Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Item No Description Unit Quantity Unit Price A) Sub-Structure 1. Excavaton and Earthworks

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

SKILL LABOUR SERVICE, BILL OF QUANTITY FOR STORE (30.2M*10.

20M)
Title: BOQ and Specification for Construction of Woreda Fodder Warehouse
Item No Description Unit Quantity Unit Price
A) SUB-STRUCTURE
1. EXCAVATON AND EARTHWORKS
1.1 Clear the site to remove top soil to an average depth of 20cm M2 500 20
Pit excavation in ordinary soil for footing to a depth not
1.2 M3 47.04 200
exceeding 150cm
Ditto item 1.2 but a depth not exceeding 300mm as determined
1.3 M3 15.68 200
by the engineer
Trench excavation for masonry foundation to a depth not
1.4 M3 32.26 200
exceeding 150cm from reduced ground level
Backfill around foundation with approved type selected and
1.5 non-expansive material from outside and well ram in layers not M3 50.68 40
exceeding 20cm

Backfill under hard core with approved type selected and non-
1.6 expansive material from outside and well ram in layers not M3 102.22 30
exceeding 20cm

Backfill underpavement around the bulding with approved type


1.7 selected and non-expansive material from outside and well ram M3 45.15 30
in layers not exceeding 20cm
Cart away surplus excavated material and depositedat suitable
1.8 M3 194.98 30
area not less than 2km distance from site
Labour cost to lay and compact 250mm thick basaltic or
1.9 equivalent stone hard core finished and blinded with crashed M2 403.84 30
stone under floor slab, pavement and ramp
Sub-Total
2) CONCRETE WORKS

Labour cost to lay 5cm thick lean concrete in C-5 with


2.1
minimum cement content of 150kg/m3 of concrete under 1:4:8

a) Footing M2 31.36 220


b) Masonry foundation M 2
53.2 220
c) Floor slab M2 292.04 220

Labour cost to cast reinforcement concrete in class C-25 (with


a 28 day 150mm cube crushing of 25MPa) and maximum
aggregate size of 30mm for footings and 20mm for columns,
2.2 beams & slabs; cast into formworks and vibrated around rod
reinforcement bars (formwork and reinforcement bars are
measured separately) " Type of cement to be ordinary portland
cement (OPC)" in:

a) Foundation footing (120cm*120cm) M3 10.37 280


b) Foundation column (30cm*20cm) M3 1.97 280
c) Grade beam (25cm*20cm) M3 5.7 280
d) 12cm thick floor slab including 12cm ramps M 3
310.04 280
Labour cost to cut & fix in position swan zigba wood or
2.3
wrought iron formwork whichever is appropriate for:
a) Foundation footing M2 34.56 220
b) Foundation column M 2
28 220
c) Grade beam M2 45.6 220
Labour cot to cut & fix reinforcement steel bars according to
2.4 structural drawing, price include cut, bend & placing in
position and tying wires
a) dia 6mm deformed bar Kg 158.74 55
b) dia 12mm deformed bar Kg 1060.21 48
Sub-Total
3) MASONRY WORK
Labour cot to lay 500mm thick, roughly dressed hard trachytic
3.1 or equivalent stone masonry foundation wall bedded in cement M3 30.4 350
sand mortar mix of 1:3

Ditto as item 3.1 but stone masonry foundation above ground


3.2 level bedded in cement mortar (1:3) in full joints. Price shall M3 7.6 350
include pointing
3.3 Labour cost to construct ramp M2 18 550
Sub-Total
Total Carried To Summary A
B) SUPER-STRUCTURE
1. CONCRETE WORKS
Labour cost to cast C-25 reinforced concrete with minimum
1.1 cement content of 360kg/m3to be poured into formwork
around reinforcement bars in:
a) Elevation column (30cm*20cm) M3 5.98 220
b) Top tie beam (30cm*20cm) M3 4.56 280
Labour cot to cut & fix in position swan zigba wood or
1.2
wrought ion formwork whichever is appropriate for:
a) Elevation column M2 55.08 220
b) Top tie beam M2 49.4 220
Labour cot to cut & fix reinforcement steel bars according to
1.3 structural drawing, price include cut, bend & placing in
position and tying wires
a) dia 6mm deformed bar Kg 338.3 45
b) dia 12mm deformed bar Kg 1150.17 48
Sub-Total
2. BLOCK WORK
Labour cost to lay 20cm thick class "B" HCB on cement snd
2.1 M2 371.2 200
mortar mi 1:3
Sub-Total
3. ROOFING
Labour cost to fix 0.4mm galvanized corrugated steel sheet
3.1 M2 377 150
roofing fixed to 5*7cm purlin
3.2 Labour cost to fix formed roof ridge in 0.4mm dev. 500mm ML 32 50
Labour cost to assemble & fix dia 12cm eucalyptus truss upper
3.3 ML 410 20
& lower chords
Labour cost to assemble & fix dia 8-10cm eucalyptus
3.4 ML 654 20
intermediate member between upper & lower chords
Labour cost to assemble & fix roof purlin in 5*7cm zigbaor
3.5 ML 576 20
equiv timber
Labour cost to assemble & fix roof purlin in 5*4cm zigbaor
3.6 ML 131 20
equiv timber
3.7 Labour cost to install fine wire mesh to all sides of the building M2 53 15
3.8 Labour cost to fix 3*30cm fascia board made of zigba or equiv ML 84 50
Sub-Total
4. METAL WORKS

Labour cost for all metal windows & doors shall be fabricated
of locally manufactured frame 38*1.5mm LTZ profile with
4.1 necessary Iron mongery approved type of locks, hinges, etc.
Price includes applying one coat of antirust paint & two coats
of enamel synthetic enamel paint

a) W1 of size 475*60cm with fine wire mesh No 8 150


Ditto as item 4.1 but metal doors covered with 1mm thick
4.2 checkered metal sheet with European made cylinderical lock &
latches;
a) D1 of size 280*330cm with all accessories sliding type No 2 5000
Sub-Total
5. FINISHING WORK
Labour cost for finishing works which shall include all surface
pre-cleaning, preparation and application of finishing and
cleaning at the end of finishing works
5.1 3 coats of plastering in c:s:m ratio of 1:3 to beams & coluns M2 154 30
Appling pointing to external and internal sides of wall with
5.2 M2 742.4 20
cement sand mortar ratio of 1:2
50mm thick cement screed floor finishing in cement sand
5.3 M2 292.04 25
mortar ratio of 1:2
15cm thick hard cores under mass concrete pavement of the
building over 100mm thick sand layer with 300mm half ditch
5.4 and joints made tight with cement ans sand mortar of ratio 1:2, ML 89 90
price include excavation of trench, backfill with selected
materials borrowed and 15*40*100cm concrete curb

Sub-Total
Total Carried To Summary B
Total Carried To Summary (A+B)

GRAND TOTAL
VAT 15%
GRAND TOTAL WITH VAT
Total Amount

10,000.00

9,408.00

3,136.00

6,452.00

2,027.20

3,066.60

1,354.50

5,849.40

12,115.20

53,408.90

6,899.20
11,704.00
64,248.80

2,903.60
551.60
1,596.00
86,811.20

7,603.20
6,160.00
10,032.00

8,730.70
50,890.08
258,130.38

10,640.00

2,660.00

9,900.00
23,200.00
334,739.28

1,315.60
1,276.80

12,117.60
10,868.00

15,223.50
55,208.16
96,009.66
74,240.00

74,240.00

56,550.00

1,600.00

8,200.00

13,080.00

11,520.00

2,620.00

795.00
4,200.00
98,565.00

1,200.00

10,000.00
11,200.00

4,620.00

14,848.00

7,301.00
8,010.00

34,779.00
314,793.66
649,532.94

1,399,952.94 with material cost


209,992.94
1,609,945.88
# Detail Construction material Unit Quantity Unit Cost
1 Cement (Dangote) Quintals 240.00 470
2 Stone M 3
256.00 280
3 Sand M 3
128.00 160
4 Selected Soil M 3
160.00 160
5 RIB dia 12mm Berga 196.00 500
6 RIB dia 6mm (staffa) Kg 400.00 60
7 Black wire Kg 50.00 80
8 Class "B" 20*20*40cm HCB Pcs 4,400.00 15
9 Corrugated Iron Sheet (G-32 Kaliti) Pcs 260.00 260
10 G-28 Flat Iron Sheet M 35.00 300
11 Fascia Board (25cm*4m) Pcs 70.00 220
12 Timber (30cm*4m) Pcs 80.00 220
13 Timber (25cm*4m) Pcs 80.00 200
14 Diagonal Mesh Wire (0.2mm) M 60.00 80
15 Purlin Zigba (7cm*5cm) Morale Pcs 72.00 55
16 Junipers wooden pole dia 12mm for horizontal & diagonal truss Pcs 340.00 80
17 Eucalyptus dia 12 Pcs 190.00 100
18 Eucalyptus dia 10 Pcs 160.00 100
19 Eucalyptus dia 8 Pcs 340.00 80
20 Bonda Kg 20.00 60
21 Nail #12 Kg 15.00 90
22 Nail #10 Kg 20.00 90
23 Nail #9 Kg 20.00 90
24 Nail #8 Kg 15.00 90
25 Nail #7 Kg 15.00 90
26 Nail #5 Kg 15.00 90
27 Roofing nail (Coped nail) Kg 30.00 180

Shatter Door of RHS and LTZ having 1.2mm thickness, 2.6m


height and 2.4m width having Italy lock & door stopper and
28 handling Pcs 2.00 4600
29 Window Pcs 8.00 1500
30 Aggregate 0.2mm M3 64.00 550
31 Water Truck 20M3 Trip 6.00 3000
32 Oliyo Lit 20.00 50
33 Transportation cost with FSR for all industrial materials Trip 4.00 2900
Total
Total Amount
112,800.00
71,680.00
20,480.00
25,600.00
98,000.00
24,000.00
4,000.00
66,000.00
67,600.00
10,500.00
15,400.00
17,600.00
16,000.00
4,800.00
3,960.00
27,200.00
19,000.00
16,000.00
27,200.00
1,200.00
1,350.00
1,800.00
1,800.00
1,350.00
1,350.00
1,350.00
5,400.00

9,200.00
12,000.00
35,200.00
18,000.00
1,000.00
11,600.00
750,420.00

You might also like