MCHW Vol 1 1000 - Web PDF
MCHW Vol 1 1000 - Web PDF
MCHW Vol 1 1000 - Web PDF
SERIES 1000
ROAD PAVEMENTS – CONCRETE
MATERIALS
Contents
Clause Title Page Clause Title Page
1000 General 2 1028 (02/16) Trial Length 30
(02/16) Strength Classes of Concrete and
1001 (01/20) Texturing of Hardened
1029
Constituent Materials for Pavement Layers 2 Concrete by Transverse Grooves 32
1002 (02/16) Air Content 7 1030 (01/20) Lower Strength Concrete 32
1003 (02/16) Density 7 (02/16) Measurement of Macrotexture
1031
Depth – Volumetric Patch Technique 34
1004 (02/16) Pavement Concrete Strength 8
1032 (02/16) Thin Bonded Repairs 34
1005 (02/16) Consistence (Workability) 9
(01/20) Full Depth Repairs
1033 34
1006 (02/16) Not Used 9
1034 (02/16) Bay Replacement 35
(02/16) Separation and Waterproof
1007
Membranes 9 1035 to 1038 (01/20) Not Used 36
1008 (02/16) Steel Reinforcement 9 (02/16) Summary of Rates for Sampling
1039
and Testing Concrete for Pavement
1009 (02/16) Transverse Joints 11
Layers 36
1010 (02/16) Longitudinal Joints 12
1040 to 1042 (02/16) Not Used 37
1011 (02/16) Dowel Bars 13
1043 (02/16) Foamed Concrete 37
1012 (02/16) Tie Bars 14
(02/16) Pavements with an Exposed
1044
1013 (02/16) Joint Grooves 16 Aggregate Concrete Surface 37
(02/16) Groove Formers and Bottom
1014 (02/16) Weather Conditions for Laying
1045
Crack Inducers 16 of Cementitious Materials 41
1015 (02/16) Joint Filler Board 17 1046 to 1047 (02/16) Not Used 41
(02/16) Preparation and Sealing of Joint
1016 (02/16) Use of Surfaces by Traffic and
1048
Grooves 18 Construction Plant 41
1017 (02/16) Joint Seals 20 1049 to 1050 (01/20) Not Used42
(02/16) Joints at Manhole and Gully Slabs
1018 21 (01/20) Roller Compacted Concrete Mixtures42
1019 (02/16) Inspection of Dowel Bars 22 1051 (01/20) General Requirements for Roller
(02/16) Side Forms, Rails and Guide Wires 22
1020 Compacted Concrete (RCC) mixtures42
1023 (02/16) Transport and Delivery 23 1053 (01/20) Storage of RCC Constituents44
1001 (02/16) Strength Classes of Concrete and Constituent Materials for Pavement Layers
1 (02/16) Concrete in rigid or rigid composite pavements shall be one of the classes given in Table 10/1, in
accordance with the pavement design alternatives permitted in contract specific Appendix 7/1.
2 (02/16) Unless otherwise specified in contract specific Appendix 7/1 concrete shall conform with the
requirements of BS EN 13877-2 and the requirements of this Series. The constituents of the concrete shall conform
with BS EN 206 and BS 8500-1 and BS 8500-2 and BS EN 13877-1 and the requirements of this Series.
NOTE: * Cores shall not be taken from ground beam anchorages. ** Minimum permitted concrete class.
(02/16) Cement
3 (01/20) The general term ‘cement’ in this Series means any of the materials in (i) or the combinations in (ii)
below:
(i) Cements Complying with:
(a) Portland cement CEM I BS EN 197-1
(b) Portland-slag cement CEM II/A-S and CEM II/B-S BS EN 197-1
(c) Blastfurnace cement CEM III/A and CEM III/B BS EN 197-1
(d) Portland-fly ash cement CEM II/A-V and CEM II/B-V BS EN 197-1
(e) Pozzolanic cement CEM IV/A BS EN 197-1
(ii) Combinations
(a) Portland cement CEM I with ground granulated blastfurnace slag BS EN 197-1
(ggbs) for use with Portland cement CEM I BS EN 15167-1 and
BS EN 15167-2
(b) Portland cement CEM I with fly ash (fa) for use as a cementitious BS EN 197-1
component in structural concrete BS EN 450-1 and
BS EN 450-2
(c) Portland cement CEM I with pozzolanic additive having current BS EN 197-1
certification complying with a product acceptance scheme as
described in sub-Clauses 104.15 and 104.16.
(iii) In each cubic metre of fully compacted concrete the cement content shall be in accordance with
Table 10/2. For 20 mm maximum size aggregate add 20 kg/m3, and for < 20mm maximum size add
40 kg/m3.
(iv) When used, the proportion of silica fume to CEM I shall be 10 ± 1%.
(v) For materials required to comply with BS EN 197-1 and/or BS EN 450-1 the Contractor shall
submit the relevant material declarations of performance to the Overseeing Organisation prior to
the inclusion of the materials into the works. The declarations of performance shall demonstrate
that the materials meet the requirements for the specification.
TABLE 10/2: (01/20) Minimum Cement or Combination Contents with 40 mm Maximum Aggregate
Class (BS 8500-1) C40/50 C32/40 C32/40 C25/30 C16/20 C12/15 C8/10 C6/8
Max/min. proportion 35/15 35/15 25/15 35/15 35/15 50/0 50/0 50/0
of fa (%)
(02/16) Water
4 (01/20) Water from a water company supply may be used without testing. Water from other sources may be
used if it conforms to BS EN 1008. The water content shall be the minimum required to provide the specified
consistence for full compaction of the concrete to the required density, as determined by trial concrete mixes or
other means, and the maximum free water/cement ratio shall be 0.45 for strength classes C32/40 and C25/30 and
0.60 for strength classes C16/20 and C12/15. The requirements for standardised prescribed concrete shall be in
accordance with BS EN 206 and BS 8500-2.
(02/16) Admixtures
5 (01/20) Concrete in at least the top 50 mm of surface slabs shall incorporate an air-entraining admixture
complying with BS EN 934-2, except:
(i) for pavements with an exposed aggregate concrete surface constructed to Clause 1044 where at least the
top 40 mm of the surface slab shall be air entrained;
or
(ii) for surface slabs of pavements with at least a class C40/50 concrete;
(iii) for surface slabs of pavements with a class C32/40 concrete which are to be overlaid by a 30 mm
minimum thickness thin surface course system complying with Clause 942; and
(iv) for surface slabs of pavements with a class C35/45 concrete which are to be overlaid by a 20 mm
minimum thickness thin surface course system complying with Clause 942.
Plasticisers or water reducing admixtures shall comply with BS EN 934-2. Admixtures containing calcium chloride
shall not be used.
The Contractor shall submit the declaration of performance for each admixture to the Overseeing Organisation
prior to the incorporation of the admixture into the works. The declaration of performance shall demonstrate that
the admixture meets the specification requirements.
(02/16) Aggregate
6 (01/20) Aggregates for all pavement concrete, including Lower Strength, shall comply with BS EN 12620.
Crushed concrete, which complies with the quality and grading requirements of BS EN 12620 and Table 2
of BS 8500-2, may also be used in all pavement concretes except aggregate concrete surface complying with
Clause 1044. Alternatively, coarse aggregate may be crushed air-cooled blastfurnace slag complying with
BS EN 12620 and shall be Category FI50 or FI35 for concrete of classes C16/20 to C25/30 and over class C25/30,
respectively. FA when used as part of the aggregate shall comply with BS EN 450. Once the appropriate gradings
have been determined they shall not be varied without the approval of the Overseeing Organisation. Irrespective of
source, the aggregate will be considered suitable if:
(i) the resistance to freezing and thawing complies with BS EN 12620 clause 5.7.1 for pavement and Lower
Strength concrete;
and
(ii) the resistance to fragmentation complies with category LA35 of BS EN 12620 clause 5.2 for concrete
surface slabs and LA40 of BS EN 12620, clause 5.2 for concrete bases and Lower Strength concrete.
The Contractor shall submit the declaration of performance for each aggregate to the Overseeing Organisation prior
to the incorporation of the aggregate into the works. The declaration of performance shall demonstrate that the
aggregate meets the specification requirements.
The water absorption (WA) of the coarse aggregate shall be determined and declared in accordance with
BS EN 12620. Where recycled coarse aggregate or recycled concrete aggregate is used in this Series, it shall
comply with the limits specified in Table 2 of BS 8500-2 and the constituents shall be declared.
7 (02/16) The maximum size of coarse aggregate (D) shall not exceed 40 mm. When the spacing between
longitudinal reinforcement is less than 90 mm, the maximum size of coarse aggregate (D) shall not exceed 20 mm.
8 (02/16) Sand (i.e. fine aggregate) containing more than 25% by mass of acid-soluble material as determined in
accordance with BS EN 196-2, in either the fraction retained on, or the fraction passing the 0.500 mm sieve, shall
not be used in the top 50 mm of surface slabs. This requirement will not apply for pavements with an exposed
aggregate concrete surface constructed to Clause 1044 or if it can be shown that the sand (ie fine aggregate)
retained on, or the fraction passing the 0.500 mm sieve, contains less than 25 per cent by weight of calcium
carbonate.
9 (01/20) The water absorption of flint coarse aggregate containing white flints for use in concrete surface slabs,
when determined in accordance with BS EN 1097-6 shall not exceed:
3.5% for any separate nominal size fraction;
2.0% for the total combination of coarse aggregates in the proportions to be used in the concrete.
Contract compliance tests shall be carried out during stockpiling or paving, once a week, or at a lesser rate when
authorised by the Overseeing Organisation.
(02/16) Source of Recycled Aggregates
10 (02/16) Where recycled coarse aggregate or recycled concrete aggregate is used, only crushed concrete resulting
from reclamation or processing of concrete previously used in construction which originates from appropriate
identified structures with a known history of use shall be used.
(02/16) Chloride Content
11 (01/20) The chloride ion content of the aggregate to be used in concrete shall be as stated in BS EN 206. The
chloride class of reinforced concrete or concrete containing embedded metal shall be Cl 0,40 and unreinforced
concrete shall be Cl 1,0. The water soluble chloride content of the aggregates shall be determined in accordance
with BS EN 12620 and declared. The acid soluble chloride content of recycled aggregates shall be determined in
accordance with BS EN 12620 and declared.
(02/16) Chemical Requirement
12 (01/20) Acid-soluble sulfate
Acid-soluble sulfate content of the aggregates and filler aggregates for concrete pavements, including Lower
Strength, shall comply with BS EN 12620, clause 6.3.1 and shall be Category AS1,0 for air-cooled blast furnace slag
and for other aggregates Category AS0,8.
13 (02/16) Total sulfur
Total sulfur content of recycled coarse aggregates, recycled concrete aggregates, aggregates and filler aggregates,
shall comply with BS EN 12620, clause 6.3.2.
2 (02/16) The air content shall be determined at the point of delivery to the paving plant by the pressure gauge
method in accordance with BS EN 12350-7, at the rate of one determination per 300 m² of slab or at least 6 times
per day, whichever is the greater, in conjunction with tests for consistence and strength. For areas less than 300 m²
the rate shall be at least one determination to each 20 m length of slab or less constructed at any one time or at
least 3 times per day. If the air content is outside the specified limits in BS EN 206 the Contractor shall remove the
concrete from the works.
3 (02/16) The air-entraining agent shall be added at the mixer, by an apparatus capable of dispensing the
correct dose within the tolerance for admixtures given in BS EN 206, to ensure uniform distribution of the agent
throughout the batch during mixing.
8 (01/20) The core shall have an average diameter of at least four times the nominal maximum aggregate size, and
in any case not less than 100 mm diameter. Where different concrete mixes are used in separate layers, the density
of each layer shall be separately determined by splitting or cutting the cores between the layers.
9 (01/20) Cores shall be taken at the rate given in Clause 1028 for the trial. If the density of any core is below the
minimum required, the concrete across the whole width of the slab constructed at the time relating to that core shall
be removed. In unreinforced concrete the whole slab length between joints shall be removed. For reinforced slabs,
in order to determine the limit of the defective area of concrete which shall be removed, additional cores shall be
taken at 5 m intervals on each side of any defective core until concrete of satisfactory density is found. Defective
areas shall be made good with new material in accordance with the specification.
10 (01/20) In calculating the density, allowance shall be made for any steel in the cores.
11 (01/20) Core holes shall be reinstated with compacted concrete with mix proportions of 1 part of Portland
cement CEM I: 2 parts of sand: 2 parts of 10 mm single sized coarse aggregate by mass.
3 (01/20) Spacing of bars shall not be less than twice the maximum size of aggregate used. Laps in longitudinal
bars shall be not less than 35 bar diameters or 450 mm whichever is greater. In continuously reinforced concrete
slabs (CRCP or CRCB), only one third of the laps may be in any one transverse section, except in single bay
width construction where half the laps may be in any one transverse section. There shall be a minimum of 1.2 m
longitudinally between groups of transverse laps or laps in prefabricated reinforcement sheets.
4 (02/16) Laps in any transverse reinforcement shall be a minimum of 300 mm. Where prefabricated
reinforcement sheets are used and longitudinal and transverse laps would coincide, no lap is required in the
transverse bars within the lap of the longitudinal reinforcement. These transverse bars may be cropped or fabricated
shorter so that the requirements for cover are met. Alternatively, prefabricated sheets incorporating splices (ie flying
ends) may be used to provide nesting of reinforcement in both directions at lap positions. The lengths of the laps
shall be the minimum values previously stated.
5 (01/20) If the reinforcement is positioned prior to concreting, it shall be fixed on chairs conforming with the
requirements of BS 7973 and retained in position at the required depth below the finished surface and distance from
the edge of the slab so as to ensure that the required cover is achieved. Reinforcement assembled on site shall be
tied, or firmly fixed, at sufficient intersections to provide sufficient rigidity to ensure that the reinforcement remains
in the correct position during construction of the slab.
6 (02/16) Alternatively, when a reinforced concrete slab (JRC, CRCP or CRCB) is constructed in two layers, the
reinforcement in the form of prefabricated sheets may be placed on or into the bottom layer which shall be spread
and compacted to such a level that it will support the reinforcement without distortion at the required position in
the slab. The sheets shall be tied together at overlaps and after the second layer has been spread and compacted, the
reinforcement shall have the required cover.
7 (02/16) When a reinforced concrete slab is constructed at maximum width as in Clause 1010 the transverse
reinforcement in the centre of each slab width shall be a minimum of 12 mm nominal diameter bars at 600 mm
centres. This reinforcement shall be at least 600 mm longer than one third of the width of the slab and be lapped to
other transverse reinforcement bars or sheets, or be continuous across the whole width of each slab.
(02/16) Jointed Reinforced Concrete Slabs
8 (02/16) The reinforcement shall be so placed that after compaction of the concrete, the cover below the finished
surface of the slab is 50 ± 10 mm for slabs less than 200 mm thick, 60 ± 10 mm for slabs 200 mm or more but
less than 270 mm thick, 70 ± 20 mm for slabs 270 mm thick or more. The negative vertical tolerance shall not be
permitted beneath road stud recesses. Where traffic signal detector loops are to be installed, the minimum cover
to the reinforcement from the surface shall be 100 mm. The vertical cover between any longitudinal joint groove
forming strip and any reinforcement or tie bars shall be a minimum of 30 mm. Any transverse bars shall be at right
angles to the longitudinal axis of the carriageway.
Any transverse reinforcement shall terminate at 125 ± 25 mm from the edges of the slab and longitudinal joints,
where tie bars as in Clause 1012 are used. No longitudinal bars shall lie within 100 mm of a longitudinal joint.
The reinforcement shall terminate 300 mm ± 50 mm from any transverse joint, excluding emergency construction
joints.
(02/16) Continuously Reinforced Concrete Slabs (CRCP or CRCB)
9 (01/20) The reinforcement shall be Grade B500B or B500C deformed steel bars with the diameters and spacings
as described in contract specific Appendix 7/1.
10 (02/16) The reinforcement shall consist of bars assembled on site, or of prefabricated sheets. Except where
otherwise shown on the drawings the longitudinal bars shall be parallel to the centre-line of the road.
11 (01/20) The reinforcement shall be positioned so that, after compaction of the concrete, it shall be at the mid
depth of the specified thickness of the slab ±25 mm. No longitudinal bar shall lie within 100 mm of a longitudinal
joint. Reinforcement longitudinal bars shall be placed immediately above any transverse bars, which shall be at
right angles to the longitudinal axis of the carriageway. Any transverse reinforcement shall terminate 125 ± 25 mm
from the edges of the slab and longitudinal joints where tie bars as in Clause 1012 are used.
5 (02/16) Tie bars may be replaced by continuous transverse reinforcement across the joints in continuously
reinforced concrete slabs which are constructed in more than one lane width in one operation, provided that the
transverse reinforcement is a minimum of 12 mm diameter bars at 600 mm centres. The transverse reinforcement in
these circumstances shall be protected by suitable bituminous paint or equivalent coating for a distance of at least
75 mm either side of the joint.
(02/16) Longitudinal Construction Joints
6 (02/16) Longitudinal construction joints between separate slabs shall have tie bars as in Clause 1012 with a joint
groove as in Clause 1013. Alternatively, if split forms are used, the transverse reinforcement, if 12 mm diameter
or more, may be continued across the joint for a minimum of 500 mm or 30 times the diameter of the transverse
reinforcement bars, whichever is the greater. The transverse reinforcement in these circumstances shall be protected
by suitable bituminous paint or equivalent coating for a distance of at least 75 mm either side of the joint. A joint
sealing groove is not required in construction joints in continuously reinforced concrete bases. Where the edge of
the concrete slab is damaged it shall be made good before the adjacent slab is constructed.
5 (02/16) Dowel bars, supported on cradles in assemblies, when subjected to a load of 110 N applied at either end
and in either the vertical or horizontal direction (upwards and downwards and both directions horizontally) shall
not deflect more than the following limits:
(i) two thirds of the number of bars of any assembly tested shall not deflect more than 2 mm per 300 mm
length of bar;
(ii) the remainder of the bars in that assembly shall not deflect more than 3 mm per 300 mm length of bar.
6 (02/16) The assembly of dowel bars and supporting cradles, including the joint filler board in the case of
expansion joints shall have the following degree of rigidity when fixed in position:
(i) For expansion joints the deflection of the top edge of the filler board shall be not greater than
13 mm, when a load of 1.3 kN is applied perpendicular to the vertical face of the joint filler board and
distributed over a length of 600 mm by means of a bar or timber packing, at mid depth and midway
between individual fixings, or 300 mm from either end of any length of filler board, if a continuous
fixing is used. The residual deflection after removal of the load shall be not more than 3 mm.
(ii) The joint assembly fixings to the sub-base shall not fail under the 1.3 kN load applied for testing the
rigidity of the assembly but shall fail before the load reaches 2.6 kN.
(iii) The fixings for contraction joints shall not fail under a 1.3 kN load and shall fail before the load reaches
2.6 kN when applied over a length of 600 mm by means of a bar or timber packing placed as near to the
level of the line of fixings as practicable.
(iv) Failure of the fixings shall be deemed to be when there is displacement of the assemblies by more than
3 mm with any form of fixing, under the test load. The displacement shall be measured at the nearest
part of the assembly to the centre of the bar or timber packing.
7 (01/20) Dowel bars shall be covered by a flexible polymeric corrosion resistant coating, bonded onto the
previously cleaned bar. The coating shall be smooth and free of indentations. During coating, the bar shall be
supported at each end. Minimum thickness shall be 0.3 mm. The coating shall also be able to withstand 250 hours
immersion in a salt fog cabinet complying with BS EN ISO 7253, without showing any visible crazing or corrosion
of the protected bar. The coated bar shall comply with the following pull out test:
(i) Four bars shall be taken at random from stock and without any special preparation shall be coated as
required in this Clause. The dowel bars which have been coated shall be cast centrally into concrete
specimens 150 x 150 x 450 mm, made of the same concrete mix proportions to be used in the pavement,
but with a maximum aggregate size of 20 mm and cured in accordance with BS EN 12390-2. At 7 days
a tensile load shall be applied to achieve a movement of the bar of at least 0.25 mm. The average bond
stress to achieve this movement shall be not greater than 0.89 N/mm2.
8 (02/16) For expansion joints, a closely fitting cap 100 mm long consisting of waterproofed cardboard or suitable
synthetic material shall be placed over one end of each dowel bar. An expansion space 10 mm greater than the
thickness of the joint filler board shall be formed between the end of the cap and the end of the dowel bar.
3 (02/16) Tie bars in warping joints and wet-formed longitudinal joints shall be made up into rigid assemblies with
adequate supports and fixings to remain firmly in position during the construction of the slab.
4 (02/16) Alternatively, tie bars at longitudinal joints may be mechanically inserted by vibration from above using
a method which ensures recompaction of the concrete around the tie bars.
5 (02/16) At longitudinal construction joints, tie bars may be adequately fixed to side forms or inserted into the side
of the slab by a method which ensures recompaction of the concrete around the tie bars and adequate bond.
6 (02/16) Tie bars in warping joints shall be positioned from the top surface of the slab within +20, -10 mm of the
mid depth of the slab.
Tie bars in other joints shall be positioned and remain within the middle third of the slab depth, approximately
parallel to the surface and approximately perpendicular to the line of the joint, with the centre of each bar on the
intended line of the joints within a tolerance of ± 50 mm, and with a minimum cover of 30 mm below any top crack
inducer of joint groove for slabs 200 mm thick or more, or 20 mm for slabs up to 200 mm thick.
7 (02/16) At transverse construction joints in continuously reinforced concrete, tie bars shall be 1.5 m long
and of the same Grade and size as the longitudinal reinforcement, and shall be fixed at twice the normal spacing
midway between the longitudinal reinforcement bars so that 750 mm ± 50 mm extends each side of the joint
at the same level as the longitudinal reinforcement and be tied to the transverse reinforcement. Where paving
from a construction joint is not resumed within 5 days, an extra longitudinal reinforcement bar 8 m long shall be
lapped and tied to each tie bar. These extra bars may be combined with the tie bars. Where the spacing between
longitudinal reinforcement and the extra 8 m long bars is less than 90 mm, the nominal size of aggregate shall be
20 mm for a sufficient number of concrete batches to complete that section of pavement.
}
All joints, except where B500C
Transverse reinforcement 750 600
is permitted in lieu
or 16 Grade B500B or 600 600
B500C
or 20 Grade B500B or 500 600
B500C
Transition from rigid to flexible 20 Grade B500B or 1000 300
construction B500C
NOTE: The transverse reinforcement may be continued across the joint in reinforced concrete if the bars are of a minimum nominal diameter
of 12 mm and the bars are protected from corrosion and the cover is as required in this Clause.
8 (02/16) Where tie bars are used in longitudinal joints in continuously reinforced concrete they shall be placed at
the same level as the transverse reinforcement and tied to the longitudinal reinforcement.
(b) This thickness, expressed as a percentage of the original thickness, is the ‘recovery’ value of the
specimen. The thicknesses shall be measured to an accuracy of 25 micron. The two new specimens
shall be weighed before and after testing. The difference in mass shall be determined with an
accuracy of 0.1% and shall be expressed as a percentage of the original mass of the specimen.
(c) The material shall be deemed to have passed the test if all four specimens have recovery values of
at least 70% and the two new specimens have not suffered a reduction of mass in excess of 1%.
(iii) Extrusion Test
(a) The third sample which passes the weathering test shall be trimmed to 100 mm square ± 0.5 mm
and be subjected to the following extrusion test.
(b) The extrusion mould shall be 100 mm x 100 mm (+ 0.5 mm, - 0) internally, of sufficient depth
to test the sample as received, open on one side only and fixed rigidly to a base plate. The mould
shall be provided with a closely fitting pressure plate which shall fit without binding, and with
an accurate horizontal measuring dial gauge or measuring device accurate to 25 microns. The
specimen shall be mounted in the extrusion mould and loaded once as described in the compression
and recovery test. The extrusion at the open side of the mould shall be measured with the gauge
when the specimen is compressed to 50% of its original thickness and before release of the load.
(c) The material shall be deemed to have passed the test if the extrusion of the free edge does not
exceed 6 mm.
6 (02/16) For hot and cold applied sealants, compressible caulking material, debonding strip or tape or cord
compatible with the sealant, of a suitable size to fill the width of the sealing groove, shall be firmly packed or
stuck in the bottom of the sealing groove to such a depth so as to provide the correct depth of seal as described in
Table 10/6 with the top of the seal at the correct depth below the surface of the concrete.
7 (02/16) All grooves shall be cleaned of any dirt or loose material by air blasting with filtered, oil-free
compressed air. The groove shall be clean and dry at the time of priming and sealing.
8 (02/16) For applied sealants the joint grooves shall be primed with the relevant primer for the hot or cold applied
sealant in accordance with the manufacturer’s recommendations and with BS 5212 : Part 2, except that when
necessary the joint grooves may be primed and sealed earlier than 14 days after construction, as soon as the grooves
have been grit-blasted and cleaned.
Type and Spacing of Joints (m) Minimum Minimum Depth of Seal (Note 1) Impregnated Depth of
Width Foam Seal Below
Cold Applied Hot Applied Compression the Concrete
Strips Surface
mm mm mm mm mm
Contraction
15 and under 13 (Note 2) 13 15 30 5±2
Over 15 to 20 20 15 30 30 5±2
Over 20 to 25 30 20 25 40 5±2
Expansion 30 20 25 40 7±2
Transverse Warping 10 10 13 30 5±2
Longitudinal Joints (if sealed) 10 10 13 30 0 to 5
Gully and Manhole Slabs 20 15 20 30 0 to 3
NOTE (1): The depth of seal is that part in contact with the vertical face of the joint groove. The depth of seal below the surface shall be
taken at the centre of an applied seal relative to a short straight edge, 150 mm long, placed centrally across the joint within 7 days of sealing.
NOTE (2): For cork seals other than in construction joints, grooves shall be 20 mm width, 50 mm depth.
6 (02/16) The guide wires shall be supported from stakes not more than 8 m apart by connectors capable of fine
horizontal and vertical adjustment. The guide wire shall be tensioned on the stakes so that a 500 gramme weight
shall produce a deflection of not more than 20 mm when suspended at the mid-point between any pair of stakes.
The ends of the guide wires shall be anchored to fixing points which shall be not closer to the edge of the slab than
the row of stakes and in no circumstances shall a guide wire be anchored to a stake.
7 (02/16) The stakes shall be positioned and the connectors maintained at their correct height and alignment from
1200 hours on the day before concreting takes place until 36 hours after the concrete has been finished. The guide
wire shall be erected and tensioned on the connectors at any section for at least two hours before concreting that
section.
Temperature of concrete at discharge Reinforced concrete slabs constructed in All other concrete slabs
from the delivery vehicle two layers, without retarding admixtures
Mixing first Between layers Mixing first Between layers in
Time is function of degree hours see layer to finishing layer to finishing two layer work
RCC concrete concrete
Not more than 25°C hours 3 hours half hour 3 hours 1.5 hours
Exceeding 25°C hours but not exceeding 2 hours half hour 2 hours 1 hour
30°C hours
Exceeding 30°C hours Unacceptable for – Unacceptable for –
paving paving
5 (02/16) Prior to being compacted, the surface level of each loose spread layer shall be adjusted to the correct
surcharge by means of rotating strike-off blades or a screw device.
6 (02/16) The concrete shall be compacted by vibration or by a combination of vibration and mechanical tamping
so as to comply with Clause 1003 throughout the full depth of the slab. Poker vibrators shall be used in each layer
adjacent to the side forms and the edge of a previously constructed slab.
7 (02/16) The initial regulation and finish to the surface of the slab shall be effected by means of a beam
oscillating transversely or obliquely to the longitudinal axis of the pavement. This beam shall be readily adjustable
for both height and tilt.
8 (02/16) Joint grooves shall be constructed in compliance with Clause 1013. When grooves are wet-formed, the
concrete shall be re-compacted around the former by a hand held vibrating plate compactor drawn along or on each
side of the joint, prior to the final regulation of the surface by a longitudinal oscillating float.
9 (02/16) The regulation and finishing of the surface of the slab shall be carried out by a machine which
incorporates twin oblique oscillating finishing beams which shall be readily adjustable for both height and tilt. The
beams shall weigh not less than 170 kg/m, be of rectangular section and span the full width of the slab. The leading
beam shall be vibrated. The beams shall be supported on a carriage, the level of which shall be controlled by the
average level of not less than four points evenly spaced over at least 3.5 m of the supporting rail, beam, or slab, on
each side of the slab that is being constructed. Except for CRCB slabs, the final regulation of the surface of the slab
shall be provided by a longitudinal oscillating float, travelling across the slab. After the final regulation and before
the macrotexture is applied, any excess concrete on top of the joint groove former, where present, shall be removed.
Additionally the longitudinal oscillating float shall complete the traverse of the slab in both directions within the
length of the float and shall have a total longitudinal stroke of 200 mm to 300 mm.
10 (02/16) The longitudinal oscillating float shall have a minimum length of 3 m and a minimum constant width of
250 mm with a maximum weight of 10 kg/m. The edges of the float shall be curved or chamfered.
11 (02/16) A minimum length of 500 mm of longitudinal oscillating float shall be within the length of the machine
tracks or wheels.
12 (02/16) When a concrete slab is constructed in more than one width, flanged wheels on the paving machines
shall not be run directly on the surface of any completed part of the slab. The second or subsequent slabs shall be
constructed either by supporting machines with flanged wheels on flat-bottom section rails weighing not less than
15 kg/m laid on the surface of the completed slab, or by replacing the flanged wheels on that side of the machines
by smooth flangeless wheels. Before flangeless wheels or rails are used, the surface regularity of the slab over
which they are to pass shall comply with Clause 702 and its surface shall be thoroughly cleaned and brushed to
remove all extraneous matter. Flangeless wheels or rails shall be positioned sufficiently far from the edge of the
slab to avoid damage to that edge.
(02/16) Construction by Slip-form Paving Machine
13 (02/16) A slip-form paving train shall consist of powered machines which spread, compact and finish the
concrete in a continuous operation.
14 (02/16) The slip-form paving machine shall compact the concrete by internal vibration and shape it between
sliding side forms or over fixed side forms by means of either a conforming plate or by vibrating and oscillating
finishing beams.
15 (02/16) The concrete shall be deposited without segregation in front of the slip-form paver across its whole
width and to a height which at all times is in excess of the required surcharge. The deposited concrete shall be
struck off to the necessary average and differential surcharge by means of a strike-off plate or a screw auger device
extending across the whole width of the slab. The equipment for striking off the concrete shall be capable of being
rapidly adjusted for changes of the average and differential surcharge necessitated by changes in slab thickness or
crossfall.
16 (02/16) The level of the conforming plate and finishing beams shall be controlled automatically from the guide
wires by sensors attached at the four corners of the slip form paving machine. The alignment of the paver shall be
controlled automatically from the guide wire by at least one sensor attached to the paver. The alignment and level
of ancillary machines for finishing, texturing and curing of the concrete shall be automatically controlled relative to
the guide wire or to the surface and edge of the slab.
17 (02/16) Slip-form paving machines shall have vibration of variable output, with a maximum energy output of
not less than 2.5 kW per metre width of slab per 300 mm depth of slab for a laying speed of up to 1.5 m per minute
or pro rata for higher speeds. The machines shall be of sufficient mass to provide adequate reaction on the traction
units to maintain forward movements during the placing of concrete in all situations.
18 (02/16) Except for CRCB slabs, the final regulation of the surface slab shall be provided by a longitudinal
oscillating float travelling across the slab. The longitudinal float shall comply with the requirements of
sub-Clauses 9, 10 and 11 of this Clause. Additionally, the longitudinal float shall either be a separate machine
closely following a slip-form paver or alternatively it shall be attached to a slip-form paver in such a manner that it
functions effectively and does not adversely affect the performance of the paver or the surface of the slab.
19 (02/16) Joint grooves shall be constructed in compliance with Clause 1013. Where grooves are wet-formed
the concrete shall be compacted around the former by a separate vibrating plate compactor with twin plates. The
groove former shall be compacted to the correct level by a vibrating pan which may be included with the transverse
joint finishing beam. Final finishing shall be carried out in accordance with sub-Clause 18 of this Clause. Any
excess concrete on top of the groove former shall be removed before the surface is macrotextured.
20 (02/16) Where a concrete slab is constructed in more than one width or where the edge needs to be matched
for one level to another section of surface slab, and the surface levels at the edges are not achieved, the slab shall
be supported by separate side forms placed before or after the paver to ensure that edge levels meet the required
tolerances.
(02/16) General
21 (01/20) While the concrete is still plastic its surface shall be treated to comply with the macrotexture
requirements specified in Clause 1026. The surface and edges of surface slabs and CRC bases shall be cured in
compliance with Clause 1027. Lower Strength concrete bases and subbases shall be cured in compliance with
Clause 1030.
22 (01/20) The spreading, compacting and finishing of the concrete shall be carried out as rapidly as possible
and the paving operation shall be so arranged as to ensure that the time between the mixing of the first batch of
concrete in any transverse section of the slab and the application of the sprayed curing membrane to the surface
of that section shall not exceed those given in Table 10/7. This working time is a function of degree hours see
sub- Clause 1054.3.
23 (02/16) Each bay in jointed concrete surface slabs shall be consecutively numbered near the verge, next to a
transverse joint while the concrete is plastic. In continuously reinforced concrete pavement the slab shall be marked
with the chainage at intervals not greater than 50 m apart.
4 (02/16) The macrotexture depth shall be determined by the volumetric patch technique as described in
BS EN 13036-1. Tests shall be taken within 100 m of commencement of paving and thereafter at least once for
each day’s paving at the times after construction as given below and in the following manner: 10 individual
measurements of the macrotexture depth shall be taken at least 2 m apart anywhere along a diagonal line across a
lane width between points 50 m apart along the pavement. No measurement shall be taken within 300 mm of the
longitudinal edges of a concrete slab constructed in one pass.
5 (02/16) Macrotexture depths shall be as required in Table 10/8.
6 (02/16) Where the required macrotexture depth is found to be deficient the Contractor shall make good the
texture across the full lane width over lengths necessary to comply with the requirements of Table 10/9, by
retexturing the hardened concrete surface as described in Clause 1029. Failure to achieve a satisfactory minimum
macrotexture depth by random grooving shall result in the removal of the full thickness of the slab to the extent
required to permit reconstruction of the slab in accordance with the specification. If the macrotexture depth is
excessive the surface shall be planed or ground or otherwise treated over lengths necessary to comply with the
requirements of Table 10/8. The treatment shall not affect the requirements of Clause 702 in respect of surface
levels or surface regularity.
12 (01/20) The average locked wheel friction of the SIPT road surface macrotexture depth of the surface shall
be measured in accordance with ASTM E274/E274M – 11, at a speed of 90 km/hr rather than 40 mph in the test
method, using a tyre that complies with ASTM E524 – 08.
13 (01/20) A SIPT method statement shall be prepared. The SIPT shall demonstrate, and enable verification of, the
installation procedures given in the SIPT method statement. This will include working methods and equipment, any
limitations, aftercare, testing methods and frequency of testing.
14 (01/20) A SIPT inspection protocol shall be prepared. It shall demonstrate qualitatively and quantitatively the
applicability of the SIPT for the system in order to satisfy the performance requirements.
15 (01/20) The SIPT method statement, SIPT inspection protocols, all inspection and testing results and the SIPT
certification shall be submitted to the Overseeing Organisation prior to the commencement of concrete pavement
construction.
16 (01/20) The SIPT shall include the following to be undertaken by the Certification Body:
(i) verification that the system installation trial has been undertaken in accordance with the SIPT method
statement;
(ii) assessment of the data from the site performance tests detailed in sub-Clause 17
17 (01/20) The installed performance of the system over the two-year trial period shall be assessed at the intervals
specified in Table 10/9. Data relating to properties in Table 10/9 shall be provided to the Overseeing Organisation
(02/16) Noise
18 (01/20) Where noise characteristics for the surface are specified in contract specific Appendix 7/1 the SIPT shall
include the assessment and measurement of the road/tyre noise levels. The road/tyre noise level of the concrete
shall be assessed as detailed in sub-Clauses 19 to 27 of this Clause, and declared as NR, 0, 1, 2 or 3 as described
in Table 10/10. If the SIPT site conditions are not appropriate for testing an alternative site shall be selected and
nominated.
19 (01/20) The influence of the road surface on traffic noise using the statistical pass-by method shall
be established at the SIPT site between 12 and 24 months after opening to traffic in accordance with
ISO 11819- 1: 2002, Sections 7 and 8.
20 (01/20) Acoustic measurements shall only be carried out when the road surface is dry and the meteorological
conditions specified in ISO 11819-1: 2002, Section 11 are met.
21 (01/20) The air and surface temperatures are monitored in accordance with the procedure described in
ISO 11819-1: 2002, Clause 8.5. The road surface temperature, T surface, must be within 5°C to 50°C during
acoustic measurements. The air temperature, T air, must be within 5°C to 30°C.
22 (01/20) The test location road speed category shall be classified as either Medium or High as defined in
ISO 11819-1: 2002, clause 3.3. Not less than two test locations are selected for each road speed category, which
may be at the same site, provided the locations are at least 100 m apart or on different carriageways. Each test
location shall be representative in terms of road speed category and traffic level. Each of the test sites selected must
meet the requirements of ISO 11819-1: 2002 Section 6 and ISO/CD 11819-2: 2000. The road must be essentially
straight, or bends with a radius of curvature greater than 500 m for medium-speed, and 1000 m for high-speed road
categories. The crossfall of the test lane at the test site must not exceed 4%.
23 (01/20) The apparatus described in ISO 11819-1: 2002 Section 5 are used. The frequency range of between
100 and 5000 Hz (centre frequencies of the one-third octave bands) should be covered.
24 (01/20) The macrotexture of the road surface used for the noise assessment shall be measured in the nearside
wheel-track along the whole length of test material in accordance BS EN 13036-1: 2010. The macrotexture depth of
the nearside wheel-track in front of a test location must be within 10 per cent of the average macrotexture measured
along the site.
25 (01/20) The microphone location at each measurement site shall be recorded accurately and marked with
appropriate methods such that the position can be readily identified for a period of at least two years.
26 (01/20) When sufficient vehicle pass-bys’ have been measured, a linear regression analysis shall be performed
in accordance with ISO 11819-1: 2002, Clause 9.1. In the case of the high-speed road category, measurements must
not be taken of vehicles travelling at speeds of less than 60 km/h in accordance with AFNOR Standard S31-119.
27 (01/20) For each category of vehicle defined in Table 10/11, the Vehicle Sound Level, Lveh, shall be
calculated as the ordinate sound level of the regression line at the reference speed for the category of road. All
levels shall be calculated to two decimal places and rounded to one decimal place.
TABLE 10/11: (02/16) Reference speeds (km•h-1) for different road speed categories
Category L vehicles — light vehicles including passenger cars and car derived vans, excluding vehicles towing trailers.
Category H1 vehicles — commercial trucks with 2 axles and greater than 3.5 tonnes.
Category H2 vehicles — commercial trucks with more than 2 axles and greater than 3.5 tonnes.
4 (02/16) At least two transverse joints and one longitudinal joint of each type that are proposed for unreinforced
concrete slabs and jointed reinforced concrete slabs in the main construction in the permanent works shall be
constructed and assessed in the trial length. If in the trial length expansion joints are not demonstrated, the first
2 expansion joints and at least the first 150 m of longitudinal construction joint for mechanised paving, or 30 m for
hand guided method of construction laid in the main construction in the permanent works, shall be considered the
trial length for these joints. One construction joint shall be demonstrated in each trial length of CRCP or CRCB.
(02/16) Assessment
5 (02/16) The trial length shall comply for strength and density with the specification in all respects, with the
following additions and exceptions:
(02/16) Surface Levels and Irregularity
(i) In checking for compliance with Table 7/1 the levels shall be taken at intervals of not more than
2.5 m along any line or lines parallel to the longitudinal centre line of the trial length.
(ii) The maximum number of permitted irregularities of pavement surfaces shall comply with the
requirements of Table 7/2 for 300 m lengths. Shorter trial lengths shall be assessed pro-rata based on
values for a 300 m length.
(02/16) Joints
(iii) At least 3 cores of minimum diameter 100 mm shall be taken from the slab at joints to check the lateral
and vertical location of joint grooves and bottom crack inducers.
(iv) Alignment of dowel bars shall be inspected as described in Clause 1019 in any two consecutive
transverse joints. If the position or alignment of the dowel bars at one of these joints does not comply
with Clause 1011 but if that joint remains the only one that does not comply after the next 3 consecutive
joints of the same type have been inspected then the method of placing dowels shall be deemed to be
satisfactory. In order to check sufficient joints for dowel bar alignment without extending the trial length
unduly, the Contractor may construct joints at more frequent joint intervals than the normal spacing
required in contract specific Appendix 7/1.
(v) If there are deficiencies in the first expansion joint that is constructed as a trial the next expansion joint
shall be a trial joint. Should this also be deficient further trial expansion joints shall be made as part of a
trial length. Deficient expansion joints shall not form part of the permanent works.
(02/16) Position of Reinforcement and Tie Bars
(vi) Compliance with Clause 1008 for the position of steel reinforcement and Clause 1012 for the position
and alignment of tie bars shall be checked by drilling additional cores from the slab unless they can be
determined from cores taken for density assessment.
(02/16) Completion of Trial
6 (02/16) The Contractor shall not proceed with normal working unless the trial length complies with the
specification and any earlier defective trial lengths have been removed, unless they can be remedied to comply with
the specification.
7 (02/16) After satisfactory completion of the trial length, the constituent materials, concrete proportions,
plant, equipment and construction methods shall not thereafter be changed, except for normal adjustments and
maintenance of plant, unless the Contractor lays a further trial length as described in this Clause to demonstrate that
the changes will not adversely affect the permanent works or agrees the changes with the Overseeing Organisation.
(02/16) Compaction
4 (01/20) The spread Lower Strength concrete shall be compacted using internal or external vibration, or a
combination of both to meet the required density. Compaction and finishing to level shall be completed within the
times given in Table 10/7.
(02/16) Joints
5 (02/16) At transverse and longitudinal construction joints between two separately constructed slabs, the
previously laid slab end or edge shall present a vertical face before construction of subsequent slabs.
6 (01/20) Longitudinal joints in Lower Strength concrete shall be staggered by at least 300 mm from the position
of longitudinal joints in any superimposed concrete slab, and by 1m for transverse joints.
(02/16) Curing
7 (01/20) The surface shall be cured, without disturbance, for a minimum period of 7 days, by the application of
a resin based aluminised curing compound, or polythene sheeting or a sprayed plastic film which hardens into a
peelable plastic sheet.
(02/16) Sampling for Testing
8 (02/16) Sampling shall be as specified in Clause 1003.
(02/16) Density
9 (02/16) The density shall be determined as required in Clause 1003.
(02/16) Strength
10 (02/16) The strength shall be determined as in Clause 1004.
(02/16) Trial Concrete Mixes
11 (02/16) Trial concrete mixes shall conform with BS 8500-2 for designed concretes for strength class C12/15 and
above or CC14 and above, unless recent data relating entirely to the proposed concrete, satisfies the requirements of
the specification.
(02/16) Trial Length
12 (01/20) At least 10 days before the start of the main Lower Strength concrete works a trial length of at least
400 m2 for mechanised construction and 30 m for hand-guided methods shall be constructed. The trial length shall
be laid to assess the suitability of the proposed material, plant, equipment and construction methods to meet the
requirements of the specification. The main construction in the permanent works shall not start unless the trial
length complies with the specification. If any trial length does not conform to the specification another trial length
shall be constructed. Trial lengths not complying shall be removed unless they can be rectified to comply with the
specification.
13 (02/16) After satisfactory completion of the trial, the material, plant, equipment and construction methods shall
not be changed unless the Contractor lays a further trial length to assess the suitability of the proposed changes or
agrees the changes with the Overseeing Organisation.
(02/16) Surface Finish
14 (01/20) The surface of the Lower Strength concrete after compaction and finishing and before overlaying shall
be free from ridges, loose material, pot holes, ruts or other defects.
4 (01/20) A surface texture as specified in Clause 1026 shall be applied and a sprayed resin based, aluminized
curing compound.
5 (01/20) Joints surrounding the new bay shall be sealed specified in Clause 1016.
1039 (02/16) Summary of Rates for Sampling and Testing Concrete for Pavement Layers
1 (02/16) Unless otherwise stated in contract specific Appendix 1/5, Table 10/12 summarises the minimum rates of
sampling and testing of specimens to the specification.
2 (02/16) Samples for testing shall be taken at the point of placing or from the relevant pavement layer.
TABLE 10/12: (01/20) Rates for Sampling and Testing Concrete for Pavement Layers
1004 Strength a) Main slab 3 cubes per 400m2 not less than 6 sets per day. 1 to be tested
at 7 days and 2 at 28 days.
1019 Inspection of dowel a) Main slab 1 joint per 1500 m length or 1 joint per 5 days whichever is
alignment the sooner
b) Slabs less than 1500 m in length At a rate of one joint for up to each 100 joints
1026 Macrotexture depth Each lane width One within 100 m of commencement of paving and
thereafter at least one set of 10 measurements per day’s work.
Strength a) Main slab 3 cubes per 600m2 not less than 6 sets per day
At least 6 cubes, half to be tested 7 days and half at 28 days
b) Trial length 3 cubes per 600m2 not less than 6 sets per day
At least 6 cubes, half to be tested 7 days and half at 28 days
(iv) The coarse aggregate shall comprise at least 60% by mass of the oven dry constituents of the concrete.
(v) The polished stone value (PSV) and the aggregate abrasion value (AAV) of the coarse aggregate
determined in accordance with BS EN 1097-8 shall be as specified in contract specific Appendix 7/1.
The Category of flakiness index of the aggregate is FI15.
(vi) Hardness and durability of the coarse aggregate shall be as described in sub-Clause 901.2.
(vii) The type of cement used in the concrete shall be limited to Class 42.5N/42.5R Portland cement CEM I
complying with BS EN 197-1. The minimum cement content of the concrete shall be 375 kg/m³ and the
maximum free water/cement ratio shall be 0.40.
(viii) The air content, density and strength requirements shall be as required in Clauses 1002, 1003 and 1004
respectively.
(02/16) General Construction Requirements
6 (02/16) The concrete paving equipment shall comply with contract specific Appendix 10/1 as completed by the
Contractor and submitted at Tender stage for approval by the Overseeing Organisation before the work commences.
The general construction requirements shall be in accordance with the requirements of this Series except where
otherwise stated in this Clause:
(i) The concrete carriageway paving operation shall be undertaken as not less than a single lane width of
construction using either slip-form paving machines or fixed form paving machines.
(ii) The concrete surface layer shall be fed, spread, compacted, regulated and finished using equipment with
elements to obtain the required uniform distribution and bonded embedment of the selected aggregate in
the finished road surface.
(iii) The spread concrete shall be compacted in such a manner that base layer concrete is not drawn into the
surfacing and selected aggregate is uniformly present in the finished road surface.
(iv) The surface layer shall be compacted and shaped to line and level by a combination of either internal
vibration and fixed conforming plate or vibrating conforming plate.
(v) The final regulation of the surface layer shall be provided by a transverse finishing screed in advance
of a longitudinal oscillating float in accordance with Clause 1024, travelling across the slab before the
application of a retarder complying with BS EN 934-2.
(02/16) Finished Surface Requirements
7 (02/16) The finished surface of the pavement shall comply with the requirements of Clause 702. Where
a pavement area does not comply with the specification for regularity, surface tolerance, thickness, material
properties or compaction or contains surface depressions, the full extent of the surface which does not comply
with the specification shall be rectified by cutting out the full depth of the slab. It shall be replaced with a new
slab complying with the procedures set out in Clause 1033 to the extent required to obtain compliance with the
specification.
(02/16) Production of an Exposed Aggregate Surface
8 (02/16) In order to obtain a suitable exposed aggregate surface the main requirement shall be the removal of the
surface mortar from the top of the slab to produce an exposed aggregate finish. This objective may be achieved by
the application of a suitable cement set retarder which is sprayed on the surface of the fresh concrete immediately
after it has been levelled and finished. Retarded mortar shall be removed by wet or dry brushing as stated in
contract specific Appendix 10/1, generally no sooner than when the surface concrete has reached a maturity of
16 hours at 20°C or after a suitable interval determined by trial, to achieve the requirements of sub-Clause 27 of
this Clause.
(02/16) Retarder
9 (02/16) The composition and viscosity of the retarder shall be such that it can be spread at an adequate and
uniform rate over the surface of the concrete slab in order to ensure adequate aggregate exposure during the
subsequent brushing operation.
10 (02/16) The retarder shall contain a pigment in sufficient quantity to give an even uniform colour after it has
been sprayed on to the slab surface. The pigment shall be fully degraded by exposure to ultra-violet light without
leaving any residue that is detrimental to the surface of the concrete.
11 (02/16) The chemical composition of the retarder and of the curing compound shall be such that they do not
react adversely following the application of the curing compound to the exposed aggregate surface.
12 (02/16) The Contractor shall use the retarder which he has nominated in contract specific Appendix 10/1.
This shall be of a type and composition to satisfy the requirements of this Clause.
(02/16) Application of the Retarder
13 (02/16) The retarder shall be spread evenly on to the surface of the wet concrete slab as soon as practicable
after the surface layer has been levelled and finished, by a spray bar over the full width of the slab in one pass. To
achieve this uniformity of spread, the spraying system shall consist of a spray bar, provided with nozzles, mounted
on a machine spanning the slab. Temporary works materials and equipment shall be chosen in order to permit
inspection to ensure adequate coverage of retarder immediately after spraying and before protection of the surface.
14 (02/16) Before commencing work, the level of the spray bar, the rate of delivery of the retarder from the nozzles
of the spray bar, and the forward speed of the spraying machine shall be adjusted to achieve the required rate of
spread. Means shall be provided and steps shall be taken to avoid excess retarder flowing on the surface of the slab.
15 (02/16) Back-up spraying equipment shall be available on the site at all times for use in case of a breakdown of
the spraying machine.
(02/16) Protection of the Surface after the Application of the Retarder
16 (02/16) The finished surface of the pavement concrete after application of retarder shall be protected against
precipitation, moisture loss, contamination and dispersal of the retarder by air movements as stated in contract
specific Appendix 10/1. This protection shall be applied immediately after the application of the retarder.
17 (02/16) Where waterproof sheeting is used it shall be laid onto the surface of the concrete immediately after the
retarder has been sprayed. It shall be retained in position until immediately prior to exposing of the aggregate.
18 (02/16) The protection system shall not adversely affect either the finish, the line or the level of the concrete
surface or the even distribution of the retarder in any way. Where sheeting is used, any air bubbling or blistering
shall be prevented.
(02/16) Exposing the Aggregate Surface
19 (02/16) Brushing equipment shall be used to expose the concrete surface aggregate. Where the brushing
equipment runs on the slab the concrete shall have gained sufficient strength to avoid any damage to the concrete.
20 (02/16) Removal of the protection system shall take place as brushing proceeds. If waterproof sheeting is used
as a protection system it shall be maintained in position until immediately in advance of the brushing operation.
21 (02/16) The Contractor shall complete the process of exposing the aggregate before the retarder becomes
ineffective. Failure to do so shall entail the remedial measures specified in sub-Clauses 29 and 30 of this Clause.
(02/16) Brushing System
22 (02/16) Sufficient brushing capability shall always be maintained on site to complete the exposure of the
aggregate before the retarder becomes ineffective. An adequate back-up brushing facility shall be available on the
site at all times for use in case of a breakdown of the brushing equipment.
23 (02/16) The brushing equipment nominated by the Contractor in contract specific Appendix 10/1 shall be used to
produce an even macrotexture on the surface of the slab. Brushing shall be carried out in the longitudinal direction
of the concrete slab.
24 (02/16) The brushing equipment shall be capable of maintaining an adequate brush rotational speed which in
conjunction with the forward working speed is sufficient to remove the surface mortar. Adequate dust suppression
and collection measures shall be in operation at all times.
25 (02/16) When complying with the requirements of sub-Clause 19 of this Clause, the wheels of any brushing
equipment which may run on the slab shall be fitted with tyres with a shallow tread pattern and a low inflation
pressure and be sufficiently wide to avoid damage to the concrete.
(02/16) Protection of the Surface Layer After Exposure of the Aggregate
26 (02/16) Within one hour of completing exposure of the aggregate the surface shall be dampened with water.
A curing compound shall be applied to the entire exposed aggregate surface of the slab in accordance with
Clause 1027. In wet weather the curing compound shall be applied as soon as practicable after the rain stops. The
surface may, alternatively, be covered by hessian provided it is maintained in a wet condition at all times during the
curing period of the concrete.
(02/16) Surface Macrotexture Depth and Remedial Measures
27 (02/16) The texture depth of the surface of the concrete shall be measured using a volumetric patch technique
described in BS EN 13036-1. The average macrotexture depth of each 1000 m section of carriageway lane, or each
carriageway lane where less than 1000 m, shall comply with the requirements of contract specific Appendix 7/1.
Any individual result shall be neither greater than the maximum, nor be less than the minimum value of
macrotexture depth stated in contract specific Appendix 7/1.
28 (02/16) During brushing, initial interim spot check measurements of the surface macrotexture depth shall be
made as soon as it is considered that the required texture depth has been reached. This shall continue until the
specified macrotexture depth has been achieved.
29 (02/16) In the event that it is not possible to achieve the specified minimum macrotexture depth by further
exposure, the Contractor shall treat the surface in accordance with Clause 1029 to achieve the specified
macrotexture depth. This treatment shall not be applied until the concrete has reached an age of 28 days and shall
not affect the requirements of sub-Clauses 702.2 to 702.4 and 702.5 to 702.9.
30 (02/16) Failure to achieve a satisfactory minimum macrotexture depth by mechanical means shall result in
removal of the full thickness of the slab to the extent required to permit reconstruction of the slab in accordance
with the specification. Where the maximum macrotexture depth is exceeded suitable remedial measures shall be
employed.
(02/16) Preliminary Trials
31 (02/16) The Contractor shall carry out preliminary trials to demonstrate to the Overseeing Organisation, not less
than one month prior to the commencement of the trial length referred to in sub-Clauses 37 to 39 of this Clause, the
materials, concrete proportions and methods for achieving the macrotexture depth requirements defined in contract
specific Appendix 7/1.
32 (02/16) Preliminary trial panels shall be constructed off-line incorporating a top surface of exposed aggregate
concrete similar to that specified for the permanent works. These panels shall be 20 m long and not less than
100 mm deep, and the maximum intended paving width. They shall be used to enable the Contractor to determine
the required application rate of the retarder and the amount of brushing required to achieve the specified
macrotexture depth.
33 (02/16) The trial panels may alternatively be constructed on-site, but in this case, they may only form part of the
permanent works if they meet all the requirements of the specification, otherwise they shall be removed after they
have served their purpose.
34 (02/16) The surface macrotexture depth shall be determined by volumetric patch technique at approximately
2 m spacings along a diagonal line across each trial panel, and shall follow the procedure described in
BS EN 13036-1.
35 (02/16) The average value of each set of 10 individual measurements shall be taken as the resulting
macrotexture depth which shall be assessed against the specification.
36 (02/16) The materials including all the aggregates, plant and equipment used in the preliminary trials shall be
equivalent to that which will be used in the Trial Length.
(02/16) Trial Length
37 (02/16) In addition to the requirements of Clause 1028, the macrotexture depth shall be tested for compliance in
accordance with sub-Clauses 38 and 39 of this Clause.
38 (02/16) Macrotexture depth shall be assessed by the volumetric patch technique for each 50 m length of the trial
length and for each lane, and shall follow the procedure in BS EN 13036-1.
39 (02/16) During the construction of the Trial Length, spot checks shall be made as soon as it is considered that
the required macrotexture depth has been reached. Should the texture depth be found to be inadequate, further
exposure of the aggregate shall be undertaken until the specified macrotexture depth has been achieved. Where the
macrotexture depth is not achieved, and the trial was intended to form part of the running surface of the permanent
works, the remedial measures described in sub-Clauses 29 and 30 of this Clause shall apply.
3 (02/16) In the absence of test data establishing compliance with sub-Clause 2 of this Clause, no vehicle with an
axle loading greater than 2 tonnes shall run on concrete slabs within a period of 14 days after placing the concrete.
Vehicles with rubber tyres with an axle loading less than 2 tonnes, or wheels or tracks of concreting plant, shall
not use any part of a newly constructed pavement within 7 days. The above periods before traffic may run on the
pavement shall be increased if the 7 day cube strength is below that required in the specification. These periods
shall be extended by one day for each night on which the temperature of the layer falls to 0ºC or below.
See NOTE 1
(f) A BS 8500-2 combination of Portland cement CEM I 270 kg/m3
conforming to BS EN 197-1 with not more than 35% fly-ash for use
as a cementitious component in structural concrete conforming to
BS EN 450-1 (SEE NOTE 2)
NOTE 1:
CEM II/A-V has a maximum siliceous fly ash content of 20%
CEM II/B-V has a maximum siliceous fly ash content of 35%
CEM IV/A (V) has a maximum siliceous fly ash content of 35%
NOTE 2: Siliceous fly ash conforming to EN 14227-4 may be used where it meets the BS 8500-2:2015 Annex A
compressive strength requirements.
For materials required to comply with BS EN 197-1 and/or BS EN 450-1 the Contractor shall submit the relevant
material declarations of performance to the Overseeing Organisation prior to the inclusion of the materials into
the works. The declarations of performance shall demonstrate that the materials meet the requirements for the
specification.
(01/20) Aggregates
2 (01/20) The aggregates used in RCC shall comply with BS EN 13242 and have declared values for the
requirements listed in Table 10/14. The Contractor shall submit the declaration of performance for the aggregate to
the Overseeing Organisation prior to the inclusion of the aggregate in the works. The declaration of performance
shall demonstrate that the aggregate meets the requirements for the specification.
5 (01/20) Laying shall be carried out in a way that avoids segregation and drying of the surface. Curing shall
be undertaken in accordance with sub-Clause 1054.19 as soon as practicable, and the curing compound shall be
applied prior to drying of the surface.
6 (01/20) Compaction of RCC shall be carried out by rollers to achieve the design compaction as demonstrated in
the installation trial.
7 (01/20) The minimum compacted thickness shall be 150 mm.
8 (01/20) Making-up of level after initial compaction is not permitted.
9 (01/20) The edge of hardened RCC material shall be vertical and straight before fresh RCC material is laid
against it within the permitted construction period in sub-Clauses 1054.2 and 1054.3. To ensure adequate bond
between wet joints compaction shall be completed before drying and within the permitted construction period in
sub-Clauses 1054.2 and 1054.3.
10 (01/20) Compaction of RCC layers by a method proven in the Trial Length (or by previous satisfactory
experience on similar projects) to provide the required density and finished profile shall be completed without
drying out and before setting of any part of the layer. Testing, controls and checking of RCC shall be carried out in
accordance with the requirements in Clause 1059.
11 (01/20) On completion of compaction the surface shall be closed, free from ridges, cracks, loose material,
visible voids, ruts, shear planes and other defects.
12 (01/20) Reworking and re-compaction of the layer to achieve the required surface finish shall only be
permitted within the construction period set out in sub-Clauses 1054.2 and 1054.3 and only when the water
content requirements of the reworked material are maintained within the limits stated in the method statement.
If rectification is not completed within the specified time period the defective area shall be removed to the full
thickness of the layer and new mixture machine laid and compacted. The minimum length of full depth replacement
shall be 15m and full width of a traffic lane.
13 (01/20) The exposed uncompacted edges of the longitudinal and transverse day joints shall be cut back to a
minimum 1.5 times the layer thickness.
14 (01/20) Transverse and longitudinal day joints shall be formed before commencing further work by sawing
vertically to the full depth.
15 (01/20) Unless otherwise specified in contract specific Appendix 7/1, all longitudinal joints shall be formed
outside wheel path zones.
16 (01/20) Longitudinal day joints shall be subject to density testing procedures 300mm from the edge. The density
shall be within 95% of that measured for the relevant test section.
17 (01/20) During cold weather:
(i) the temperature of RCC shall not be less than 5ºC at the time of laying;
(ii) RCC shall not be laid on a frozen surface;
(iii) laying of RCC shall cease when the air temperature falls below 3ºC, and laying shall not be resumed
until the rising air temperature reaches 3ºC.
18 (01/20) In the case of heavy or persistent rain, production shall cease and any laid material shall be compacted
immediately. The above also applies for light rain that results in any roller pick up and/or ponding of water on the
uncompacted RCC.
(01/20) Curing, Protection and Use of Surfaces by Traffic and Construction Plant
19 (01/20) On completion of compaction the layer shall be cured to prevent loss of water by the following.
(i) Application of a bitumen emulsion spray complying with Class C40B4, as specified in the National
Foreword to BS EN 13808 to produce an even and complete coverage of at least 0.2 kg/m2 of residual
bitumen. Before spraying commences, the surface shall be free of all loose material and standing water.
The curing membrane shall be protected from any damage until the construction of the overlaying layer.
(ii) Application shall be by metered mechanical spraying equipment, spray tanker or spraying device to
ensure consistent and adequate cover rate. The machine spread rate shall be calibrated using the method
in BS 594987. The spraying equipment used shall not cause permanent deformation in the surface. For
small or inaccessible areas, application may be by hand held sprayer.
20 (01/20) RCC shall not be trafficked within 7 days of laying unless test specimens made at the time of
construction as required in Clause 1059 and cured under the same conditions as the in-situ RCC achieve 20 N/mm2.
21 (01/20) Should the RCC when trafficked exhibit signs of damage, trafficking shall cease immediately and shall
only resume once the layer has gained sufficient stability to resist damage.
22 (01/20) Surface contamination shall be avoided as far as is practicable and any unavoidable contamination shall
be removed prior to overlaying.
(01/20) Rectification
23 (01/20) Before overlaying the finished pavement, high spots shall be removed by fine milling, grinding or bump
cutting. Milling, grinding or bump cutting shall only be carried out after 7 days or when the material has achieved
a strength of 20 N/mm2. No visible damage shall be evident to the upper section of the layer. Damage can include
delamination, cracking and/or spalling of the surface.
24 (01/20) Depressions which exceed the permitted level tolerances under Clause 702 shall be removed and
replaced to the full depth of the layer. Any loose material shall be removed and replaced to the full depth of the
layer. The minimum length of the full depth replacement shall be 15m and full width of a traffic lane.
(01/20) Daily Records
25 (01/20) Daily record sheets shall be included in the Health and Safety file at the completion of the works and
shall include the following information:
(i) suppliers’ details including name/company name and address;
(ii) mixing plant production batch record results (to include: date of production, aggregate content, cement
content, added water, time of completion of mixing, vehicle identification);
(iii) records that demonstrate that the constructed layer is within the permitted tolerances;
(iv) density test measurements;
(v) sample and test locations;
(vi) site construction period records showing the time(s) of arrival, vehicle identification, time(s) of
completion of compaction and time(s) of application of curing membrane;
(vii) construction period calculated in accordance with sub-Clauses 1054.2 and 1054.3;
(viii) weather records at point of laying.
3 (01/20) The mixture strength after immersion shall be at least 80% of the non-immersed strength, when tested in
accordance with the laboratory mixture design requirements specified in Clause 1060.
4 (01/20) The method of construction shall be in accordance with Clause 1054.
5 (01/20) The laboratory performance of the mix shall comply with the requirement of contract specific
Appendix 7/1, when sampled and tested in accordance with Clause 1059.
TABLE 10/16: (01/20) Requirements for Testing, Control and Checking of RCC
Table 10/17: (01/20) Laboratory Mechanical Performance Testing Requirements for RCC
12 (01/20) Compliance of the area specified in sub-Clause 1059.5 shall be assessed using the results for test
specimens that are cured and tested in accordance with Table 10/17 using compression testing to the class of
mechanical performance specified in contract specific Appendix 7/1.
For the purposes of this specification, any reference to ‘characteristic strength’ in BS EN 14227-1 shall be
superseded by the requirements of this sub-Clause.