Api 653 Daily Points To Recall (Day 3)
Api 653 Daily Points To Recall (Day 3)
Consultation
3. Alternative to point no. 2 above for internal inspection interval may be altered
based on RBI. The RBI basis shall be reviewed at intervals not exceeding 10 years
by authorized inspector and tank engineer.
6. New materials for repair/alteration/ reconstruction: All plate material used for
shell and the bottom plates welded to shell shall be identified.
7. Thickness of shell plates to be used for checking the tank design shall be within
180 days before relocation.
8. The strength values Sd and St for reconstructed tank shall be on the basis of
allowable stress as per table 3-2 of API 650.
9. The replacement shell plate thickness ≥ thickness of the shell course where
replacement is proposed and dimensions and spacing shall be as per Figure 9-1.
a. owner specifies
b. only on shell plates ≤ ½ inch
c. must be within spacing requirements as per Fig. 9-1
d. maximum size 48” vertical x 72 horizontal and minimum dimension 4”
e. areas on which lap patch is to be put shall be UT checked
f. lap on lap is not permitted
11. All shell plate defects like the cracks, gauges, tears, widely scattered .pits and
corroded areas shall be evaluated case by case as per chapter 4 of API 653.
12. New reinforcements can be added to existing unreinforced nozzles as per Fig. 9-
3a and 9-3b.
13. Repairs within critical zone of the bottom require additional precautions like
“Tombstone” type patch and additional PT or MPI testing after visual examination
of patch welds, and weld shall be made by minimum 2 passes.
14. If impact test was not done on original tank material, the hot taps shall be limited
to NPS 4 (max).
15. Toe-to-toe minimum spacing between hot tap and adjacent nozzle shall be =
RT where R= tank shell radius in inches T is shell plate thickness in inches.