REQUEST FOR INSPECTION SUMMARY

Project/Job No.: CW2169487 Client: BP Exploration (Epsilon) Limited

Project Title: SWX-GE-GAS EXPORT PIPELINE Contractor: GPS


6-Apr-2020 Project Area
Submittal Date: GAS EXPORT PIPELINE

SI RFI Planned Date of


Inspection Stages
RFI No. Rev. Discipline Planned Time of Inspection Description Location / Equipment IFC Drawing No. & Rev. No. ITP/Activity Reference No # Contact/ Tel no Client Inspector (BP/Jacobs) Status Remarks
No Code Inspection GPS BP/Jacobs

1 2026 A civil 7-Apr-2020 10:30 AM Inspection of Post-padding for pipeline trench from CH:66+300 TO CH: 66+400 CH:66+300 KZ02-IC-LAY-68-3016- 003-C03 KZ02-QA-PLN-66-1003-B04 H W JASPHER 95161401 MR. MANOHAR

2 2030 N/A civil 7-Apr-2020 10:30 AM Installation of FOC Duct & orange euromash at RDX-12(CH:66+400) CH:66+400 KZ02-CV-LAY-68-3006- 004-C02 KZ02-QA-PLN-66-1013-B02 H W JASPHER 95161401 MR. MANOHAR

3 2031 N/A civil 7-Apr-2020 10:00 AM Inspection of Electrical cable CPF KZ02-EL-LAY-68-2008 KZ02-QA-PLN-66-1013-B02 H W JASPHER 95161401 MR. MANOHAR

4 2032 N/A civil 7-Apr-2020 1:30 PM Inspection of Electrical cable TRENCH Prepadding CPF KZ02-EL-LAY-68-2008 KZ02-QA-PLN-66-1013-B02 H W JASPHER 95161401 MR. MANOHAR

5 2033 N/A SURVEY 7-Apr-2020 2:15 PM Verification of As built Co-ordinates for Electrical cable CPF KZ02-IC-LAY-68-3016- 003-C03 KZ02-QA-PLN-66-1002-B01 H R SHAFQAT MR. SURESH

6 2034 N/A civil 7-Apr-2020 3:00 PM Inspection of Postpadding,Cable Tile and warning tape installation CPF KZ02-EL-LAY-68-2008 KZ02-QA-PLN-66-1013-B02 H W JASPHER 95161401 MR. MANOHAR

7 2035 N/A Mechanical 7-Apr-2020 7:00 AM Flange Management FCS KZ02-PI-ISO-68-GBA-PJ-3472005-001 KZ02-CM-MET-66-1019 B03 W W SATHISH MR. D KUTTY

8 2036 N/A Mechanical 7-Apr-2020 10:00 AM Inspection for Structural Material From DAK(Handrails etc) CPF KZ02-CV-GAS-68-2001&2002-SHEET-1,2,3& 1.2 - W/S W/S NALAN MR. JOHN MILAN

9 2037 N/A ELECTRICAL 7-Apr-2020 2:00 PM Inspection for Electrical cable laying(from Petrofac) in Trench as per site condition CPF KZ02-EL-LAY-68-2008 KZ02-QA-PLN-66-1010-B01 W S/W Pringal 95891840 Mr. RIC IDIO