement, various active proprietary chemicals, and a
synthetic aggregate hardener that has been crushed and graded to particle
sizes suitable for concrete floors.
Page 36 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
6. Product must possess third party assurance, confirming that the product, when
used in the concrete, will have no detrimental side effects in terms of Alkali
Silica Reaction (ASR), corrosion of Steel Reinforcement etc.
7. The product performance shall not be affected by wear abrasion of the treated
concrete surface and crystalline treated concrete shall not require protection
layer.
8. Potable Water Compatibility: Nontoxic & suitable for use in potable water
facilities- NSF listed as per ANSI 61 listing.
Total quantity of the Integral Crystalline water proofing dry shake material
required shall be arranged only after obtaining the prior approval of the
Engineer-in-Charge in writing. Materials shall be kept under double lock and
key and proper account of water proofing compound used in the work shall be
maintained. It shall be ensured that the consumption of the compound is as
per specified requirements. Contractor shall associate himself with anyone of
the specialist firms mentioned in approved list of specialized agencies for the
work relating to the Water Proofing Treatment.
ii. Concrete should be free of bleed water and be able to support the weight of a
power trowel. Float open the surface.
Page 37 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
iii. Immediately after floating open the surface and within one hour of finishing the
concrete, apply one-half of the Integral Crystalline water proofing dry-shake
material by hand or mechanical spreader, in one direction only. The Integral
Crystalline water proofing dry-shake material must be spread evenly.
iv. As soon as the Integral Crystalline water proofing dry-shake material has
absorbed moisture from the base slab, it should be power floated to the
surface.
10.7.6 Curing: Curing is important and shall begin as soon as final set has occurred
but before surface starts to dry. Conventional moist curing procedures such
as water spray, wet burlap or plastic covers may be used. Curing should
continue for at least 48 hours. In hot dry sunny or windy conditions, it is
advisable to use an evaporation retardant on the fresh concrete surface to
prevent premature drying of the slab conditions due consultations should be
made from the technical representatives of the manufacturer for specific
instructions. In lieu or moist curing, concrete sealers and curing compounds
may be used. In all cases, recommended guidelines for proper curing should
be followed.
10.7.7 Recommended uses: Foundations /Rafts Slabs, Water tank base slab ,
Sewage and Water Treatment Plants, Below Grade Structures, Warehouses
Floors, Traffic Bearing Surfaces, Parking Structures
10.7.8 Precaution / Special Consideration: For the best results when applying
Integral Crystalline dry shake materials, the air content of the concrete shall
not exceed 3% (a high air content can make it difficult to achieve a proper
application).
In hot, dry, or windy conditions, it is advisable to use an evaporation retardant
on the fresh concrete surface to prevent premature drying of the slab. Chronic
moving cracks or joints will require a suitable flexible sealant.
Page 38 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.7.9 Storage / Shelf Life: Integral Crystalline dry shake must be stored dry at a
minimum temperature of 7º C and its shelf life is one year when stored under
proper conditions.
10.8 Crystalline water proofing mortar: (CPWD DSR 2018: Item No. 22.25)
The active chemicals react with moisture and the by-products of cement
hydration to cause a catalytic reaction, which generates an insoluble integral
crystalline complex. These crystalline complexes grow in the presence of
water and block the capillaries of the concrete and minor shrinkage cracks,
thus water proofing the concrete. Chemicals activation begins when the power
is mixed with water and may take several days to completely block the
capillaries, depending on ambient temperature and environmental conditions.
It can be applied to the positive or negative water pressure sides of a structure.
Total quantity of the water proofing Crystalline Mortar material required shall
be arranged only after obtaining the prior approval of the Engineer-in-Charge
in writing. Materials shall be kept under double lock and key and proper
account of water proofing compound used in the work shall be maintained. It
shall be ensured that the consumption of the compound is as per specified
requirements. Contractor shall associate himself with anyone of the specialist
Page 39 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
firms mentioned in approved list of specialized agencies for the work relating
to the Water Proofing Treatment.
10.8.5 Mixing
i. For routed cracks, coves and non-moving joints: Add water to crystalline water
proofing mortar powder until a medium stiff, trowel able consistency reached.
The texture of the mix should be pliable enough to be trowelled into the cracks
with some pressure, but not so pliable that it would run out or sag out of the
crack.
Approximate mixing ratio (by volume) is 4.5 parts crystalline water proofing
mortar powder to 1 part water. Alternatively, 450gm of crystalline water
proofing mortar powder to 100 ml of water is to be mixed.
ii. Tie holes and pointing applications: Add only a small amount of water. Mixed
consistency should be that of “dry earth” holding a shape when squeezed but
easily crumbled when pressed between fingers. Mix only as much material as
can be used within 20 minutes.
Page 40 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
ii. For repairing spalled & honeycombed areas, prepared the surface and chiesel
back upto sound concrete and then primed the area with integral crystalline
slurry @0.70 kg per sqm. and while the surface is tacky repair and level the
honeycomb area with crystalline mortar @ 22.70 kg per sqm. for an average
thickness of 10mm. Once crystalline mortar is touch dry then finally two coats
of integral crystalline slurry @ 0.70kg per sqm. per coat.
iii. For patching of tie rod holes, prepared tie rod hole surface and primed the area
with integral crystalline slurry @ 0.07 kg per sqm and while the surface is tacky
repair and filled the tie rod holes with crystalline mortar @ 0.040 kg per hole.
The crystalline mortar shall be tightly rodded into tie holes or packed tightly.
For 25x25x25 mm hole, use 0.040 kg per hole to fill the tie hole.
10.8.7 Curing: Provide protection against extreme weather conditions, such as heavy
rain or freezing conditions, during the setting period. Curing is not normally
required except during hot, low humidity weather. In these conditions, a light
mist of water approximately 25 hours after the repair is completed will help to
ensure a controlled cure. In extreme dry heat, water misting may be carried
out at required intervals more frequently.
10.8.9 Storage / Shelf Life: Crystalline mortar shall be stored in a dry enclosed area
off the ground at a minimum temperature of 7ºC. Shelf life when stored in
proper conditions in unopened, undamaged packaging is 12 months.
10.9 Fibre reinforced elastomeric liquid water proofing membrane having sun
reflectivity index (SRI) of 105: (CPWD DSR 2018: Item No. 22.22A)
Page 41 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.9.4 Preparation of Surface: All the substrates, whether they are new or old, must
be sound, clean, dry and free of all traces of oil, grease, old paint, rust, mould
and nay other material which could compromise the bond.
Concrete and in general mineral substrates must be sound and dry with no
rising damp. Any loose parts must be removed. All wax, water-repellent
treatments, etc. must be removed from the surface of ceramic substrates with
a suitable detergent and/ or by sanding. Any hollows and gaps in the surface
must be repaired properly with appropriate material as described and
instructed by the manufacturer of this product. The tools to be used must be
properly cleaned.
10.9.5 Application Procedure: All the area of operation shall be thoroughly cleaned
as described in para 10.9.3 above. Mix the content in such a manner that they
are perfectly blended into a homogenous state of liquid which can be applied
by long haired roller or airless spray. For applying 1st coat of self-priming
Page 42 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
elastomeric water proofing liquid the material should be diluted with water in
the ratio of 3:1 (3 parts of elastomeric water proofing liquid and 1 part of water).
Wait until the 1st coat is completely dry and becomes slightly darker in colour.
After the 1st coat has dried completely apply 2nd coat with undiluted elastomeric
water proofing liquid in a criss-cross direction to the previous coat. After the
drying of 2nd coat completely apply the final coat of undiluted elastomeric water
proofing liquid in a direction perpendicular to previous coat. The minimum
thickness of the dry film of complete application should not be less than as
recommended by manufacturer’s specification. The overall dry thickness
should not be in any case less than 500 microns. Protect the membrane from
rain unless it is completely dry. The overall consumption of the material should
be as per nomenclature of the item and should also adhere to the
specifications detailed in the approved schedule of the manufacturer.
10.10.3 Preparation of Surface: All substrates must be structurally sound, stable and
solid, with all loose material removed. Thoroughly clean the surface of any
Page 43 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
substance that could interfere with the bond of the installation material,
including dirt, paint, tar, asphalt, wax, oil, and grease, latex compounds, from
release agents, laitance, loose toppings, foreign substances and any other
residues. Concrete surfaces must be mechanically profiled and prepared by
shot blasting, sandblasting, diamond-grinding, water-jetting, scarifying or other
engineer-approved methods to obtain an acceptable profile. Concrete
substrate and ambient room temperatures must be maintained between 45°F
and 95°F (7°C and 35°C) before application. Temperatures must be
maintained within this range for at least of 72 hours after the application
coating.
10.10.4 Application Procedure: Apply the coating on to this sound and dry surface
using a long-haired roller, brush or spray. The dilution of the compound the
water should be done in a clean mixing pail. The ratio of mixing with water is
to be done in accordance with the nomenclature of the item along with
corresponding coats and manufacturer specifications. The number of coats to
be applied should be as directed under the nomenclature of the item and the
total material used in complete process should not be less than 14.35 kg per
10 sqm under any circumstances. The 1st coat should be applied on to the
properly prepared and dried surface. More coats should be applied when the
coat below is still wet. All the coats should be applied in perpendicular direction
to each other. The final surface is to be protective from excessive heat or draft
conditions during the first 24 to 72 hours. Final surface should be cured for at
least 5 to 7 days. Use of damp burlap, polyethylene sheeting or water-based
curing compound is also recommended to be used for curing.
10.11 Swellable type water stop tape (CPWD DSR 2018: Item No. 22.26)
10.11.2 Material: This is a swellable type sealing compound which expand rapidly after
coming in to contact or exposed to moisture. This acts as a self-healing
material and is used for applications in construction joints.
Page 44 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.11.5 Recommended Uses: Typical applications for swellable type waterstop tape
include building foundations, slabs, retaining walls, storage tanks, and similar
non-moving cold construction joints
10.11.6 Application:
i. The entire surface length where the water stop is to be applied is cleaned
thoroughly by using blower and brush. Apply one coat of required primer
throughout the length of the joint @ 3.78 litre per 240 running metre. Allow the
primer to dry for 10 to 15 minutes at the temperature of 25°C. This should be
allowed to dry for some longer time in the areas where the temperature are
low.
ii. By using the heel of the hand and moderate pressure, press the self expanding
joint material firmly into the position on the structure on the entire area which
has been primed and dried. Make sure that the product has bonded with the
primed area.
iii. Where required, splice ends to from a continuous, uninterrupted seal. For best
results, cut each end at opposite 45deg. angles and tightly butt ends together.
DO NOT OVERLAP ENDS. Gently knead the spliced ends creating an
uninterrupted seal.
iv. Peel the protective covering from the exposed side of the installed expandable
joints sealing compound.
v. Pour the matting structural member in position.
Notes:
Always use sellable type waterstop primer to avoid displacement of the
swellable type waterstop tape during concrete pouring. It may be necessary to
utilize masonry nails or other mechanical means to hold the sealant in place
on vertical surfaces.
Page 45 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Place swellable type water stop tape so that it is not closer than 5 cm away
from the outer surface of poured structure. If a Keyway is utilized, place the
swellable type water stop tape into the bottom of the formed Keyway area.
10.11.7 Precaution / Special Consideration: Always use swellable type water stop
primer to ensure tight adhesion and to aid in preventing swellable type water
stop tape from moving during the concrete pour. For vertical surfaces, nails
may be used to hold the product in place in conjunction with swellable type
water stop primer. Swellable type water stop tape shall be used at a minimum
depth of 50 mm inside the concrete. When used on pipes and other structural
penetrations, swellable type water stop tape shall be cut to measured length
and placed around the penetration with ends butted. In all cases, swellable
type water stop tape shall be in direct contact with the substrate along the
entire length of the installation. Swellable type water stop tape is not an
expansion joint sealant and only suitable for non-moving concrete joints.
Swellable type water stop tape should not be installed in standing water or on
frozen or icy surfaces.
10.11.8 Storage / Shelf Life: When stored in a dry enclosed area off the ground at a
minimum temperature of 45°F (7°C) in unopened, undamaged cartons, its
shelf life is unlimited.
10.12 Water proofing by Nano Technology (CPWD DSR 2018: Item No. 26.59 -
26.60):
Nanotechnology, shortened to “Nanotech”, is the study of the controlling of
matter on an atomic and molecular scale. Generally, Nanotechnology deals
with structures of the size 100 nanometers or smaller in at least one dimension,
and involves developing materials within that size. Nanotechnology is very
diverse approach based upon molecular self assembly, from developing new
materials with dimensions on the nanoscale to investigating whether we can
directly control matter on the atomic scale. Any technology based on particles
size less than 10 ηm is considered Nano Technology. Molecule of modern
nanotechnology based water proofing compounds, when dissolved in solvent
has estimated size of 5-6 ηm.
Polymers contain many thousands of monomers attached with each other and
form a long chain molecule. These polymers form clusters in a solution or
emulsion. When this polymers form a film on the substrate surface, polymer
molecular clusters are forced to adhere to the surface. Then polymers further
undergo shear stress because of exposed heat and moisture. As a result, the
cohesive forces are weakened. Additionally, Polymers are visco-elastic i.e.
they always move to attain thermodynamically stable format. Under these
circumstances, molecular bonds are weakened and UV, a high energy source,
can attack the polymer network to form free radicals. Free radicals are reactive
centers on the molecule and can easily react with oxygen (oxidation),
Page 46 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
ASTM D 6489 regarding Concrete water penetration Less than 15% after 24
& 48 Hours
ASTM G 154 regarding Accelerated Weathering Less than 5% Loss after
2000 hours
Page 47 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 48 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
joined to a beam. This allows a crack to form along a straight line within the
joint since the thin section provides a path with less resistance than a thicker
section. These micro cracks are normally 0.1 to 0.2 mm width and 2-3 mm
deep. Nanotechnology based hydrophobic water proofing compound
penetrates inside the concrete structures and protect it from water infiltration.
Vertical Surfaces:
Pressure washing (min. 1400 psi) followed by drying.
Chemical cleaners may be used to remove and/ or neutralize surface
contamination.
Remove all traces of dirt, efflorescence, mold, mildew, grease, oil, asphalt,
laitance, curing compounds, paint, coatings or any other surface contaminant.
Repair all visible cracks greater than 1/32 of an inch.
Insure all caulking or sealants have formed a heavy skin prior to application of
nanotechnology based water proofing compounds.
Horizontal Surface
Pressure washing (minimum 1400 psi) followed by drying or shot blasting prior
to application is suggested. Preparation should include all surfaces to be
Page 49 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
10.12.5 Application: Applications requiring a warranty require approval and sign off of
a product representative prior to application. Safety instructions on the
container and the information manual/sheet prior to the application should be
read carefully.
a) Diluted sealer is applied by low pressure pump up airless spray (15-20 psi)
b) Insure that all windows and metal trim have been cleaned during the cleaning
process. The sealer will not react with metal or glass, but will react with dirt
making removal more difficult.
c) Cover or pre-wet with clean water any vegetation to reduce the chances of
temporary browning. Check if the active ingredient is toxic.
d) Cover or pre-wet asphalt to avoid any asphalt residue from leaching out and
staining adjacent surfaces.
e) On horizontal surfaces, apply enough material to flood the surface. Move
around any material which has not penetrated the surface after 5-10 seconds.
Keep traffic off the surface until the sealer has dried.
f) On vertical surfaces, work from the bottom up. Saturate the surface with the
sealer; run downs are not required as with other sealers.
g) After the surfaces have dried, rinse off any over spray on windows or metal
trim with water. If the windows or metal trim were not cleaned prior to the
application of the sealer, warm soapy water will be required.
Page 50 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Treat the cold Joint Vertical surface of PCC/RCC with one coat of diluted
waterproofing solution.
Pour concrete mix for the first 100mm of the cold joint. Use mechanical vibrator
for compaction followed by wet–on-wet pouring of design specified concrete.
This reduces water breakout from the cold joint.
Grade slab should be cured completely and dried before treatment.
Prepare the surface by removing loose particles, laitance, dust and dirt by
manual cleaning and water jet cleaning. Dry the surface.
Apply diluted waterproofing solution on the grade slab by flooding procedure.
Test the dry surface for water absorption.
Prepare the treated surface free from dirt by water spray then dry.
Apply one coat of sealant before further works like screed, concreting,
plastering as per designed specification.
11.1.1 Application Procedure: Various steps involved in this system areas under:
One part of slaked lime and two parts of burnt brick pozzolana / surkhi, by
volume, shall be mixed on a water tight platform.
This shall then be sprinkled with required quantity of water and well ground in
a mill or using mechanical grinder to obtain lime pozzolana mortar.
Page 51 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 52 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
iii) Curing :- The lime concrete after compaction shall be cured for a minimum of
10 days or until it hardens by covering with a thin layer of grass or straw which
shall be kept wet continuously.
iv) Treatment at junction of roof and parapet:- All along the junction of roof
surface with parapet wall, a strip of lime concrete fillet shall be laid and finished
smooth.
v) Finish:- In case of accessible roof, one layer of burnt clay flat terracing tiles
(according to IS:2690 Part-1 and Part-2) may be laid over a thin layer of lime
mortar. However, in the extreme condition where there is considerable
expansion and contraction, two layers of tiles may be put on the top of lime
pozzolana concrete. These tiles should be joined with non-shrinking
impervious cement mortar.
For more details, IS: 3036 – Laying Lime Concrete for Water Proofed Roof
Finish, may be referred.
i) Soil for Mud Phuska: The soil for mud phuska shall be free from gravel and
coarse sand (of particle size greater than 2mm), vegetable matter and fine
kankar particles. The soil shall also be free from harmful and efflorescent salts.
The coarse material shall not exceed 25% by mass. The plasticity index of the
soil shall be between 10- 15 percent. Generally soil suitable for brick making
is suitable for mud-phuska.
ii) Soil for Mud Plaster and Mud Mortar: The soil shall be free from vegetable
roots, gravel and coarse sand of particle size greater than 2mm. The coarse
material shall not exceed 10% by mass. The soil shall also be free from harmful
and efflorescent salts. The plasticity index of the soil shall be between 10-15
percent.
iii) Mud Plaster: The mud plaster shall be prepared from soil conforming to above
ii). The dry soil shall be reduced to fine powder and mixed with water in a pit,
adding wheat straw 6% by mass and cow dung 12% by mass. The mixture
shall be allowed to rot for a period of not less than 7 days. During this period,
it shall be pugged manually using spades, if necessary, to get a homogeneous
mass free from lumps and clods. The consistency of the mortar shall be
adjusted by taking it in a trowel and observing how it slides off the face of
trowel. The mortar shall readily slide off, but at the same time shall not be so
wet as to part into large drops before falling. Alternatively, slump test may be
Page 53 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
performed in accordance with the procedure laid down in IS: 1199. The slump
should be about 70mm.
iv) Mud Mortar: Mud mortar, used as bedding under brick tile layer, shall be
prepared in the same manner as mud plaster but without any addition of fibrous
reinforcing material and binding material. The mud mortar may be used
immediately without any rotting period.
v) Brick Tiles: These shall conform to the requirements given in IS: 2690 (Part-
1) or IS: 2690 (Part-II).
11.2.2 Application Procedure: Various steps involved in this system are as under:
ii) Cleaning of Roof Surface: The surface of roof and the part of the parapet
and gutters, drain mouths, etc. over which the water proofing treatment is to
be applied shall be thoroughly cleaned of all foreign matter, namely fungus
and dust etc. by wire brushing and dusting.
iii) Application of Bitumen over Cleaned Roof Surface: After cleaning of roof
surface, a coat of hot bitumen (Residual type bitumen 80/100) over the roof
surface shall be applied evenly over the entire surface without any gap.
Bitumen coat is extended over the vertical surfaces meeting with the slab.
Bitumen commonly used is residual type petroleum bitumen of grade 80/100
or hot cut back bitumen. Residual type bitumen is heated to a temp of not less
than 165oC and not more than 170o C. The quantity of bitumen to be spread
per 10sqm of the surface is approx. 17 kg.
Page 54 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
b) Laying:
v) Applying Mud Plaster: After laying the mud phuska, mud plaster shall be laid
to a total thickness of not less than 25mm over the surface. The plaster may
be applied in a single coat or two coats of 15mm and 10mm. After the
application, the coat of plaster shall be allowed to dry. The surface shall be
checked once more for slope and evenness with a straight edge and spirit
level and made up wherever necessary by application of the plaster.
vi) Paving with Brick Tiles: After application of mud plaster, the brick tiles shall
be laid flat on a thin layer of mud mortar. The tiles shall be laid close to each
other and the thickness of joints shall not be less than 6mm and not more than
15mm. It shall be ensured while laying tiles that mud mortar rises vertically in
joints to a height of about 15mm. The brick tile shall be allowed to dry for a
period of 24 hours before grouting the joint. After drying, the joint shall be
grouted with cement sand mortar (1:3). It shall be ensured that the joints are
completely filled by mortar. The mortar shall be allowed to set for a minimum
of 12 hours before further pointing of the joints which need to be done only if
necessary. Before pointing, the grouted joints shall be brushed clean with a
soft brush.
vii) Curing: The surface of finished roof shall be kept wet for a period of not less
than 7 days.
For more details IS: 2115 – Code of Practice for Flat Roof Finish: Mud- Phuska,
may be referred.
11.3 Integral cement based water proofing treatment with Brick Bat Coba
(CPWD Specification 2009: Item No. 22.7):
Before taking up the water proofing work the construction of parapet walls,
including finishing should be completed. Similarly, the ancillary items like
haunches, khurras, grooves to tack the fibre cloth layer, fixing up of all down
take pipes, water pipes and electric conduits etc. should be completed and no
Page 55 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
such work should be allowed on the area to be treated during the progress of
water proofing treatment or even later.
Depending upon the area of surface that has to be covered, the required
quantity of slurry should be prepared using 2.75 kg cement + water per sqm
area to be covered, taking particular care to see that only that much quantity
of slurry shall be prepared which can be used within half an hour of preparation
i.e. before the initial setting time of cement.
The prepared slurry shall be applied over the dampened surface with brushes
very carefully, including the joints between the floor slab and the parapet wall,
holes on the surfaces, joints of pipes, masonry/concrete etc.
The application of the slurry should continue upto a height of 300 mm on the
parapet wall and also in grooves. Slurry should also be applied upto a height
of 150 mm over pipe projections etc.
Page 56 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
The haunches/gola at the junction of parapet wall and the roof shall be formed
only with brick bat coba.
In case the brick bat coba is laid on the base coat immediately on initial set
there will be no necessity of applying cement slurry over the base coat before
laying the brick bat coba.
However, if the brick bat coba is to be laid on the subsequent day, cement
slurry prepared as described in clause 11.3.2 shall be applied over the top
surface of the base coat, then only the brick bat coba shall be laid.
After two days of curing of brick bat coba cement slurry prepared as per clause
11.3.2 shall be applied on the surface of brick bat coba. The application of
slurry shall be the same as described in clause 11.3.5 (i) which should cover
the haunches/gola, and the remaining small portion of parapet wall and also
inside the groove.
The consistency of the slurry should be such as to cover the desired area by
using 0.488 kg of cement per sqm of area.
On deciding the correct quantity of water required per sqm. area the required
quantity of slurry should be prepared which can be applied over the desired
surface within half an hour of mixing with 0.488 kg. of cement + 0.253 kg. water
proofing compound as per manufacturer specifications + x litres of water per
sqm. Area and the required quantity of slurry thus prepared should only be
used for first application.
The first layer shall be applied with painting brushes over the specified and
dampened area carefully including the corners, holes on the surfaces and
joints of pipes in concrete etc. and the application should continue at least upto
150 mm height of fixtures of pipes from the surface.
The surface on application shall be air cured for 4 hours.
Immediately on applying the cement slurry over the surface of the brick bat
coba and when the slurry applied is still green, the fiber glass cloth as specified
in clause 11.3.6.(ii) shall be spread evenly on the surface without any kink &
pressed to see that no air spaces exist.
The fiber glass cloth shall be taken up to a height of 300 mm on parapet walls
& tucked in the groove specially prepared at that height. 20mm thick layer of
cement plaster, without leaving any joints shall be applied with cement mortar
1:4 (1 cement: 4 coarse sand) over the entire fibre glass cloth including the
haunches/gola and the small portion on the parapet wall.
The groove in the parapet wall over the haunches shall also be filled neatly
packing the mortar firmly in the groove.
The surface of the finishing layer (protective coat) shall be neatly finished with
cement slurry prepared as per clause 11.3.2.
Page 57 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
The finished surface shall be allowed to dry for a while and then pattern of 300
mm x 300 mm groove, 8 mm deep shall be made over the entire surface.
(i) Providing and Laying of Cement Slurry - The procedure to prepare and
apply the cement slurry shall be same as detailed in clause 11.3.5.(i) except
that over projected pipes etc. slurry shall be applied just upto 100 mm height
instead of 150 mm height. The slurry shall be applied upto a height of 300 mm
on parapet walls and in the groove where the fibre glass cloth is to be tucked.
The fibre glass cloth shall be of approved brand and shall be thin, flexible
uniformly bonded mat composed of chemically resistant borosilicate glass fibre
distributed in random open porous structure bonded together with a
thermosetting resin.
Immediately on applying the slurry on a sufficiently workable area as detailed
above in clause 11.3.6.(i) when the slurry applied is still green the fibre glass
as specified shall be spread evenly on the surface without any kink and
pressed in such a way that no air spaces exist.
The fibre glass cloth shall be taken upto a height of 30 cm on parapet walls
and tucked in the groove specially prepared at that height.
A minimum overlap of 100 mm width shall be provided when the fibre cloth has
to be joined. The joining of 100 mm overlap shall be done with the same slurry
used for the application on surface as first layer.
The fibre cloth shall also be extended upto a height of 100 mm over pipes
projecting from the surface.
11.3.7 Curing and Testing the Treatment: The entire surface thus treated shall be
flooded with water by making kiaries with weak cement mortar, for a minimum
period of two weeks.
Fig. 9
Page 58 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
11.4 Water proofing Treatment with Bitumen Felt (CPWD DSR 2018: Item no.
22.8-22.11& Specification 2009 Vol.-2: Item No. 22.8):
Water proofing treatment with self-finished felt shall be four courses or six
courses as described in the item. Four course water proofing treatment with
self-finished felt is a normal duty treatment suitable for buildings where the cost
of roof treatment is required to be restricted.
Six course water proofing treatment with self-finished felt is a heavy duty
treatment suitable for important structures.
11.4.1 Materials
1. Self finished felt (Appendix A and B) shall conform to the type and grade given
in the description of the item. This shall be one of the following types:
(i) Type 3 grade 1 hessian base felt conforming in all respects to IS 1322.
(ii) Type 2 grade 1 fibre base bitumen felt conforming to IS 1322.
(iii) Type 2 grade 2 glass fibre base felt conforming in all respects to IS 7193.
3. Stone Grit and Pea- sized Gravel: Stone grit shall be 6 mm and down size.
Where pea sized gravel is used it shall be hard, round and free from dust, dirt
etc. The stone grit or pea-sized gravel shall not be spread over vertical and
sloping faces of flashings and at drain mouths. At these places the surface
shall be painted with two coats of bituminous solution.
Page 59 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
The quantity of stone grit or pea-sized gravel required for the final course of
four or six course treatment with hessian base self finished bitumen felt type 3
grade 1 shall be 6 cubic decimetre/ sqm.
a. The surface to be treated shall have a minimum slope of 1 in 120. This grading
shall be carried out with cement concrete or cement plaster with coarse sand,
as per direction of Engineer-in charge, to the average thickness required and
finished smooth. Such grading shall be paid for separately.
b. Junctions between the roof and vertical faces of parapet walls, chimneys etc.
shall be cased by running triangular fillets 7.5 x 7.5 cm size, in cement
concrete. At the drain mouths, the fillets shall be suitably cut back and rounded
off for easy application of water proofing treatment and easy flow of water.
Cement concrete where used shall be 1:2:4 mix (1 cement: 2 coarse sand: 4
graded stone aggregate 20 mm nominal size). The provision of fillets shall be
deemed to be covered by the item of water proofing and shall not be measured
or paid for separately.
c. In existing roof where gola and drip course are provided at the junction of roof
and vertical face of parapet wall, chimney stacks etc., these shall be dressed
suitably and finished smooth so as to ensure an easy and gradual turning of
the flashing. Any dismantlement or forming and finishing smooth the junction
for forming the base of the flashing shall not be measured or paid for separately
and shall be deemed to form part of the preparation of the surface in the water
proofing treatment.
d. While the grading of roof surface is being done, it shall be ensured that the
outlet drain pipe have been fixed and mouth at the entrance have been eased
and rounded off properly for easy flow of water.
e. When any pipe passes through the roof to be treated, angular fillet of shape
shown in Fig. 10 shall be built around it for the water proofing treatment to be
taken over it. These fillets shall not be measured or paid for separately.
f. For carrying over and tucking in the water proofing felts into the parapet walls,
chimney stacks etc. a horizontal groove 6.5 cm deep, 7.5 cm wide section with
its lower edge at not less than 15 cm above the graded roof surface shall be
left on the inner face of the same during construction if possible. When such
groove has not been left, the same shall be cut out neatly and the base at rear
of the groove shall be finished smooth with cement plaster 1:4 (1 cement: 4
coarse sand). Such cutting of the groove and its finishing smooth shall be
deemed to be part of the water proofing item and shall not be measured or
paid for separately. No deduction shall be made either for not making the
groove or when the later has already been left in the masonry by the
construction agency.
Page 60 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
g. Tucking in the water proofing felt will be required where the parapet wall
exceeds 45 cm in the height from the graded surface. Where the height is 45
cm or less, no groove will be required as the water proofing treatment will be
carried over the top of the parapet wall to its full thickness. In the case of low
dividing walls of height 30 cm or less, outlets therein shall be cut open for full
height and the bottom and sides shall be rendered smooth and corners
rounded and such treatment shall not be measured and paid for separately.
h. Where expansion joints are left in the slab, the provision of dwarf walls and/or
RCC slabs for covering them and finishing the surface smooth shall be the
responsibility of the construction agency, which had laid the roof slab and will
not be included the operation of water proofing.
i. The graded surface of the roof and concrete fillets and the faces of walls shall
be thoroughly cleaned with wire brushes and all loose scales etc. removed.
The surface shall then be dusted off. Any crack in the roof shall be cut to ‘V’
section, cleaned and filled up flush with cement mortar slurry 1:4 (1 cement: 4
coarse sand) or blown type petroleum bitumen of IS grade 85/25, or approved
quality conforming to IS 702. Such cleaning of the surface or treating the cracks
shall not be paid for separately.
11.4.4 Underlay
Where a floating treatment of water proofing with self finished bitumen felt is
required i.e. where water proofing treatment is required to be isolated from the
roof structure, a layer of bitumen saturated felt (underlay) shall be spread over
the roof surface and tucked into the flashing groove. No bonding material shall
be used below the underlay in order to keep the underlay free of the structure.
The adjoining strips of the underlay shall overlap to a minimum of 7.5 cm at
sides and 10 cm at ends. The overlaps shall be sealed with the same bonding
material as used for the self finished felt treatment. Unless specifically included
in the water proofing item, the underlay treatment shall be paid for separately.
The underlay shall be of type 1 saturated felt conforming to IS 1322 in all
respects and having a total minimum weight of the finished bitumen felt in dry
condition with mica dusting powder @ 6.8 kg per 10 sqm. The roll shall not be
damaged or crack on being unrolled on a fairly smooth and flat surface.
11.4.5 Treatment
a. The water proofing shall consist of a four or six course treatment, as given in
the description of the item, each layer of bonding materials, self finished
bitumen felt or stone grit or pea sized gravel being counted as a course.
Page 61 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
b. The choice of a four or six course treatment will depend on the climatic
condition, the importance of the building, the durability required, cost and other
relevant considerations.
i. Initial layer of bonding material applied hot at specified weight per unit area.
ii. 2nd layer of self finished bitumen felt conforming to the type and grade given
in the description of the item.
iii. Third layer of bonding material.
iv. Final layer of stone grit of pea sized gravel spread at specified volume of
material per unit area.
d. In a six course treatment, the first, second and third layer shall be of the same
as in the four course treatment. The fourth and fifth layer shall consist of self
finished felt and bonding material respectively. The sixth layer shall consist of
stone grit or pea sized gravel.
e. The primer or underlay where required to be provided shall not count against
the number of courses specified.
11.4.6 Laying
(i) Blown type petroleum bitumen of IS grade 85/25 or 90/15 - 180 degree C.
(ii) Residual type petroleum bitumen of penetration 30/40 - 180 degree to 190
degree C (IS grade S35).
b. Drain outlets shall be given a four or six course treatment as specified for the
roof in the description of the item in the manner specified for the flat roof
surface. Water proofing treatment shall be carried into the drain pipe or outlets
by at least 10 cm. The water proofing treatment laid on the roof surface shall
overlap the upper edge of the water proofing treatment in the drain outlets by
at least 10 cm.
c. The self finished felt shall be cut to the required length, brushed clean of
dusting material and laid out flat on the roof to eliminate curls and subsequent
stretching. The felt shall normally be laid in length at right angles to the
direction of the slope and laying shall be commenced at the lowest level and
worked upto crest. The felt shall not be laid in single piece of very long lengths
as they are likely to shrink; 6 to 8 m are suitable lengths. The roof surface shall
be cleaned and dried before the felt treatment is begun. Each length of felt
Page 62 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
shall be laid in position and rolled up for a distance of half its length. The hot
bonding material shall be poured on the roof across the full width of the rolled
felt as the latter is steadily rolled out and pressed down. The pouring shall be
so regulated that the correct weight of bonding material per unit area is spread
uniformly over the surface. Excess bonding material that gets squeezed out at
the ends shall be levelled up as laying proceeds. When the first half of the strip
of felt has been bonded to the roof, the other half shall be rolled up and then
unrolled on the hot bonding material in the same way. Subsequent strips shall
also be laid in the same manner. Each strip shall overlap the preceding one by
at least 7.5 cm at the longitudinal edges and 10 cm at the ends. All overlaps
shall be firmly bonded with hot bitumen. Streaks and trailings of bitumen near
edges of laps shall be levelled by heating the overlap with a blow lamp and
levelling down unevenness. The third layer of bonding material in the four
course treatment shall be carried out in a similar manner after the flashing has
been completed.
d. In a six course treatment the third and fourth layers of bonding material and
self finished felt shall be laid in the manner already described, taking care that
laps in the felt are staggered from those in the second layer. The fifth layer of
bonding material shall be carried out after the flashing is done (See Fig. 10).
e. High Parapet Walls, Chimney Stacks etc.: Felts shall be laid as flashings
wherever junctions of vertical and horizontal surfaces occur. Longitudinal laps
shall be 10 cm. The lower layer of flashing felt in a six course treatment shall
overlap the roof water proofing by not less than 20 cm while the upper layer
shall overlap the roofing felt by 10 cm. The minimum overlap of the flashing felt
in four course specification over the roofing felt shall be 10 cm. The flashing
shall consist of the same four or six course treatment as for the roof except
that the final course of stone grit or pea-sized gravel shall be replaced by an
application of bituminous solution of approved quality in two coats on the
vertical and sloping faces only, of the flashing. The overlap along the length of
flashing shall stagger with those in the second layer of flashing felt (in a six
course treatment and with the joints in the roof felt). The upper edge of the
flashing felt shall be well tucked into the flashing grooves in the parapet,
chimney stacks etc. to a depth of not less than 6.5 cm. Corresponding
applications of bonding material shall also be made. The flashing treatment
shall be firmly held in place in the grooves with wood edges at intervals and
the grooves shall be filled up with cement mortar 1:4 (1 cement: 4 coarse sand)
or cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate
6 mm nominal size) and surface finished smooth with the rest of the wall. The
cement work shall be cured for 7 days. When dry, the exposed plaster joints of
grooves shall be painted with bitumen and two coats of bituminous solution
shall be applied on the vertical and sloping surface of flashing (see Fig. 10).
After the top flashing felt layer has been fixed, the penultimate layer of bonding
material shall be applied over the roofing felt and the horizontal overlaps and
vertical and sloping surfaces of the flashings at the specified rate. Stone grit or
pea sized gravel shall then be spread uniformly over the hot bonding material
on the horizontal roof surface at the specified quantity per unit area and
pressed into it with a wooden roller.
Page 63 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Where parapet walls are of height 45 cm or less, bitumen felt flashings shall
be provided in the same manner as for flashings in the case of high parapet
walls except that the upper edge shall be carried upto the full height of the wall
and taken right across the top of the parapet and down on the external vertical
faces to a minimum distance of 5 cm (see Fig. 10).
Where low dividing walls or inverted beams are met with, the same shall be
covered with a four or six layer treatment as for the main roof, the latter bearing
carried down both sides of the wall and overlapping the roofing treatment as in
the case of flashing of high parapet walls (see Fig. 10). Drain outlets where
formed in the low dividing walls, shall be given water proofing treatment of the
same number of courses as specified for the flat roof surface. The bottom and
sides shall be so treated that all overlaps are in the direction of flow of drainage.
h. Expansion Joints:
Where the expansion joints are provided in the slabs, the joints and their cover
slabs shall be suitably treated with water proofing. A typical sketch of an
expansion joint with the RCC slabs on either side of the joint turned vertically
up and covered with precast RCC cover slabs as given in Fig. 10. The cover
slabs shall cover the vertical turned up dwarf walls by not less than 7.5 cm and
are provided with throatings on their underside along their length. The water
proofing treatment shall be taken up the sloping junction fillets and the vertical
faces of the walls to the underside of the cover slabs. The cover slabs are
given the water proofing treatment like the roof slabs, after the cross joints
between adjacent cover slabs are first sealed with 15 cm width of roofing felt
struck to them with bitumen. The water proofing treatment shall be carried
down the sides of the cover slabs to their full thickness. Care shall be taken to
see that overlaps if any in the roofing over the cover slabs stagger with the
joints between cover slabs. The formation of the expansion joints and provision
of cover slabs shall be the responsibility of the construction agency. The
formation of the junction fillets and the water proofing treatment of the joint and
cover slabs shall be carried out by the water proofing agency. No extra shall
be paid for the junction fillers or for the sealing of the cross joints in the cover
slab with 15 cm width of bitumen strips.
i. Pipes:
Where vertical pipe outlets are met with 7.5 x 7.5 cm fillets of lime or cement
concrete of the type and section shown in Fig. 10 shall be provided and flashing
of four or six course treatment, same as for the roofing treatment shall be laid.
The upper edge of the flashing shall be laid sloping down forward and butted
against the pipe and annular depression so formed shall be filled with hot
Page 64 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
bitumen. A circular metal collar in the shape of an inverted truncated cone shall
be fixed on the pipe to throw off the rain water clear of the flashing and this
shall be paid for separately.
j. Terrace:
Where roof surfaces are expected to be used precast cement concrete tiles or
40 mm thick cement concrete shall be laid on the water proofing treatment. In
such cases, the final course of stone grit or pea sized gravel shall not be laid
in the water proofing treatment. Suitable adjustment in the rates will be effected
for not providing the stone grit or pea sized gravel layer. Cement concrete in
situ flooring shall be laid in panel not exceeding 0.4 square metres each.
Precast tiles or in situ concrete flooring where laid shall be paid for separately
unless included in the description of the water proofing item.
Fig. 10
11.5 Water proofing using polyethylene film:
11.5.1 i) On slopped roof surface, polyethylene film can be laid. This system is
suitable for new as well as old construction. This treatment generally consists
of application of following courses:
ii) A coat of bitumen primer conforming to IS: 3384 applied to the prepared
surface at the rate of 0.3 to 0.5 kg/m2.
iii) Application of hot applied bitumen (straight run bitumen conforming to IS:73 )
at the rate of 0.70 kg/m2 minimum.
iv) Laying of polyethylene film conforming to IS: 2508 with cold cutback adhesive
in overlaps.
v) Laying of 100 gm brown kraft paper laminated in situ over the film with semi
hot layer of straight run bitumen.
vi) Application of semi hot applied bitumen at the rate of 0.7 kg/m2 dusted with
fine sand.
vii) Laying of finishing layer of tiles or Indian Patent Stones i.e. 1:2:4 cement
concrete with 10mm down aggregate or cement concrete.
Page 65 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
iii) Treatment at the junction of roof with parapet wall:- Where down water
pipes are provided to drain off the rain water, extra piece of polyethylene film
shall be provided in the opening covering the edge of the water pipe and
covered with cement plaster 1:6.
iv) Surface Finish:- After completion of treatment, roof shall be provided with any
one of the following:
a) Cement concrete flooring tiles conforming to IS: 1237;
Page 66 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
b) Burnt clay flat terracing tiles conforming to IS:2690 (Pt-1) or IS: 2690 (Pt-
2);
c) Indian Patent Stone i.e. 1:2:4 concrete 40mm thick with 10 mm down
aggregate.
For more details IS: 7290 -Recommendations for Use of Polyethylene Film for
Water Proofing of Roofs, may be referred.
11.6.1 Polymer modified cementitious slurry coatings are applied over the base
Concrete. This system can be used over new as well as old roofs. This
technique of water proofing is latest development in the field of water proofing.
Polymer imparts significant improvement in impermeability. Polymer modified
cementitious slurry have coefficient of expansion very similar to concrete
thereby it does not get cracked due to thermal variation of concrete.
Page 67 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Cracks and depression shall be filled up by fillers (cement sand mortar as per
recommendation of suppliers). Prepared surface shall be thoroughly pre-
wetted for one hour.
ii) Preparation of polymer modified cementitious slurry:- Dry blend and liquid
blend shall be mix into the desired ratio as per recommendation of supplier.
The mix shall be stirred thoroughly, until no bubbles remain in the mix. Any
lump found in mix shall be removed.
iii) First coat of polymer modified cementitious slurry shall be applied by brush on
wet cleaned surface.
iv) Subsequently, fiber glass cloth shall be laid over first coat of polymer modified
cementitious slurry.
iii) Second coat of polymer modified cementitious slurry shall be laid over fibre
glass cloth.
iv) Polymer modified cementitious brush topping shall be applied over second
coat of polymer modified coating.
viii)On brush topping, screed concrete, 1:2:4 admixed with suitable integral
waterproofing compound 25 to 40mm thick to a min. slope of 1 in 100 with
aggregate size down 10mm with maximum water cement ratio 0.45, shall be
laid. Above system may slightly differ from case to case depending upon the
instruction of supplier of water proofing system. There is no relevant Indian
standard/ other code of practice for this system. Therefore, work should be
carried out as per manufacturers'/suppliers instructions. Users are advised to
collect complete literature from manufacturer and study carefully prior to
application of treatment.
11.6.3 Since, there is no relevant Indian or any other standards available, this system
needs to be adopted carefully.
11.7.1 Method of application :- Steps involved in this water proofing system may be
as given below:
Page 68 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
11.7.2 Since there is no relevant Indian or any other standards available, this system
needs to be adopted carefully.
Concrete having proper mix design, low water – cement ratio and sound
aggregate will be impervious and needs no additives. However, resistance of
concrete to penetration of moisture can be improved by adding, chemically
active water repelling agents like soda and potash soap. These admixtures
prevent water penetration of dry concrete. So far, no established track records
are available to prove life of chemical water proofing. These products have a
tendency to become brittle and crack up due to stress in buildings, especially
the thermal stresses. These products are cement, silica or polymer based and
are specially formulated and designed to control the capillary pores. These
products not only make concrete water proof, but also help in resisting water
penetration.
Admixture used for reducing permeability of concrete are termed integral water
proofing Admixtures, while admixtures imparting the property of water
repellency are termed as damp proofing admixtures.
These admixtures are manufactured and marketed by a large number of firms.
Page 69 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
A. Hand Mixing:
With normal concrete & sand /cement mortar mix use 1kg of Waterproof
Powder to the dry mix and mix it evenly with a spade until an even color is
obtained or as instructed by manufacturer. Cure the surface as per regular
practices.
B. Machine Mixing:
With normal concrete and sand/cement mortar mixes use1kg of Water Proof
Powder for every 50kgs bag of Cement. Mix the dry materials for at least 2
minutes or as instructed by manufacturer. Add the normal measured quantity
of water and mix it evenly as usual practice to completion. Cure the surface
as per regular practices.
12.1 General:
Water proofing needs to be done not only during construction stage, but it also
may happen that existing building may experience dampness. A table to help
in analysis of reason of dampness in existing building is given below-
Visual effects Occurrence Time diagnosis
Lime efflorescence Just above floor All the time although A rising ground
more or less level height may vary with moisture by
horizontal with stained season Capillary
and damp area below
Persistent dampness One spot All the time, but may Leakage from
Dry up for a while in some pipe.
summer
Widespread Mainly on During first year after Entrapped water
efflorescence and massive building or longer, introduced during
moulds constructions there are impervious construction.
surface
Dampness On or behind In cold weather or on Condensation
widespread on cold surface sudden changes from
patches, without cold to warm humid
efflorescence but weather
often with moulds
Dampness in patches On plastered Appears when air is Condensation
with a little or no surface humid, disappears encouraged
efflorescence when air is dry. contamination with
deliquescent salts
Page 70 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
12.2 Inspection and maintenance for leaky roofs: Before taking any decision
regarding remedial measures to be adopted for leaky roofs, it is necessary that
the roofs are inspected thoroughly. The inspection should preferably be done
during rainy season. Based on the observations, future course of action should
be decided depending upon the condition of leakage in the roofs. Minor repairs
at isolated locations may be carried out immediately on dry day and
performance of repair should be observed after next rainfall. Major repairs, like
complete replacement of water proofing system, may be carried out after rainy
season prior to next monsoon.
12.3 Thorough inspection: The inspection of roof should cover all the essential
aspects, which may affect waterproofing system and may cause leakage in the
roofs. Following aspects should be specifically covered:
Page 71 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
proofing system adopted on roof, action should be taken to rectify the defect.
In case of roofs provided with bitumen felt, there may be debonding or leakage
through joints. In that case, defective locations have to be identified, cut and
removed and new layer of bitumen felt may be provided duly keeping desired
overlap length. Similarly, in other bituminous treatment, existing bituminous
layer may be removed and fresh layer may be laid. In case of roofs provided
with lime terracing with tiles, there may be depression on roof surface or loss
of cement mortar between tiles. Such defects may be rectified by fresh
pointing/ plaster. Preferably pointing should be done with non-shrink polymer
modified cement mortar. In case wetness is observed on the wall just below
the junction of roof & parapet wall, condition of fillet & drain outlets need to be
examined. Broken pipes may be replaced and fillet may be constructed again
after dismantling old fillet. Plaster on walls and coping should also be examined
and repaired, if necessary.
12.5 Course of action for roofs leaking at isolated points: Following course of
action should normally be followed for repairs of roofs leaking at isolated
points:
12.5.1 Cleaning of roof surface and openings: First of all, entire roof surface and
all the openings should be cleaned so as to ensure effective and un-obstructed
flow of rain water through the openings provided on the roofs. Weeds and any other
foreign material on roof surface should be removed. The blockage in the
openings should be cleared. It should be ensured that openings are functional.
12.5.5 Repair to joints of tiles : Condition of pointing at joints in between tiles should
be examined and wherever mortar has come out, fresh pointing in cement
mortar 1:3 should be done. After pointing curing should also be ensured.
Page 72 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
12.5.7 After taking above steps, behaviour of roof surface should be watched and if
leakage still persists, following steps have to be taken:
(a) Removal of complete top surface and repair of lime concrete: Entire top
surface which may be consisting of tiles and bitumen felts etc. should be
removed and conditions of the layer below it i.e. lime concrete/ mud plaster
should be examined. Minor cracks should be sealed with cement sand slurry
or bitumen compounds after making ‘V’ groove in case of lime concrete.
Defective concrete should be replaced by fresh lime concrete. In case of mud-
phuska, minor cracks may be filled up by bituminous compound. Decayed mud
plaster and mud- phuska should be replaced by fresh mud-phuska and mud-
plaster.
(b) Provision of adequate slope: Many of the old roofs may not have adequate
slope. For lime concrete terracing, a minimum slope of 1 in 60 is necessary.
Therefore, after removal of top surface, slope of existing roof should be
examined and if necessary, re-grading of roof surface should be carried out
using lime concrete/ cement concrete. Prior to re-grading of roof surface, level
should be marked on roof and parapet. Subsequently existing lime concrete
surface should be made rough. After that re-grading work should be taken up.
After re-grading, top surface should be made smooth using cement plaster 1:3
and surface should be cured for 7 days. Similarly, on mud-phuska roofs a slope
of 1 in 40 shall be ensured. If necessary, roof surface should be re-graded
using mud-phaska and mud plaster. After regarding, layer of mud-plaster
should be allowed to dry before relaying of top surface.
(c) Re-laying of top surface: After completion of re-grading, a layer of burnt clay
tiles should be laid. Old tiles may be used if they are in good condition. Tiles
should be laid over 20 mm cement mortar 1:3. Tiles should be joined with
impervious cement mortar.
Page 73 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 74 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
ANNEXURE
The products of manufacturers’ detailed below is based on the information
provided by firm / internet and no actual testing or trial of the product has been
carried out by this office. Details are provided only for the ease of field Engineers.
Before selecting suitable product please go through the product broacher
provided by firm. At initial stage, the product of the firm may be used as trial.
(A) DETAILS OF SOME OF THE KNOWN WATERPROOFING PRODUCTS
MANUFACTURERS (Products of other manufactures may be available in
market)
1. STP Limited:
707, Chiranjiv Tower, 43, Nehru Place
New Delhi - 110019, Delhi, India
Telephone: +(91)-(11)-46561359
Fax: +(91)-(11)-46561358
Email- info@stpltd.com, hasan@stpltd.com Sri Hasan Rizvi (Sr. VP STP Ltd.)
Page 75 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 76 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 77 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 78 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
17. Water stopper / Sika Swell A Profile Acrylic based Hydro swelling
Waterbar Water stopper
Sika Swell S2 PU Based hydro swelling liquid
Sika Waterbar h PVC based Water stopper
18. Coal Tar coating InertolPoxitar Coal tar epoxy coating for
for ETP / STP STP/ETP tanks
tanks
19. Repair mortar Sika Top 122HS, Ready-to-use repair mortar for
Sika Monotop 122R, concrete structures
Sika Monotop 122F
20. Epoxy mortar / Sikadur 31 (IN), Sikadur Epoxy based adhesive and
adhesives 41, Sikadur 43, Sikadur- mortars for repair works in
43 HE (h), Sikadur-52 concrete structures
(IN) SLV Mortar,
Sikadur 53UF Mortar,
Sikadur 31C
Page 79 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 80 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
4. Pidilite Industries,
Ramkrishna Mandir Road
Off Sir Mathuradas Vasanji Road,
Andheri (East) Mumbai - 400059 Maharashtra.
INDIA Phone: +91 22 3308 7000
Fax: +91 22 2835 7700
E-mail: pil@pidilite.com
Page 81 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 82 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
Page 83 of 84
Guideline on Waterproofing in New/Old Construction (Report No. RDSO/WKS/2015/1 Rev.-2)
References:
Page 84 of 84