Introduction To Quantity Surveying
Introduction To Quantity Surveying
Introduction To Quantity Surveying
Introduction:
He must be able to describe clearly, fully and precisely the requirement of the architect
and arrange the BOQ in such a way that the works can be quickly and accurately cost.
Must be able to write in clear technical language that will not be miss-understood
Examples
2.1.1 Cost Based Contracts
(Happens under negotiated tenders) A cost REIMBURSEMENT/ COST PLUS CONTRACTS
Here a contractor agrees that his expenditure on labour and materials will be met by the client
(thus cost reimbursed) on top of which he will charge a fee on an agreed basis, to cover his
profits and overheads
This type of contract encourages wastes and extravagancy
Main Benefits
i. Great flexibility of design changes
ii. Easy client participation
iii. Permits earlier Start of the project
iv. Low risks to the contractor
v. Full knowledge of the costs
Dis-advantages
i. The client cannot forecast the total cost of the project with high degree of certainity
ii. No incentive for the contractor to reduce costs
iii. Encourages wastes and extravagancy
iv. High caliber client management skills are required
v. Difficulty in evaluation of competitive tenders
Types
a) Cost Plus Percentage
In this type of contract, the contractor charges a certain agreed percentage on the amount spent
on the materials, labour and plants, for his profits and overheads
The major disadvantage is that the greater the cost, the higher the fee to the contractor.
Types
a) Schedule of rates
Here, expected items of work to be done are listed (without their quantities) for the contractor
to price. It is used where it is not possible to pre-determine the nature and full extent of the
proposed work. It is difficult for the contractors to price the schedule realistically in absence
of quantities. It is commonly used on repair works, agent works, etc.
b) Schedule of materials
This is alternative to the schedule of rates. Here a list of all materials to be used for the
expected works is given and the contractor attaches the price on each. The contractor may
then add a percentage of the total sum for the materials for hos labour, profit and overheads.
(Cost for running the contract)
Examples
2.2.1 Price In Advance
Under this type of contract, the contractor agrees to carry-out his obligation for the sum of
money agreed upon in advance.
The contractor is responsible for all the labour, materials, and plants. Etc. This type of contract
gives the client almost no control over the detail of methods of neither work programming nor
expenditure. The contractor bears all the risk
Types
a) Contracts based on BOQ
This is generally the soundest form of contract. It is suitable for all projects, provided all
planning and design work has been completed at tender stage.
The scheme is designed and a number of contractors are asked to submit in Lump-
sum tenders based up on the pricing and totaling of the BOQ prepared on the behalf
of the client
Standard qualitative and quantitative information enables tenders to be compared on
the price alone
Is the most common type of contract used for all major construction projects
Provides the client with good degree of control over financial aspects of the project
It does not provide for contractor participation at the design stage
The prices BOQ provides are the basis for valuation of variation
Merits
It gives a chance of tendering to a firm which wishes to do so.
Since there is no restriction, there can be no chance of favouritism.
Demerits
6|Quantity Surveying notes prepared By Mr. Zzigwa Marvin
Email:zzigwabrenda@gmail.com; Tel No 0775984782
There are a large number of tenders to evaluate hence much time and money wasted.
There is normally pressure to accept low tenders.
There is a high cost on the contractor’s side as he tenders for very many jobs and wins
nothing or only one.
There is difficult in selecting the right firm.
Merits
It’s possible to select the most competent firm.
Since tenders are few, there is time and cost saving.
Demerits
The firms are sometimes overloaded as they may be reluctant to decline some tenders at
the time they have a lot of jobs.
It breeds/ brings favoritism and corruption.
There is always reluctance to strike off incompetent firms from the list.
Newly formed firms that are competent cannot tender for the job.
There is always higher quotation than obtainable by open tendering as there is less
competition.
Merits
It is cheap to evaluate the tender.
The firms with tested results are employed.
Demerits
It’s usually expensive as a single contractor tenders.
Merits
It encourages keener prices than would project for single project.
Experience gained on the earlier project will be useful later on.
Demerit
Rapid inflation tends to curtail this type of contract
Merits
It’s time saving as no documents/ drawings are prepared.
It offers a more rational price basis for the contracts perhaps stimulate design
improvement.
Demerits
It’s hard to satisfy the test of the public accountability.
Suffers from higher cost due to lack of competition.
Merits
8|Quantity Surveying notes prepared By Mr. Zzigwa Marvin
Email:zzigwabrenda@gmail.com; Tel No 0775984782
The same as for selective tendering.
Demerits
The same as for selective tendering except leaving out of new firms.
It contains general conditions of the contract, draft contracts for work, form of bid,
technical specifications, and bill of quantities, drawings, forms of item/final certificates
invitation to bid and instructions of bidders.
This is the part of the bidding document drawn up by the architect to suppliment the
drawings which clearly describe in detailed manner.
i. The quantity and standard of materials to be used ( and where applicable the
possible supplier )
ii. Handling and treatment of materials
iii. Nature of fixing ,assembling and installation of any materials and service
iv. Quality of work manship required
v. Any other special treatment or handling of material that needs to be brought to the
attention of the contractor.
4.1.6 Drawings
Are plans, elevation, sections and large scale details of construction projects all drawn on
a suitable scales which give the dimensions of the structure to be erected .
4.1.7 Preliminaries
(As part of BOQ)
Are works or services done by the contractor on site but are not part of the main or basic
work on the site ,these works are just done to enable the main work to be executed .i.e.
supply of water for works ,storage of materials ,hoarding ,scaffolding etc.
10 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
4.2.0 Contract documents
4.2.1 Form of agreement, It is a legal document signed by both the employer and the
contractor which states that the contractor is to undertake the works in accordance with
the drawings and specifications and the client ‘contracts to pay him the contract sum in
consideration.in general it contains the essentials of an enforceable contract. For a contract,
certain conditions must be fulfilled. (This form of agreement must contain the essentials of
contract).
Essentials of contract
i. Offer and acceptance
An offer is when a contractor submits a quotation. An employer invites him to
make a proposal .when an employer selects him, and then this is acceptance.
ii. Consideration .This is something of value exchanged by hands .The
employer must undertake to pay something to; the contract sum is the
consideration to hold the contractor to build the house.
iii. The subject matter should be clear on drawings etc
iv. Parties, these must be identified ,name of contractor ,name of company
,employer etc
Contract drawings
1. These contracts the subject matter
2. Parties
3. Consideration contract sum
11 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
4.2.4 Bills of Quantities
Tendering on the same basis
Valuations
Valuing variation
The contract will also use the BOQ for their future activities to aviod gender
bids
4.2.5 Drawings
Drawings are plans evaluation sections and large scale details of the construction projects
all drawn on suitable scale which give the dimension of the structure to be selected
Its use is that it depicts what is to be done ,scope plus details
Estimations use the drawings to see the shape of the structure ,the extent and
characteristics
A contractor bases on drawings tos build his bills of quantities
It Is Record Purposes
It is a form of offer; it contains things like tender ,figures ,tender period ,and
appendix
Day work
We record (resource, materials, labour and plant, per day .Therefore, a day work
section will be included in BOQ in order to get percentage over heads and profits.
Why include P.C sum is to cater for work that could appear and not easily be measured as
per the BOQ.
Why is that section included?
Reason is to get over heads
To judge its impact on over all costs of the project
12 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Sport items
Is work to be executed on site but whose extent and nature can-not be established by the
contractor unless if he visited the site, this kind of work is normally kept together under a
separate section of the BOQ, precisely headed under demolition and attention. The details
of the spot items are always obtained on site.
Other methods-to provide provisional quantities
Preamble
Several items having same characteristics
Preamble are introductory clauses entered at the head of each section or trade in BOQ
relating to matters which affect the contractor in pricing the BOQ and which ought to be
drawn to his notice. The materials and workmanship are specified.
i.e
Brick work in c.m 1.4
100mm these are items
150mm of preamble
230mm
Where work departs from CES mm e.g house, toilet, it has to be put in preamble.
13 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
This is a special type of provision sum which is met to meet or off set assets of work or
expenses which cannot be fore seen before construction begins and which may not rise at
all.
Attaining any sum has no real action therefore to the contract work at all and in practise
merely serves to reduce the total net as of any extra or more expensive work than urgently
receive this sum has to be spend under the discretion of the architect
(in short this is our contingency sum)
Money allowed for unexpected expenditure
Helps to include what had not been seen before ( by using the allowed money)
The percentage of contingency sum varies depends on the nature of work / contract
but renovation works takes a higher percentage sum
Provision sum
You realize that an item is required but its details are not available, we use our judgment
and prepare a provisional sum (item has been identified but no detail is
measured)Designer has not given enough information but work has to be done .Work is
done and we negotiate a provisional sum (this is included in section of work you are
measuring)
Attendance
General attendance
Is an item given in the BOQ for work ,that involves nominated sub contractors and is
deemed to include such item as use of elected scaffoldings, mess rooms ,welfare facilities
like water and lighting ,storage of materials and any other items of general nature.
Alternative is shown on the PS sum of the nominated sub-contractor in addition to
contractor’s profits.
Special attendance
Is an item like the above but for items which are not too general, like provision of power
,provision of special scaffoldings, use of contractor’s labour for offloading and any other
items of similar nature
Fluctuations
Are price changes in the cost of materials, labour, fuel or even taxes ,compared to the
original basic prices at the time of preparing the BOQ
Contractual requirement
These are already covered by the contractor and must comply with them, you must know
the nature of contract you want to undertake, and they should be adhered to because they
are in contract conditions.
Specified requirements
These items are not required by contractors. If an employer needs them ,he tells the
contractors / bidders that he needs them and they price / include them e.g fencing, good
hoarding ,a special officer for an Engineer, etc
Adjustment items
Here a tenderer prepares a quotation and puts in BOQ ,he adds items e.g day work etc and
gets the total to date .He wishes to adjust on the tender figures, he gives a discount.
Vat 5 million (deducted or added)
Adjustment 12,000/=
Item
(Provides space where tenderer can adjust)
Total paid 4,880,000
2. Valuing variations , if you bring a plant on site , employer does not provide
information and your work is disrupted , you have a value to claim.If you had
indicated as time related i.e if you are delayed the method of being paid will be
easily.
3. Claims of disruption of progress move easy
4. Arrange cash flow with certainity to supply
Bond
Is a sum of money which is on conditionally granted to the client by an established financial
institution on behalf of the contractor in the event of the contractor absenting from work or
incase he produces shoddy work
Letter of acceptance
Is a formal document by the client to the contractor, informing him that he has been
accepted his/her offer “bid” to execute the work for the sum of the money quoted by the
contractor in the BOQ.
16 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Date of possession of site
Is the date when the successful contractor is handed over the site by the employer (not
necessarily when he commences to work)
Commencement date
Is the date when the contractor practically starts the work, on this very day the completion
is to be calculated.
Retention fund
Retention provision is mainly made in building contracts for the retains by the employer of
a proportion of money due to the contractor on each interim certificate, this is normally
calculated as the total contractors’ claim
The objective retention is to safe guard the employer against unsatisfactory performance of
the contractor.
The retained money is released to the contractor at the expiry of the defect liability period
after ascertaining that the work is free of any defects.
17 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Defect liability period
(Maintenance period)
Is the period of time stated in the contract document, after the practical completion of
work within which the contractor is responsible for making good all the defects which may
appear, after this period, the contractor qualifies for a final certificate of completion of
work and retention fund.
Variation order, this is a written instruction by the architect to the contractor, instructing
him to alter or modify the design, quality or quantity of the works as shown up on contract
drawing as described by or referred to in the contract bills.
Interim certificate, this is a formal written due the architect to the contractor, certifying
payments on account in installments to contractor by the employer. The stages of the
construction at which payments should be made are agreed upon by the architect and the
contractor on behalf of the client so that the contractor is relieved of a heavy financial
out lay of completing the project and the client is safe guarded against poor work
quantity.
Usually the contract surveyor prepares the valuation which consists of:-
Retention fund is calculated 10% and deducted from the valuation, the amount for
the previous payments is also deducted, then the Q. surveyor will pass on this
valuation to the architect. If the architect is in agreement, he will then issue a
certificate to the client to process payments.
The fluctuation clause in the contract agreement and schedule of conditions for building
work provides for an increase in the amount due to the contractor by the employer by
the net decrease in price
Penultimate certificate
This is the certificate issued by the employer to the contractor at the practical completion
of the work .it contains the whole value of the work done properly, payments so far done to
the contractor, amount due to contractor by this certificate and the final amount due to the
contractor after the maintenance period which may be paid on the final certificate.
18 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Completion certificate
Contractor’s Estimate
Contractors need knowledge or someone with the knowledge to prepare quantities, for
such work where quantities are not provided and for purposes for cross checking, the
surveyor is the only one to do valuation.
Note the difference between the contractor ‘s estimates and the BOQ is at the former is
not as detailed as the latter ,since it is not prepared for interpretation by number of
bidders.
Clerk of work, is generally appointed by the employer and owes his contractual duties to
the employer through the architect, his/her duties include;
A. Staying on the site, takes time to inspect the materials and workmanship seeing to it
that their specification. He has the authority to reject whatever is not in
conformation with the works specifications
B. Being on site every time, he/she has an opportunity to see all work before being
covered and can thus keep records which might be required by the quantity
Surveyor in adjusting variations on the contract.
C. He keeps record of the progress of the project and he gives a weekly report to the
architect
The architect is however, not relieved of his responsibilities and duties by the action of
clerk of work.
CONTRACT RELATIONSHIP
Client; is the employer / developer of project owner, he has two main function
1. During execution of work, they supervise the activities of the contract and ensure
work is done by the contractor, are in conformity with the architect’s
specifications.
2. Values the work done by the contractor, and processes the necessary document for
the client ‘consideration and action.
3. Communicates information, requests, views, variation and other requirements
between the client and contractor.
4. Addresses and approves the materials used on site by the contractor ,issues
instructions ,drawings, specifications and other necessary data to the contractor
,when and where is required.
5. In case of disputes between the client contractor ,he impartially addresses /or
attributes between the parties
The contractor
Responsibility
1. Makes an offer to the client to execute the works( the contractor bids)
2. He signs the contract with the client
3. Under takes planning and management of the project work
4. Mobilizes labour, materials ,plants and equipment required for work
5. Carries out the work in accordance with the requirements laid out in the
contract documents
Resolving conflicts
During the execution of the contract works, several issues may arise which will affect the
progress or manner of executing the work
Such issue may lead to a “Breach of contract “by either party, which may in turn lead to
extra claim by the affected party or termination of a contract.
Some of the common issues that arise in the process of execution of the contract include
the following;
Site meetings; holding regular site meetings by stake holders is a very health way to
discuss what would have been an expensive situation.
Site inspections; regular inspections of work in progress is a key element in avoiding mis-
understanding among the stakeholders.
Site supervision; the client should have a competent site representative on site to monitor
all activities
Site diary; the contractor is always mandated to document all site activities on a day to day
basis which include: progress of work Hindrance like uncondussive weather ,strikes or
demonstrations, official visitors, inspectors must endorse in the sit diary and make
remarks on their findings.
Claims; we have two types of claims commonly found in contract works execution process
1. Contractual claims ; are claims which appear in the contract documents ,and are
documented by the concerned parties, they are therefore, catered for under the
contract
21 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
2. Ex- contractual claims; are claims which are un catered for under the contract,
they lie in the hands of the clients and the contract manager has no powers to deal
with them as his authority is limited to what is specified in the contract.
The client may consider termination of the contract in the following situation
In the eventuality of the occurrence of any of the above, the client shall notify the
contractor in writing .The contractor shall have to correct the defect within five working
days ,following the date of receipt of the written notification from the client. Failure to do
so ,the client may ,without prejudice to any other remedy .cancel the contract
22 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.0 Theory of measurement and description of construction works
Bills of quantities are usually prepared using one of the three methods, namely the
traditional method, a meth0d known as “cut and shuffle” or with the aid of a computer .
In this course we shall confine our-selves in the traditional method, which comprises:
1. “Taking off”- taking dimensions from drawings and entering them, with
appropriate description on dimensions sheets.
2. “Squaring the dimension” – working out the areas, volumes etc., from dimensions
and totaling the results for each item on the dimension sheets.
3. “Abstracting”- transferring the totals and items from the dimension sheets to
abstract sheets in bill order and collecting together quantities like items so that they
may be cast to totals in readiness for billing.
4. “Billing “- Writing the draft bill from the abstract
Stages (2),(3) and (4) above are collecting known as working up”. Every calculation and
every transferred entry performed during any stage is checked by second person to
ensure there has been no arithmetical or copying errors .
23 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.2 DIMENSIONS SHEETS
Traditional dimension sheets are ruled as shown in overleaf 1. Each sheet is ruled with an
identical set of four columns each side of vertical center line.
24 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
1 2 3 4 1 2 3 4
25 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
The dimension column is used for entering the dimensions and timesing column is used for
entering any multiplication factor which applies to dimensions .The squaring column is
used for entering resultant calculated from the dimensions and their multiplication factors.
The description column is used for entering the description of the work to which the
dimensions relate. Additionally, the right hand side of description column is used to build
up dimensions; these preliminary calculations are known as “waste”. Location reference of
the work are sometimes entered on the right hand side of the description column.
Dimension sheets are used working from top to bottom of the left hand set columns and
then continuing down from top to bottom of the right hand set of columns.
Each dimension sheet should be headed with its job name, number or other code.
Completed dimension sheets should be numbered .On small jobs where one person is
taking the whole of dimensions they can be numbered consecutively as the measuring
proceeds. On larger jobs where a number of people are involved in taking dimensions , it is
prudent to number sheets consecutively as batches are issue for taking off and to keep a
running total of the sheets issued .When the completed sheets are collected a check can
then be made to ensure that all sheets are accounted for
Spoiled and misused sheets should be retained until this check is complete. if necessary the
collected dimension sheets should be re-arranged into a convenient order for future
reference during re-measurements and re-numbered consecutively before abstracting
starts. On jobs with large number of sheets index to dimensions is useful.
The dimensions for lengths, areas and volumes are entered in the dimension column to
two places of decimals.
Waste collections should be made using the dimensions given on the drawings.
Rounding off to two places of decimals for the transfer to the dimension column should be
left until the waste is collected total.
Dimensions are set down under each other in the dimension column with a line drawn
beneath, as shown. A single dimension with a line beneath indicates that it is a linear
dimension .Two dimensions with a line beneath indicate a set of two dimensions from
which the area of surface is to be calculated. Three dimensions with a line beneath indicate
a set of dimensions from which the volume of solid is to be calculated .
Numbers for numbered items are entered in the centre of the dimension column with a line
beneath.
26 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Within each of the dimensions, the dimensions are set down in order of (1) length, (2)
width and (3) depth or height. This order should always be used.
6.00 Length
3.00 Width
0.40 Depth or height
5.5 “Timesing”
Timesing is effected by entering the required number followed by an olblique stroke. The
conention 2/means multiply by 2. The convention 2/2 means 2 x 2 and so on .The
conventions are illustrated below.
2/ 1.00
3.00
2/2/ 2.00
4.00
27 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Decimal fractions are not used in timesing column because the decimal point may be
mistaken for the “dotting on” symbol. They are expressed as equivalent vulgar fractions.
The line between the numerator and demoninator of the vulgar fractions should be
horizontal, to prevent it being mistaken for obligue timesing stroke as illustrated.
When repeating dimensions, which have been timesed, previously it may be found that
they cannot be multiplied and it is required to add. In this circumistances resort is made
to what is called “dotting on”.A dot in the timesing column is used in place of the
conventional plus sign to indicate an addition to multiplying factor previously entered
the conventional is illustrated below; i.e. This indicates that the cubic measurement is
two be multiplied by (2+3)
2.
3/ 10.00 Plain concrete good
5.00 15 in fdns
0.50
Locational differences given at the right hand side of the description column should be used
whenever possible.
28 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.8 Deductions
When surface or solids are perforated by opening or their outline is indented ,it is convenient to
first over measure by assuming either that they are un perforated or that they are regular outline
,as the case may be ,and to follow with deductions to adjust for the openings or indents.in such
cases the symbol”Ddt” is added as a prefix to the item description attached to dimensions which
are to be deducted .See worked example below ;
3.00
6.00 Ddt Ditto
When one more than one set of dimensions relate to the same item description, the dimensions are
bracketed as shown above.
When the same dimensions apply to more than one item description, ampersand inserted centrally
to the description column before each succeeding description after the first, signifies that the same
dimensions apply to each of the items. see below;
29 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.11 Abbreviations
Abbreviations are used when writing description, during taking off and abstracting
There is no standard dictionary of abbreviations for civil engineering or building work .it is
simply a matter of adopting those which are in general use in the organization in which one
works.
5.12 Abstracting
The sequence of items in taking off is not necessarily the same as that of the finished bill
.An abstract provides the facility to arrange items in bill order and to collect together the
quantities of like items .It will be found convenient in some instances to transfer items
direct from the dimensions sheets to appropriate place in the bill. The operations is
termed: billing direct “.When an abstract is used ,it will note items which are not
abstracted and which are to be billed direct. The dimension sheet will also be marked to
indicate the items or series of items noted in the abstracting for billing.
“Bills of quantities shall fully describe and accurately represent the quantity and
quality of the works to be carried out. Work, which cannot be measured, shall be
given a provisional sum. Work the extent of which is not known shall be described as
provisional or given in bills approximate quantizes.(SMM A1)”
Thus the billed descriptions are to be comprehensive and sufficient to enable the estimator
fully understand what required and to give a realistic price. All quantities must be accurate
as the information available permits, as inaccurate bills cause major problems.
It is most important that all work whose extent cannot be determined with a reasonable
degree of accuracy should be described as provisional bills of quantities and items of this
kind should be kept separate from those, which contain accurate quantities. In this way the
contractor is made aware of the uncertain nature of the quantity entered and that it will be
any work where the Architect in unable to give full details as the time of measurements.
SMM A2 emphasizes the measurements that relate to work net as fixed in position and are
to be taken to the nearest 10mm (5mm and over the regaurded as 10mm and less than
5mm shall be disregaurded ). Lengths are entered in the dimension column in metres to
two places of decimals. When billing in metres the quantity is billed to the nearest whole
unit ( whole unit ( SMM A6(a) and (b) .
Where void allowances are mentioned in standard method, as for example 0.50m2 for
rooting these shall not apply the openings or wants are within and detached from the
boundaries of measured areas (SMM, 2(b))
Bills items are generally ‘deemed to include’ .that is without the need for specific mention:
labour ,materials, including all associated costs; fixing ;use of plant ;waste materials;
square cutting, establishment and overhead charges and profit (SMM A3(b).
30 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.14 Entering dimensions
a) Spacing of items
It is essential that ample space is left between all items on the dimension sheets, which may
so that is possible to follow he dimensions easily and to enable any item have been
omitted which may have been omitted when the dimensions were first taken off ,to be
subsequently inserted without cramping s the dimensions unduly . The cramping of
dimensions is a common failing among examination candidates and does cause loss of
marks.
b) ‘Waste ‘
The use of the right hand side of the description column for preliminary calculations,
buildup of lengths ,explanatory notes, location of measured work and the like should note
be over looked .All steps that have been taken in arriving at dimensions ,no matter how
elementary or trivial they appear ,should be entered in the waste section of the
description column .Following this procedure will do much to prevent doubts and
misunderstanding concerning dimensions arising at some future date .It also enables all
calculations for dimensions to be checked.
c) Order of dimensions
A constant order of entering dimensions should be maintained throughout in accordance
with SMM A.3 (a) that is (i) length ,(ii) width or breadth and (iii) height or depth ,even
although the SMM requirement strictly relates to description .In this way there can be no
doubt as to shape of the item being measured .
It will be noted that dimensions are usually recorded in meters to two places of decimals
with a dot between the meters and fractions and line drawn across the dimension column
under each set of figures.
The unit symbol mm has been omitted from all descriptions since it is considered
superfluous (unnecessary) and should not cause any confusion.
d) Adjustments for opening for voids
When measuring areas for excavation, concrete over site, brickwork, face work, and block
work, the most convenient practices is usually to measure the full area in the first instance,
and subsequently adjust for any void openings .The adjustment for the brickwork
,facework, finishings to the window and door openings are taken at the time of taking -
off the windows or doors .This is more logical and satisfactory methods of measuring and
results in smaller overall error occurring in window or door is inadvertently omitted from
dimensions.
e) Figured dimensions
When taking off ,it is most desirable to use figured dimension on the drawings in
preference to scaling since the drawings are almost invariably in the form of prints which
are not always true scale. It is sometimes necessary to build up over all dimensions from
series of figured dimensions and this work must be set down in “ waste” on the right hand
side of the description column.
31 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
5.15 Descriptions
D. General requirements
Considerable care and skill is required to frame adequate, and yet at the same time,
concise description. This is probably one of the most difficult aspects of “taking off”. Work
and one which students should take great pain to master .In addition to covering up all the
matters detailed in the SMM, the description must include all the information which the
estimator will require to build up a realistic price for the item in question.
E. Order of wording
The first few words of a description should clearly indicate the nature of the item being
described .The description is badly worded if the reader has to wait almost to the end of
description to determine the subject of the item.
F. Measurements of similar items
Where an entry of the dimension paper is followed by a similar item, the use of the word
“ditto” or” do “meaning that which has been said before, will permit the description of the
next items to be reduced considerably.
G. “Extra over” Items
When measuring certain items of work that are describes as ‘extra over’ another item of
work ,which has been previously measured ,the estimator will price the extra or additional
cost involved in the second item as compared with the first.
H. ‘Deemed to be included items ‘
The expression deemed to be included ‘ is used in the SMM to indicate that this particular
work is covered in the billed item without specific mention .Typical example is getting out
excavated materials in excavation work.
I. Preambles
‘Preambles ‘are introductory clauses entered at the head of each section or trade in bills
of quantities ,relating to matters which affect the contractor in pricing the bills of
quantities and which ought to be drawn to his notice .
J. Prime cost sums
The term ‘prime cost sum(P.C sum) is defined as a term for work or service to be executed
by a nominated sub-contractor ,a statutory authority or public under taking or for
materials or goods to be obtained from a nominated supplier.
Such sums shall be deemed to be excusive of any profit required be general contractor and
provision shall be made for ‘addition thereof .A typical example of prime cost as follows;
Provide the P.C sum of Sum 20 ,000,000
shillings 20million for
electrical installation to be
executed by a niminated sub
contractor
%
Add contractors profits
32 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Allow for general attendance
upon the sub-contractor
K. Provisonal sums
The term provisional sum is defined in the SMM as a’ sum provided for work or for costs
which can not be foreseen ,defined or detailed at the time the tendering documents are
issued .A. typical example of provisional sum is as follows .
33 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
6.0 BILLS OF QUANTITIES AND DATA IN CONSTRUCTION INDUSTRY
6.1 Purpose of bills of quantities
It will be apparent that with the increasing size and complexity of building operations ,it
would be impossible for contractor to price a medium to large sized project without bills
of quantities .For this reason it has been the practice for contractors to refrain from
tendering in competition for all but the smallest contracts without bills of quantities being
supplied.
In the absence of a bill of quantity being prepared by the building owner ,each contractor
would have to prepare his own bill of quantities in limited amount of time allowed
tendering .This places a heavy burden on each contractor and also involves him in
additional cost, which must be spread over contracts in which he is successful.
Consideration will now be given to the main purpose of a bill of quantities”
i. Enables all contrcators tendering for acontract to price on exactly the same
information with minmium effort.
ii. Allows for better comparisions of tenders
iii. Valuation for interim certificates
iv. Ordering of materials if used with caution and awareness of posible errors and
future variations
v. Cost analysis for use in future approximate estimating
vi. Reference, particularly on site during construction
vii. Planning and process by contractors site planner
viii. Final accounting
ix. Quality by reference technical specifications
x. Domestic sub-contractors quotations
xi. Cost information
6.2 Formats of bills of quantities
6.2.1 Work section format
In this format the items are arranged under their respective work sections. The work
section are normally classified as follows:
a) Excavation
b) Concrete work
c) Brick work and block work
d) Asphalt
e) Roofing
f) Woodwork
g) Structural steel work
h) Metalwork
i) Plumbing and mechanical engineering installations
j) Electrical installations
k) Floor, wall and ceiling finishes
l) Glazing
m) Painting and decorating
n) Drainage and trenches
o) Fencing
34 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
6.2.3 Elemental bills formats
In this format the works are grouped not in work section order but according to their
positions in building .Hence Excavation and earth work ,concrete work and brick work
and block work rare replaced by bills heading as sub structures ,External walls ,internal
walls and floors. Within each element work may be billed in trade order or grouped pm
building sequence .
A typical element list for multi-story building as follows:
1) Substructure
2) Frame
3) Upper floors
4) Roofing
5) Stairs
6) External walls
7) Windows and external partitions
8) Internal doors
9) Internal finishings
10)Fittings
11)Plumbing and mechanical engineering installation
12)Electrical engineering
Merits
Secures more precise tendering by making the location of the work more readily
identifiable
Makes the work of cost plannings and cost analysis much easier
Demerits
An estimator has to collect like items in all elements to be able to access the total
quantity of each materials required for the work.
6.3 Preliminary
This covers the general matters in the projects which cannot be attributed to specific part
of the work .They are therefore, priced in lump sum as opposed to the approach used for
measured work in the bills of quantities
Qualification criteria
Evaluation criteria including any regional preference of bidders
Whether bid security is required and the amount
Date of opening of bids
Period of bid validity
How to address queries during bid period
6.6 General condition of contract
There are several standard contracts that are use today.The standard contracts are
published by professional Associations such as the East African Institute of Architects
(EAIA), FIDIC etc as well as World Bank, African Development bank and European Union.
36 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
The contract chosen for a project will therefore, depend on the financier and the nature of
the project.
SMM for East Africa Published by the Architectural Association of Kenya (Quantity
Surveying Chapter) forms the basis for measurement of building works in Uganda and the
whole of East Africa Region
37 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Sub Module 2 Foundations for storied buildings:
Oversite strip,
Excavations, planking, strutting
Concrete in pad foundation, strip foundation & ground beam
Plinth wall, Hardcore, DPC concrete floor bed
General Rules
a) Work shall be measured not as fixed in position and each measurement shall be taken to
the nearest 10mm. this rule shall apply to any dimensions stated in the description
b) Where scaling is to be used, a check should be made to ensure that the dimensions are
accurate to scale as some reproduction methods affect the Scale
Original surface
Used especially where we have to excavate two different levels e.g. retaining wall, Original
surface is the ground surface where excavations start from.
Final surface
Is ground surface where excavation is to stop.
Excavated surface
Is approved surface to approved strata recommended by Engineer, its where a contractor
during excavation will stop and its Engineers‘s approved surface as bearing.
Topic 2
Foundations:
Taking of quantities
Oversite strip,
Excavations of foundation trenches
Concreting to foundations
Substructure for simple buildings up to including DPC and concrete floor bed
38 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Topic 3
Super Structure:
Taking of quantities,
Topic 4
Pitched roof:
Taking of quantities
Topic 5
Taking of quantities,
39 | Q u a n t i t y S u r v e y i n g n o t e s p r e p a r e d B y M r . Z z i g w a M a r v i n
Email:zzigwabrenda@gmail.com; Tel No 0775984782
Site slope 1:10 S to N