Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
Download as pdf or txt
Download as pdf or txt
You are on page 1of 40

J~Ji.-..:.

JJ J
I •a
Qatar Petroleum

STANDARDS PUBLICATION

QP SPECIFICATION
FOR MAINTENANCE WELDING
Part 1: Process Piping -(offshore)
(Formerly QP-MN-001)

DOC NO: QP- SPC - R- 010 -1

REVISION 1

OPERATIONS ENGINEERING - OFFSHORE FIELDS


I

III 1111111
I1IIIIIIIIIIIIIIIIIIIIIIIIilii 111111
INCI 141 11223

J~-.fi . II J
f I f a
Qatar Petroleum

STANDARDS PUBLICATION

QP SPECIFICATION
FOR MAINTENANCE WELDING
Part 1: Process Piping -(offshore)
(Formerly QP-MN-001)

DOC NO: Qp. SPC • R· 010 ·1

Issued as
pecification fo
811212014 1
Corporate
Implementation

Approved Corporate
By Endorsement

Doc. File No.: SPC.R.010-1R Page 1 of 39 Custodian Dept.: OE/(O)


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

TABLE OF CONTENTS

Page No.

FOREWORD

1.0 OBJECTIVE . 5

2.0 SCOPE . 5

3.0 APPLICATION . 5

4.0 POLICY . 5

5.0 TERMINOLOGY . 5
5.1 DEFINITIONS . 5
5.2 ABBREVIATIONS . 5

6.0 REFERENCE STANDARDS AND CODES . 6


6.1 INTERNATIONAL REFERENCE . 6
6.2 QP RELATED DOCUMENTS . 6

7.0 HEALTH, SAFETY AND ENVIRONMENT . 7

8.0 RESPONSIBILITIES . 7

9.0 MATERIALS . 8
9.1 GENERAL. .. 8
9.2 MARKING AND VERIFING THE MATERIAL. . 8
9.3 TRANSPORTATION, STORAGE AND HANDLlNG . 8

10.0 WELDING PROCEDURES AND WELDER QUALIFICATIONS . 9


10.1 WELDING PROCEDURES . 9
10.2 WELDER QUALIFICATIONS . 9

11.0 WELDING DESIGN AND PREPARATION FOR WELDING . 10


11.1 JOINT FIT-UP . 10
11.2 THICKNESS VARIATIONS . 10
11.3 CUTTING . 10
11.4 CLEANING . 11
11.5 ALIGNMENT . 11
11.6 PROXIMITY OF WELDS . 12

12.0 WELDING CONSUMABLES . 12


12.1 PERMISSIBLE CONSUMABLES . 12
12.2 RECEIPT AND STORAGE . 12
12.3 BAKING AND HOLDING OF ELECTRODES . 12
12.4 SHIELDING GASES . 12

13.0 WELD EXECUTION . 13


13.1 WORKMANSHIP . 13
13.2 WELDING PROCESS . 13
13.3 WELD BEAD SEQUENCE AND WEAVING . 13
13.4 SEAL WELDING . 13
13.5 SOCKET WELDING . 14

tV
Doc. File No.: SPC.R.010-1 R1 Page 2 of 39 Custodian Dept.: OE/(O)
()

QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

14.0 PREHEAT AND INTERPASS TEMPERATURE . 14


14.1 PREHEAT . 14
14.2 INTERPASS TEMPERATURE . 14
14.3 POST WELD HEAT TREATMENT .. 14

15.0 REPAIR WELDING . 15


15.1 WELDING DEFECTS . 15
15.2 REPAIR OF DEFECTIVE WELDS . 15

16.0 INSPECTION AND TESTING . 16


16.1 VISUAL INSPECTION . 16
16.2 NON DESTRUCTIVE TESTING . 17
16.3 HARDNESS TESTING . 17
16.4 HYDROSTATIC TEST .. 18

17.0 PAINTING & WRAPPING OF METAl. SURFACES . 18

18.0 QUAl.ITY REQUIREMENTS . 19

19.0 DOCUMENTATION . 19

20.0 APPENDICES . 20
20.1 APPENDIX I - RECOMMENDED WELDING CONSUMABLES
(INFORMATIVE) . 20
20.2 APPENDIX 11- PREHEAT AND HEAT TREATMENT REQUiREMENTS .. 22
20.3 APPENDIX 111- EXTENT OF NON DESTRUCTIVE TESTING .. 24
20.4 APPENDIX IV - NON DESTRUCTIVE TESTING - ACCEPTANCE
CRITERIA . 25
20.5 APPENDIX V - DIMENSIONAL TOLERANCES . 26
20.6 APPENDIX VI - POST WELD HEAT TREATMENT REQUIREMENTS FOR
SET-ON AND SET-IN NOZZLES . 27
20.7 APPENDIX VII - LOCAL HEAT TREATMENT FOR BRANCH
CONNECTIONS . 28
20.8 APPENDIX VIII- ADDITIONAL WELD DETAILS QUALIFIED BY SITE
WELDING INSTRUCTION SHEETS . 29
20.9 APPENDIX IX- GENERAL REQUIREMENTS FOR MAINTENANCE
WELDING .. 30
20.10 APPENDIX X - REGISTER OF THE RECOMMENDED SITE WELDING
PROCEDURE SPECIFICATIONS . 32
20.11 APPENDIX XI - OFFSHORE PIPING REPAIR REQUIREMENTS
(INFORMATIVE) . 34
20.12 APPENDIX XII- WELDING PROCEDURES FORMATS (WPS & PQR) .. 35

REVISION HISTORY LOG................................................................................ 39

Doc. File No.: SPC.R.010-1 R1 Page 3 of 39 Custodian Dept.: OE/(O)

¥
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

FOREWORD

This document has been developed by Operation offshore inspection Department, reviewed by
corporate Quality and Management systems Department, User Departments and endorsed by
concernedQP Managementfor use as CorporateSpecification.
This documentwill supersede QP-MN-001 procedure and serve as technical guidance for maintenance
welding - Processpiping in QP offshorefacilities.
This document is published for QP Departments/ Contractors/ Consultants utilisation. It should be
emphasised that the document is be used for QP operations wherever applicable and appropriate.

This standard,QP specificationfor maintenancewelding Part 1, Processpiping QP-SPC-R-010-1, is the


first part of series covering QP MaintenanceWelding.
Other new parts will be issued separatelyas follows:
• QP-SPC-R-010-2 QP Specificationfor MaintenancePart 2: Pipelines
• QP-SPC-R-010-3 QP Specificationfor MaintenancePart 3 : PressureVessels
• QP-SPC-R-010-4 QP Specificationfor MaintenancePart 4: Tanks
• QP-SPC-R-010-5 QP Specificationfor MaintenancePart 5 : Steel Structures

The document in its present form reflects as far as possible the current QP requirements taking into
account the known available industry practices and the applicable latest national and internationalcodes
and standards.

This document is subjected to periodical review to re-affirm its adequacy, to conform to any changes
in the corporate requirements, or to include new developments on its subject.

It is recognised that there will be cases where addenda, data sheets, or other clarifications need to be
attachedto the standard to suit a specific applicationor service environment. As such, the content of the
document shall not be changed or re-edited by any user (QP or its contractors, suppliers, agents, etc.),
but any addenda or clarifications entailing major changes shall be brought to the attention of the
Custodian Department.

The custodian of this document is Operation Engineering Offshore Field Department Therefore, all
comments views recommendations etc, on this document should be forwarded to the same and
copied to The Manager Corporate Quality and Management Systems Department.

Edition Year 2014


Copyright C aatar Petroleum. Except when expressly pennitted under these laws, no part of the information contalned In this document may be reproduced or transmitted In
any form or by any means (eledronic. mechanical. photocopying. recording. or otherwise). or used for advertising or promotional purposes. general disbibution. creating new
collective woo1<s. or for resale. without prtor wrttten permission of the publisher.

Although every reasonable effort has been made to incorporate accurate and usefUl information into this document. the copyrfght holders make no representation about the
suitability of the Informatlon therein for any purpose. It Is provided "as is" without expressed or implied warranty.

Doc. File No.: SPC.R.010-1 R1 Page 4 of 39 Custodian Dept.: OE/(O)

~
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

1.0 OBJECTIVE
This specification identifies the minimum requirements for the maintenance welding and
inspection of the process piping associated with QP offshore facilities.
2.0 SCOPE
This specification defines the minimum requirements for the maintenance welding and
inspection of the process piping associated with QP offshore facilities.
The document is not a comprehensive specification for these areas; this is covered more
adequately by another documents. It is intended to be used by competent personnel who have
the appropriate background and qualifications in welding fabrication.
It provides general and process specific requirements for welding which are based on accepted
QP and International Standards, good working practices, pre and post weld heat treatment
requirements, ~Non destructive testing acceptance criteria and the site welding instruction
sheets.
3.0 APPLICATION
This document is applicable to QP Departments! Contractors/ Consultants utilisation in all QP
offshore facilities.
4.0 POLICY
It is the corporate policy to maximize the reliability of the corporate Asset; from this point of
view, this specification has been developed to meet the corporate standards requirements and
the latest international codes and standards.
5.0 TERMINOLOGY
5.1 DEFINITIONS
Mill Test Report A certified document that permits each component to be identified
according to the original heat of material from which it was produced
and identifies the applicable material specification (including
documentation of all test results required by the material
specification).
Positive Material Any physical evaluation or test of a material to confirm that the
Identification material, which has been or will be placed into service, is consistent
(PMI) Testing with the selected or specified alloy material designated by the
owner!user. These evaluations or tests may provide either qualitative
or quantitative information that is sufficient to verify the nominal alloy
composition.
QP Engineer The appointed QP Discipline Specialist Representative under the
conditions of the Contract or by the department.
5.2 ABBREVIATIONS
DC-VE Direct Current Electrode Negative
DC+VE Direct Current Electrode Positive
GTAW Gas Tungsten Arc Welding
LPM Litres per Minute
PT Penetrant Testing

Doc. File No.: SPC.R.010-1 R1 Page 50f39 Custodian Dept.: OE/(O)

¥
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

MT Magnetic Testing
NDT Non Destructive Testing
PWHT Post Weld Heat Treatment
PQR Procedure Qualification record
RT Radiographic Testing
SAW Submerged Arc Welding
SMAW Shielded Metal Arc Welding
WPS Welding procedure specification
UT Ultrasonic Testing

6.0 REFERENCESTANDARDSAND CODES


All welding covered by the specification shall be carried out in accordance with the
requirements of QP-STD-R-002 R1 & QP-STD-R-003 R1, ASME B31.3, ASME IX and the
specific requirements of this document.
6.1 INTERNATIONAL REFERENCES
The following Standards, Codes and Specifications shall apply, as appropriate.
ASME B31.3 Process Piping (ASME Code for Pressure Piping, B31)
ASME PV SEC IX Boiler and Pressure Vessel Code - Welding, Brazing, and Fusing
Qualifications - Qualification Standard for Welding, Brazing, and
Fusing Procedures; Welders; Brazers; and Welding, Brazing, and
Fusing Operators
BPVC Section 11- Ferrous Materials Specifications (2 Volumes)
Materials-Part A
BPVC Section 11- Nonferrous Material Specifications
Materials-Part B
ASME II Part C Specifications for Welding Rods, Electrodes, and Filler Metals
BPVC Section II-Materials Part C-Specifications for Welding Rods
Electrodes and Filler Metals
ASMEV Non-destructive Examination
API 570 Piping Inspection Code: In-service Inspection, Rating, Repair, and
Alteration of Piping Systems
API RP 574 Inspection Practice for Piping Systems Components
API RP 578 Material Verification Program for New and Existing Alloy Piping
Systems
API 579-1 IASMEFFS- Fitness-For-Service
1

6.2 QP RELATED REFERENCES


QP-STD-Q-004 Corporate Standard for Quality Requirements for Projects
<..
QP-STD-R-001 QP Technical Standard for Material for Sour Service

Doc. File No.: SPC.R.010-1 R1 Page 6 of 39 Custodian Dept.: OE/(O)

#
.....__()~ QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~J-=
I , II ~a DOC. No. QP-SPC-R-010-1 Rev. 1
...:atar PetroIa.m

QP-STD-R-002 QP Standard for Fabrication, Inspection and Installation of Carbon,


Carbon-Manganese And Low Alloy Ferritic Steel Process Pipework
(Addendum To ASME B 31.3-2008)
QP-STD-R-003 QP Standard For Fabrication, Inspection And Installation of
Austenitic And 25% Cr Super Duplex Stainless Steels, Copper Base
And Nickel Base Alloys Process Pipework(Addendum To ASME B
31.3-2008)
QP-STD-R-008-1 QP Standard For Non Destructive Testing
Part 1 : Contractor/ Subcontractor Management System and
Personnel Qualification
QP-STD-R-008-2 QP Standard For Non Destructive Testing
Part 2 : Radiographic Testing
QP-SPC-L-002 QP Specification for Painting & Wrapping of Metal Surfaces
(New Construction And Maintenance)
ES-S-60 Specification for Non Destructive Testing of Welds
In the event of conflict between this document and the standards / codes referenced herein
or other purchase or contractual requirements, the most stringent requirement shall apply.
7.0 HEALTH. SAFETY AND ENVIRONMENT
7.1 The information and proceduresgiven in this document do not cover hot working conditions and
therefore shall not be used for welding on "live" equipment.
7.2 All necessary health, safety and environmental procedures shall be employed to protect
personnel and the surrounding environment during on-site and field works.
7.3 All relevant safety requirementsof QP Safety and Fire Regulationsand the Corporation's HSE
policy shall be adhered to while performing works within QP operation areas.
8.0 RESPONSIBILITIES
The parties who are involved in the piping repair processes and their roles are identified in the
Flowchart in Appendix XI, accordingly QP will decide the scope of the different parties in the
repair process and may invite contractor/contractors to conduct all or part of the repair process
according to a specific scope of work. This is very important to ensure that each party of the
repair process declare his role and the repair activities specified clearly.
The CONTRACTOR shall, as a minimum, submit the following documentation to QP for
approval at least two weeks prior to the commencement of work:
a. An Inspection and Test Plan (ITP) for fabrication, welding, installation and testing which
complies with the applicable clauses and elements of ISO 9001 standard and project
specifications, these documents shall define the structure, welding, fabrication, installation
and testing responsibilities, authority levels and internal and/or external interface
arrangements of personnel. And also shall identify the items and services to which this
specification applies the level of control and verification.
b. Fabrication, welding and installation procedures.
c. Detailed fabrication drawings including identification of material grades, weld details and
NDT requirements.
d. List of proposed welding consumables.
e. A Register of proposed welding procedures and their areas of application.

Doc. File No.: SPC.R.010-1 R1 Page 7 of 39 Custodian Dept.: OE/(O)

~
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

W~ DOC. No. QP-SPC-R-010-1 Rev. 1

f. POR'S and qualified WPS'S including those for weld repair, In accordance with this
specification for both permanent work and temporary attachments.
g. Certificates of welders and welding operators qualified in accordance with this specification.
h. Documents detailing qualifications and experience of engineers and all OA and OC
personnel.
i. Procedures for the receipt, storage, handling and issue of welding consumables.
j. Material identification (including welding consumables) and control procedures.
k. Certificates for all CONTRACTORS supplied material/equipment (including welding
consumables).
I. Procedures for Inspection, NOT, Examination and Testing, Format of the reports and
personnel qualifications.
m. Post Weld Heat Treatment procedures and instructions sheets.
n. Forming/Bending Procedures.
o. Hydrostatic Test Procedure.
9.0 MATERIALS
9.1 GENERAL
All replacement materials for service in sour environments shall conform to the requirements
of OP-STD-R-001 and as such all material certificates shall be checked for compliance with
this document and its references. If there is any doubt concerning the application of a material
then the OP Engineer shall be consulted. The new materials should be like-to-like of the old
one unless it is intentionally changed.
9.2 MARKING AND VERIFING THE MATERIAL
All pipe material, fittings, etc.., shall be fully identified against the relevant Mill Test Certificate.
The following information shall be marked on the component, where applicable as follows:-
a. Mill certificate number and,
b. Item Number,
c. Manufacturer,
d. Steel/Material Grade,
e. Heat/Cast Number,
f. Class Rating.
These identification marks shall be maintained at all times and shall be verified by the
welding/mechanical inspector. A quarantine area shall be established to hold material awaiting
proof of compliance with specified requirements.
If the existing material certificates are not available, then the material shall be subjected to wet
chemical analysis to establish the nearest material specification. If wet chemical analysis is not
possible, then it will be evaluated in accordance with API PUB 578 and also Hardness test
then compare the results with the as built drawing and the relevant materials Specification (e.g.
ASME Section" or ASTM specifications) to ensure the material Type/grade verification.
9.3 TRANSPORTATION, STORAGE AND HANDLING
The alloy materials shall be storage and handling of in a proper way that it shall not be
contaminated with carbon steel material. The storage area shall also be separated from the
carbon steel storage area. The tools used shall also be dedicated solely for the subject grade
material and were never used previously on Carbon Steel surfaces.

Doc. File No.: SPC.R.010-1 R1 Page 8 of 39 Custodian Dept.: OE/(#


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~Pitr~ DOC. No. QP-SPC-R-010-1 Rev. 1

CONTRACTOR shall adopt the colour coding system specified in QP-STD-R-001 to identify
different types of materials.
All media used for marking shall be free from sulphur, chlorides and other halogens and if the
fabricated spools are to be subjected to PWHT the media shall not contain more than 250 ppm
of copper, lead, tin or zinc. The use of adhesive tapes is not permitted.
Adequate protection against damage shall be provided for all components during any storage,
loading and transportation activities, by providing adequate timber bearers during the transport
and the wrapping of lifting points.
Pipes, completed spools or component parts shall be stored on pallets, timber blocking or other
similar supports, so as to be kept above the level of any standing water and be kept free from
dirt, grease, paint sprays and any other harmful treatments which could affect its ability to
perform its intended function.
Contractor shall segregate between ferrous and non ferrous metal & Ensure that the lay down
or storage area for alloy steels is non-metallic to prevent any carbon contamination.
NOTE: All open ends of pipes and flanges shall be protected by the use of plastic end caps
and timber blinding respectively.
CONTRACTOR shall provide adequate certified safe lifting slings or similar equipment during
handling or lifting operations, which shall be in line with QP- Corporate Lifting Regulations (QP-
REG-Q-001 R4). The use of chains for lifting is not acceptable. When pipes are lifted by their
ends, soft faced hooks shall be used.
Damage to any part of the pipework or sub-assemblies either before, during or after installation
shall immediately be brought to the notice of the Engineer.
All completed spools shall be transported by a method which does not induce significant
deformations or stresses. Care shall be taken in the suitable placement of lifting lugs and/or
temporary attachments.
Particular care shall be taken in the storage and handling of parts which have been metal
sprayed, galvanised, painted, etc., and should the coating be damaged it shall be restored to
comply with the appropriate specification.
The cutting of pipes and/or plates and transferring of marks and where pertinent, the particular
identity of the piece shall be carried out in such a manner that a particular grade of steel can
at any time be identified within a structure. If any material is found without the appropriate
reference the identity of the material shall be proven by mechanical and chemical testing.
10.0 WELDING PROCEDURES AND WELDER QUALIFICATIONS
10.1 WELDING PROCEDURES
Contractor(s) shall submit a list of approved WPSs &PQRs recommended in Appendix X and
their repair procedures.
If there is no qualified WPS that covers a specific application, then PQR shall be developed
by the contractor according to QP-STD-R-002, QP-STD-R-003 and this standard using QP
WPS & PQRs forms in Appendix XII (the approved WPSs and PQRs Will be owned by QP and
may be used within QP deferent facilities).
The weld details and dimensions shown in Appendix VIII should be adhered to, however, it is
accepted that they may vary widely in the field. If at any stage the conflict between the field
situation and this document is considered too large then the QP Engineer or consultancy
should be consulted.
10.2 WELDER QUALIFICATIONS
All QP and contractors welders proposed for maintenance/repair welding shall be qualified to
6G in accordance with QP standards QP-STD-R-002 &3 and ASME IX. Previously qualified

Doc. File No.: SPC.R.010-1 R1 Page 9 of 39 Custodian Dept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1


PItroIam

welders may be used provided that documentary evidence supporting continued qualification
is submitted to the QP rep. (According to QP-STO-R-002&3) for review and approval prior to
commencing work.
All welders and welding operators shall not qualify on production welds but shall carry out
performance tests. The weider's shall be qualified for all passes, the use of partially qualified
welder's is not be permitted
All welder and welding operator tests shall be witnessed by the QP rep. before permitted to
weld on any pipework. The decision taken by QP rep. regarding the qualification of any welder
or welding operator shall be final.
The approval of a welder on a pipe of outside diameter "0.0." shall include approval for
diameters in the following ranges:-
Th e W e Iders Qua rfi
meatiion > O'lame ter R anges
OUTSIDE DIAMETER TESTED RANGE APPROVED

0.0. s 33.4mm (NPS 1) 0.0. TO 33.4mm (NPS 1)


33.4mm < 0.0. s 73mm (NPS 2%) 0.5 x 0.0. TO2 x 0.0.
0.0. ;;::168.3mm (NPS 6) 0.0.;;::168.3mm (NPS 6)
The use of qualification tests made on plate to qualify welders and/or welding operators for
pipework is not permitted.

11.0 WELDING DESIGN AND PREPARATION FOR WELDING


11.1 JOINT FIT-UP
Poor fit-up of the joint is considered to be the most common cause of bad welds. For consistent
weld quality, the dimensions specified in the qualified WPSs should be adhered to.
Joint preparation should be optimised to avoid the following conditions:-
a. If the bevel is too narrow, lack of fusion and trapped slag may result. A thick root face or a
narrow gap can cause lack of penetration of the weld metal into the root.
b. A feather edge (thin root face) or a wide gap can cause excessive penetration. If the welder
tries to correct for this by welding faster, then lack of penetration, trapped slag, porosity
and lack of fusion may occur.
11.2 THICKNESS VARIATIONS
Abrupt changes in thickness can cause high stress concentrations. A welder cannot make a
good butt weld in pipe welded from one side if the two components are not essentially flush at
the inner or back surface of the joint. For pressure piping this problem is solved by using a 1:4
taper on the thicker member.
Seamless pipe often has significant variations in wall thickness because the 10 and 00 are
not concentric. Welding difficulties can be encountered when the thicker portion of the wall of
one pipe is matched with the thinner portion on the other. This is solved by counter boring the
pipe to give the same 10 or by trimming the thicker pipe to get an 10 match. Misalignment of
equal wall thicknesses (high-low) on pipe or plate should be held to 1.6 mm or 0.1t for
thicknesses more than 3 mm and 0.25t when thicknesses is less than 3 mm. Larger
misalignment of high-low can result not only in a severe notch or stress raiser, but also in lack
of fusion, lack of penetration and slag inclusions.
11.3 CUTTING
All weld preparations including fittings shall, wherever possible, be machined on. Where this
is not possible, the weld preparations may be thermally cut with the prior approval of QP rep.

Doc. File No.: SPC.R.010-1 R1 Page 10 of 39 Custodian Dept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1


PWoIam

If flame cutting is used the cut surface shall be dressed to remove approximately 2mm of
material from the bevel by grinding.
NOTE: Gougingis only to be usedfor the repair of defects or the preparationof the second side of
a double sidedjoint prior to welding it out.
All surfaces to be welded shall be 100% visually inspected and shall be free from burrs, tears,
cracks or any other discontinuity which would adversely affect the weld quality.
All cut edges and surfaces for a distance of 150 mm back from the weld preparation (including
the outer surface of nozzles) shall be examined by MT/PT, and for Carbon Steel, ultrasonic
examination shall be used if the thickness exceeds 6mm and the pipe is longitudinally seam
welded. Laminations are not acceptable and should a lamination type defect be detected, the
problem should be referred to QP rep. before proceeding any further work.
11.4 CLEANING
Removal of foreign materials such as rust, sand, oxide scale, oil or grease, paint and cutting
dross resulting from flame cutting or arc-air gouging is essential prior to welding. This can be
accomplished by grit blasting, grinding, degreasing or pickling.
Cleaning of the base material shall extend for at least 75 from the edge of the bevel on both
the internal and external surfaces of the parts to be welded. This area shall also be degreased
prior to welding using a suitable chloride-free and sulphide-free solvent.
Where thermal cutting is used the surface which will be incorporated into the completed joint
shall be dressed back by grinding to remove any notches and scales, the cut surface shall be
dressed to remove approximately 2mm of material from the bevel by grinding.
For alloy and stainless steel, the pipe and fitting surface shall be wire brushed using a stainless
steel wire brush for a distance of 75mm up the bore and on the outer surface. This area shall
also be degreased prior to welding using a suitable chloride free solvent.
11.5 ALIGNMENT
a. Tack Welds
All tack welding, shall be accomplished with low hydrogen processes, which shall deposit
weld metal with a diffusible hydrogen content less than 5ml per 100gm of deposited weld
metal.
Tack welds for fit-up should be kept short, approximately 13 mm to 25mm long and ground
to a feather edge in order to eliminate poor fusion and cracks. They shall be of two passes
and of sufficient cross section to prevent cracking and shall be deposited with the same
care, materials, electrodes, preheat and procedures as permanent welds.
Tack welds shall be removed completely from heavy wall pipe as they can result in
incomplete weld penetration along their length.
Where bullets are used instead of tack welds they shall be of a compatible material
approved by QP rep., shall be spaced uniformly around the circumference and shall not
be welded in the root.
b. Circumferential Welds
The maximum internal pipe diameter misalignment shall be 0.25t where 't' is less than
3mm and 1.6mm when 't' is larger than 3mm, where 't' is the pipe wall thickness.
c. Fabrication Tolerances
The dimensions of the fabricated piping shall conform to the dimensions on the piping
drawings and the tolerances shown in Figure 1.
Allowances for gasket thickness shall be as dimensioned on the drawings.
Pipe runs shall not deviate from the horizontal or vertical by more than 3mm in every
1000mm, unless otherwise specified on the drawing.

Doc. File No.: SPC.R.010-1 R1 Page 11 of 39 CustodianDept.: OE/(~


() QP SPECIFICATION FOR MAINTENANCE WELDING


~~~

11.6
Part 1: Process Piping (Offshore)

DOC. No. QP-SPC-R-010-1

PROXIMITY OF WELDS
Rev. 1

Adjacent welds shall be separated by a minimum distance between the toes of four (4) times
the nominal wall thickness of the pipe but not less than 50mm. This is in order to avoid the
lining up or the overlapping of the weld heat affected zones (HAZ) which can weaken the joints
and result in failure during service.
If unavoidable the contractor shall seek approval for the specific configuration from QP and the
area to be welded over shall be subjected to 100% surface crack detection and 100%
ultrasonic examination prior to welding. After welding the Joints, the adjacent area shall be
similarly examined.
12.0 WELDING CONSUMABLES
12.1 PERMISSIBLE CONSUMABLES
The welding consumables used for welding process piping shall comply with Appendix I.
12.2 RECEIPT AND STORAGE
All consumables shall be stored and handled in accordance with the manufacturers'
recommendations, these being the minimum requirements.
All Welding Electrodes shall be supplied in clearly identified hermetically sealed cartons of
good condition complete with a valid test certificate correlated to the consumables by the batch
numbers.
Upon completion of receipt inspection to verify the condition, quantity and type, the
consumables shall be placed in/or marked as quarantine pending release for use.
All consumables shall be stored under a controlled environment of 20·C minimum temperature
and 60% maximum humidity. The temperature and humidity shall be measured and recorded
on a weekly basis.
12.3 BAKING AND HOLDING OF ELECTRODES
Prior to use ALL low hydrogen electrodes (eg..E7016, E7018, E8018 C3, etc..) shall be baked
at 350°C for two (2) hours then placed in a holding oven maintained at 150°C or the baking
oven temperature shall be dropped to 150°C. During baking electrodes shall not be stacked
more than six (6) high.
These electrodes shall be withdrawn as required for immediate use if the holding oven is close
to the workface or sufficient electrodes for the work in hand shall be placed in a heated quiver
maintained at a minimum temperature of 75°C and carried to the workface.
All electrodes in quivers that are unused after a period of four (4) hours or at the end of the job
whichever is earlier shall be returned to the stores where the uncoated end of the electrode
shall be dipped into white paint. All electrodes so marked with white paint shall be re-baked
once in the manner prescribed above.
ELECTRODES SHALL BE ONLY BE SUBJECTED TO ONE (1) REBAKING CYCLE.
All unidentifiable, damaged, wet, rusty or otherwise contaminated consumables including any
consumables left lying about shall be removed and scrapped. Different types/makes of
electrodes must be clearly separated and identified whilst in ovens.
GTAW wire shall be withdrawn from the controlled store as and when required.
12.4 SHIELDING GASES
The shielding gas used for GTAW shall be 99.997% pure Argon. The moisture content of the
gas shall correspond to a dew point of -30°C or lower.

Doc. File No.: SPC.R.010-1 R1 Page 12 of 39 Custodian Dept.: OE/(O)

#
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

_~Pitr~ DOC. No. QP-SPC-R-010-1 Rev. 1

Only gas supplied by the manufacturer in specially marked containers shall be used. Gas purity
and quality for all containers shall be certified before use. Gases that are of questionable purity
and those in containers that show signs of damage shall not be used. All containers shall be
stored away from direct sunlight.
13.0 WELD EXECUTION
13.1 WORKMANSHIP
Arc strikes, gouges and other indications of careless workmanship can result in service failure
and should therefore be prevented.
Clean, sound weld metal shall be provided as a base for further weld metal deposition and this
may necessitate grinding.
Each run of weld metal shall be thoroughly cleaned and all slag removed prior to deposition of
the next run. The welding arc shall only be struck on the parent metal fusion faces or deposited
weld metal.
13.2 WELDING PROCESS
All pipes 2" NPS and below shall be fully welded using the GTAW process. For pipes in the
range 21/2" to 6" inclusive a GTAW root pass is preferred and a hot pass deposited by the
SMAW process using a 2.5 mm diameter electrode. All pipes greater than 6" may have the
root deposited using SMAW.
Vertical down welding shall not be used under any circumstances.
13.3 WELD BEAD SEQUENCE AND WEAVING
Controlling the deposition sequence of weld beads is a very effective method of reducing the
level of residual stresses and hardness and achieving good toughness in the welded joint. All
SMAW welding shall be performed by the stringer bead technique and the maximum bead
width for SMAW shall be:- 2.5 to 3 times the core diameter of the electrode.and for SAW -
7 times the diameter of the filler wire.
Unless specifically agreed otherwise, welding and preheat maintenance shall be a continuous
operation.
Welding shall not be interrupted nor shall a joint be lifted or transported before 50% of the
throat thickness has been deposited.
When an interruption in welding is agreed, the preheat may be removed if slow controlled
cooling of the weld area by the use of insulation blankets is ensured. In any event, the joint
shall be inspected visually and by MT/PT for linear defects prior to recommencement of
welding and full preheating shall always be re-established before welding is restarted.
13.4 SEAL WELDING
Seal welding of threaded connections and auxiliary piping associated with machinery and
instruments is required to prevent possible leaks of corrosive, flammable or toxic gases/fluids.
Seal welding is also required on structures and equipment that are located offshore or in high
moisture containing environments to protect against crevice corrosion. Seal welds are not
strength welds.
The requirement to seal weld all exposed threads is to prevent crack initiation at the root of the
thread due to equipment vibration and notch effect. Small diameter electrodes should be used
to minimise possible distortion due to the welding heat. A minimum of two weld passes should
be used to seal threaded connections in order to minimise residual stresses.
A qualified welder shall perform welding in accordance with a qualified welding procedure.

Doc. File No.: SPC.R.010-1 R1 Page 13 of 39 Custodian Dept.: OEl~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1


Qata" PItroIam

13.5 SOCKET WELDING


A common error in socket welding is failure to leave a clearance between the inserted tip of
the branch connection or pipe nipple, and the recessed surface of the sockets on headers,
valves, flanges, etc.,. This can result in service failure of the socket weld due to the large
internal stresses induced by the solidification of the weld metal and the expansion/contraction
of the components being welded. A minimum of 1.6 mm joint clearance should be allowed to
prevent socket weld failures.
Note: Installation and Welding of threaded sockets on to pipe should be avoided. Where
instrument take offs are required, then a branch fitting should be installed and welded
14.0 PREHEAT AND INTERPASS TEMPERATURE
14.1 PREHEAT
Preheating shall be carried out by electrical resistance or with gas burners specifically made
and shaped for the operation. Hand held torches shall not be used for preheating purposes
unless approved by QP.
Note: Electrical resistance pads are the preferred method of preheating.
If the scope of work involves making welded connections to existing pipework of A 106 Grade
Band A333 Grade 6 (or equivalents) then the preheat shall be in accordance with the
requirements of Appendix I of this specification.
If the welded connections are in purely new pipe then the preheat shall be as specified on the
appropriate WPS or Appendix II
The method of applying preheat shall be by either gas burner or electrical preheating elements.
If a gas burner is utilised then the heating gas shall be acetylene or propane only combined
with a suitable heating nozzle.
Welding and/or cutting nozzles shall not be used for preheating.
Preheat shall be applied and maintained over the full length of the joint and for a width of 75mm
each side of the joint for the duration of welding.
The preheat temperature shall be measured by digital thermometer or thermocouples.
Lagging shall be provided on adjacent areas, if necessary to maintain the required degree of
preheat.
14.2 INTERPASS TEMPERATURE
During welding, the interpass temperature shall not exceed the following and shall not be less
than the minimum preheat.
Material * Interpass
C & C-Mn Steels 250°C
300 Series Austenitic Stainless Steels 175°C
Nickel Base Alloys 150°C

* Interpass temperature may be vary depend on the material grade


14.3 POST WELD HEAT TREATMENT
Where post weld heat treatment is required then it shall be carried out in accordance with the
requirements of Appendix II of this specification.
LOCAL PWHT
PWHT of localised welds in piping and pipefittings is often required during repair and
maintenance are usually carried out by local methods. Precautions must be taken to avoid

Doc. File No.: SPC.R.010-1 R1 Page 14 of 39 Custodian Dept.: ~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

W~ DOC. No. QP-SPC-R-010-1 Rev. 1

damaging the part being heat-treated. Before heating, the work should be adequately
supported and free to expand.
All local PWHT shall be carried out using electrical resistance pads wrapped around the pipe.
For local PWHT, the welded joint shall be well insulated and temperature measured using
thermocouples, which shall be welded and covered effectively with putty. The temperature
shall be measured constantly on an automatic chart recorder.
The number of thermocouples used shall be as per Appendix II of this specificatiori. A
maximum temperature spread of 120°C among thermocouples is recommended during
heating and cooling above 300°C. At the heat treatment temperature, the permissible range is
usually+ 10°C.
It is advisable, where practicable, to plug off the ends to prevent drafts. Insulation should not
be removed until the metal has cooled down to about 300°C.
15.0 REPAIR WELDING
15.1 WELDING DEFECTS
A number of defects, including incomplete penetration, excessive penetration and lack of
fusion, usually occur as a result of poor joint preparation, improper bevel, root gap, root face,
etc., They can also occur as a result of poor welding technique as can undercut, burn through,
porosity and slag inclusions.
Acceptance and rejection of weld defects shall be as specified in Appendix- IV. The nature of
the service should always be considered when accepting weld defects. For example, a slight
undercut on a vibrating compressor-piping weld could be much more serious than lack of
penetration in a water line. Good judgement must be used in evaluating the seriousness of
weld defects.
15.2 REPAIR OF DEFECTIVE WELDS
A common problem in repair work is failure to remove the entire defect before making the
repair weld, resulting in a reject on post-weld NDT. The technique of defect removal should be
such as to assure that the defect has been eliminated before re-welding. This requires close
inspection.
In addition, it is common for the repair weld to be worse than the original defect. This is because
the gouged out area has an excessively wide gap and feather edges. This can be avoided by
good techniques in metal removal. If such conditions exist, however, then a three-stringer-
bead technique should be utilised. This involves the deposition of a stringer bead on each side
of the ground bevel to narrow down the gap and depositing a closing bead at the centre to
provide a sound weld.
The extent of cracks in welds or base metal shall be ascertained by the use of non-destructive
inspection. The cause of cracking shall be established prior to removal/repair and a full report
issued on the cause and the proposed corrective action.
The removal of defective areas shall be done by chipping, grinding, machining or thermal
cutting. Where any thermal process is employed the minimum preheat that would be used for
welding that material shall be applied. When thermal cutting is to be used for removing a
complete weld prior to repair, the last 6mm through the root shall be removed by mechanical
means.
The resulting excavation shall ensure complete removal of the defect, shall be of a profile
suitable for welding and shall be ground to bright metal. The removal of the defect shall be
assured by either MT or PT.

Doc. File No.: SPC.R.010-1 R1 Page 15 of 39 Custodian Dept.: o~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

Removal and repair of cracks in weld deposits or base metal shall be witnessed by a qualified
Inspector. In the event that an Inspector is not available then a suitable representative shall be
nominated by the OP Engineer.
Repair welding shall be performed in accordance with the appropriate welding procedure and
the following:-
a. The defect and 50mm of sound metal beyond each end of the crack shall be removed by
a method described above. If the diameter of the pipe is such that this is not possible then
the whole weld shall be removed and the joint re-welded using approved procedure.
b. For repairs in pipe butt welds of austenitic stainless steels and nickel alloys use the original
welding procedure. For Carbon and low alloy steel use the original welding procedure with
an increase in the preheat process by +50°C.
Subsequent to repair the repair area plus 100mm on either side shall be subjected to 100%
re-inspection by all the NOT methods prescribed for the original weld.
No weld may be repaired more than once in any particular location. If a second repair is
necessary on any area that has already been repaired. the QP Engineer shall be consulted.
The use of single pass weld repairs and the rectification of damage at any location by spot
weld deposition shall not be permitted.
All rectification, repairs and modifications shall be fully identified and documented. This shall
include detailed inspection procedures, with an accurate description of the dimensions and
locations of all defects and repairs for reference during final and/or in-service inspection.
The CONTRACTOR shall maintain an up-to-date register of all welds found to contain
unacceptable defects. Repairs performed both prior to and after PWHT shall be recorded and
the register shall be freely available for inspection by OP at any reasonable time. The register
shall include but not limited to the following information:
a. Weld identification.
b. Weld type and thickness.
c. Welding procedure number.
d. Welding process or processes.
e. Welder or welding operator.
f. Details of defect.
g. Date welded.
h. Date defect found.
i. Repair procedure.
j. Date of repair and date repair accepted by CONTRACTORlQP
k. HT records, NOT Methods / Techniques
16.0 INSPECTION AND TESTING
16.1 VISUAL INSPECTION
Visual inspection by trained and practiced personnel before, during and after welding is the
single most effective method for eliminating and minimizing weld defects and costly repairs.
16.1.1 Prior to Welding
The material should be examined for harmful surface conditions, such as seams, scale,
laminations or other defects that could cause welding problems. After the parts are assembled
in position for welding, the Inspector should check the following for conformance to the
applicable specification:
a) Joint preparation, dimensions and finish.
b) Alignment and fit-up of pieces.

Doc. File No.: SPC.R.010-1 R1 Page 16 of 39 Custodian Dept.: 7'


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

c) Cleanliness.
16.1.2 During Welding
The following items shall be thoroughly checked to assure compliance to the specification.
a. Welding process, including voltage and amperage settings, progression and speed of travel
b. Filler metal used and flux or shielding gas.
c. Preheat and interpass temperatures.
d. Welding technique.
e. Cleanliness and completeness of cleaning.
f. Distortion control.
g. Post heating temperature and time.
h. Soundness of the first layer, or root pass is most important therefore, a thorough inspection
of the root pass should be made. When root passes are known to be sound, subsequent
welding problems are minimized.

16.1.3 After the Weld is Completed


Visual inspection is used for verification of the following conditions:
a. Dimensional accuracy of the weldment.
b. Conformity to drawing requirements (weld size, contour and height of reinforcement).
c. Acceptability of welds with regard to appearance (surface roughness, weld spatter, etc.).
d. The presence of defects (unfilled craters, undercuts, overlaps and cracks).
16.2 NON DESTRUCTIVE TESTING
The type and extent of NDT is detailed in Table 5 and the required acceptance criteria in Table
6 of this document. Welds to existing members/items shall be subjected to 100% NDT.
It may, on occasion, be necessary to employ other additional NDT techniques in order to
ensure full evaluation of welds or clarification of defect indications. This shall be at the
discretion of the Inspector.
All NDT shall be carried out in accordance with OP-STD-R-002& OP-STD-R-003. ES S 60,
QP-STD-R-008-2, and ASME V.
On welds which are not subject to PWHT, NDT for acceptance purposes shall not be performed
sooner than 24 hours after weld completion unless a post weld hydrogen release treatment on
accordance with Table 2 is undertaken.
On welds which have been subjected to PWHT, NDT for acceptance purposes may be
performed immediately after PWHT has been completed and the joint has cooled to ambient
temperature.
Surfaces to be inspected shall be free from spatter and heavy oxidation or any other
contaminant, which might affect NDT interpretation.
16.3 HARDNESS TESTING
Hardness checks shall be carried out on all production welds in piping to the following extent:
a. One (1) hardness check per 10m of weld or per 10 circumferential welds, whichever, yields
the greater number of tests (minimum of one test).
b. The cap of the weld shall be removed and the surface ground smooth. Three
measurements shall be taken on the weld and HAZ and the average of the three shall be
taken as the result. Welds to existing members/items shall be subjected to 100% hardness
test.

Doc. File No.: SPC.R.010-1 R1 Page 17 of 39 Custodian Dept.: o~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

16.4 HYDROSTATIC TEST


16.4.1 Test Fluid
The test medium shall be potable water unless stated otherwise on the contract drawings or
by OP. However, The PH of the potable water shall be in the range from 6.5 to 7.5 and the
chloride content shall be 25 ppm maximum. After testing, the tested piping system shall be
dried as required by the service fluid.
16.4.2 Test Pressure
Prior to testing all equipment and piping shall be thoroughly cleaned of all dirt and construction
debris or other foreign matter using potable water. All lines shall be flushed with water prior to
testing.
Testing of the piping lines with valves in closed conditions is not permitted.
Differently rated systems shall be tested independently.
For field welds completed between "old" and "new" material, the whole line shall be hydro-
tested at 1.1 the maximum operating pressure or design pressure or top of piping class rating
pressure, take into consideration the corrosion rating and the existing pipe thickness (actual
thickness) according to API 570 clause 5.8, ASME 31.3 & Additional considerations for
pressure testing which are provided in API 574, API 579-1/ASME FFS-1 and ASME PCC-2.
In case that the specified Hydrostatic test for existing piping can not be conducted then it can
be replaced by service test.
In situations where it is impractical to hydro-test, (the reasons why shall be documented and
recorded). It shall be OP's decision to waive hydro-test.
The pressure test shall be carried out in increments of 25% total pressure value or as
designated by OP at the time of testing up to the test pressure. There will be a hold for 15
minutes at each increment. This is to ensure that the system is stabilized and to avoid over
pressurizing. The pressure shall be maintained at each incremental stage for a minimum of
two minutes or as specified by OP. Once the test pressure has been attained it shall be
maintained for a period of approximately one hour before the detailed inspection takes place.
Depressurizing of the system shall be carried out at a maximum rate 200 pSig/minute to avoid
vacuum collapse of any part of the system while draining the water after the test. However,
depressurizing shall be carried out in steps at 25% of total pressure value and there will be a
hold for 15 minutes at each step.
Check valves shall be opened to ensure that water is completely drained.
A record charts shall be made of the pressures and temperatures during pressurizing/
depressurizing as well as during actual testing.

17.0 PAINTING & WRAPPING OF METAL SURFACES


Preparation of the surface for coating and coating system and procedure shall be according to
OP specification For Painting & Wrapping of Metal Surfaces (New Construction and
Maintenance) OP-SPC-L-002.
18.0 QUALITY REQUIREMENTS
The CONTRACTOR shall have a current and implemented OA system and OC procedures for
shop and field piping fabrication, erection, etc., in compliance with the requirements of OP-
STD-O-004 and ISO 9001:2008 for all works undertaken and shall meet OP's specified
requirements.

Doc. File No.: SPC.R.010-1 R1 Page 18 of 39 Custodian


Dept.:
0#
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

Contractor shall establish and implement the required corrective and preventive actions to
mitigate any reported nonconformities or potential nonconformities. Contractor may need to
run technical investigation to establish the root cause of such nonconformities.
The CONTRACTOR shall be responsible for ensuring that the final documentation and records
provide the necessary objective evidence that the quality required has been achieved. This
shall include the results of inspections, tests, monitoring of work performance, material and
weld identification and related data such as qualifications of personnel and procedures.
The CONTRACTOR shall provide all necessary certification and documents in accordance
with this Specification's requirements or any alternative specification identified by QP.
The CONTRACTOR shall appoint only qualified and experienced personnel with the necessary
level of authority to ensure compliance with the requirements of this specification.
19.0 DOCUMENTATION
By the end of the project (the pipe repair process) the contractor shall submit the approved
Mechanical completion certificate and Quality records as per QP Standard QP-STO-Q-004.

Doc. File No.: SPC.R.010-1 R1 Page 19 of 39 CustodianDept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.0 APPENDICES
20.1 APPENDIX-I: RECOMMENDED WELDING CONSUMABLES (INFORMATIVE)
MATERIAL GRADE SMAW GTAW
Carbon Steel - Sour Service A106 Grade B E7016 ER 70 S3
API 5L Grade B E7018
A234-WPB
A105N
Low Temperature Carbon A333 Grade 6 E7016-1 ER 70 S G
Steel - Sour Service A671 Grade CC65 E7018-1
A420 -WPL6
A350 - LF2
Stainless Steel A358 -TP316L E316L-16 ER316L
A312 -TP316L
A403 - WP - 316L
A182 - F316L
Dissimilar Carbon Steel to Stainless Steel E309L - 15 ER309L
Incoloy 825 B424 ENiCrM03 ERNiCrM03
B423
B425
CuNiFe B466 ECuNi ERCuNi

Recommended Welding Consumables for Austenitic Stainless Steel

BASE METAL
SMAW GTAW
Wrought I Cast (a)
,
304 H ,, E308 H ER308
304 CF-3 E 308 L ER 308 L
304 L CF-8 E 347 ER347
304 LN
309 CH-8 E 309 L ER309
E 309 Cb
310 CK-20 E 310 ER310
310 S E 310 ER 310
E 310 Cb
316 CF-8M
316 H CF-12M E 316 L ER 316 L
316 L CF-3M
316Nb E 318
317
E 317 L ER 317 L
317 L
321 E 347 ER347
321 H
347 CF-8C E 347 ER347
347 H
348
,,
348 H ,,

Doc. File No.: SPC.R.010-1 R1 Page 20 of 39 Custodian Dept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~,rb::sS DOC. No. QP-SPC-R-010-1 Rev. 1


Qatar ParoIeIn

Recommended Welding Consumables for Nickel Base Alloys

BASE METAL SMAW GTAW


Monel Alloy 400 & R405 ENiCu-7 ERNiCu-7
Monel K500 & K502 ENiCu-7 ERNiCu-7
Inconel Alloy 600 ENiCrFe-1/ENiCrFe- ERNiCrFe-5/ErNiCr-3
3
Inconel Alloy 601 ENiCrFe-1/ENiCrFe- ERNiCrMo-3/ERNiCr-3
3/ ENiCrMo-3
Inconel Alloy 625 ENiCrMo-3 ERNiCrMo-3/ERNiCr-3
Inconel Alloy 718 & 706 - ERNiFeCr-2
Inconel Alloy )f750 - ERNiFeCr-2
Incoloy 800 & 800H ENiCrMo-3/ENiCrFe- ERNiCr-3/ErNiCrMo-3
2
Incoloy 801 & 802 ENiCrMo-3 ERNiCrMo-3
Incoloy 825 ENiCrMo-3 ErNiCrMo-3

Table 5: Recommended Welding Consumables for Copper Alloys

BASE METAL SMAW GTAW


Coppers ECu ERCu
Copper-Nickel Alloys ECuNi ERCuNi
Silicon Bronzes Brasses ECuSi ERCuSi-A
Phosphor Bronzes Brasses ECuSn-A ERCuSn-A
Phosphor Bronzes Brasses ECuSn-C ERCuSn-A
Aluminium Bronzes Brasses ECuAI-A2 ERCuA1-A2
Silicon Bronzes Manganese Bronzes
Aluminium Bronzes ECuAI-B ERCuA1-A3
Nickel-Aluminium Bronzes ECuNiA1 ERCuNiA1
Manganese-Nickel-Aluminium Bronzes ECuMnNiA1 ECuMnNiA1
Brasses Copper RBCuZn-A
Brasses Manganese Bronzes RCuZn-B
Brasses Manganese Bronzes RCuZn-C

All welding consumables shall have a recognised approval from the following classification
societies: ABS, BV, DnV, GL and LRS.

Doc. File No.: SPC.R.010-1R1 Page21 of 39 CustodianDept.: OE/~


()

QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.2 APPENDIX - II: PREHEAT AND HEAT TREATMENT REQUIREMENTS


a) Preheat and Heat Treatment Requirements for Welding involving existing Pipework of
A106 or A333 or equivalent

Preheat

Pipe Thickness (mm) t~ 19 t » 19


Minimum Preheat Temperature (GC)(1) 100 150
Post Weld Heat Treatment

Heating Rate (OC/Hr) (5) (5)


Post Weld Heat Treatment Temperature (OC)(3) 190/210 590/610
Duration of Soak (Hrs) 2 (4)
Cooling Rate (OC/Hr) (6) (6)

(1) On pipe diameter'sgreater than 10 inch, use electric resistancemats ONLY. Gas heating is
not permitted.
(2) Not necessaryif weld NOT carried out a minimumof 24 hours after welding is complete.
Otherwise, NOT may be carried out immediatelyafter post weld soak.
(3) Use electrical resistancemats.
(4) For thicknessesup to 25mm, one (1) hour minimum,thereafter2/1/2 minutes/mm.
(5) The heating rate shall be 220·C/Hr for t up to and including25mm and for t greater than
25mm, (5500/t) or 55·C/Hr whichever is the greater.
(6) The cooling rate shall be 275·C/Hr for t up to and including25mm and for t greater than
25mm, (6875/t) or 55·C/Hr whichever is the greater.
b) Preheat and Heat Treatment Requirements for Welding involving new Pipework of A106
or A333 or equivalent

Preheat

Pipe Thickness (mm) t s 25 1>25


Minimum Preheat Temperature (OC) (1) 15 100
Post Weld Heat Treatment

Pipe Thickness (mm) t s 19 1> 19

Heating Rate (OC/Hr) (2) N/A (2)

Soak Temperature (OC) (5) N/A 600 ± 10°


Duration of Soak (Hrs) N/A (4)
Cooling Rate (OC/Hr) (4) N/A (2)

(1) On pipe diameter'sgreaterthan 10 inch, use electric resistancemats ONLY. Gas heating is not
permitted.
(2) The heating rate shall be 220 °C/Hr for t up to and including25mm and for t greater than 25mm,
(5500/t) or 55 °C/Hr whichever is the greater.
(3) The cooling rate shall be 275 °C/Hr for t up to and including25mm and for t greater than 25mm,
(6875/t) or 550C/Hr whichever is the greater.
(4) Use electricalresistancemats.
(5) For thicknesses up to 25mm, one (1) hour minimum,thereafter 2/1/2 minutes/mm.

Doc. File No.: SPC.R.010-1 R1 Page 22 of 39 Custodian Dept.: #-


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

J,.fo..,.lJ,;.b:sS DOC. No. QP-SPC-R-010-1 Rev. 1


Qatar PEtroIaIn

Number and Location of Thermocouples

The No. of thermocouples used shall be as follows:-

Outside Diameter N° of Thermocouples Position


OD <40mm 1 @ 12 o'clock
50mm s OD < 250mm 2 6 & 12 o'clock
OD ~300mm 3 4, 8 & 12 o'clock

OD~300mm

Doc. File No.: SPC.R.010-1 R1 Page 23 of 39 Custodian Dept.: OE/(O)

#
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.3 APPENDIX - III: EXTENT OF NON DESTRUCTIVE TESTING


The minimum level of NDT is given below. This minimum level may by increased (at any level up to 100%) if the welds
are questionable or the NDT indicates excessive defects.

Group Service of Line Type of NOT & Percent


MT RT
A Flare Systems (LP, MP & HP)
Fuel Gas
Helifuel 100 100
Kill Fluid (2)
Propane
Sour Condensate
Sour Gas
Sour Product Instrument Lines
B Closed Drains 20 100
Fire Wat~r/Fighting (2)
Glycol
BA Cascade (H.P. Side).
C Atmospheric Vents 20 20
Corrosion Inhibitor (1)
Drinking Water
Methanol Injection
BA Cascade (L.P. Side)
D Halon System 5 5
Hot Oil (1)
Open Drains
Sanitary Effluent
Slop Oil
Utility Water
Wet Diesel Fuel

Notes

1) 20% examination means 20 welds in 100 welds which are examined 100%, similarly for 5% examination.

2) Ultrasonic examination may be specified by the EMPLOYER for thicknesses greater than 19mm.

3) Welds to existing items/equipment shall be subjected to 100% MT and RT or MT and UT.

Doc. File No.: SPC.R.010-1 R1 Page 24 of 39 Custodian Dept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.4 APPENDIX- IV: NON DESTRUCTIVE TESTING - ACCEPTANCE CRITERIA

Type of Defect Chemical Plant and Petroleum Refinery Piping


ASME B31.3: - Cyclic Conditions
Circumferential, Longitudinal and Branch Connections
Cracks Not Permitted.
Lack of Fusion Not Permitted.
Incomplete Penetration. Not Permitted.
Internal Porosity Isolated Pores
The maximum size of isolated pores shall be 1/4 t or 4.0mm,
whichever the lesser. If the separation of two isolated pores
is greater than 25.4mm then maximum size is 113 t or 6.4mm.
For t > 50.Bmm, maximum isolated pore size is 9.5mm.
Aligned Rounded Indications
Summation of the diameters < t in any 12 t (As per ASME VIII
Division 1 Appendix 4).
Slag Inclusions, Tungsten Individual Lenqth s 'Is.
Inclusions or Elongated Individual Width::; 2.4mm or t;3.
Indications.
Cumulative Lenqth s t in any 12 t of weld length.
Undercutting Not Permitted.
Surface Porosity or exposed Not Permitted.
Slag Inclusion (for t s 5mm).
Concave Root Surface Total Joint Thickness, including weld reinforcement ~ Tw
Reinforcement or Internal Fort Height
Protrusion ::;6.4mm s 1.6mm
> 6.4mm and s 12.7mm ::;3.2mm
> 12.7mm and s 25.4mm ::;4.0mm
> 25.4mm ::;4.Bmm.
Misalignment 0.25t where 't' is less than 3mm and 1.6mm when 't' is larger
than 3mm.

Tw = the nominal wall thickness of the thinner of the two components being joined together.

Doc. File No.: SPC.R.010-1 R1 Page 25 of 39 Custodian Dept.: o~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.5 APPENDIX -V: DIMENSIONAL TOLERANCES


Dimensional Tolerances

Shall conform to fit-up tolerances


qualified in Welding Procedure.

1) ± 3mm maximum from the indicated


dimensions for face to face, centre to face,
location of attachments, etc ..

2) ± 3mm maximum lateral translation of


branches or connections.

3) ± 1.5mm maximum rotation of flanges from


the indicated position measured as shown.

4) ± O.8mm out of alignment of flanges from


the indicated position measured across any
! diameter .

. ~) Tolerances on dimensions which do not


i include pipe segments are to be based on
i ANSI specifications for fittings and/or
1 4 i........flanges

Doc. File No.: SPC.R.010-1 R1 Page 26 of 39 Custodian Dept.: o~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~j\..,JJ~ DOC. No. QP-SPC-R-010-1 Rev. 1


Qatar PmoIam

20.6 APPENDIX -VI: POST WELD HEAT TREATMENT REQUIREMENTS FOR SET-ON
AND SET-IN NOZZLES

Set-On Nozzle Set-In Nozzle


PWHT if T b + tc > 38mm (NTS) or 20mm (LTS) PWHT if T h + tc > 38mm (NTS) or 20mm (LTS)

O.5Tr
O.5Tr

Set-On Nozzle + Reinforcement Set-In Nozzle + Reinforcement


x = the greater of T b + tc or Tr + tc PWHT if T h + T, + tc > 38mm (NTS) or 20mm (LTS)
PWHT if X > 38mm (NTS) or 20mm (LTS)

Tb = nominal thickness of branch.


T h = nominal thickness of header.
T, = nominal thickness of reinforcing pad or saddle.
tc = O.7T b or 6.4mm whichever the lesser
tmin = the lesser of T b or Tr.

Doc. File No.: SPC.R.010-1 R1 Page 27 of 39 Custodian Dept.: /


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.7 APPENDIX -VII : LOCAL HEAT TREATMENT FOR BRANCH CONNECTIONS

SHADED AREAS TO BE HEAT TREATED

r1 = Nominal Bore Radius of Main Pipe.

r2 = Nominal Bore Radius of Branch Pipe.

t1 = Thickness of Main Pipe.

tz = Thickness of Main Pipe.

Doc. File No.: SPC.R.010-1 R1 Page 28 of 39 Custodian


Dept.:OE,/
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

Ju..,.1l~ DOC. No. QP-SPC-R-010-1 Rev. 1


Qatir PEtroIem

20.8 APPENDIX -VIII: ADDITIONAL WELD DETAILS QUALIFIED BY SITE WELDING


INSTRUCTION SHEETS

Branch Connections (with and without reinforcing pads)

1.6mm g .J
before welding

(1) Front and Back Welds (2) Faceand Back Welds (3) Socket Welding Flange

Typical Details for Double· Welded Slip·On and Socket Welding Flange Attachment Welds

1.6mmgap (approx..)
J
Cx (min..) = 11/4t
not less than 3.2mm
before welding

Socket Weld Connection

Doc. File No.: SPC.R.010·1 R1 Page 29 of 39 CustodianDept.:OE~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

20.9 APPENDIX -IX-: GENERAL REQUIREMENTS FOR MAINTENANCE WELDING

GENERAL

a. ADHERE STRICTLY TO THE WPS content


b. ENSURE THAT THE MINIMUM PREHEAT IS APPLIED
c. CHECK THE INTERPASS TEMPERATURE BEFORE EACH PASS & WAIT FOR THE METAL TO
COOL IF ABOVE THE MAXIMUM ALLOWABLE

CLEANING

a. THE PARENT METAL SHALL BE CLEANED FOR A DISTANCE OF 150 mm FROM THE EDGE OF
THE BEVEL ON BOTH INTERNAL AND EXTERNAL SURFACES

ALIGNMENT

a. ALWAYS ENSURE THAT THE FIT UP IS WITHIN THE ALLOWABLE TOLERANCES


b. ALL TACKS WELDS SHALL BE DEPOSITED TO AN APPROVED WPS
c. ALL TACK WELDS SHALL BE 13 TO 25mm LONG, OF TWO PASSES AND GROUND TO A
FEATHER EDGE
d. IF BULLETS ARE USED INSTEAD OF TACK WELDS THEN THEY SHALL BE OF A COMPATIBLE
MATERIAL AND SHALL BE WELDED OUT OF THE ROOT.

CONSUMABLES

a. ENSURE THAT ALL LOW HYDROGEN BASIC ELECTRODES ARE BAKED AT 3500C FOR 2
HOURS AND HELD AT 1500C and as per manufacturer recommendation.
b. ALL HEATED QUIVERS SHALL BE MAINTAINED AT 750C
c. ALL ARGON SHALL BE 99.997% PURE

WELD EXECUTION

a. THE GTAW PROCESS SHALL BE USED FOR ALL PIPES 2" NPS AND LESS
b. MAXIMUM WEAVE WIDTHS FOR FERRITC ELECTRODES ARE:-
• 2.5mm = 7.5mm • 3.25mm = 12mm • 4.0mm = 12mm • 5.0mm = 15mm
c. DEPOSIT 50% OF THE WELD THROAT THICKNESS BEFORE THE JOINT IS LIFTED OR
TRANSPORTED

REPAIR WELDING

a. ALL REPAIR WELDS IN FERRITIC MATERIALS SHALL BE CARRIED OUT WITH A PREHEAT OF
+50oC ABOVE THAT USED FOR THE ORIGINAL WELD.

Doc. File No.: SPC.R.010-1 R1 Page 30 of 39 Custodian Dept.: OE/~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

HEAT TREATMENT REQUIREMENTS FOR WELDING INVOLVING NEW PIPEWORK OF A106 OR A333
PREHEAT
PIPE THICKNESS (MM) t s 25 t>25
MINIMUM PREHEAT TEMPERATURE (OC) (1) 20 100

POST WELD HEAT TREATMENT

PIPE THICKNESS (MM) t s 19 t » 19


HEATING RATE (OC/HR) (2) N/A (2)
SOAK TEMPERATURE (OC) (5) N/A 600 + 10°
DURATION OF SOAK (HRS) N/A (4)
COOLING RATE (OC/HR) (4) N/A (2)

HEAT TREATMENT REQUIREMENTS FOR WELDING INVOLVING EXISTING PIPEWORK OF A106 OR


A333

PREHEAT

PIPE THICKNESS (MM) t s 19 t » 19


MINIMUM PREHEAT TEMPERATURE (OC) (1) 100 150

POST WELD HEAT TREATMENT

PIPE THICKNESS (MM) t s 19 t » 19-


HEATING RATE (OC/HR) (2) (2) (2)
SOAK TEMPERATURE (OC) (5) 200 + 10° 600 + 10°
DURATION OF SOAK (HRS) 2 (4)
COOLING RATE (OC/HR) (4) (3) (3)

NOTES

1. ON PIPE DIAMETER'S GREATER THAN 10" (273mm) USE ELECTRIC RESISTANCE MATS
ONLY. GAS HEATING IS NOT PERMITTED.
2. THE HEATING RATE SHALL BE 2200C/HR FOR T UPTO AND INCLUDING 25mm AND FOR T
GREATER THAN 25mm, (5500/T) OR 550C/HR WHICHEVER IS THE GREATER.
3. THE COOLING RATE SHALL BE 2750C/HR FOR T UPTO AND INCLUDING 25mm AND FOR T
GREATER THAN 25mm, (6875/T) OR 550C/HR WHICHEVER IS THE GREATER.
4. USE ELECTRICAL RESISTANCE MATS.
5. FOR THICKNESSES UPTO 25mm, ONE (1) HOUR MINIMUM, THEREAFTER 2/1/2
MINUTES/mm.

Doc. File No.: SPC.R.010-1 R1 Page 31 of 39 CustodianDep~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~PElra;rn DOC. No. QP-SPC-R-010-1 Rev. 1

20.10 APPENDIX- X : REGISTER OF THE RECOMMENDED SITE WELDING


PROCEDURE SPECIFICATIONS

WPS No. & Diameter Thickness


Material Process
Test Piece Range(mm) Range(mm)
QP-WPS-P-01-1/2
25 :::;OD:::;50 1.6 to 11
Dim. 50"5.5mm
A106 Gr ..B 1 API 5l Gr..B GTAW
QP-WPS-P-01-2/2
OD<!:75 1.6 to 19
Dim. 152"9.5mm
QP-WPS-P-02 Dim.
152"9.5mm A106 Gr..B 1 API5l Gr ..B OD<!:75 1.6 to 19 GTAW/SMAW

QP-WPS-P-03 Dim. SMAW


152"9.5mm A106 Gr..B 1 API 5l Gr..B OD<!:75 1.6 to 19

QP-WPS-P-04 A 106 Gr..B 1 API 5l Gr ..B 5 to 42.88 SMAW


Dim.305"21.44mm OD<!:75
H. Treatment

QP-WPS-P-05-1/2
25 :::;OD:::;50 1.6 to 11
Dim. 50"5.5mm
A333 Gr..6 GTAW
QP-WPS-P-05-2/2
OD<!:75mm 1.6 to 19
Dim. 152"9.5mm

QP-WPS-P-06 5 to 42.88 SMAW


A333 Gr..6 OD<!:75
Dim.305"21.44mm H. Treatment

QP-WPS-P-07-1/2
25 :::;OD:::;50 1.6to 11
Dim. 50"5.5mm
A312 TP 316l GTAW
QP-WPS-P-07 -2/2
Dim. 152"9.5mm OD<!:75 1.6 to 19

QP-WPS-P-08
Dim.305"21.44mm A312 TP 316l OD<!:75 5 to 42.88 GTAW/SMAW

QP-WPS-P-09
A312 TP 316l OD<!:75 5 to 42.88 SMAW
Dim.305"21.44mm

QP-WPS-P-10-1/2
Dim. 50"5.5mm 25 :::;OD:::;50 1.6 to 11
90/10 CuNiFe GTAW
QP-WPS-P-10-2/2
OD<!:75mm 1.6 to 19
Dim. 152"9.5mm

QP-WPS-P-11 Dim. 90/10 CuNiFe GTAW/SMAW


OD<!:75mm 1.6 to 19
152"9.5mm

QP-WPS-P-12 INCOlOY 825 25:::;OD:::;50mm 1.6 to 11 GTAW


Dim. 50"5.5mm

Doc. File No.: SPC.R.010-1 R1 Page 32 of 39 Custodian DePt~)


---------------------------------------------

QP SPECIFICATION FOR MAINTENANCE WELDING


Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

WPSNo.& Diameter Thickness


Material Process
Test Piece Range(mm) Range(mm)
QP-WPS-P-13Dim. INeOlOY 825 GTAW/SMAW
152"9.5mm OD2:75mm 1.6 to 19mm

QP-WPS-P-14Dim. A106 Gr..BI API5l Gr..B to 25 SODS50mm 1.6 to 11mm GTAW


152"9.5mm A312 TP 316l
QP-WPS-P-15Dim. A106 Gr..B I API 5l Gr..B to GTAW/SMAW
152"9.5mm A312 TP 316l OD2:75mm 1.6to 19mm

Welding Procedure Diameter Qualification Ranges according to QP-5TD-R-002&3

Nominal Pipe Size Outside Diameter Thickness Range


Qualification Test Range Qualified Qualified
Less than NPS 6 0.50DtoOD As per ASME IX
Greater than or equal to NPS 6 NPS 3 and above. As per ASME IX

Doc. File No.: SPC.R.010-1 R1 Page 33 of 39 CustodianDept.:~


()


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1


Qata- P£trokun

20.11 APPENDIX -XI: OFFSHORE PIPING REPAIR REQUIREMENTS (INFORMATIVE)

DEI (0) Div Raise SIR &


Enter Into IRR To Asset
Holder

Asset Holder to
Obtain Engineering

< .~

Method
>
MRO have
Capabilities
to conduct
repair to QP

yo
MRO submit the
Statement: WPS
Contractor to MRO Action 10 proposed
& PQR Supplied amend Job pGckas
amend job pack Method
: ITP : Job pack
A~ Annlicahle
applicable
~ SfMPmp.nt& Inh
to Asset Holder

OEIReceiveMethod
Statement: WPS & OEI(O) Div review
!
OEl(O) Div Receive
MethodStatement:
PQR:ITPJobPack
from Asset Holder for
ail documents and
oreoare UteITP
OEI(O) Div review ........... WPS &. PQR Job Pack
from Asset Holder &.
all documents and Compile ITP for
Review Review
oreoare the ITP

~
SUJlCI"'ised: by contnu:tor Supervised: Piping Repllirs Conducted By
rcp.,/fPlITPC MRO in Accordance with QP
Piping Welding Repairs
QNQ!::. Inspoction:DEI MRO Rep SllUldnrds&.ProccdurCll
Conducted by Contractor (O)o;vl«p QNQC Inspection and ail
In Accordance with QP NOT by OEI(O) Div Rep

1
Standards & Procedures

QNQCFinal
Work Package JobCompletedBv
Job Completed By QAlQC FinalWork OEI(O)
Package Compiledby
Contractor Contractor and Inspectors
AnnrnVMhv OFJ(O)

J IR Close Out SIR


DEI (0) Inspector
I
I I
~
General Notes Still t0 Consider:
I ADd HolderCloseOut IR
I
OEI (0) Division to review all work packs from MRO which
involve welding could have 8 significant increase in workload. With
the potential of waiting time.

This process will not cover any welding work conducted by MRO in
locations not in the remit orOEl(O) OJ,,

This process now requires a OEI(O) Div inspection repon 10 initiate


all repair welding on piping.

Doc. File No.: SPC.R.010-1 R1 Page 34 of 39 Custodian DePL~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

L,
';::f-~
.11. L....iI DOC. No. QP-SPC-R-010-1 Rev. 1
'ot'Itar PEIroIe.m

20.12 APPENDIX -XII WELDING PROCEDURES FORMATS (WPS & PQR)


a. Welding procedurespecification

~--
~
(\ WlEll..l:MNGPADCEDllIFIIE 8IPECIFlCATlDN WIIIS_
..u-.r ,..J-II
, PaR 1kI!>1:
----
...........
I"'__'

.-.r.
.•..
1!Ia:.""
lii_
p
!111M ......
IirJID
~
iii
1='-
I
Gt--*

~ ~
I'IIIIIII1It
.IIIiIUIk ~ at..:: IZJ!QSI'Il9l ~..u;g
~i1iM.lQ
~ [1iW<!
~~ o-tIq>-~ .. II .:1ft I

1::;::lIDlfL ~
~.--
""m-.
~
!lia,,"," ~
.s.......
U'A'lb
rI__
R/R!\b
.
IIlIIbIa T-..

...Iiil
1'111; .....

~Ita:az;;
:IJnI:k
a.n_
_
~
~
PDmuIal-
Nt:8:n c:I :d:I
... 'NeiII!

~~
8Ip"rl
~1

1Iy~
~~r:

'_-.:I~
1

IIIf9T ........,.IE..u~
'!:
....... I!d"MT "'«'1'1 Iln
SIrqa._....
Q1IaalJi!llll
""

il"- It! ~
JtJl. "O"l IItttt!taiJ rI-
ot: It. '1:fl DIaMIIr
Coa:*KI U:III b
IGM L• ...... ....... ars.v-
Qaa ,. D:D; !'!iN ". ..an.:H
~ 1!!IIiaI_~
I!-.q I~_'_'
-
Amv
T.Srv

An'PLI.np .•
~.
'
- ~

I=:
illd.ct.dIr.
I~'_"-

.- ..-_
m:d!I. !iiIM1I
~ _1DM'f'_ E:"":"""

..
I~
~
W..HI
'--- ~-= ~ft

IDa~ =: ::
!;;. unI

1"'=Il~
-
!51IHII
!IiI.u:.,

I~

-.
,.... I:1tH ..., ,-
Doc. File No.: SPC.R.010-1 R1 Page 35 of 39 Custodian Dept.: ;
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

Cont.. Appendix -XII


b. Procedure Qualification Records(page1 of 3)
PRDCmlll1E ~ RE!CDRDI1!IUI;1 II!I3I/fllJI-
.lUS:lle.1II: .. ~ DP ISIbJllllllnl
Itfllll.4l1

..

IIIIIIIoUW '.

t'l!t:llWlOIZ IJJW"I'!Q
i&_a.:!-
Ci',blll!;!lll~
1i'iiiIf~
1illlll:lal[1II~

gp DIqIU .. __ .. TPC ar TIll

Doc. File No.: SPC.R.010-1 R1 Page 36 of 39 Custodian Dep~


QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

Cont.! Appendix -XII


b. Procedure Qualification Records (page 2 of 3)
~
t
=" I~ .,b::d 1CJIi'." ..............
Qiirt.. PII!hIun 1IJID:I!DUftE 1Z.III.IPE"'11EHI .I!!COIUI SIIHIi Zal ,l
IJIII!\!

_ IDI!SlKU::1'IM'!.DMlOO\'lWIII

nlPl! ,~ I'n' .... liLT IN


1'IaaU.1
T"'~NII.

TI!IIIULI! Tel
~._,. ,: 'fWJl PDII'1 :=~ill'
I~
Ior ,mil!!!!
IIci • 11ft
-.: h ~
lh[ Tala
K ~.,..
Ib_ IIIiID lDC,W,11IJII

TOm~6111!IST~I~,aw~ml

II.
IiIrn:lt
LX'i' ..
I~
~
1= "C
~~.~,
c: IJ ['\....
1A..-mlIolll!!lPlllll5.11Ui
Z l ~'t :z
~5HUrJI
INti

Gii till!! elD IIII! II D T' :SiT LtM""'1II:I1


IUlJ:J!D ~mtI n::uw I"'~ ,._. '"'" Pl, ... JIa..
HII I!E.:t ,

WaJd I!cC a
~ Ihno!l I
1I_mH:~ II~" I

...
D~PQ 1111"iI!oll"L"'IIIIS!fI!IW"'~

.., c 1m Cr NI ... c• 1WI+1"Il 51 P 15 AI' II' 1\1

--- 1"nIm

rlLLI!T WELD ll'ie ISTtDMI·,

,.....-~ ~ ...........
=-.JI'Id~.,,*- 1l1li111
~-=--
'!ail&

.,.,.,..:.- 1lil':Na.

-r-I.:zn:&lCIICl_ ......
~
w. ~jUj e. ~IIII 1:a,1HDII II1IIr:ar.:1Im1 In1 _ prtIIJ:LI...t wd:IRI ..... IiDIRI
III ~ ."Itt Jw ____ r/lA!ilII!!OIK

FIIpInd By III, ... IlIr V.... 1!y 1:.... 11"

Doc. File No.: SPC.R.010-1 R1 Page 37 of 39 Custodian Dept.: OE/(O)

~
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

~~ DOC. No. QP-SPC-R-010-1 Rev. 1

Cont., Appendix -XII


b. Procedure Qualification Records (page 3 of 3)
f"IJR lib. r
&9.~~ WELDlNG 8ECIUEltfCE ~
Shut
II
21.... 3

wehf... Sialuem Dnr.wi

-... PfIDCI!S5 s..i-* ~


""*
_.... ....... -
__.
_I_~I
~
.
1Ifttt!S!I Da.;n.~ .... \l
--
I rar.'!'Ic

...... .a:~~ .... -.1_ ~~ ___ '__"'-J:I!I"

Doc. File No.: SPC.R.010-1 R1 Page 38 of 39 Custodian


Dept;
QP SPECIFICATION FOR MAINTENANCE WELDING
Part 1: Process Piping (Offshore) (Formerly QP-MN-001)

W~ DOC. No. QP-SPC-R-010-1 Rev. 1

REVISION HISTORY LOG

Revision Number: 1 Date: 8/12/2014

Reason for Change/Amendment:


Item Revised:

This specification has been developed to incorporate latest QP


requirements such as QP-STD-R-001, QP-STD-R-002, QP-STD-R-003
etc.. And the updated International codes and standards referenced in
the document.

It has been also revised to satisfy the requirements of the


standardization documents (QP-PRC-A-001 & QP-PRC-A-003).

The revision history log shall be updated with each revision of the document. It shall contain a
written audit trail of the reason why the changes/amendments have occurred, what the
changes/amendments were, and the date at which the changes/amendments were made.

Doc. File No.: SPC.R.010-1 R1 Page 39 of 39 Custodian Dept.: OE/(O)

You might also like