A Study On Fatigue Durability of RC Slab With Metal-Grid Instead of Steel Re-Bar
A Study On Fatigue Durability of RC Slab With Metal-Grid Instead of Steel Re-Bar
A Study On Fatigue Durability of RC Slab With Metal-Grid Instead of Steel Re-Bar
1
Dr. E, Prof., Nihon University, Dept. of Civil Engineering, 1-2-1, Izumi-cho,
Narasino-shi, Chiba 275-8575, Japan
2
Dr. E, Associate prof., Nihon University, Dept. of Civil Engineering 1-2-1, Izumi-
cho, Narasino-shi, Chiba 275-8575, Japan
3
Dr. E, Assistant prof., National Taipei University of Technology, Dept. of
Architecture, 1, Sec. 3, Zhongxiao E. Rd., Taipei 10608 Taiwan, R.O.C.
4
JFE Civil Engineering & Construction Corporation, Technical Development Dept.,
2-17-4, kuramae, taitou-ku, Tokyo 111-0051, Japan
ABSTRACT:
For this research, the new developed steel metal-grid has been used in RC slabs. The
practicality and the fatigue resistance has been verified by using wheel-running fatigue
load experiment. As the results, the steel metal-grid used as reinforcement in the RC
slabs has good constructability and shorten the construction time. Moreover,
comparing the results with the steel re-bars used in the RC slab, the equivalent number
of running times is similar by using wheel-running fatigue load experiment. Hence,
the fatigue resistance of steel metal-grid used in RC slabs is recognized. Therefore, the
steel metal-grid used in RC slab proposed in this paper has achieved the practicality of
rationalization and labor-saving construction.
INTRODUCTION
Page 1
In recent years, rationalization and labor-saving construction materials aredesired
from a lack of workers in the construction business in Japan. Particularly in the
construction site of the concrete structure, insufficient of workers perform the
assembling and processing of steel re-bars. Therefore, two types of metal-grid material
have been developed as a substitute to the steel re-bars (K.Minakuchi, et al. 2015). The
first type is the steel metal-grid that the steel plate was cut slit shapes by a laser and
stretched out to form the grid shapes by hydraulic jack. The second type metal-grid is
cutting steel plate directly to form the grid shapes by laser. For using in the actual
concrete structure, these two types of metal-grid can be machining bended according
to the shape of the actual structure. Then, the formwork can be assembled around the
steel metal-grid before the concrete pouring. Hence, this steel metal-grid material can
be achieved the rationalization and labor reduction in construction site.
In this study, we have verified the load carrying capacity and the fatigue
durability of the steel metal-grid used in the RC slabs of Highway Bridge, and the steel
metal-grid has been shown the applicability of using in the actual bridge RC slabs.
Moreover, this experimental study is carrying out for verifying the load carrying
capacity and the fatigue durability under the load carrying wheel tracking machine.
Finally, for verifying the practicality, this study is going to compare the RC slab with
steel re-bars and the RC slab with steel metal-grids.
Page 2
the grid shape (PIC 1 (1)). The laser cut steel metal-grid is shown in PIC 1 (2). The
longitudinal direction of the steel metal-grid is seem as the main re-bars, and the axle
direction of the steel metal-grid is seen as the distribution re-bars. The cross section of
grid can be cut freely as according to the design. The steel metal-grid can be used as
the reinforced material. Therefore, the shape of the steel metal-grid can be bend
according to the structure that needed to be reinforced. For rust prevention, the anti-
rust inhibitor can be placed on the steel metal-grid as reinforced material (PIC 1 (3)).
As described above, unlike the steel metal-grid, the stretched steel metal-grid
is stretched to form a grid shape by hydraulic jack after the slit shape cut on the
checkered steel plate by laser. These two types of steel metal-grid have been tasted
with various materials and adhesion testing. Moreover, these two types have also been
tested in the structure experiment lab and adopted as reinforced material that sale as
commercial material.
Page 3
Table 1. Formula condition of concrete for RC slab
Slump Air W/C s/a Unit weight(kg/m³)
(cm) (%) (%) (%) C W S G Ad
18 4.5 49.5 47.6 344 170 832 956 3.4
2) Grid Dimension
The size of tensile re-bars in RC slab was D10 (The cross-section was
71.3mm2) that placed on axle and longitudinal direction with 100mm spacing. The
compression re-bars was half amount of the tensile re-bars with 200mm spacing.
Therefore, the steel metal-grid had 100mmx100mm grid spacing size in the tensile
side. The cross-section of steel metal-grid was 72mm2 that the thickness was 9.0mm
Page 4
and the width was 8.0mm. Moreover, it provided 2mm protrusion per 9mm spacing in
order to increase the adhesion of steel metal-grid. FIG 1 shows the dimension and
shape of steel metal-grid.
Outline of Specimen
(1) RC Slab Specimen
The design of the test specimen was from 2014 of the Highway Bridge
Specifications (Japan Road Association 2014). For this test, one half of the mode in
the Specifications was been designed. The figuration of RC slab specimen and re-bars
arrangement are shown in FIG 2 (1).
The RC slab specimens had a span of 1200mm between supports and had
135mm over hanging over the supports. The total length was 1470mm. Moreover, the
D10 of tensile re-bars were placed in axle and longitudinal direction with 100mm
spacing. The effective depths of tensile re-bars ware 95mm and 105mm for axle and
longitudinal direction, respectively. In the compression size, the compression re-bars
were half amounts of tensile re-bars and had 200mm in spacing. The effective depths
of compression re-bars ware 35mm and 25mm for axle and longitudinal direction,
respectively. Hereafter, the RC slab specimen is referred as RC-1.
Page 5
For the arrangement of reinforcement in the MG slab specimens, the tension
side had placed a layer of the steel metal-grid with 100mm gird spacing dimension.
The effective depths of tension side was 105.5mm for both axle and longitudinal
direction. For compression side, the amount of reinforcement was half of the tension
side, and the effective depths was 24.5mm for both axle and longitudinal direction.
Hereafter, the MG slab specimens are referred as MG-1 and MG-2.
Assembling of Specimens
The assembling procedure of RC slab specimen is shown in FIG 3.1. As shown
in FIG 2, the main tensile re-bars were placed alone the longitudinal direction with
100mm spacing in the RC slab specimen. Next for the axle direction, the spacing of
re-bars was 100mm that same as the longitudinal direction. Future, assembling the axle
and longitudinal re-bars together to form a grid shape by using the steel wire (FIG
3.1.1). Assembling of the compression re-bars is shown in FIG 3.1.2. The compression
re-bars had same assembled method as the tensile re-bars, but the re-bars spacing was
200mm in axle and longitudinal direction. Next, the tensile and compression re-bars
were assembled together inside the formwork as shown in FIG 3.1.3. This whole
assembling process took approximately 60 mins to complete. At the end, the concrete
was poured into the formwork.
Page 6
The assembling procedure of MG slab specimen is shown in FIG 3.2. The steel
metal-grid at tensile side had 100mm grid spacing dimension that was same as the RC
slab tensile re-bars’ spacing. The steel metal-grid had 200mm grid spacing dimension
at compression side that was same as the compression re-bars’ spacing in RC slab. For
rust prevention, the steel metal-grid had coated the anti-rust inhibitor on the surface in
the factory and before shopping out. FIG 3.2.1 and 3.2.2 are shown the tensile and
compression steel metal grid, respectively. On the job site, the steel metal grid and
formwork had assembled together and shown in FIG 3.2.3. This assembling process
took approximately 30 mins to complete. At the end, the concrete was poured into the
formwork.
As above, the assembling procedure of MG slab specimens had shorter time as
the RC slab specimens. That means the rationalization construction and cost down
could be happening by using the steel metal-grid.
Page 7
Outline of Test Equipment
For evaluating the fatigue durability of RC slab and MG slab specimens, the
wheel-running fatigue load test had been carried out by using the wheel-running
vibration fatigue test equipment. As used for this research, the equipment had consisted
of a hydraulic structural vibration fatigue device (500kN) equipped with steel wheel
(dimension is 450mm and width is 250mm), fastened to the beam of a steel reaction
force frame. A truck which the test specimen was placed was moved laterally back and
forth by a motor and crank arm to simulate the running of vehicle. PIC 2 shows the
wheel-running fatigue test unit.
Page 8
times. Therefore, the fatigue durability evaluation of MG slab specimens could be
evaluated from the equivalent number of running times.
∑ ⁄ (1)
Page 9
(1) RC Slab Specimen
The e1uivalent number of running times (Neq) for RC slab specimen RC-1 has
6.09106 running times. This result of Neq will be used as reference to compare and
evaluate the fatigue durability of the MG slab specimens.
Failure Condition
At failure, the cracking pattern of the RC slab and MG slab specimens are
shown in FIG 4.
Page 10
failure of RC slab specimen is punching shear failure, the tensile re-bars has dowel
effect, and the clearance part of concrete is peeled off at bottom.
CONCLUSIONS
The practical usage of the steel metal-grid in the RC slab of Highway Bridge
is been verified under the wheel-running fatigue loading in this paper. The
constructability and the fatigue resistance have been also verified. The conclusions are
summarized as follows:
1. By substituted the steel re-bars, the checkered steel plate or steel plate has
been cut directly by laser to form steel metal-grid in the factory. The grid
spacing dimension, necessary cross-section, protrusion on the surface for
adhesion, and bending shape can be customized according to the
construction needs. The steel metal-grid can also assembled at
construction site. Moreover, for rust prevention, the epoxy paint or
galvanized process can be applied on the steel metal-grid after assembling.
Therefore, the rust prevented steel metal-grid can be effective material
using in salt damage regions.
2. Manufacturing the steel metal-grids at factory have good constructability.
Moreover, for making the RC slab specimens, the re-bars assembling takes
2 people in 60 mins. For the steel metal-grid, the assembling time reduce
to 30 mins for 2 people. This means that the construction time can be
reduced by using the steel metal-grid. Therefore, the usage of steel metal-
grid has significant contribution on the rationalization and labor-saving in
the construction.
3. Comparing the results of RC slab and MG slab specimens, the equivalent
number of running times by using wheel-running fatigue load test are
Page 11
similar. Therefore, the fatigue resistance of steel metal-grid use in RC slab
has been recognized, and the steel metal-grid can be practical used in RC
slab.
REFERENCES
K.Minakuchi, et al. (2015). “Evaluation of reinforcing effects and fatigue resistance by
RC slabs bottom surface thickness increase method using two kinds of metal grid.”
JCI Annual Convention, Vol.37, No.2, pp.379-384.
Japan Road Association. (2014). “Japanese Specifications for Highway Bridge”
S.Matsui. (2007). “Design of Highway Bridge slab ・ Construction and
Maintenance.” Morikita Publishing Co.,Itd.
Page 12