Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MCHW Vol 1 1000 - Web PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 51

MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS

VOLUME 1 SPECIFICATION FOR HIGHWAY WORKS

SERIES 1000
ROAD PAVEMENTS – CONCRETE
MATERIALS
Contents
Clause Title Page Clause Title Page
1000 General 2 1028 (02/16) Trial Length 30
(02/16) Strength Classes of Concrete and
1001  (01/20) Texturing of Hardened
1029 
Constituent Materials for Pavement Layers 2 Concrete by Transverse Grooves 32
1002 (02/16) Air Content 7 1030 (01/20) Lower Strength Concrete 32
1003 (02/16) Density 7 (02/16) Measurement of Macrotexture
1031 
Depth – Volumetric Patch Technique 34
1004 (02/16) Pavement Concrete Strength 8
1032 (02/16) Thin Bonded Repairs 34
1005 (02/16) Consistence (Workability) 9
(01/20) Full Depth Repairs
1033  34
1006 (02/16) Not Used 9
1034 (02/16) Bay Replacement 35
(02/16) Separation and Waterproof
1007 
Membranes 9 1035 to 1038 (01/20) Not Used 36
1008 (02/16) Steel Reinforcement 9 (02/16) Summary of Rates for Sampling
1039 
and Testing Concrete for Pavement
1009 (02/16) Transverse Joints 11
Layers 36
1010 (02/16) Longitudinal Joints 12
1040 to 1042 (02/16) Not Used 37
1011 (02/16) Dowel Bars 13
1043 (02/16) Foamed Concrete 37
1012 (02/16) Tie Bars 14
(02/16) Pavements with an Exposed
1044 
1013 (02/16) Joint Grooves 16 Aggregate Concrete Surface 37
(02/16) Groove Formers and Bottom
1014  (02/16) Weather Conditions for Laying
1045 
Crack Inducers 16 of Cementitious Materials 41
1015 (02/16) Joint Filler Board 17 1046 to 1047 (02/16) Not Used 41
(02/16) Preparation and Sealing of Joint
1016  (02/16) Use of Surfaces by Traffic and
1048 
Grooves 18 Construction Plant 41
1017 (02/16) Joint Seals 20 1049 to 1050 (01/20) Not Used42
(02/16) Joints at Manhole and Gully Slabs
1018  21 (01/20) Roller Compacted Concrete Mixtures42
1019 (02/16) Inspection of Dowel Bars 22 1051 (01/20) General Requirements for Roller
(02/16) Side Forms, Rails and Guide Wires 22
1020  Compacted Concrete (RCC) mixtures42

1021 to 1022 (02/16) Not Used 23 1052 (01/20) RCC Constituents43

1023 (02/16) Transport and Delivery 23 1053 (01/20) Storage of RCC Constituents44

1024 (02/16) Construction by Machine 23 1054 (01/20) General Requirements for


Production and Layer Construction
(02/16) Construction by Small Paving
1025  of RCC44
Machines or Hand Guided Methods 26
1055 (01/20) Production of Roller Compacted
(02/16) Finished Surface Requirements
1026  26 Mixtures47
1027 (02/16) Curing 30 1056 (01/20) Method Statement and Trial
Length of RCC47

Amendment – January 2020 1


MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS
VOLUME 1 SPECIFICATION FOR HIGHWAY WORKS

Clause Title Page


1057 (01/20) Induced Cracking of RCC48

1058 (01/20) Roller Compacted Concrete


Mixtures48
1059 (01/20) Testing, Control and Checking
of RCC49
1060 (01/20) Determination of the Coefficient
of Linear Thermal Expansion of RCC51F
1061 (01/20) RCC Laboratory Mixture
Design Procedure51F

Amendment – January 2020 2


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

ROAD PAVEMENTS – CONCRETE MATERIALS


1000  (02/16) General
1 (02/16) This Series is part of the Specification for Highway Works. Whilst this Series is particularly relevant to
the subject matter in its title it must be read in conjunction with the general requirements in Series 000 and 100 and
with all other Series relevant to the specification for the particular works to be undertaken.
2 (01/20) The Contractor shall undertake the testing of concrete pavements as detailed in the Clauses of this Series
unless detailed otherwise in contract specific Appendices 1/5, 1/6 or 7/1.

1001  (02/16) Strength Classes of Concrete and Constituent Materials for Pavement Layers
1 (02/16) Concrete in rigid or rigid composite pavements shall be one of the classes given in Table 10/1, in
accordance with the pavement design alternatives permitted in contract specific Appendix 7/1.
2 (02/16) Unless otherwise specified in contract specific Appendix 7/1 concrete shall conform with the
requirements of BS EN 13877-2 and the requirements of this Series. The constituents of the concrete shall conform
with BS EN 206 and BS 8500-1 and BS 8500-2 and BS EN 13877-1 and the requirements of this Series.

TABLE 10/1: (01/20) Pavement Layers — Concrete Strength Classes

Pavement Layer BS EN 206, BS 8500-2, BS EN 13877-2 BS 8500-1 BS Clause


Designed Standardised Designated EN 13877-1
Concrete Prescribed Concrete
Concrete

(i) Surface slabs: C40/50** C32/40**


Unreinforced concrete (URC)
Jointed reinforced concrete (JRC) 1001 to
Continuously reinforced concrete pavement (CRCP) 1039 and
1044
(ii) Continuously reinforced concrete base (CRCB) C40/50** C32/40**
(iii) CRCP and CRCB ground beam anchorages * C25/30
(iv) Lower Strength concrete 4) For bases or sub-bases ST4 GEN 3 C16/20
as required in contract
(v) Lower Strength concrete 3) specific Appendix 7/1 ST3 GEN 2 C12/15
1030
(vi) Lower Strength concrete 2) ST2 GEN 1 C8/10

(vii) Lower Strength concrete 1) ST1 GEN 0 C6/8

NOTE: * Cores shall not be taken from ground beam anchorages. ** Minimum permitted concrete class.

(02/16) Cement
3 (01/20) The general term ‘cement’ in this Series means any of the materials in (i) or the combinations in (ii)
below:
(i) Cements Complying with:
(a) Portland cement CEM I BS EN 197-1
(b) Portland-slag cement CEM II/A-S and CEM II/B-S BS EN 197-1
(c) Blastfurnace cement CEM III/A and CEM III/B BS EN 197-1
(d) Portland-fly ash cement CEM II/A-V and CEM II/B-V BS EN 197-1
(e) Pozzolanic cement CEM IV/A BS EN 197-1

Amendment – January 2020 3


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(ii) Combinations
(a) Portland cement CEM I with ground granulated blastfurnace slag BS EN 197-1
(ggbs) for use with Portland cement CEM I BS EN 15167-1 and
BS EN 15167-2
(b) Portland cement CEM I with fly ash (fa) for use as a cementitious BS EN 197-1
component in structural concrete BS EN 450-1 and
BS EN 450-2
(c) Portland cement CEM I with pozzolanic additive having current BS EN 197-1
certification complying with a product acceptance scheme as
described in sub-Clauses 104.15 and 104.16.
(iii) In each cubic metre of fully compacted concrete the cement content shall be in accordance with
Table 10/2. For 20 mm maximum size aggregate add 20 kg/m3, and for < 20mm maximum size add
40 kg/m3.
(iv) When used, the proportion of silica fume to CEM I shall be 10 ± 1%.
(v) For materials required to comply with BS EN 197-1 and/or BS EN 450-1 the Contractor shall
submit the relevant material declarations of performance to the Overseeing Organisation prior to
the inclusion of the materials into the works. The declarations of performance shall demonstrate
that the materials meet the requirements for the specification.

TABLE 10/2: (01/20) Minimum Cement or Combination Contents with 40 mm Maximum Aggregate

Class (BS 8500-1) C40/50 C32/40 C32/40 C25/30 C16/20 C12/15 C8/10 C6/8

In surface slabs In at least


overlaid by 30 the top
mm minimum 50 mm of
thin surface surface
course system slabs
complying with
Cement Clause 942
Min. Portland cement Ref BS8500-1 320 320 280 180 160 130 120
CEM I, BS EN 197-1
(kg/m3)
Min. other cements 340 340 300 180 160 130 120
or combinations
permitted in sub-
Clauses 3(i) and 3(ii)
(kg/m3)
For mixtures pre-blended or mixed on site
Maximum proportion 50 50 35 65 65 65 65 65
of ggbs (%)

Max/min. proportion 35/15 35/15 25/15 35/15 35/15 50/0 50/0 50/0
of fa (%)

Min. CEM I content 220 220 255 200 160 – – –


(kg/m3)

Amendment – January 2020 4


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Water

4 (01/20) Water from a water company supply may be used without testing. Water from other sources may be
used if it conforms to BS EN 1008. The water content shall be the minimum required to provide the specified
consistence for full compaction of the concrete to the required density, as determined by trial concrete mixes or
other means, and the maximum free water/cement ratio shall be 0.45 for strength classes C32/40 and C25/30 and
0.60 for strength classes C16/20 and C12/15. The requirements for standardised prescribed concrete shall be in
accordance with BS EN 206 and BS 8500-2.
(02/16) Admixtures

5 (01/20) Concrete in at least the top 50 mm of surface slabs shall incorporate an air-entraining admixture
complying with BS EN 934-2, except:
(i) for pavements with an exposed aggregate concrete surface constructed to Clause 1044 where at least the
top 40 mm of the surface slab shall be air entrained;
or
(ii) for surface slabs of pavements with at least a class C40/50 concrete;
(iii) for surface slabs of pavements with a class C32/40 concrete which are to be overlaid by a 30 mm
minimum thickness thin surface course system complying with Clause 942; and
(iv) for surface slabs of pavements with a class C35/45 concrete which are to be overlaid by a 20 mm
minimum thickness thin surface course system complying with Clause 942.
Plasticisers or water reducing admixtures shall comply with BS EN 934-2. Admixtures containing calcium chloride
shall not be used.
The Contractor shall submit the declaration of performance for each admixture to the Overseeing Organisation
prior to the incorporation of the admixture into the works. The declaration of performance shall demonstrate that
the admixture meets the specification requirements.
(02/16) Aggregate

6 (01/20) Aggregates for all pavement concrete, including Lower Strength, shall comply with BS EN 12620.
Crushed concrete, which complies with the quality and grading requirements of BS EN 12620 and Table 2
of BS 8500-2, may also be used in all pavement concretes except aggregate concrete surface complying with
Clause 1044. Alternatively, coarse aggregate may be crushed air-cooled blastfurnace slag complying with
BS EN 12620 and shall be Category FI50 or FI35 for concrete of classes C16/20 to C25/30 and over class C25/30,
respectively. FA when used as part of the aggregate shall comply with BS EN 450. Once the appropriate gradings
have been determined they shall not be varied without the approval of the Overseeing Organisation. Irrespective of
source, the aggregate will be considered suitable if:
(i) the resistance to freezing and thawing complies with BS EN 12620 clause 5.7.1 for pavement and Lower
Strength concrete;
and
(ii) the resistance to fragmentation complies with category LA35 of BS EN 12620 clause 5.2 for concrete
surface slabs and LA40 of BS EN 12620, clause 5.2 for concrete bases and Lower Strength concrete.
The Contractor shall submit the declaration of performance for each aggregate to the Overseeing Organisation prior
to the incorporation of the aggregate into the works. The declaration of performance shall demonstrate that the
aggregate meets the specification requirements.
The water absorption (WA) of the coarse aggregate shall be determined and declared in accordance with
BS EN 12620. Where recycled coarse aggregate or recycled concrete aggregate is used in this Series, it shall
comply with the limits specified in Table 2 of BS 8500-2 and the constituents shall be declared.

Amendment – January 2020 5


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

7 (02/16) The maximum size of coarse aggregate (D) shall not exceed 40 mm. When the spacing between
longitudinal reinforcement is less than 90 mm, the maximum size of coarse aggregate (D) shall not exceed 20 mm.
8 (02/16) Sand (i.e. fine aggregate) containing more than 25% by mass of acid-soluble material as determined in
accordance with BS EN 196-2, in either the fraction retained on, or the fraction passing the 0.500 mm sieve, shall
not be used in the top 50 mm of surface slabs. This requirement will not apply for pavements with an exposed
aggregate concrete surface constructed to Clause 1044 or if it can be shown that the sand (ie fine aggregate)
retained on, or the fraction passing the 0.500 mm sieve, contains less than 25 per cent by weight of calcium
carbonate.
9 (01/20) The water absorption of flint coarse aggregate containing white flints for use in concrete surface slabs,
when determined in accordance with BS EN 1097-6 shall not exceed:
3.5% for any separate nominal size fraction;
2.0% for the total combination of coarse aggregates in the proportions to be used in the concrete.
Contract compliance tests shall be carried out during stockpiling or paving, once a week, or at a lesser rate when
authorised by the Overseeing Organisation.
(02/16) Source of Recycled Aggregates
10 (02/16) Where recycled coarse aggregate or recycled concrete aggregate is used, only crushed concrete resulting
from reclamation or processing of concrete previously used in construction which originates from appropriate
identified structures with a known history of use shall be used.
(02/16) Chloride Content
11 (01/20) The chloride ion content of the aggregate to be used in concrete shall be as stated in BS EN 206. The
chloride class of reinforced concrete or concrete containing embedded metal shall be Cl 0,40 and unreinforced
concrete shall be Cl 1,0. The water soluble chloride content of the aggregates shall be determined in accordance
with BS EN 12620 and declared. The acid soluble chloride content of recycled aggregates shall be determined in
accordance with BS EN 12620 and declared.
(02/16) Chemical Requirement
12 (01/20) Acid-soluble sulfate
Acid-soluble sulfate content of the aggregates and filler aggregates for concrete pavements, including Lower
Strength, shall comply with BS EN 12620, clause 6.3.1 and shall be Category AS1,0 for air-cooled blast furnace slag
and for other aggregates Category AS0,8.
13 (02/16) Total sulfur
Total sulfur content of recycled coarse aggregates, recycled concrete aggregates, aggregates and filler aggregates,
shall comply with BS EN 12620, clause 6.3.2.

Amendment – January 2020 6


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1002 (02/16) Air Content


1 (01/20) In the top 50mm concrete requiring air entrainment to satisfy Clause 1001.5 shall meet the requirement
for exposure class XF4 in BS EN 206. With the exception of concrete class C40/50 as defined in BS8500 this
shall be achieved by the use of an air-entraining agent. The minimum quantity of air in air-entrained concrete as a
percentage of the volume of the concrete shall be as in Table 10/3:

TABLE 10/3: (01/20) Minimum Air Contents

Maximum aggregate size Minimum air content Maximum air content


mm % %
20 3.5 6.5
40 3 5.5

2 (02/16) The air content shall be determined at the point of delivery to the paving plant by the pressure gauge
method in accordance with BS EN 12350-7, at the rate of one determination per 300 m² of slab or at least 6 times
per day, whichever is the greater, in conjunction with tests for consistence and strength. For areas less than 300 m²
the rate shall be at least one determination to each 20 m length of slab or less constructed at any one time or at
least 3 times per day. If the air content is outside the specified limits in BS EN 206 the Contractor shall remove the
concrete from the works.
3 (02/16) The air-entraining agent shall be added at the mixer, by an apparatus capable of dispensing the
correct dose within the tolerance for admixtures given in BS EN 206, to ensure uniform distribution of the agent
throughout the batch during mixing.

1003  (02/16) Density


(01/20) The Permanent Works
1 (01/20) With the exception of the trial length, the density shall be measured by non-destructive methods.
2 (01/20) A correlation shall be established for each mix and each measuring device and shall be established
from the trial length where cores have been taken. The correlation established shall be provided to the Overseeing
Organisation before commencement of the permanent works. The device chosen shall achieve a repeatability of at
least 90%.
3 (01/20) The concrete density measured by the device shall not be less than 95% of the average density of at least
six fully compacted saturated moulded specimens made from the same mix in the trail area and tested at the same
age.
4 (01/20) The density shall be measured routinely at a distance of 0.8 to 1.2m from the edge of the slab and at the
rate shown in Table 10/12.
5 (01/20) If a non-compliance in an area is indicated then cores shall be taken as required in the trial area. Density
measurements shall be taken at the locations at which material is placed that has been sampled for cube testing.
(01/20) The Trial Length
6 (01/20) In the trial length as required in Clause 1028 the density of a saturated core cut from the full depth of
the concrete pavement shall not be less than 95% of the average density of at least six fully compacted saturated
moulded specimens made from the same concrete and tested at the same age.
7 (01/20) The density of the concrete pavement shall be determined in accordance with BS EN 13877-2. The
density of a saturated core cut from the full depth of the concrete pavement shall be determined in accordance with
BS EN 12390-7. The determination of the saturated density of the fully compacted moulded specimens shall be in
accordance with BS EN 12350-1, BS EN 12390-1 and BS EN 12390-2.

Amendment – January 2020 7


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

8 (01/20) The core shall have an average diameter of at least four times the nominal maximum aggregate size, and
in any case not less than 100 mm diameter. Where different concrete mixes are used in separate layers, the density
of each layer shall be separately determined by splitting or cutting the cores between the layers.
9 (01/20) Cores shall be taken at the rate given in Clause 1028 for the trial. If the density of any core is below the
minimum required, the concrete across the whole width of the slab constructed at the time relating to that core shall
be removed. In unreinforced concrete the whole slab length between joints shall be removed. For reinforced slabs,
in order to determine the limit of the defective area of concrete which shall be removed, additional cores shall be
taken at 5 m intervals on each side of any defective core until concrete of satisfactory density is found. Defective
areas shall be made good with new material in accordance with the specification.
10 (01/20) In calculating the density, allowance shall be made for any steel in the cores.
11 (01/20) Core holes shall be reinstated with compacted concrete with mix proportions of 1 part of Portland
cement CEM I: 2 parts of sand: 2 parts of 10 mm single sized coarse aggregate by mass.

1004  (02/16) Pavement Concrete Strength


1 (01/20) A trial length shall be constructed in accordance with Clause 1028.
2 (01/20) Concrete cores of 150mm diameter shall be taken from the trial length, cured and tested in accordance
with BS EN 12504-1 with the exception that the core shall be cured under water at 20°C ±2°C from as soon as
practically possible. A minimum of 9 cubes and 6 cores taken and at a minimum of 3 locations shall be taken from
the trial length. For each set of 6 cores, three shall be tested at 7 days and three at 28 days
3 (01/20) The end preparation of the core shall be by grinding and the height/diameter (h/d) ratio of the tested
specimen shall be between 1 and 2.
4 (01/20) The ratio of core density to non-destructive density measurement taken within 1m of the core location
shall be determined from the trial length as described in Clause 1003.
5 (01/20) If multi-layer construction is being used the cores shall be tested for adequacy of bond between layer in
accordance with BS EN 13877-2 with fv=1mPa at 7 days.
6 (01/20) Once a satisfactory trial construction has been achieved strength monitoring of the main construction
will be by the use of cubes cast at the rate of a set of 3 cubes for every 400 m2 of concrete laid. A minimum of
6 sets of cubes shall be taken each day with each set being from a different delivery of concrete.
7 (01/20) If the 7-day cube strength fails to conform with the requirements of BS EN 206 table B1 sampling and
testing for, and compliance with the specified characteristic core strength of designed concretes shall be undertaken
by compressive strength testing in accordance with BS EN 13877-2 on cores cut from the full depth of the slab.
8 (01/20) The strength of the concrete slab shall be evaluated in accordance with BS EN 206 (Annex B – Identity
Testing: Table B.1).
9 (01/20) To assess the time for use of a concrete slab by traffic, the strength development rate may be
predetermined by cubes stored at 20°C made from trial concrete mixes and maturity meters placed in the
pavement. Alternatively, pairs of cubes may be made for each 400 m² or less and stored alongside the pavement
in containers or in such a way that their sides are well insulated. If thermal insulation is used for accelerated curing
the cubes shall be similarly insulated. Pairs of cubes shall be tested at the intervals specified in contract specific
Appendix 7/1.

Amendment – January 2020 8


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1005  (02/16) Consistence (Workability)


1 (01/20) The consistence shall be determined by the Degree of Compactibility (Compaction Index) test in
accordance with BS EN 12350-4, or the Vebe test in accordance with BS EN 12350-3. Alternatively for concrete
class C16/20 or below, consistence may be determined by the slump test in accordance with BS EN 12350-2. The
sampling for all concrete classes shall be undertaken in accordance with BS EN 12350-1 and the rate of testing in
accordance with Table 17 of BS EN 206. Consistence shall be carried out at the point of placing, in conjunction
with tests for strength and any tests for air content. The consistence shall be maintained at the optimum within the
limits specified in BS EN 206.
2 (02/16) If any determination of consistence gives a result outside the tolerance, a further test shall be made
immediately on the next available load of concrete. The average of the two consecutive results and the difference
between them shall be calculated. If the average is not within the tolerance or the difference is greater than 0.1 for
CI or 20 mm for slump, or 6 seconds for Vebe, subsequent samples shall be taken from the delivery vehicles, which
shall not be allowed to discharge into the works until compliance with the specification has been established.

1006  (02/16) Not Used

1007  (02/16) Separation and Waterproof Membranes


1 (01/20) Over a bound sub-base a waterproof membrane shall be provided, which shall be a bituminous spray
in accordance with Clause 920. Where a bituminous spray has been used to cure cement-bound material or low
strength concrete then only those areas, which have been damaged or degraded, shall be resprayed after making
good.

1008  (02/16) Steel Reinforcement


(02/16) General
1 (01/20) Reinforcement shall comply with any of the following standards and shall be cut and bent in accordance
with BS 8666. The reinforcement materials shall be obtained from an organisation which has current, valid product
acceptance scheme certification, such as CARES certification, in accordance with sub-Clause 104.16. Re-bending
of carbon steel bars and fabric reinforcement on site shall not be permitted:
Hot Rolled and Cold Worked Carbon Steel Bars
(i) BS EN 10080 and BS 4449 (Grade B500B or B500C).
Steel Wires
(ii) BS EN 10080 and BS 4482 (Ribbed Grade B500).
Steel Fabric
(iii) BS EN 10080 and BS 4483 (Grade B500A, B500B or B500C). Steel fabric reinforcement shall have
a minimum nominal bar size of 6 mm (8 mm for Grade B500A). Steel fabric reinforcement shall be
delivered to site in flat mats or pre-bent.
2 (02/16) For hot rolled and cold worked carbon steel bars, and for steel fabric reinforcement, the bond property
requirements for BS 4449 shall be complied with based on the surface geometry requirements of that standard.
For steel wire, the bond property requirements of BS 4482 shall be complied with based on the surface geometry
requirements of that standard.

Amendment – January 2020 9


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

3 (01/20) Spacing of bars shall not be less than twice the maximum size of aggregate used. Laps in longitudinal
bars shall be not less than 35 bar diameters or 450 mm whichever is greater. In continuously reinforced concrete
slabs (CRCP or CRCB), only one third of the laps may be in any one transverse section, except in single bay
width construction where half the laps may be in any one transverse section. There shall be a minimum of 1.2 m
longitudinally between groups of transverse laps or laps in prefabricated reinforcement sheets.
4 (02/16) Laps in any transverse reinforcement shall be a minimum of 300 mm. Where prefabricated
reinforcement sheets are used and longitudinal and transverse laps would coincide, no lap is required in the
transverse bars within the lap of the longitudinal reinforcement. These transverse bars may be cropped or fabricated
shorter so that the requirements for cover are met. Alternatively, prefabricated sheets incorporating splices (ie flying
ends) may be used to provide nesting of reinforcement in both directions at lap positions. The lengths of the laps
shall be the minimum values previously stated.
5 (01/20) If the reinforcement is positioned prior to concreting, it shall be fixed on chairs conforming with the
requirements of BS 7973 and retained in position at the required depth below the finished surface and distance from
the edge of the slab so as to ensure that the required cover is achieved. Reinforcement assembled on site shall be
tied, or firmly fixed, at sufficient intersections to provide sufficient rigidity to ensure that the reinforcement remains
in the correct position during construction of the slab.
6 (02/16) Alternatively, when a reinforced concrete slab (JRC, CRCP or CRCB) is constructed in two layers, the
reinforcement in the form of prefabricated sheets may be placed on or into the bottom layer which shall be spread
and compacted to such a level that it will support the reinforcement without distortion at the required position in
the slab. The sheets shall be tied together at overlaps and after the second layer has been spread and compacted, the
reinforcement shall have the required cover.
7 (02/16) When a reinforced concrete slab is constructed at maximum width as in Clause 1010 the transverse
reinforcement in the centre of each slab width shall be a minimum of 12 mm nominal diameter bars at 600 mm
centres. This reinforcement shall be at least 600 mm longer than one third of the width of the slab and be lapped to
other transverse reinforcement bars or sheets, or be continuous across the whole width of each slab.
(02/16) Jointed Reinforced Concrete Slabs
8 (02/16) The reinforcement shall be so placed that after compaction of the concrete, the cover below the finished
surface of the slab is 50 ± 10 mm for slabs less than 200 mm thick, 60 ± 10 mm for slabs 200 mm or more but
less than 270 mm thick, 70 ± 20 mm for slabs 270 mm thick or more. The negative vertical tolerance shall not be
permitted beneath road stud recesses. Where traffic signal detector loops are to be installed, the minimum cover
to the reinforcement from the surface shall be 100 mm. The vertical cover between any longitudinal joint groove
forming strip and any reinforcement or tie bars shall be a minimum of 30 mm. Any transverse bars shall be at right
angles to the longitudinal axis of the carriageway.
Any transverse reinforcement shall terminate at 125 ± 25 mm from the edges of the slab and longitudinal joints,
where tie bars as in Clause 1012 are used. No longitudinal bars shall lie within 100 mm of a longitudinal joint.
The reinforcement shall terminate 300 mm ± 50 mm from any transverse joint, excluding emergency construction
joints.
(02/16) Continuously Reinforced Concrete Slabs (CRCP or CRCB)
9 (01/20) The reinforcement shall be Grade B500B or B500C deformed steel bars with the diameters and spacings
as described in contract specific Appendix 7/1.
10 (02/16) The reinforcement shall consist of bars assembled on site, or of prefabricated sheets. Except where
otherwise shown on the drawings the longitudinal bars shall be parallel to the centre-line of the road.
11 (01/20) The reinforcement shall be positioned so that, after compaction of the concrete, it shall be at the mid
depth of the specified thickness of the slab ±25 mm. No longitudinal bar shall lie within 100 mm of a longitudinal
joint. Reinforcement longitudinal bars shall be placed immediately above any transverse bars, which shall be at
right angles to the longitudinal axis of the carriageway. Any transverse reinforcement shall terminate 125 ± 25 mm
from the edges of the slab and longitudinal joints where tie bars as in Clause 1012 are used.

Amendment – January 2020 10


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1009  (02/16) Transverse Joints


(02/16) General
1 (02/16) Transverse joints shall be provided in unreinforced and jointed reinforced concrete slabs and shall be
contraction, expansion or warping joints at the spacings described in contract specific Appendix 7/1, such that for
unreinforced concrete slabs the length/width ratio shall be not greater than 2.0. The spacings may be increased by
20% if limestone coarse aggregate is used throughout the depth of the slab.
2 (02/16) Joints in the surface slab and sub-base shall be staggered so that they are not coincident vertically and
are at least 1 m apart.
3 (02/16) Transverse joints shall be straight within the following tolerances along the intended line of the
joint, which is the straight line transverse to the longitudinal axis of the carriageway, except at road junctions or
roundabouts where the positions shall be as shown on the drawings.
(i) deviations of the filler board or bottom crack inducer from the intended line of the joint shall be not
greater than ± 10 mm;
(ii) the best fit straight line through the joint groove as constructed shall be not more than 25 mm from the
intended line of the joint;
(iii) deviations of the joint groove from the best fit straight line of the joint shall be not greater than 10 mm.
4 (02/16) Transverse joints on each side of a longitudinal joint shall be in line with each other and of the same
type and width. The position of the joints relative to manholes and gullies shall be in accordance with Clause 1018.
5 (02/16) Concrete pavement layers shall be isolated from fixed structures by expansion joints, or earthworks
or a granular layer over the structure, or by bridge-type expansion joints, or by lengths of fully flexible pavement
construction. End of pavement surface slabs shall have a transition bay as shown on the drawings, leading into the
fully flexible construction.
6 (02/16) Transverse joints shall have a sealing groove which shall be sealed in compliance with Clause 1016.
(02/16) Contraction Joints
7 (02/16) Contraction joints shall consist of:
(i) a sawn joint groove complying with Clause 1013;
(ii) dowel bars complying with Clause 1011;
(iii) a sealing groove complying with Clause 1016.
(02/16) Expansion Joints
8 (02/16) Expansion joints shall consist of:
(i) a joint filler board complying with Clause 1015;
(ii) dowel bars complying with Clause 1011;
(iii) a sealing groove complying with Clause 1016.
9 (02/16) The filler board shall be positioned vertically within the prefabricated joint assemblies along the line of
the joint within the tolerances given in sub-Clause 3 of this Clause, and at such depth below the surface as will not
impede the passage of the finishing beams on the paving machines. The joint filler board together with the sealing
groove shall provide a complete separation of adjacent slabs and any spaces around dowel bars and between the
sub-base and the filler board shall be packed with a suitable compressible material after fixing the joint assembly.

Amendment – January 2020 11


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Warping Joints


10 (02/16) Warping joints shall consist of:
(i) a sawn joint groove complying with Clause 1013;
(ii) tie bars complying with Clause 1012;
(iii) a sealing groove complying with Clause 1016.
(02/16) Construction Joints
11 (02/16) Construction joints made at the end of a working day in unreinforced concrete slabs and jointed
reinforced concrete slabs shall be contraction joints. In the event of mechanical breakdown of the concreting
machinery, or at the onset of adverse weather, emergency joints may be formed.
12 (02/16) Emergency joints in unreinforced concrete slabs shall be contraction joints not less than 2.5 m from the
preceding or succeeding joint position.
13 (02/16) Emergency joints in jointed reinforced concrete slabs shall be not less than 2.5 m from the preceding
or succeeding joint position. The stop end formwork shall be sufficiently rigid to ensure that dowel bars, tie bars
or reinforcement will be held in position in compliance with the specification, and placed in such a position that it
permits the longitudinal reinforcement to project through the joint for a distance of at least 750 mm.
14 (02/16) Construction joints in continuously reinforced concrete slabs (CRCP and CRCB) at end of day or in
an emergency shall not be constructed within 1.5 m of any lap in the longitudinal reinforcement. The stop end
formwork shall be sufficiently rigid to ensure that the longitudinal reinforcement and the tie bars as required in
sub‑Clause 1012.7 which project through the joint are held in the correct position.

1010  (02/16) Longitudinal Joints


(02/16) General
1 (02/16) Sawn or wet-formed longitudinal joints shall be provided in surface slabs between or at the centre
of traffic lanes within the allowable positions as shown on the drawings, so that bay widths are not greater than
4.2 m (or 5.0 m with limestone aggregate) for unreinforced slabs, or 6 m (or 7.6 m with limestone aggregate) for
reinforced concrete surface slabs with transverse reinforcement as in sub-Clause 1008.7. Longitudinal joints shall
be provided in CRCB between lanes or at the centre of lanes, within a tolerance of ± 150 mm so that bay widths are
not greater than 6 m (or 7.6 m with limestone aggregate).
Joints in the surface slab, base or sub-base shall be staggered so that they are not coincident vertically and are at
least 300 mm apart.
2 (02/16) Wet-formed longitudinal joints shall consist of wet-formed joint grooves complying with Clause 1013,
a bottom crack inducer complying with Clause 1014 and tie bars complying with Clause 1012, except where
transverse reinforcement is permitted in lieu.
3 (02/16) Longitudinal joints shall be constructed within the following tolerances:
(i) deviations of the bottom crack inducer from the intended line of the joint, parallel to the axis of the road
shall be not greater than ± 13 mm;
(ii) the joint groove shall be located vertically above the bottom crack inducers within a horizontal tolerance
of ± 25 mm;
(iii) the best fit line along the constructed joint groove, shall be not more than 25 mm from the intended line
of the joint;
(iv) deviations of the joint groove from the best fit line of the joint shall be not greater than 10 mm.
4 (02/16) Sawn longitudinal joints shall consist of joint grooves complying with Clause 1013.

Amendment – January 2020 12


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

5 (02/16) Tie bars may be replaced by continuous transverse reinforcement across the joints in continuously
reinforced concrete slabs which are constructed in more than one lane width in one operation, provided that the
transverse reinforcement is a minimum of 12 mm diameter bars at 600 mm centres. The transverse reinforcement in
these circumstances shall be protected by suitable bituminous paint or equivalent coating for a distance of at least
75 mm either side of the joint.
(02/16) Longitudinal Construction Joints
6 (02/16) Longitudinal construction joints between separate slabs shall have tie bars as in Clause 1012 with a joint
groove as in Clause 1013. Alternatively, if split forms are used, the transverse reinforcement, if 12 mm diameter
or more, may be continued across the joint for a minimum of 500 mm or 30 times the diameter of the transverse
reinforcement bars, whichever is the greater. The transverse reinforcement in these circumstances shall be protected
by suitable bituminous paint or equivalent coating for a distance of at least 75 mm either side of the joint. A joint
sealing groove is not required in construction joints in continuously reinforced concrete bases. Where the edge of
the concrete slab is damaged it shall be made good before the adjacent slab is constructed.

1011  (02/16) Dowel Bars


1 (01/20) Dowel bars shall meet the requirements of BS EN 13877-3 with a minimum tensile strength of 250MPa
and shall be free from oil, dirt, loose rust and scale. They shall be straight, free of burrs and other irregularities
and the sliding ends sawn cleanly with no protrusions outside the normal diameter of the bar. For expansion joints,
dowel bars shall be 25 mm diameter at 300 mm spacing and 600 mm long for slabs up to 239 mm thick and 32 mm
diameter for thicker slabs. For contraction joints, dowels shall be 20 mm diameter at 300 mm spacing and 400 mm
long for slabs up to 239 mm thick, and 25 mm diameter at 300 mm spacing and 600 mm long for thicker slabs.
The Contractor shall submit the declaration of performance for the dowel bars to the Overseeing Organisation prior
to the incorporation of the dowel bars into the works. The declaration of performance shall demonstrate that the
dowel bars meet the specification requirements.
2 (02/16) Dowel bars shall be supported on cradles in prefabricated joint assemblies positioned prior to
construction of the slab. For contraction joints, as an alternative to prefabricated assemblies, dowel bars may be
mechanically inserted with vibration into the concrete by a method which ensures full recompaction of the concrete
around the dowel bars and the surface finished by a diagonal finishing beam, or a longitudinal oscillating float
travelling across the slab.
3 (02/16) Dowel bars shall be positioned at mid-depth from the surface level of the slab ± 20 mm. They shall be
aligned parallel to the finished surface of the slab, to the centre line of the carriageway and to each other within the
following tolerances:
(i) for bars supported on cradles prior to construction of the slab and for inserted bars in two layer
construction prior to placing the top layer:
(a) all bars in a joint shall be within ± 3 mm per 300 mm length of bar;
(b) two thirds of the bars shall be within ± 2 mm per 300 mm length of bar;
(c) no bar shall differ in alignment from an adjoining bar by more than 3 mm per 300 mm length of
bar in either the horizontal or vertical plane;
(ii) for all bars, after construction of the slab:
(a) twice the tolerances for alignment as in (i) above;
(b) equally positioned about the intended line of the joint within a tolerance of 25 mm.
4 (02/16) Cradles supporting dowel bars shall not extend across the line of the joint.

Amendment – January 2020 13


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

5 (02/16) Dowel bars, supported on cradles in assemblies, when subjected to a load of 110 N applied at either end
and in either the vertical or horizontal direction (upwards and downwards and both directions horizontally) shall
not deflect more than the following limits:
(i) two thirds of the number of bars of any assembly tested shall not deflect more than 2 mm per 300 mm
length of bar;
(ii) the remainder of the bars in that assembly shall not deflect more than 3 mm per 300 mm length of bar.
6 (02/16) The assembly of dowel bars and supporting cradles, including the joint filler board in the case of
expansion joints shall have the following degree of rigidity when fixed in position:
(i) For expansion joints the deflection of the top edge of the filler board shall be not greater than
13 mm, when a load of 1.3 kN is applied perpendicular to the vertical face of the joint filler board and
distributed over a length of 600 mm by means of a bar or timber packing, at mid depth and midway
between individual fixings, or 300 mm from either end of any length of filler board, if a continuous
fixing is used. The residual deflection after removal of the load shall be not more than 3 mm.
(ii) The joint assembly fixings to the sub-base shall not fail under the 1.3 kN load applied for testing the
rigidity of the assembly but shall fail before the load reaches 2.6 kN.
(iii) The fixings for contraction joints shall not fail under a 1.3 kN load and shall fail before the load reaches
2.6 kN when applied over a length of 600 mm by means of a bar or timber packing placed as near to the
level of the line of fixings as practicable.
(iv) Failure of the fixings shall be deemed to be when there is displacement of the assemblies by more than
3 mm with any form of fixing, under the test load. The displacement shall be measured at the nearest
part of the assembly to the centre of the bar or timber packing.
7 (01/20) Dowel bars shall be covered by a flexible polymeric corrosion resistant coating, bonded onto the
previously cleaned bar. The coating shall be smooth and free of indentations. During coating, the bar shall be
supported at each end. Minimum thickness shall be 0.3 mm. The coating shall also be able to withstand 250 hours
immersion in a salt fog cabinet complying with BS EN ISO 7253, without showing any visible crazing or corrosion
of the protected bar. The coated bar shall comply with the following pull out test:
(i) Four bars shall be taken at random from stock and without any special preparation shall be coated as
required in this Clause. The dowel bars which have been coated shall be cast centrally into concrete
specimens 150 x 150 x 450 mm, made of the same concrete mix proportions to be used in the pavement,
but with a maximum aggregate size of 20 mm and cured in accordance with BS EN 12390-2. At 7 days
a tensile load shall be applied to achieve a movement of the bar of at least 0.25 mm. The average bond
stress to achieve this movement shall be not greater than 0.89 N/mm2.
8 (02/16) For expansion joints, a closely fitting cap 100 mm long consisting of waterproofed cardboard or suitable
synthetic material shall be placed over one end of each dowel bar. An expansion space 10 mm greater than the
thickness of the joint filler board shall be formed between the end of the cap and the end of the dowel bar.

1012  (02/16) Tie Bars


1 (02/16) Tie bars in transverse or longitudinal joints shall conform to Clause 1008, in accordance with the
requirements given below and Table 10/5.
2 (01/20) Tie bars for use across joints shall have corrosion protection in the form of a flexible polymeric
corrosion resistant coating, bonded centrally onto 200 mm of the previously cleaned centre section of the bars.
Where tie bars are to be cranked for construction joints and later straightened, the coating shall be shown to be
capable of being straightened through 90 degrees without cracking.
The coating for both straight and cranked bars after straightening shall be able to withstand 250 hours immersion in
a salt fog cabinet complying with BS EN ISO 7253, without showing any visible crazing or cracking, or corrosion
of the protected part of the bar.

Amendment – January 2020 14


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

3 (02/16) Tie bars in warping joints and wet-formed longitudinal joints shall be made up into rigid assemblies with
adequate supports and fixings to remain firmly in position during the construction of the slab.
4 (02/16) Alternatively, tie bars at longitudinal joints may be mechanically inserted by vibration from above using
a method which ensures recompaction of the concrete around the tie bars.
5 (02/16) At longitudinal construction joints, tie bars may be adequately fixed to side forms or inserted into the side
of the slab by a method which ensures recompaction of the concrete around the tie bars and adequate bond.
6 (02/16) Tie bars in warping joints shall be positioned from the top surface of the slab within +20, -10 mm of the
mid depth of the slab.
Tie bars in other joints shall be positioned and remain within the middle third of the slab depth, approximately
parallel to the surface and approximately perpendicular to the line of the joint, with the centre of each bar on the
intended line of the joints within a tolerance of ± 50 mm, and with a minimum cover of 30 mm below any top crack
inducer of joint groove for slabs 200 mm thick or more, or 20 mm for slabs up to 200 mm thick.
7 (02/16) At transverse construction joints in continuously reinforced concrete, tie bars shall be 1.5 m long
and of the same Grade and size as the longitudinal reinforcement, and shall be fixed at twice the normal spacing
midway between the longitudinal reinforcement bars so that 750 mm ± 50 mm extends each side of the joint
at the same level as the longitudinal reinforcement and be tied to the transverse reinforcement. Where paving
from a construction joint is not resumed within 5 days, an extra longitudinal reinforcement bar 8 m long shall be
lapped and tied to each tie bar. These extra bars may be combined with the tie bars. Where the spacing between
longitudinal reinforcement and the extra 8 m long bars is less than 90 mm, the nominal size of aggregate shall be
20 mm for a sufficient number of concrete batches to complete that section of pavement.

TABLE 10/5: (01/20) Tie Bar Details

Joints Diameter Grade of Steel Length Spacing


mm mm mm
Transverse construction joints in As for main Grade B500B or 1500 Twice the spacing of
continuously reinforced concrete reinforcement B500C main reinforcement
Emergency construction joints in jointed 12 Grade B500B or 1000 600
reinforced concrete slabs other than at B500C
contraction or expansion joints 750 600

Warping joints 12 Grade B500B or 1000 300


B500C
750 600

Longitudinal 12 Grade B500B or 1000 600

}
All joints, except where B500C
Transverse reinforcement 750 600
is permitted in lieu
or 16 Grade B500B or 600 600
B500C
or 20 Grade B500B or 500 600
B500C
Transition from rigid to flexible 20 Grade B500B or 1000 300
construction B500C

NOTE: The transverse reinforcement may be continued across the joint in reinforced concrete if the bars are of a minimum nominal diameter
of 12 mm and the bars are protected from corrosion and the cover is as required in this Clause.

8 (02/16) Where tie bars are used in longitudinal joints in continuously reinforced concrete they shall be placed at
the same level as the transverse reinforcement and tied to the longitudinal reinforcement.

Amendment – January 2020 15


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1013  (02/16) Joint Grooves


(02/16) General
1 (02/16) Transverse contraction or warping joint grooves shall be sawn in the hardened concrete.
2 (02/16) Transverse joint grooves which are initially constructed less than the full width of the slab shall be
completed by sawing through to the edge of the slab and across longitudinal joints as soon as any forms have been
removed and before an induced crack develops at the joint.
(02/16) Sawn Transverse and Longitudinal Joint Grooves
3 (02/16) Sawing shall be undertaken as soon as possible after the concrete has hardened sufficiently to enable a
sharp edged groove to be produced without disrupting the concrete and before random cracks develop in the slab.
The grooves shall be between 1/4 and 1/3 of the specified depth of the slab and of any convenient width not less
than 3 mm. The sealing groove may be sawn to the required width later. Expansion joint sealing grooves shall be
sealed as soon as practical after sawing.
(02/16) Wet-formed Longitudinal Joint Grooves
4 (02/16) When slabs are constructed in more than one lane width in one operation a joint groove shall be formed
by inserting a groove former ahead of the finishing beams from dispenser. The concrete so displaced shall be
recompacted by a vibrating compactor or similar device, at least 300 mm wide operating symmetrically along the
line of the joint. After finishing the concrete, the groove forming strip shall be in the correct position and alignment,
within 10° of the vertical, and to sufficient depth below the surface to allow for the passage of the finishing beam
within the range 0-3 mm below the finished level of the slab. Groove forming strips in wet-formed longitudinal
joint grooves shall be left in place.
(02/16) Construction Joint Grooves in Surface Slabs
5 (02/16) The grooves shall be formed by fixing a groove-former or strip or cork seal along the top edge of the
slab already constructed, before concreting the adjacent slab. Where the edge of the concrete is damaged it shall
be ground or made good before fixing the groove forming strip. Alternatively the subsequent slab may be placed
adjacent to the first and a sealing groove sawn later in the hardened concrete to the minimum depth required in
Table 10/6 or to the manufacturer’s instructions if greater, and to sufficient width to eliminate minor spalling of the
joint arris, up to a maximum of 25 mm for longitudinal joints and 40 mm for transverse joints. The joint shall be
sealed in compliance with Clause 1016.

1014  (02/16) Groove Formers and Bottom Crack Inducers


(02/16) General
1 (02/16) Except where joint grooves are sawn, a bottom crack inducer shall be provided at each longitudinal joint
position.
2 (02/16) The bottom crack inducer shall be triangular or inverted Y-shaped fillet, with a base width not less than
the height, made of timber or rigid synthetic material. It shall be firmly fixed to the sub-base so as to remain in
position during the whole process of constructing the slab.
3 (02/16) The combined depth of groove formers and bottom crack inducers shall be between 1/4 and 1/3 of the
depth of the slab and the difference between the depth of the groove former and the height of the bottom crack
inducer shall not be greater than 20 mm.
(02/16) Longitudinal Joints
4 (02/16) Groove forming sealing strips for wet-formed longitudinal joints shall be of firm compressible strips of
ethylene vinyl acetate foam of minimum density 90 kg/m3, or synthetic rubber, or equivalent material. They shall
have a minimum thickness of 5 mm and shall be sufficiently rigid to remain vertical and straight in the concrete
without curving or stretching. They shall be inserted continuously along the joint.

Amendment – January 2020 16


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) CRCP Universal Beam Anchorage Transverse Joint


5 (02/16) One side of the beam shall be separated from the CRCP slab by an expansion joint filler board against
the vertical face and ethylene vinyl acetate foam in accordance with HCD Drawing C20.

1015  (02/16) Joint Filler Board


1 (01/20) Joint filler board for expansion joints and manhole and gully slab joints shall be 25 mm thick unless
otherwise shown in the drawings, within a tolerance of ± 1.5 mm. It shall be a firm compressible material or a bonded
combination of compressible and rigid materials of sufficient rigidity to resist deformation during the passage of the
concrete paving plant. The depth of the joint filler board for manhole and gully slabs shall be the full depth of the
slab less the depth of the sealing groove. In expansion joints, the filler board shall have a ridged top as shown on the
drawings, except where a sealing groove former is indicated on the drawings.
Holes for dowel bars shall be accurately bored or punched out to form a sliding fit for the sheathed dowel bar.
2 (01/20) The joint filler board shall meet the requirements given when tested in accordance with the procedures
in the following sub-Clauses:
(i) Weathering Test
(a) Three specimens, each 115 mm square ± 2.5 mm, shall be placed in a ventilated drying oven
maintained at a temperature of 55°C ± 5°C for 7 days, after which they shall immediately be
immersed in water at room temperature of between 16°C and 21°C for 24 hours. They shall then be
subjected to five cycles of freezing and thawing in the following manner.
(b) The specimens shall be placed in a watertight weathering test pan having a ribbed bottom and a
fitted slotted lid designed to hold the three specimens vertically on edge. The pan shall be filled
with water to half the depth of the specimens and then frozen to minus 7°C or below, for at least
four hours after the initial freezing of the water. The pan shall then be placed in a water bath
maintained at 18°C to 38°C without disturbing the specimens and shall remain there for one hour
after thawing has completed. The pan and specimens shall then be returned to the refrigerator
and freezing and thawing shall be repeated in precisely the same manner until five cycles of the
process have been completed. The specimens shall be removed from the pan and air dried at room
temperature for 48 hours before examination.
(c) The material shall be deemed to have passed the weathering test if the specimens show no signs of
disintegration or shrinkage.
(ii) Compression and Recovery Test
(a) Two of the specimens which pass the weathering test, and two new specimens, each trimmed
to 100 mm square ± 0.5 mm, maintained at room temperature and humidity for 24 hours, shall
be subjected to three applications of load at 24 hour intervals in a compression test machine
complying with BS EN ISO 7500-1, with auxiliary platens 100 mm2, minimum 13 mm thick.
During each application of load each specimen shall be compressed to 50% of its original thickness
at a rate of strain of 1.3 mm per minute. The load required to achieve this amount of compression
shall be:
• not less than 0.7 N/mm2 nor more than 10 N/mm2 for material to be used in pavements; and
• not less than 0.7 N/mm2 and not more than 0.4 N/mm2 for material to be used in bridge joints.
The load shall be released immediately the required degree of compression is reached and after the
third application a recovery period of 30 minutes shall be allowed after which the thickness of the
specimen shall be measured.

Amendment – January 2020 17


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(b) This thickness, expressed as a percentage of the original thickness, is the ‘recovery’ value of the
specimen. The thicknesses shall be measured to an accuracy of 25 micron. The two new specimens
shall be weighed before and after testing. The difference in mass shall be determined with an
accuracy of 0.1% and shall be expressed as a percentage of the original mass of the specimen.
(c) The material shall be deemed to have passed the test if all four specimens have recovery values of
at least 70% and the two new specimens have not suffered a reduction of mass in excess of 1%.
(iii) Extrusion Test
(a) The third sample which passes the weathering test shall be trimmed to 100 mm square ± 0.5 mm
and be subjected to the following extrusion test.
(b) The extrusion mould shall be 100 mm x 100 mm (+ 0.5 mm, - 0) internally, of sufficient depth
to test the sample as received, open on one side only and fixed rigidly to a base plate. The mould
shall be provided with a closely fitting pressure plate which shall fit without binding, and with
an accurate horizontal measuring dial gauge or measuring device accurate to 25 microns. The
specimen shall be mounted in the extrusion mould and loaded once as described in the compression
and recovery test. The extrusion at the open side of the mould shall be measured with the gauge
when the specimen is compressed to 50% of its original thickness and before release of the load.
(c) The material shall be deemed to have passed the test if the extrusion of the free edge does not
exceed 6 mm.

1016  (02/16) Preparation and Sealing of Joint Grooves


(02/16) General
1 (02/16) All transverse joints in surface slabs, except for construction joints in CRCP shall be sealed using one
of the joint seals described in Clause 1017. Additionally longitudinal joints which are sawn or widened, shall be
sealed.
(02/16) Preparation of Joint Grooves for Sealing
2 (02/16) Joint grooves shall be prepared in accordance with BS 5212 : Part 2 and sub-Clauses 3 to 8 of this
Clause.
3 (02/16) That part of the groove former used to form the sealing groove or any temporary seal shall be removed
cleanly without damaging the joint arrises to a minimum depth of 25 mm where compression seals are used or
otherwise to such depth as will provide an applied seal to the dimensions shown in Table 10/6, after allowing
for any necessary caulking material described in sub-Clause 6 of this Clause. If joint grooves are not initially
constructed to provide the minimum dimensions for the joint seals as given in Table 10/6, they shall be widened
by sawing. Joint grooves formed by tapered formers need not be widened. The sealing grooves shall be cleaned
out immediately after sawing using high pressure water jets, to remove all slurry from the joint, before the slurry
hardens.
4 (02/16) If rough arrises develop when grooves are made they shall be ground to provide a chamfer
approximately 5 mm wide. If the groove is at an angle up to 10° from the perpendicular to the surface, the
overhanging edge of the sealing groove shall be sawn or ground perpendicular. If spalling occurs or the angle
of the former is greater than 10° the joint sealing groove shall be sawn wider and perpendicular to the surface to
encompass the defects up to a maximum width, including any chamfer, of 40 mm for transverse joints and 25 mm
for longitudinal joints. If the spalling cannot be so eliminated then the arris shall be repaired by suitable thin
bonded arris repair using cementitious materials as specified in Clause 1032.
5 (02/16) For applied sealants the sides of the joint sealing groove shall be scoured by dry abrasive blasting.
This shall not be carried out before the characteristic compressive strength of the concrete is expected to reach
15 N/mm². When compression seals are used, the sides of the groove may be ground or wire brushed.

Amendment – January 2020 18


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

6 (02/16) For hot and cold applied sealants, compressible caulking material, debonding strip or tape or cord
compatible with the sealant, of a suitable size to fill the width of the sealing groove, shall be firmly packed or
stuck in the bottom of the sealing groove to such a depth so as to provide the correct depth of seal as described in
Table 10/6 with the top of the seal at the correct depth below the surface of the concrete.
7 (02/16) All grooves shall be cleaned of any dirt or loose material by air blasting with filtered, oil-free
compressed air. The groove shall be clean and dry at the time of priming and sealing.
8 (02/16) For applied sealants the joint grooves shall be primed with the relevant primer for the hot or cold applied
sealant in accordance with the manufacturer’s recommendations and with BS 5212 : Part 2, except that when
necessary the joint grooves may be primed and sealed earlier than 14 days after construction, as soon as the grooves
have been grit-blasted and cleaned.

TABLE 10/6: (01/20) Dimensions of Applied Joint Seals

Type and Spacing of Joints (m) Minimum Minimum Depth of Seal (Note 1) Impregnated Depth of
Width Foam Seal Below
Cold Applied Hot Applied Compression the Concrete
Strips Surface
mm mm mm mm mm
Contraction
15 and under 13 (Note 2) 13 15 30 5±2
Over 15 to 20 20 15 30 30 5±2
Over 20 to 25 30 20 25 40 5±2
Expansion 30 20 25 40 7±2
Transverse Warping 10 10 13 30 5±2
Longitudinal Joints (if sealed) 10 10 13 30 0 to 5
Gully and Manhole Slabs 20 15 20 30 0 to 3

NOTE (1): The depth of seal is that part in contact with the vertical face of the joint groove. The depth of seal below the surface shall be
taken at the centre of an applied seal relative to a short straight edge, 150 mm long, placed centrally across the joint within 7 days of sealing.
NOTE (2): For cork seals other than in construction joints, grooves shall be 20 mm width, 50 mm depth.

(02/16) Sealing with Applied Sealants


9 (02/16) Sealing shall be carried out continuously along the full length of joint in any one rip, except for remedial
areas. When hot or cold applied sealants are used the sealant shall be applied within the minimum and maximum
drying times of the primer recommended by the manufacturer. Priming and sealing with applied sealants shall
not be carried out when the naturally occurring temperature in the joint groove to be sealed is below 10°C except
between 8°C and 10°C it may be carried out when the temperature is rising.
10 (02/16) Hot-applied sealants shall be prepared and applied in accordance with the manufacturer’s instructions.
11 (02/16) The components of cold-applied sealants shall be thoroughly mixed in the correct proportions in
accordance with the manufacturer’s instructions. As soon as possible after mixing and within the worklife of the
sealant, the material shall be dispensed into the joint, or applied using a caulking gun, to the correct level below
the concrete surface. The tack-free time shall be achieved within 3 hours for machine dispensed material, or within
12 hours for hand applied material.

Amendment – January 2020 19


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Testing of Applied Sealants


12 (01/20) No additional testing of sealants is required provided a declaration of performance for cold-applied
sealants in accordance with BS EN 14188-2 or for. BS EN 14188-1 has been provided to the Overseeing
Organisation.
(02/16) Sealing with Compression Seals
13 (02/16) When compression seals are used, the widths of the seal shall be selected in relation to the width of the
sealing groove, the bay lengths and manufacturer’s recommendations so that the estimated maximum width of the
joint opening shall be not more than 70% of the original width of the seal, the estimated maximum width being
calculated on the basis of a movement of 4 mm per 10 m run of slab. The maximum calculated width of sealing
groove shall be 30 mm. The depth of groove shall be such that the contact face of the seal with the side of the
groove shall be not less than 20 mm and that the top of the seal shall be a minimum of 3 mm below the surface of
the concrete.
14 (02/16) Compression seals shall be inserted into the grooves without prior extension or rotation and, where
recommended by the manufacturer, with a lubricant adhesive which is compatible with the seal and the concrete.
The adhesive shall be applied to both sides of the sealing groove or the seal, or to both. The seal shall be positioned
with its axis perpendicular to the concrete surface. Excess adhesive on top of the seal shall be removed to prevent
adhesion of the top faces of the seal under compression. Except when compression seals are used in longitudinal
joints the transverse joint seal shall be continuous across the slab and the longitudinal joint groove forming
strips shall be cut to the required depth after the concrete has hardened for the transverse seal to be inserted. If
compression seals are used in longitudinal joints where the grooves have been sawn after construction of the slab
they shall be continuous across transverse joints, with the transverse seals butted and fixed to the longitudinal seals
with adhesive.

1017  (02/16) Joint Seals


1 (01/20) Joint seals shall consist of hot or cold applied sealants or compression seals complying with this Clause.
The colour of the joint seal material shall comply with the requirements of contract specific Appendix 7/2.
For hot-applied and cold applied sealants the Contractor shall submit the declaration of performance for each
sealant to the Overseeing Organisation prior to the incorporation of the sealant into the works. The declaration of
performance shall demonstrate that the sealant meets the specification requirements.
(02/16) Hot-applied Sealants
2 (01/20) Hot-applied sealants shall be Type N1 or Type F1 or Type F2, as stated in contract specific
Appendix 7/1, and conforming to BS EN 14188-1.
3 (02/16) For joints between concrete surface slabs and bituminous surfacing, hot applied Type N1 sealants
conforming to BS EN 14188-1 shall be used. Alternatively polymer modified bitumen sealing strips may be used
and shall be applied in accordance with the manufacturer’s instructions. Hot-applied Type N1 sealants may be used
in joints in asphalt kerbs laid on concrete pavements.
(02/16) Cold-applied Sealants
4 (01/20) Cold-applied sealants shall be Type N conforming to BS EN 14188-2 except that Type F shall be used
for lay-bys and hardstandings.
5 (02/16) For joints in kerbs and joints other than in pavements, seals may be any of the pavement sealants if
they have the suitable characteristics for the application, or gunning grade cold applied plasticised bituminous
rubber sealant or gunning grades of two part polysulphide-based sealants complying with BS 4254 may be used.
Alternatively, polyurethane-based sealing compounds may be used provided their performance is not inferior to
BS 4254 material.

Amendment – January 2020 20


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Compression Seals


6 (01/20) Compression seals shall be pre-compressed neoprene impregnated expanding foam sealing strip having
current product acceptance scheme certification in accordance with sub-Clauses 104.15 and 104.16 such as HAPAS
certification, or rubber seals made of polychloroprene elastomers complying with BS 2752 and conforming with
the requirements of ASTM Standard D2628-91. Seals of butadiene-acrylonitrile or other synthetic rubbers may be
used if certificates are produced to show that they conform to the performance requirements of ASTM Standard
D2628- 91 for oven ageing, oil and ozone resistance, low temperature stiffening and recovery. Seals made of
ethylene vinyl acetate in microcellular form and other synthetic materials may be used in longitudinal joints and
in structures if test certificates are produced to show adequate resistance to heat ageing when tested in accordance
with BS EN ISO 2440 and resistance to fuel oils. The compression set of any seal shall not be greater than
15% when the specimen is subjected to a 25% compression in accordance with BS EN ISO 1856. When immersed
in standard oils for 48 hours at 25°C in accordance with BS ISO 1817, the volume change shall not be greater
than 5%.
7 (02/16) Compression seals shall be shaped so that they will remain compressed at all times in accordance with
Clause 1016 and shall have a minimum of 20 mm contact face with the sides of the sealing groove. If lubricant-
adhesive is used, it shall be compatible with the seal and the concrete and shall be resistant to abrasion, oxidization,
fuels and salt.

1018  (02/16) Joints at Manhole and Gully Slabs


1 (02/16) Manhole covers, gullies and their frames shall be isolated from the pavement slabs and be contained in
separate small slabs, which shall be larger than the exterior of the manhole and gully shafts, including any concrete
surround less than 150 mm below the underside of the sub-base layer. The joint around the manhole or gully slab
shall be vertical and incorporate joint filler board as in Clause 1015 but without dowel bars and tie bars.
2 (02/16) Gully slabs in unreinforced concrete slabs shall be adjacent to or straddle a transverse joint, extending
the gully slab as necessary to a maximum of 2 m. Where this is impractical, an extra tied warping joint shall be
provided adjacent to or within the gully slab and at least 2 m from the next transverse joint. If the edge of an
isolator slab is within 1 m of any longitudinal joint the isolator slab shall be extended to that joint.
3 (02/16) Manhole slabs in unreinforced concrete slabs shall be adjacent to or straddle transverse or longitudinal
joints. If the manhole is within the middle third of the bay length a warping joint shall be constructed on one side of
the manhole slab across the whole width of the bay to the nearest longitudinal joint.
4 (02/16) Reinforcement as shown on the drawings shall be placed in the main concrete slabs in the corners
between the manhole and gully slabs and the transverse or longitudinal joints. Extra reinforcement as described in
the Contract shall be placed in reinforced concrete slabs around the manhole or gully slabs.
5 (02/16) Manhole and gully slabs shall have square corners, at all corners which are not adjacent to a transverse
or longitudinal joint in the main slab.
6 (01/20) Reinforcement as shown on the drawings shall be placed in the gully or manhole slab and concrete
Class C32/40 shall be placed by hand in the space between the main slab and the manhole frame. The concrete shall
be fully compacted and finished in compliance with Clause 1025.
7 (02/16) A sealing groove shall be made directly above the joint filler board and sealed in compliance with
Clause 1016.

Amendment – January 2020 21


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1019  (02/16) Inspection of Dowel Bars


1 (02/16) Compliance with Clause 1011 for the position and alignment of dowel bars at contraction and expansion
joints shall be checked by measurement relative to the side form or guide wires.
2 (01/20) When the slab has been constructed, the position and alignment of dowel bars and any filler board shall
be measured after carefully exposing them across the whole width of the slab. When the joint is an expansion joint
the top of the filler board shall first be exposed sufficiently in the plastic concrete to permit measurement of any
lateral or vertical displacement of the board. During the course of normal working these measurements shall be
carried out at a rate of one joint per 1500 m length of slab or one per 5 days whichever occurs the sooner. For small
areas the rate shall be one joint for up to each 100 joints. For trial lengths measurements shall be carried out at two
consecutive joints.
3 (02/16) If the position or alignment of the bars in a single joint in the slab is unsatisfactory then the next two
joints shall be inspected. If only the one joint of the three is defective, the rate of checking shall be increased to one
joint per day until compliance is being achieved. In the event of non-compliance in two or more successive joints,
the Contractor shall revert to the construction of trial lengths and make any necessary alterations to the concrete
mix, paving plant or methods until the dowel bar position and alignment is satisfactory.
4 (02/16) After the dowel bars have been examined, the remainder of the concrete shall be removed 500 mm on
each side of the line of the joint, and reinstated to the requirements of the specification. Alternatively if the dowels
are examined in the penultimate joint of a day’s work that joint shall be made a construction joint for the next day’s
work and the remainder of the concrete in the last slab may be discarded.

1020  (02/16) Side Forms, Rails and Guide Wires


(02/16) Side Forms and Rails
1 (01/20) All side forms and rails shall be made of steel or timber and be sufficiently robust and rigid to support
the weight and pressure caused by the paving equipment. Side forms for use with wheeled paving machines shall
incorporate metal rails firmly fixed at a constant height below the top of the forms.
2 (02/16) The forms shall be secured by using not less than three pins for each 3 m length having one pin fixed at
each side of every joint. Forms shall be tightly joined together by a locked joint, free from play or movement in any
direction. Forms shall be cleaned and oiled immediately before each use. The rails or running surface shall be kept
clean in front of the wheels of any paving machines. The forms shall be straight within a tolerance of 3 mm in 3 m.
3 (02/16) The forms shall be bedded on low moisture content cement mortar or concrete class C6/8 and set to
the pavement surface level as shown on the drawings within a tolerance of ± 3 mm. The bedding shall not extend
under the slab. There shall be no vertical step between the ends of adjacent forms greater than 3 mm. The horizontal
alignment for forms shall be to the required alignment of the pavement edge as shown on the drawings within a
tolerance of ± 10 mm. The Contractor shall ensure that the forms are set to the correct profile immediately prior to
concreting. The mortar or concrete bedding shall be broken out after use.
4 (02/16) Side forms shall not be removed earlier than 6 hours after the completion of the construction of the slab.
Care shall be taken to prevent damage to the concrete and any projecting tie bars during the removal of the forms.
If the removal of forms results in any damage to the concrete the period of 6 hours shall be increased to that which
is necessary to avoid further damage and the Contractor shall make good the damaged areas.
(02/16) Guide Wires
5 (01/20) Unless a laser or electronically controlled level system capable of meeting the vertical and horizontal
tolerances stated below is used, a guide wire shall be provided along each side of the slab to be constructed by
slip form paving plant. Each guide wire shall be at a constant height above and parallel to the required edges of
the slab as shown on the drawings, within a vertical tolerance of ± 3 mm. Additionally one of the wires shall be at
a constant horizontal distance from the required edge of the pavement as shown in the drawings within a lateral
tolerance of ± 10 mm.

Amendment – January 2020 22


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

6 (02/16) The guide wires shall be supported from stakes not more than 8 m apart by connectors capable of fine
horizontal and vertical adjustment. The guide wire shall be tensioned on the stakes so that a 500 gramme weight
shall produce a deflection of not more than 20 mm when suspended at the mid-point between any pair of stakes.
The ends of the guide wires shall be anchored to fixing points which shall be not closer to the edge of the slab than
the row of stakes and in no circumstances shall a guide wire be anchored to a stake.
7 (02/16) The stakes shall be positioned and the connectors maintained at their correct height and alignment from
1200 hours on the day before concreting takes place until 36 hours after the concrete has been finished. The guide
wire shall be erected and tensioned on the connectors at any section for at least two hours before concreting that
section.

1021 to 1022  (02/16) Not Used

1023  (02/16) Transport and Delivery


1 (02/16) The number of delivery vehicles provided shall be sufficient to ensure a constant supply of concrete to
enable the paving plant to proceed continuously.

1024  (02/16) Construction by Machine


1 (02/16) The concrete slab shall be constructed in a continuous process by either slip-form or by fixed
form paving plant in accordance with this Clause or by small paving machines or hand guided methods as in
Clause 1025.
2 (01/20) The slab may be constructed in either one or two layers. In two layer construction the thickness of the
top layer shall be not less than 40 mm or twice the maximum size of the coarse aggregate, whichever is the greater,
and shall be at least 15 mm thicker than the depth of the groove former, if used.
(02/16) Construction by Fixed Form Paving Machines
3 (02/16) A fixed form paving train shall consist of separate, powered machines which spread, compact and finish
the concrete in a continuous operation.
4 (02/16) Concrete shall be discharged without segregation into a hopper spreader which is equipped with
the means of controlling its rate of deposition on to the sub-base or on to the lower layer. The concrete shall be
spread in each layer without segregation and to a uniform uncompacted density over the whole area of the slab.
The deposited concrete shall be struck off to the necessary level by the underside of the hopper as it is traversed
across the spreading machine. The machine shall be capable of being rapidly adjusted for changes in average and
differential surcharge necessitated by changes in slab thickness or crossfall. When the slab is constructed in two
layers, the spreading of the concrete in the top layer shall follow the completion of the bottom layer within the
times given in Table 10/7.

Amendment – January 2020 23


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

TABLE 10/7: (01/20) Maximum Working Times

Temperature of concrete at discharge Reinforced concrete slabs constructed in All other concrete slabs
from the delivery vehicle two layers, without retarding admixtures
Mixing first Between layers Mixing first Between layers in
Time is function of degree hours see layer to finishing layer to finishing two layer work
RCC concrete concrete

Not more than 25°C hours 3 hours half hour 3 hours 1.5 hours
Exceeding 25°C hours but not exceeding 2 hours half hour 2 hours 1 hour
30°C hours
Exceeding 30°C hours Unacceptable for – Unacceptable for –
paving paving

5 (02/16) Prior to being compacted, the surface level of each loose spread layer shall be adjusted to the correct
surcharge by means of rotating strike-off blades or a screw device.
6 (02/16) The concrete shall be compacted by vibration or by a combination of vibration and mechanical tamping
so as to comply with Clause 1003 throughout the full depth of the slab. Poker vibrators shall be used in each layer
adjacent to the side forms and the edge of a previously constructed slab.
7 (02/16) The initial regulation and finish to the surface of the slab shall be effected by means of a beam
oscillating transversely or obliquely to the longitudinal axis of the pavement. This beam shall be readily adjustable
for both height and tilt.
8 (02/16) Joint grooves shall be constructed in compliance with Clause 1013. When grooves are wet-formed, the
concrete shall be re-compacted around the former by a hand held vibrating plate compactor drawn along or on each
side of the joint, prior to the final regulation of the surface by a longitudinal oscillating float.
9 (02/16) The regulation and finishing of the surface of the slab shall be carried out by a machine which
incorporates twin oblique oscillating finishing beams which shall be readily adjustable for both height and tilt. The
beams shall weigh not less than 170 kg/m, be of rectangular section and span the full width of the slab. The leading
beam shall be vibrated. The beams shall be supported on a carriage, the level of which shall be controlled by the
average level of not less than four points evenly spaced over at least 3.5 m of the supporting rail, beam, or slab, on
each side of the slab that is being constructed. Except for CRCB slabs, the final regulation of the surface of the slab
shall be provided by a longitudinal oscillating float, travelling across the slab. After the final regulation and before
the macrotexture is applied, any excess concrete on top of the joint groove former, where present, shall be removed.
Additionally the longitudinal oscillating float shall complete the traverse of the slab in both directions within the
length of the float and shall have a total longitudinal stroke of 200 mm to 300 mm.
10 (02/16) The longitudinal oscillating float shall have a minimum length of 3 m and a minimum constant width of
250 mm with a maximum weight of 10 kg/m. The edges of the float shall be curved or chamfered.
11 (02/16) A minimum length of 500 mm of longitudinal oscillating float shall be within the length of the machine
tracks or wheels.
12 (02/16) When a concrete slab is constructed in more than one width, flanged wheels on the paving machines
shall not be run directly on the surface of any completed part of the slab. The second or subsequent slabs shall be
constructed either by supporting machines with flanged wheels on flat-bottom section rails weighing not less than
15 kg/m laid on the surface of the completed slab, or by replacing the flanged wheels on that side of the machines
by smooth flangeless wheels. Before flangeless wheels or rails are used, the surface regularity of the slab over
which they are to pass shall comply with Clause 702 and its surface shall be thoroughly cleaned and brushed to
remove all extraneous matter. Flangeless wheels or rails shall be positioned sufficiently far from the edge of the
slab to avoid damage to that edge.
(02/16) Construction by Slip-form Paving Machine
13 (02/16) A slip-form paving train shall consist of powered machines which spread, compact and finish the
concrete in a continuous operation.

Amendment – January 2020 24


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

14 (02/16) The slip-form paving machine shall compact the concrete by internal vibration and shape it between
sliding side forms or over fixed side forms by means of either a conforming plate or by vibrating and oscillating
finishing beams.
15 (02/16) The concrete shall be deposited without segregation in front of the slip-form paver across its whole
width and to a height which at all times is in excess of the required surcharge. The deposited concrete shall be
struck off to the necessary average and differential surcharge by means of a strike-off plate or a screw auger device
extending across the whole width of the slab. The equipment for striking off the concrete shall be capable of being
rapidly adjusted for changes of the average and differential surcharge necessitated by changes in slab thickness or
crossfall.
16 (02/16) The level of the conforming plate and finishing beams shall be controlled automatically from the guide
wires by sensors attached at the four corners of the slip form paving machine. The alignment of the paver shall be
controlled automatically from the guide wire by at least one sensor attached to the paver. The alignment and level
of ancillary machines for finishing, texturing and curing of the concrete shall be automatically controlled relative to
the guide wire or to the surface and edge of the slab.
17 (02/16) Slip-form paving machines shall have vibration of variable output, with a maximum energy output of
not less than 2.5 kW per metre width of slab per 300 mm depth of slab for a laying speed of up to 1.5 m per minute
or pro rata for higher speeds. The machines shall be of sufficient mass to provide adequate reaction on the traction
units to maintain forward movements during the placing of concrete in all situations.
18 (02/16) Except for CRCB slabs, the final regulation of the surface slab shall be provided by a longitudinal
oscillating float travelling across the slab. The longitudinal float shall comply with the requirements of
sub-Clauses 9, 10 and 11 of this Clause. Additionally, the longitudinal float shall either be a separate machine
closely following a slip-form paver or alternatively it shall be attached to a slip-form paver in such a manner that it
functions effectively and does not adversely affect the performance of the paver or the surface of the slab.
19 (02/16) Joint grooves shall be constructed in compliance with Clause 1013. Where grooves are wet-formed
the concrete shall be compacted around the former by a separate vibrating plate compactor with twin plates. The
groove former shall be compacted to the correct level by a vibrating pan which may be included with the transverse
joint finishing beam. Final finishing shall be carried out in accordance with sub-Clause 18 of this Clause. Any
excess concrete on top of the groove former shall be removed before the surface is macrotextured.
20 (02/16) Where a concrete slab is constructed in more than one width or where the edge needs to be matched
for one level to another section of surface slab, and the surface levels at the edges are not achieved, the slab shall
be supported by separate side forms placed before or after the paver to ensure that edge levels meet the required
tolerances.
(02/16) General
21 (01/20) While the concrete is still plastic its surface shall be treated to comply with the macrotexture
requirements specified in Clause 1026. The surface and edges of surface slabs and CRC bases shall be cured in
compliance with Clause 1027. Lower Strength concrete bases and subbases shall be cured in compliance with
Clause 1030.
22 (01/20) The spreading, compacting and finishing of the concrete shall be carried out as rapidly as possible
and the paving operation shall be so arranged as to ensure that the time between the mixing of the first batch of
concrete in any transverse section of the slab and the application of the sprayed curing membrane to the surface
of that section shall not exceed those given in Table 10/7. This working time is a function of degree hours see
sub- Clause 1054.3.
23 (02/16) Each bay in jointed concrete surface slabs shall be consecutively numbered near the verge, next to a
transverse joint while the concrete is plastic. In continuously reinforced concrete pavement the slab shall be marked
with the chainage at intervals not greater than 50 m apart.

Amendment – January 2020 25


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1025  (02/16) Construction by Small Paving Machines or Hand Guided Methods


1 (01/20) As an alternative to fixed form or slip-form paving trains, the concrete slab may be constructed using
parts of trains, small paving machines, truss type finishing beams, roller beams or hand guided methods. Hand
tamping beams may only be used for short lengths or infill bays or tapers. Reinforcement, dowel bars and tie bars
shall be supported in position in accordance with Clauses 1008, 1011 and 1012 respectively, except where two
layer construction is used and reinforcement is placed on the bottom layer.
2 (01/20) The concrete shall be spread uniformly without segregation or varying amounts of pre-compaction,
by conveyor, chute, blade or auger. The concrete shall be struck off by a screed or auger so that the average and
differential surcharge is sufficient for the surface of the slab to be at the correct levels after compaction of the
concrete.
3 (02/16) The concrete shall be compacted by vibrating finishing beams across the slab and with vibrating pokers
adjacent to the side forms or the edge of a previously constructed slab. In addition, internal poker vibration shall be
used for slabs thicker than 200 mm and may be used for lesser thicknesses. When used, the pokers shall be at points
not more than 500 mm apart over the whole area of the slab, or drawn continuously across the slab in front of the
finishing beams.
4 (02/16) The finishing beams shall be metal with a contact face at least 50 mm wide. They shall be rigid or
supported by a frame or truss without sag across the width of slab being paved. The beams shall be supported on
rails or forms or an adjacent slab and shall be moved forward at a steady speed of 0.5 m to 2 m per minute whilst
vibrating, to compact the concrete and to produce a smooth surface finished to the correct crossfalls, crowns and
levels relative to the top of the forms or adjacent slab.
5 (02/16) Joint grooves shall be constructed in compliance with Clause 1013. Any irregularities at wet-formed
joint grooves shall be rectified by means of a vibrating float at least 1.0 m wide drawn along the line of the joint.
The whole area of the slab shall be regulated by two passes of a scraping straight edge not less than 1.8 m wide or
by a further application of a twin vibrating finishing beam. Any excess concrete on top of the groove former shall
be removed before the surface is macrotextured.
6 (02/16) The surface shall be brush-textured as described in Clause 1026.
7 (02/16) The surface shall be cured in compliance with Clause 1027, within the time to completion given in
Table 10/7.

1026  (02/16) Finished Surface Requirements


(02/16) Macrotexture of Running Surfaces
1 (01/20) The macrotexture of running surfaces for pavement widening, partial reconstruction and repair
shall comply with sub-Clauses 2 to 6 of this Clause, other pavements shall comply with sub-Clause 2 and
sub- Clauses 7 to 27 of this Clause.
2 (01/20) The finished surface of the pavement shall comply with the requirements of Clause 702. Where a
pavement area does not comply with the specification in any respect the full extent of the surface which does not
comply shall be rectified in accordance with Clause 702.
(02/16) Brush Finish Macrotexture
3 (02/16) After the final regulation of the surface of the slab and before the application of the curing membrane,
the surface of concrete slabs to be used as running surfaces shall be brush-macrotextured in a direction at right
angles to the longitudinal axis of the carriageway. The macrotexture shall be applied evenly across the slab in one
direction by a brush not less than 450 mm wide. The macrotexture shall be uniform both along and across the slab.

Amendment – January 2020 26


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

4 (02/16) The macrotexture depth shall be determined by the volumetric patch technique as described in
BS EN 13036-1. Tests shall be taken within 100 m of commencement of paving and thereafter at least once for
each day’s paving at the times after construction as given below and in the following manner: 10 individual
measurements of the macrotexture depth shall be taken at least 2 m apart anywhere along a diagonal line across a
lane width between points 50 m apart along the pavement. No measurement shall be taken within 300 mm of the
longitudinal edges of a concrete slab constructed in one pass.
5 (02/16) Macrotexture depths shall be as required in Table 10/8.
6 (02/16) Where the required macrotexture depth is found to be deficient the Contractor shall make good the
texture across the full lane width over lengths necessary to comply with the requirements of Table 10/9, by
retexturing the hardened concrete surface as described in Clause 1029. Failure to achieve a satisfactory minimum
macrotexture depth by random grooving shall result in the removal of the full thickness of the slab to the extent
required to permit reconstruction of the slab in accordance with the specification. If the macrotexture depth is
excessive the surface shall be planed or ground or otherwise treated over lengths necessary to comply with the
requirements of Table 10/8. The treatment shall not affect the requirements of Clause 702 in respect of surface
levels or surface regularity.

TABLE 10/8: (01/20) Macrotexture Depths

Time of Test Required Macrotexture Depth (mm)


Specified value Tolerance
(i) Between 24 hours and 7 days after An average of 10 measurements 1.00 +0.25
the construction of the slab or until the -0.10
slab is first used by vehicles
(ii) Not later than 6 weeks before the An average of 10 measurements 1.00 +0.25
road is opened to public traffic -0.10

(02/16) Performance Characteristics of Concrete Road Surfaces


7 (01/20) The surface macrotexture shall meet the performance requirements stated in Table 10/8.
8 (01/20) The Contractor shall demonstrate that the ‘as installed’ concrete pavement can meet the requirements of
the specification. This shall be demonstrated by the system meeting the stated material requirements and by having
undergone a System Installation Performance Trial (SIPT) for the surface finish. The SIPT shall comply with the
requirements of sub-Clauses 9 to 27 of this Clause and the requirements of sub-Clause 104.16. The Contractor shall
submit details of the SIPT for the systems to be used in the contract as required in sub-Clause 15 to the Overseeing
Organisation for acceptance.
With respect to the requirements of this Clause ‘the system’ shall be the combination of materials, equipment and
working methods to be used in the works. The SIPT shall have been undertaken with the same materials, equipment
and working methods.
(01/20) System Installation Performance Trial (SIPT) Requirements
9 (01/20) The surface finish used in the SIPT shall meet the performance requirements of the surface course to be
supplied under the contract. The SIPT shall demonstrate, and enable verification of, the performance of the road
surface.
10 (01/20) The SIPT shall be undertaken during daylight hours and shall be a minimum of 200 metres in length and
3.5 metres wide.
11 (01/20) The system shall be assessed, tested and certified by a Certification Body using one or more trial
areas of pavement. The Certification Body shall be accredited to BS EN 45011 by UKAS or equivalent European
Accreditation organisation which is party to a multi-lateral agreement (MLA) with UKAS or any equivalent
International Accreditation Forum MLA signatory with a scope that includes relevant standard(s) or scheme(s).

Amendment – January 2020 27


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

12 (01/20) The average locked wheel friction of the SIPT road surface macrotexture depth of the surface shall
be measured in accordance with ASTM E274/E274M – 11, at a speed of 90 km/hr rather than 40 mph in the test
method, using a tyre that complies with ASTM E524 – 08.
13 (01/20) A SIPT method statement shall be prepared. The SIPT shall demonstrate, and enable verification of, the
installation procedures given in the SIPT method statement. This will include working methods and equipment, any
limitations, aftercare, testing methods and frequency of testing.
14 (01/20) A SIPT inspection protocol shall be prepared. It shall demonstrate qualitatively and quantitatively the
applicability of the SIPT for the system in order to satisfy the performance requirements.
15 (01/20) The SIPT method statement, SIPT inspection protocols, all inspection and testing results and the SIPT
certification shall be submitted to the Overseeing Organisation prior to the commencement of concrete pavement
construction.
16 (01/20) The SIPT shall include the following to be undertaken by the Certification Body:
(i) verification that the system installation trial has been undertaken in accordance with the SIPT method
statement;
(ii) assessment of the data from the site performance tests detailed in sub-Clause 17
17 (01/20) The installed performance of the system over the two-year trial period shall be assessed at the intervals
specified in Table 10/9. Data relating to properties in Table 10/9 shall be provided to the Overseeing Organisation

TABLE 10/9: (01/20) Installed Performance Characteristics

Property Frequency Requirement


Average locked wheel friction (L- Initial, 12 and 24 months >0.3 L-Fn90
Fn90) measured at 90km/hr. by
Pavement Friction Tester
Noise (Voluntary assessment and Between 12 and 24 months Table 10/11
declaration)

(02/16) Noise
18 (01/20) Where noise characteristics for the surface are specified in contract specific Appendix 7/1 the SIPT shall
include the assessment and measurement of the road/tyre noise levels. The road/tyre noise level of the concrete
shall be assessed as detailed in sub-Clauses 19 to 27 of this Clause, and declared as NR, 0, 1, 2 or 3 as described
in Table 10/10. If the SIPT site conditions are not appropriate for testing an alternative site shall be selected and
nominated.

TABLE 10/10: (01/20) Road/Tyre Noise Levels

Level Equivalence to Traditional Surfacing Materials Road Surface Influence


RSI
3 Very quiet surfacing material -3.5 dB(A)
2 Quieter than HRA surfacing materials -2.5 dB(A)
1 Equivalent to HRA surfacing materials -0.5 dB(A)
0 Noisier than HRA Surfacing materials +1.2 dB(A)
NR No requirement No requirement

19 (01/20) The influence of the road surface on traffic noise using the statistical pass-by method shall
be established at the SIPT site between 12 and 24 months after opening to traffic in accordance with
ISO 11819- 1: 2002, Sections 7 and 8.

Amendment – January 2020 28


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

20 (01/20) Acoustic measurements shall only be carried out when the road surface is dry and the meteorological
conditions specified in ISO 11819-1: 2002, Section 11 are met.
21 (01/20) The air and surface temperatures are monitored in accordance with the procedure described in
ISO 11819-1: 2002, Clause 8.5. The road surface temperature, T surface, must be within 5°C to 50°C during
acoustic measurements. The air temperature, T air, must be within 5°C to 30°C.
22 (01/20) The test location road speed category shall be classified as either Medium or High as defined in
ISO 11819-1: 2002, clause 3.3. Not less than two test locations are selected for each road speed category, which
may be at the same site, provided the locations are at least 100 m apart or on different carriageways. Each test
location shall be representative in terms of road speed category and traffic level. Each of the test sites selected must
meet the requirements of ISO 11819-1: 2002 Section 6 and ISO/CD 11819-2: 2000. The road must be essentially
straight, or bends with a radius of curvature greater than 500 m for medium-speed, and 1000 m for high-speed road
categories. The crossfall of the test lane at the test site must not exceed 4%.
23 (01/20) The apparatus described in ISO 11819-1: 2002 Section 5 are used. The frequency range of between
100 and 5000 Hz (centre frequencies of the one-third octave bands) should be covered.
24 (01/20) The macrotexture of the road surface used for the noise assessment shall be measured in the nearside
wheel-track along the whole length of test material in accordance BS EN 13036-1: 2010. The macrotexture depth of
the nearside wheel-track in front of a test location must be within 10 per cent of the average macrotexture measured
along the site.
25 (01/20) The microphone location at each measurement site shall be recorded accurately and marked with
appropriate methods such that the position can be readily identified for a period of at least two years.
26 (01/20) When sufficient vehicle pass-bys’ have been measured, a linear regression analysis shall be performed
in accordance with ISO 11819-1: 2002, Clause 9.1. In the case of the high-speed road category, measurements must
not be taken of vehicles travelling at speeds of less than 60 km/h in accordance with AFNOR Standard S31-119.
27 (01/20) For each category of vehicle defined in Table 10/11, the Vehicle Sound Level, Lveh, shall be
calculated as the ordinate sound level of the regression line at the reference speed for the category of road. All
levels shall be calculated to two decimal places and rounded to one decimal place.

TABLE 10/11: (02/16) Reference speeds (km•h-1) for different road speed categories

Vehicle category Road speed category (km·h-1)


Medium High
L 80 110
H1 70 90
H2 70 90

Category L vehicles — light vehicles including passenger cars and car derived vans, excluding vehicles towing trailers.
Category H1 vehicles — commercial trucks with 2 axles and greater than 3.5 tonnes.
Category H2 vehicles — commercial trucks with more than 2 axles and greater than 3.5 tonnes.

(02/16) Texture of Concrete Bases


28 (01/20) The surface of wet-laid concrete bases (prior to the application of a bituminous overlay) shall be
roughened before the application of any curing compound by brushing with a wire brush or stiff broom to achieve
min 0.5 mm texture depth.

Amendment – January 2020 29


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1027  (02/16) Curing


1 (01/20) Immediately after the surface treatment described in Clause 1026, the surface and exposed edges of the
surface shall be cured, without disturbance, for a minimum period of 7 days, by the application of a resin based
aluminised curing compound, or polythene sheeting or a sprayed plastic film which hardens into a peelable plastic
sheet and which shall be removed before road marking and opening to traffic. Where the concrete is to receive a
thin surfacing overlay, the surface and exposed edges shall be cured for a minimum of 7 days by the application of
a curing agent. If the concrete is to be overlaid by bituminous surfacing the curing agent shall be compatible with
the bond coat and installation requirements for the thin surfacing in accordance with Series 900.
2 (02/16) Resin based aluminised curing compound shall contain sufficient flake aluminium in finely divided
dispersion to produce a complete coverage of the sprayed surface with a metallic finish. The compound shall
become stable and impervious to evaporation of water from the concrete surface within 60 minutes of application
and shall have an efficiency index of 90% when tested as described in BS 7542.
3 (02/16) The curing compound shall not react chemically with the concrete to be cured and shall not crack, peel
or disintegrate within three weeks after application.
4 (02/16) Prior to application, the contents of any containers shall be thoroughly agitated. The curing compound
shall be mechanically applied using a fine spray on to the surface at a rate of at least 0.22 1/m². For the sides of
slip‑formed slabs or when the side forms are removed within 24 hours and for small areas where mechanical
application cannot be used, the compound shall be sprayed by hand lance at a rate of at least 0.27 1/m². The rate of
spread shall be checked during construction of each trial length and for each 1000 m² of treated slab.
5 (02/16) The mechanical sprayer shall incorporate an efficient mechanical device for continuous agitation and
mixing of the compound in its container during spraying.
6 (02/16) Continuously reinforced concrete bases shall be cured in accordance with this Clause. Immediately prior
to laying the bituminous surfacing or upper base, a cationic bituminous tack coat shall be applied in accordance
with Clause 920 at a rate between 0.35 l/m² to 0.55 l/m².
7 (01/20) To achieve high early strength for early use by vehicles, insulation blankets as described in Clause 1045
may be used for accelerated curing.

1028  (02/16) Trial Length


(02/16) General
1 (01/20) Except in rapid construction projects and unless otherwise described in contract specific Appendix 7/1,
at least 2 weeks prior to the construction of the trial length of surface slabs or CRCB the Contractor shall submit a
detailed description of the proposed constituent materials, concrete proportions, plant, equipment and construction
methods to the Overseeing Organisation. No trials of new constituent materials, plant, equipment or construction
methods; nor any development of them shall be permitted either during the construction of the trial length or in any
subsequent paving work, unless they form part of further satisfactory trials.
2 (02/16) Unless otherwise described in contract specific Appendix 7/1, the Contractor shall demonstrate the
constituent materials, concrete proportions, plant, equipment and methods of construction that are proposed
for concrete paving, by first constructing a trial length of slab, at least 150 m but not more than 300 m long for
mechanised construction, and at least 30 m long for hand guided methods. The concrete proportions decided
by trial concrete mixes may be adjusted during the trial but shall not be changed once the trial length has been
satisfactorily completed unless the Contractor lays a further trial area to assess the suitability of the proposed
changes.
3 (02/16) The trial length shall be constructed in two parts over a period comprising at least part of two separate
working days, with a minimum of 75 m constructed each day when mechanised paving plant is used and a
minimum of 15 m on each day for hand guided methods. The trial length shall be constructed at a similar rate to
that which is proposed for the main construction in the permanent works.

Amendment – January 2020 30


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

4 (02/16) At least two transverse joints and one longitudinal joint of each type that are proposed for unreinforced
concrete slabs and jointed reinforced concrete slabs in the main construction in the permanent works shall be
constructed and assessed in the trial length. If in the trial length expansion joints are not demonstrated, the first
2 expansion joints and at least the first 150 m of longitudinal construction joint for mechanised paving, or 30 m for
hand guided method of construction laid in the main construction in the permanent works, shall be considered the
trial length for these joints. One construction joint shall be demonstrated in each trial length of CRCP or CRCB.
(02/16) Assessment

5 (02/16) The trial length shall comply for strength and density with the specification in all respects, with the
following additions and exceptions:
(02/16) Surface Levels and Irregularity
(i) In checking for compliance with Table 7/1 the levels shall be taken at intervals of not more than
2.5 m along any line or lines parallel to the longitudinal centre line of the trial length.
(ii) The maximum number of permitted irregularities of pavement surfaces shall comply with the
requirements of Table 7/2 for 300 m lengths. Shorter trial lengths shall be assessed pro-rata based on
values for a 300 m length.
(02/16) Joints
(iii) At least 3 cores of minimum diameter 100 mm shall be taken from the slab at joints to check the lateral
and vertical location of joint grooves and bottom crack inducers.
(iv) Alignment of dowel bars shall be inspected as described in Clause 1019 in any two consecutive
transverse joints. If the position or alignment of the dowel bars at one of these joints does not comply
with Clause 1011 but if that joint remains the only one that does not comply after the next 3 consecutive
joints of the same type have been inspected then the method of placing dowels shall be deemed to be
satisfactory. In order to check sufficient joints for dowel bar alignment without extending the trial length
unduly, the Contractor may construct joints at more frequent joint intervals than the normal spacing
required in contract specific Appendix 7/1.
(v) If there are deficiencies in the first expansion joint that is constructed as a trial the next expansion joint
shall be a trial joint. Should this also be deficient further trial expansion joints shall be made as part of a
trial length. Deficient expansion joints shall not form part of the permanent works.
(02/16) Position of Reinforcement and Tie Bars
(vi) Compliance with Clause 1008 for the position of steel reinforcement and Clause 1012 for the position
and alignment of tie bars shall be checked by drilling additional cores from the slab unless they can be
determined from cores taken for density assessment.
(02/16) Completion of Trial
6 (02/16) The Contractor shall not proceed with normal working unless the trial length complies with the
specification and any earlier defective trial lengths have been removed, unless they can be remedied to comply with
the specification.
7 (02/16) After satisfactory completion of the trial length, the constituent materials, concrete proportions,
plant, equipment and construction methods shall not thereafter be changed, except for normal adjustments and
maintenance of plant, unless the Contractor lays a further trial length as described in this Clause to demonstrate that
the changes will not adversely affect the permanent works or agrees the changes with the Overseeing Organisation.

Amendment – January 2020 31


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Rejection and Further Trials


8 (02/16) Trial lengths which do not comply with the specification, with the exception of areas within the
pavement surface which can be remedied in accordance with Clause 1029, shall be removed and the Contractor
shall construct a further trial length.

1029  (02/16) Texturing of Hardened Concrete


1 (01/20) Worn, rain damaged or inadequately textured surface slabs shall be macrotextured by sawing grooves in
the hardened concrete surface at right angles to the longitudinal axis of the pavement with machines using diamond
or other abrasive cutting discs. This produces a high noise surface and shall only be carried out with the agreement
of the Overseeing Organisation.
2 (02/16) Grooves shall be irregularly spaced and shall be not less than 2 mm and not more than 5 mm wide.
The sequence of distances between groove centres in mm shall be: 40, 45, 35, 45, 35, 50, 30, 55, 35, 30, 50, 30,
45, 50, 30, 55, 50, 40, 35, 45, 50, 40, 55, 30, 40, 55, 35, 55. A tolerance of ± 3 mm shall be allowed on each of the
spacings. The minimum width of grooving head shall be 500 mm and a head not providing a complete sequence of
spacings shall use the number of spacings appropriate to its width commencing at the start of the sequence.
3 (02/16) Groove depths shall be measured using a tyre tread depth gauge and measurements shall be taken as
follows:
(i) At 10 locations at least 2 m apart along a diagonal line across a lane width between points 50 m apart
longitudinally. No measurement shall be taken within 300 mm of the longitudinal edge of a slab.
(ii) At each of the 10 locations the depth of 10 adjacent grooves shall be measured.
(iii) Where a grooved area is less than 50 m in length the locations where measurements are taken shall be as
(i) but the number shall be proportional to the requirements for 50 m.
(iv) The average of each set of 10 measurements shall be not less than 3 mm, nor greater than 7 mm.
4 (02/16) Slurry from the sawing process shall be prevented from flowing into joints, drains or into lanes being
used by traffic, and all resultant debris from the grooving shall be removed.

1030  (01/20) Lower Strength Concrete


(02/16) Grades and Constituents
1 (01/20) The strength for Lower Strength concrete shall be as described in Clause 1001 with the following
constituents:
(i) cements as described in sub-Clause 1001.3 and water/cement ratio as described in sub-Clause 1001.4;
(ii) aggregate shall be in accordance with sub-Clause 1001.6.
(02/16) Consistence (Workability)
2 (02/16) Consistence shall comply with Clause 1005.
(02/16) Placing
3 (01/20) Lower Strength concrete shall be spread uniformly, without segregation and without varying degrees
of pre-compaction. The concrete shall be struck off to a level so that the surcharge is sufficient to ensure that after
compaction the surface is at the required level.

Amendment – January 2020 32


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Compaction
4 (01/20) The spread Lower Strength concrete shall be compacted using internal or external vibration, or a
combination of both to meet the required density. Compaction and finishing to level shall be completed within the
times given in Table 10/7.
(02/16) Joints
5 (02/16) At transverse and longitudinal construction joints between two separately constructed slabs, the
previously laid slab end or edge shall present a vertical face before construction of subsequent slabs.
6 (01/20) Longitudinal joints in Lower Strength concrete shall be staggered by at least 300 mm from the position
of longitudinal joints in any superimposed concrete slab, and by 1m for transverse joints.
(02/16) Curing
7 (01/20) The surface shall be cured, without disturbance, for a minimum period of 7 days, by the application of
a resin based aluminised curing compound, or polythene sheeting or a sprayed plastic film which hardens into a
peelable plastic sheet.
(02/16) Sampling for Testing
8 (02/16) Sampling shall be as specified in Clause 1003.
(02/16) Density
9 (02/16) The density shall be determined as required in Clause 1003.
(02/16) Strength
10 (02/16) The strength shall be determined as in Clause 1004.
(02/16) Trial Concrete Mixes
11 (02/16) Trial concrete mixes shall conform with BS 8500-2 for designed concretes for strength class C12/15 and
above or CC14 and above, unless recent data relating entirely to the proposed concrete, satisfies the requirements of
the specification.
(02/16) Trial Length
12 (01/20) At least 10 days before the start of the main Lower Strength concrete works a trial length of at least
400 m2 for mechanised construction and 30 m for hand-guided methods shall be constructed. The trial length shall
be laid to assess the suitability of the proposed material, plant, equipment and construction methods to meet the
requirements of the specification. The main construction in the permanent works shall not start unless the trial
length complies with the specification. If any trial length does not conform to the specification another trial length
shall be constructed. Trial lengths not complying shall be removed unless they can be rectified to comply with the
specification.
13 (02/16) After satisfactory completion of the trial, the material, plant, equipment and construction methods shall
not be changed unless the Contractor lays a further trial length to assess the suitability of the proposed changes or
agrees the changes with the Overseeing Organisation.
(02/16) Surface Finish
14 (01/20) The surface of the Lower Strength concrete after compaction and finishing and before overlaying shall
be free from ridges, loose material, pot holes, ruts or other defects.

Amendment – January 2020 33


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1031  (02/16) Measurement of Macrotexture Depth – Volumetric Patch Technique


1 (01/20) For repairs and widening of existing concrete pavements only the macrotexture depth of the road surface
will be determined using the method described and the equipment specified in BS EN 13036-1.

1032  (02/16) Thin Bonded Repairs


(02/16) Materials
1 (01/20) Cement mortar shall be used for depths less than 20 mm and fine concrete for greater depths. Resin
mortar may be used for patch repairs where insufficient time for adequate curing of a cementitious cement mortar
exists.
2 (02/16) The cements, aggregates, admixtures and water shall comply with Clause 1001. The sand (ie fine
aggregate) for mortars or fine concrete shall be within the limits of 0/4 (CP), 0/4 (MP), 0/2 (MP) or 0/2 (F/P)
of BS EN 12620. Coarse aggregate for fine concrete shall be (4/10) single sized aggregate complying with
BS EN 12620. All aggregates shall have the same thermal properties as the aggregate in the original concrete, and
match other properties as closely as possible. Filler and aggregate for resin mortars shall be prepacked in the correct
proportions and mixed with the resin all in accordance with the manufacturer’s instructions.
3 (01/20) The proportions of cement, admixtures, additives to water and aggregates shall be sufficient to provide
high early strength mortar or fine concrete or concrete complying with Clauses 1001, 1003 and 1004. For cement
mortar the sand (ie fine aggregate) to cement ratio shall not be greater than 3. For resin mortar the sand content
shall be in accordance with the manufacturer’s requirements in the range between 7 and 11 to 1 of resin. High early
strength concrete shall be able to achieve 25 N/mm2 before opening to traffic. For thin bonded repairs using high
early strength concrete, air entrainment is not required.

1033  (01/20) Full Depth Repairs


(02/16) General
1 (01/20) Full depth repairs shall be repairs which will require full depth reinstatement of the concrete slab in
accordance with this Clause to the extent instructed by the Overseeing Organisation, repairs may also require
reinstatement of sub-base. Full width repairs shall be repairs over the full width of a bay or bays. Part width
repairs shall be repairs over part of the width of a bay or bays. A bay shall be that portion of the concrete pavement
bounded by adjacent longitudinal and transverse joints.
2 (01/20) For continuously reinforced concrete slabs (CRCP or CRCB) the edge of the repair shall be not less than
0.5 m from the nearest crack and not less than 3 m from a transverse construction joint at ground beam anchorages.
Where this and the provisions of sub-Clause 3 of this Clause would otherwise require a longitudinal repair joint
within 1 m of the existing longitudinal joint or edge, the repair shall be extended to align with that longitudinal
joint or edge.
3 (01/20) High early strength concrete shall be able to achieve 25 N/mm2 before opening to traffic. For full depth
repairs using high early strength concrete, air entrainment is not required.
(02/16) Part Width Repairs
4 (01/20) Providing all the following criteria are met, part width repairs may be carried out in accordance with
sub-Clause 4 of this Clause:
(i) the transverse width of the repair shall not exceed 45% of the width of the slab under repair; and
(ii) the longitudinal joint which would be formed by the repair shall not occur within the wheeltrack; and
(iii) the minimum transverse width of the repair shall not be less than 1.0 m.
If these criteria and those in sub-Clause 2 of this Clause cannot be met, a full-width repair shall be made in
accordance with this Clause.

Amendment – January 2020 34


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Full Width Repairs


5 (01/20) For full width repairs the following criteria shall apply unless otherwise specified in contract specific
Appendix 7/2:
(i) Repair lengths which do not replace an existing transverse joint shall be constructed with two transverse
contraction joints and the longitudinal joint shall have tie bars in repair lengths which are greater than
1 metre.
(ii) Repair lengths which replace a single existing transverse joint shall be constructed with two transverse
joints: one expansion and one contraction. The new expansion joint shall be formed at the end which
will have the shortest longitudinal distance between this joint and the joint in the adjacent lane(s). The
longitudinal joint(s) between the existing joint(s) and the new expansion joint shall be constructed
without tie bars and shall have 5 mm thick compressible foam within the joint for the full depth of the
concrete slab. The longitudinal joint between the new contraction joint and the joint in the adjacent
bay(s) shall be constructed with tie bars where the exposed length so permits.
(iii) Repair lengths which replace more than one existing transverse joint shall be constructed with transverse
joints to match expansion and contraction joints in the adjacent bay(s). Where the repair length does not
replace an existing expansion joint, one end joint shall be formed as an expansion joint. Except for the end
joints all transverse joints shall be formed to coincide with the existing transverse joints. Where one end
joint is an expansion joint, the longitudinal joint(s) between the existing joint(s) and the new expansion
joint shall be constructed without tie bars and shall have 5 mm thick compressible foam within the joint
for the full depth of the concrete slab. All other longitudinal joints shall be constructed with tie bars.
(02/16) Repair Work
6 (01/20) Any replacement dowels and tie bars shall comply with the requirements of Clauses 1011 and 1012
respectively. Epoxy mortar shall be to the manufacturer’s recommendation for this specific application.
Where repairs straddle a movement joint with an adjacent slab, tie bars shall be omitted and the joint between the
slabs debonded to ensure that movement patterns are not restricted.
(02/16) Crack Repairs
7 (01/20) Stitched crack repairs shall be either:
Type 1 – Staple Tie Bar Repair
Type 2 – Diagonal Tie Bar Repair
as described in contract specific Appendix 7/2 and compliant with sub-Clauses 7 and 8 of this Clause.
8 (01/20) For Type 1 crack repairs, slots 25 – 30 mm wide by 470 mm long at 600 mm centres and at right angles
to the line of the crack shall be chased out to a depth such that, when bedded, the tie bars lie between 1/3 and 1/2 of
the depth of the slab below the surface.
9 (01/20) For Type 2 crack repairs drilling points shall be at a distance from the crack equivalent to the depth of
the slab, at 600 mm intervals along the crack with alternate points on opposite sides of the crack.

1034  (02/16) Bay Replacement


1 (01/20) Where individual bays are to be replaced they shall match the design thickness of the original concrete
including reinforcement if originally included.
2 (01/20) The replacement bay shall be connected to the surrounding concrete with new dowel and tie bars at
transverse and longitudinal joints in accordance with Clause 1011.
3 (01/20) Grooves shall be formed in accordance with Clause 1013.

Amendment – January 2020 35


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

4 (01/20) A surface texture as specified in Clause 1026 shall be applied and a sprayed resin based, aluminized
curing compound.
5 (01/20) Joints surrounding the new bay shall be sealed specified in Clause 1016.

1035 to 1038  (01/20) Not Used

1039  (02/16) Summary of Rates for Sampling and Testing Concrete for Pavement Layers
1 (02/16) Unless otherwise stated in contract specific Appendix 1/5, Table 10/12 summarises the minimum rates of
sampling and testing of specimens to the specification.
2 (02/16) Samples for testing shall be taken at the point of placing or from the relevant pavement layer.
TABLE 10/12: (01/20) Rates for Sampling and Testing Concrete for Pavement Layers

Clause Test Rate (the greater number shall be used)

1002 Air content a) Main slab 1 per 300 m2 or 6 per day

b) Slabs less than 300 m² 1 per 20 m length or 3 per day

1003 Density a) Trial length


A minimum of 3 cores at a rate of 1 core per 1000 m2 sets of
3 cubes for every 400m2 of concrete laid
b) Main Slab

1004 Strength a) Main slab 3 cubes per 400m2 not less than 6 sets per day. 1 to be tested
at 7 days and 2 at 28 days.

b) Trial length At least 9 cubes, 3 to be tested 7 days and 6 at 28 days

1005 Consistence a) Main Slab – Initial 50 m3 3 samples


– Subsequently 1 per 150 m3 or 1 per production day

b) Slabs less than 150 m3 3 samples in the first 50 m3 then 1 more

1019 Inspection of dowel a) Main slab 1 joint per 1500 m length or 1 joint per 5 days whichever is
alignment the sooner

b) Slabs less than 1500 m in length At a rate of one joint for up to each 100 joints

c) Trial lengths 2 consecutive joints. If one defective, inspect next


3 consecutive joints

1026 Macrotexture depth Each lane width One within 100 m of commencement of paving and
thereafter at least one set of 10 measurements per day’s work.

1030 Lower Strength As in Clause 1003 and 1004


concrete

In situ density A minimum of 3 cores at a rate of 1 core per 1000 m2

Strength a) Main slab 3 cubes per 600m2 not less than 6 sets per day
At least 6 cubes, half to be tested 7 days and half at 28 days

b) Trial length 3 cubes per 600m2 not less than 6 sets per day
At least 6 cubes, half to be tested 7 days and half at 28 days

Amendment – January 2020 36


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1040 to 1042  (02/16) Not Used

1043  (02/16) Foamed Concrete


1 (02/16) Foamed concrete used in reinstatements shall comply with the requirements of the “Specification for the
Reinstatement of Openings in Highways” issued by the Highway Authorities and Utilities Committee.
2 (02/16) Foamed concrete used for backfilling excavations, including trench reinstatement, under road pavements
shall have the following compressive strengths:
(i) A minimum cube compressive strength of 4 N/mm2 at an age of 7 days.
(ii) A maximum cube compressive strength of 10 N/mm2 at an age of 7 days.
(The compressive strength shall be determined by testing foamed concrete cubes which have been made in
accordance with BS EN 12390-1 except that the foamed concrete shall be placed in the mould without any tamping
or vibration other than gently rocking the mould on a firm base. The test cubes shall be cured in accordance with
BS EN 12390-2 and tested for compressive strength in accordance with BS EN 12390-3.
3 (02/16) All aggregate used in foamed concrete shall pass a 6.3 mm sieve and shall comply with the MP and
FP grading limits given in BS EN 12620. Larger size aggregate may be used provided it can be shown to be
practicable.
4 (02/16) After placing, foamed concrete shall not be tamped, or otherwise compacted.
5 (02/16) Reinstatement of the sub-base and base over the foamed concrete shall not be carried out until the
foamed concrete has attained sufficient strength to allow compaction of the sub-base and base material.

1044  (02/16) Pavements with an Exposed Aggregate Concrete Surface


(02/16) General
1 (01/20) Pavements with an exposed aggregate concrete surface shall comply with all the requirements of this
Series except Clause 1026 and where otherwise specified in this Clause.
2 (02/16) The Contractor shall complete contract specific Appendix 10/1 and submit this with his tender
documents. If after acceptance the Contractor wishes to change the proposals contained in contract specific
Appendix 10/1 this change shall only be with the consent of the Overseeing Organisation.
3 (02/16) The concrete slab shall be laid in either a single layer or in two layers as stated in contract specific
Appendix 10/1. If laid in two layers the surface layer shall be laid monolithically with the lower layer.
4 (02/16) The Contractor shall carry out trials, as specified in sub-Clauses 31 to 39 of this Clause, to demonstrate
that the materials, concrete proportions and methods for exposing the aggregate will meet the requirements of this
Clause.
(02/16) Quality of Concrete in the Slab
5 (02/16) The surface layer concrete shall comply with the following requirements:
(i) The surface layer shall be not less than 40 mm thick. The coarse aggregate shall comply with the size
requirements of contract specific Appendix 7/1.
(ii) For 6.3/10 mm coarse aggregate or 4/8 mm coarse aggregate as required in contract specific Appendix
7/1, the amount of aggregate retained on the 10 mm sieve and 8 mm sieve respectively shall not exceed
3% by mass. The aggregate passing the 6.3 mm sieve and 4 mm sieve respectively shall not exceed 10%
by mass.
(iii) The fine aggregate grading shall comply with the 0/2 (FP) or 0/1 (FP) grading in BS EN 12620 except
that not less than 99% of the mass of the material shall pass the 2 mm sieve.

Amendment – January 2020 37


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(iv) The coarse aggregate shall comprise at least 60% by mass of the oven dry constituents of the concrete.
(v) The polished stone value (PSV) and the aggregate abrasion value (AAV) of the coarse aggregate
determined in accordance with BS EN 1097-8 shall be as specified in contract specific Appendix 7/1.
The Category of flakiness index of the aggregate is FI15.
(vi) Hardness and durability of the coarse aggregate shall be as described in sub-Clause 901.2.
(vii) The type of cement used in the concrete shall be limited to Class 42.5N/42.5R Portland cement CEM I
complying with BS EN 197-1. The minimum cement content of the concrete shall be 375 kg/m³ and the
maximum free water/cement ratio shall be 0.40.
(viii) The air content, density and strength requirements shall be as required in Clauses 1002, 1003 and 1004
respectively.
(02/16) General Construction Requirements
6 (02/16) The concrete paving equipment shall comply with contract specific Appendix 10/1 as completed by the
Contractor and submitted at Tender stage for approval by the Overseeing Organisation before the work commences.
The general construction requirements shall be in accordance with the requirements of this Series except where
otherwise stated in this Clause:
(i) The concrete carriageway paving operation shall be undertaken as not less than a single lane width of
construction using either slip-form paving machines or fixed form paving machines.
(ii) The concrete surface layer shall be fed, spread, compacted, regulated and finished using equipment with
elements to obtain the required uniform distribution and bonded embedment of the selected aggregate in
the finished road surface.
(iii) The spread concrete shall be compacted in such a manner that base layer concrete is not drawn into the
surfacing and selected aggregate is uniformly present in the finished road surface.
(iv) The surface layer shall be compacted and shaped to line and level by a combination of either internal
vibration and fixed conforming plate or vibrating conforming plate.
(v) The final regulation of the surface layer shall be provided by a transverse finishing screed in advance
of a longitudinal oscillating float in accordance with Clause 1024, travelling across the slab before the
application of a retarder complying with BS EN 934-2.
(02/16) Finished Surface Requirements
7 (02/16) The finished surface of the pavement shall comply with the requirements of Clause 702. Where
a pavement area does not comply with the specification for regularity, surface tolerance, thickness, material
properties or compaction or contains surface depressions, the full extent of the surface which does not comply
with the specification shall be rectified by cutting out the full depth of the slab. It shall be replaced with a new
slab complying with the procedures set out in Clause 1033 to the extent required to obtain compliance with the
specification.
(02/16) Production of an Exposed Aggregate Surface
8 (02/16) In order to obtain a suitable exposed aggregate surface the main requirement shall be the removal of the
surface mortar from the top of the slab to produce an exposed aggregate finish. This objective may be achieved by
the application of a suitable cement set retarder which is sprayed on the surface of the fresh concrete immediately
after it has been levelled and finished. Retarded mortar shall be removed by wet or dry brushing as stated in
contract specific Appendix 10/1, generally no sooner than when the surface concrete has reached a maturity of
16 hours at 20°C or after a suitable interval determined by trial, to achieve the requirements of sub-Clause 27 of
this Clause.

Amendment – January 2020 38


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(02/16) Retarder
9 (02/16) The composition and viscosity of the retarder shall be such that it can be spread at an adequate and
uniform rate over the surface of the concrete slab in order to ensure adequate aggregate exposure during the
subsequent brushing operation.
10 (02/16) The retarder shall contain a pigment in sufficient quantity to give an even uniform colour after it has
been sprayed on to the slab surface. The pigment shall be fully degraded by exposure to ultra-violet light without
leaving any residue that is detrimental to the surface of the concrete.
11 (02/16) The chemical composition of the retarder and of the curing compound shall be such that they do not
react adversely following the application of the curing compound to the exposed aggregate surface.
12 (02/16) The Contractor shall use the retarder which he has nominated in contract specific Appendix 10/1.
This shall be of a type and composition to satisfy the requirements of this Clause.
(02/16) Application of the Retarder
13 (02/16) The retarder shall be spread evenly on to the surface of the wet concrete slab as soon as practicable
after the surface layer has been levelled and finished, by a spray bar over the full width of the slab in one pass. To
achieve this uniformity of spread, the spraying system shall consist of a spray bar, provided with nozzles, mounted
on a machine spanning the slab. Temporary works materials and equipment shall be chosen in order to permit
inspection to ensure adequate coverage of retarder immediately after spraying and before protection of the surface.
14 (02/16) Before commencing work, the level of the spray bar, the rate of delivery of the retarder from the nozzles
of the spray bar, and the forward speed of the spraying machine shall be adjusted to achieve the required rate of
spread. Means shall be provided and steps shall be taken to avoid excess retarder flowing on the surface of the slab.
15 (02/16) Back-up spraying equipment shall be available on the site at all times for use in case of a breakdown of
the spraying machine.
(02/16) Protection of the Surface after the Application of the Retarder
16 (02/16) The finished surface of the pavement concrete after application of retarder shall be protected against
precipitation, moisture loss, contamination and dispersal of the retarder by air movements as stated in contract
specific Appendix 10/1. This protection shall be applied immediately after the application of the retarder.
17 (02/16) Where waterproof sheeting is used it shall be laid onto the surface of the concrete immediately after the
retarder has been sprayed. It shall be retained in position until immediately prior to exposing of the aggregate.
18 (02/16) The protection system shall not adversely affect either the finish, the line or the level of the concrete
surface or the even distribution of the retarder in any way. Where sheeting is used, any air bubbling or blistering
shall be prevented.
(02/16) Exposing the Aggregate Surface
19 (02/16) Brushing equipment shall be used to expose the concrete surface aggregate. Where the brushing
equipment runs on the slab the concrete shall have gained sufficient strength to avoid any damage to the concrete.
20 (02/16) Removal of the protection system shall take place as brushing proceeds. If waterproof sheeting is used
as a protection system it shall be maintained in position until immediately in advance of the brushing operation.
21 (02/16) The Contractor shall complete the process of exposing the aggregate before the retarder becomes
ineffective. Failure to do so shall entail the remedial measures specified in sub-Clauses 29 and 30 of this Clause.
(02/16) Brushing System
22 (02/16) Sufficient brushing capability shall always be maintained on site to complete the exposure of the
aggregate before the retarder becomes ineffective. An adequate back-up brushing facility shall be available on the
site at all times for use in case of a breakdown of the brushing equipment.

Amendment – January 2020 39


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

23 (02/16) The brushing equipment nominated by the Contractor in contract specific Appendix 10/1 shall be used to
produce an even macrotexture on the surface of the slab. Brushing shall be carried out in the longitudinal direction
of the concrete slab.
24 (02/16) The brushing equipment shall be capable of maintaining an adequate brush rotational speed which in
conjunction with the forward working speed is sufficient to remove the surface mortar. Adequate dust suppression
and collection measures shall be in operation at all times.
25 (02/16) When complying with the requirements of sub-Clause 19 of this Clause, the wheels of any brushing
equipment which may run on the slab shall be fitted with tyres with a shallow tread pattern and a low inflation
pressure and be sufficiently wide to avoid damage to the concrete.
(02/16) Protection of the Surface Layer After Exposure of the Aggregate
26 (02/16) Within one hour of completing exposure of the aggregate the surface shall be dampened with water.
A curing compound shall be applied to the entire exposed aggregate surface of the slab in accordance with
Clause 1027. In wet weather the curing compound shall be applied as soon as practicable after the rain stops. The
surface may, alternatively, be covered by hessian provided it is maintained in a wet condition at all times during the
curing period of the concrete.
(02/16) Surface Macrotexture Depth and Remedial Measures
27 (02/16) The texture depth of the surface of the concrete shall be measured using a volumetric patch technique
described in BS EN 13036-1. The average macrotexture depth of each 1000 m section of carriageway lane, or each
carriageway lane where less than 1000 m, shall comply with the requirements of contract specific Appendix 7/1.
Any individual result shall be neither greater than the maximum, nor be less than the minimum value of
macrotexture depth stated in contract specific Appendix 7/1.
28 (02/16) During brushing, initial interim spot check measurements of the surface macrotexture depth shall be
made as soon as it is considered that the required texture depth has been reached. This shall continue until the
specified macrotexture depth has been achieved.
29 (02/16) In the event that it is not possible to achieve the specified minimum macrotexture depth by further
exposure, the Contractor shall treat the surface in accordance with Clause 1029 to achieve the specified
macrotexture depth. This treatment shall not be applied until the concrete has reached an age of 28 days and shall
not affect the requirements of sub-Clauses 702.2 to 702.4 and 702.5 to 702.9.
30 (02/16) Failure to achieve a satisfactory minimum macrotexture depth by mechanical means shall result in
removal of the full thickness of the slab to the extent required to permit reconstruction of the slab in accordance
with the specification. Where the maximum macrotexture depth is exceeded suitable remedial measures shall be
employed.
(02/16) Preliminary Trials
31 (02/16) The Contractor shall carry out preliminary trials to demonstrate to the Overseeing Organisation, not less
than one month prior to the commencement of the trial length referred to in sub-Clauses 37 to 39 of this Clause, the
materials, concrete proportions and methods for achieving the macrotexture depth requirements defined in contract
specific Appendix 7/1.
32 (02/16) Preliminary trial panels shall be constructed off-line incorporating a top surface of exposed aggregate
concrete similar to that specified for the permanent works. These panels shall be 20 m long and not less than
100 mm deep, and the maximum intended paving width. They shall be used to enable the Contractor to determine
the required application rate of the retarder and the amount of brushing required to achieve the specified
macrotexture depth.
33 (02/16) The trial panels may alternatively be constructed on-site, but in this case, they may only form part of the
permanent works if they meet all the requirements of the specification, otherwise they shall be removed after they
have served their purpose.

Amendment – January 2020 40


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

34 (02/16) The surface macrotexture depth shall be determined by volumetric patch technique at approximately
2 m spacings along a diagonal line across each trial panel, and shall follow the procedure described in
BS EN 13036-1.
35 (02/16) The average value of each set of 10 individual measurements shall be taken as the resulting
macrotexture depth which shall be assessed against the specification.
36 (02/16) The materials including all the aggregates, plant and equipment used in the preliminary trials shall be
equivalent to that which will be used in the Trial Length.
(02/16) Trial Length
37 (02/16) In addition to the requirements of Clause 1028, the macrotexture depth shall be tested for compliance in
accordance with sub-Clauses 38 and 39 of this Clause.
38 (02/16) Macrotexture depth shall be assessed by the volumetric patch technique for each 50 m length of the trial
length and for each lane, and shall follow the procedure in BS EN 13036-1.
39 (02/16) During the construction of the Trial Length, spot checks shall be made as soon as it is considered that
the required macrotexture depth has been reached. Should the texture depth be found to be inadequate, further
exposure of the aggregate shall be undertaken until the specified macrotexture depth has been achieved. Where the
macrotexture depth is not achieved, and the trial was intended to form part of the running surface of the permanent
works, the remedial measures described in sub-Clauses 29 and 30 of this Clause shall apply.

1045  (02/16) Weather Conditions for Laying of Cementitious Materials


1 (01/20) Road pavement materials in a frozen condition shall not be incorporated in the works.
2 (02/16) Road pavement materials shall not be laid on any surface which is frozen or covered with ice.
3 (01/20) The temperature of concrete in any pavement layer shall not be less than 5ºC at the point of delivery.
These materials shall not be laid when the air temperature falls below 3ºC and laying shall not be resumed until
the rising air temperature reaches 3ºC unless all surfaces of the concrete slabs are protected by thermal insulation
blankets laid immediately after placing and finishing the concrete. The insulation shall be placed before the
temperature of the concrete surface has dropped below 2ºC. It shall be retained for a minimum of 3 days or until
the concrete is assessed to have reached 50% of the specified characteristic 5 N/mm2 compressive strength based on
testing of samples cured adjacent to the placed concrete provided the air temperature is above 0ºC and rising at that
time. Thermal insulation blankets shall be closed cell polyethylene foam sheets, minimum 10 mm thick with a ‘U’
value of 4 watts/m ºC (or K value of 0.04 watts/m Kelvin) or suitable material with an equivalent or lower thermal
conductivity. They shall be sufficiently robust and capable of being held in place against variations in wind and
weather conditions for the necessary curing time.

1046 to 1047  (02/16) Not Used

1048  (02/16) Use of Surfaces by Traffic and Construction Plant


1 (02/16) Construction plant and traffic used on pavements under construction shall be suitable in relation to the
material, condition and thickness of the courses it traverses so that damage is not caused to the subgrade or the
pavement courses already constructed. The wheels or tracks of plant moving over the various pavement courses
shall be kept free from deleterious materials.
2 (02/16) Concrete slabs may be used by traffic when the cube compressive strength is assessed to have reached
25 N/mm2 for pavement surface slabs, or 20 N/mm2 for bases with asphalt surfacing. The method of assessing the
time when this strength is reached shall be as described in Clause 1004.

Amendment – January 2020 41


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

3 (02/16) In the absence of test data establishing compliance with sub-Clause 2 of this Clause, no vehicle with an
axle loading greater than 2 tonnes shall run on concrete slabs within a period of 14 days after placing the concrete.
Vehicles with rubber tyres with an axle loading less than 2 tonnes, or wheels or tracks of concreting plant, shall
not use any part of a newly constructed pavement within 7 days. The above periods before traffic may run on the
pavement shall be increased if the 7 day cube strength is below that required in the specification. These periods
shall be extended by one day for each night on which the temperature of the layer falls to 0ºC or below.

1049 to 1050 (01/20) Not Used

(01/20) Roller Compacted Concrete Mixtures

1051 (01/20) General Requirements for Roller Compacted Mixtures


1 (01/20) Roller Compacted Concrete (RCC) shall be produced, constructed and tested in accordance with
Clauses 1051 to 1060. Unless otherwise specified in Clauses 1051 to 1060 the works shall conform to the
requirements of this Series.
2 (01/20) The terms listed below shall apply to the RCC Clauses of this specification:
RCC Roller Compacted Concrete
FA fly ash (also known as ‘pulverized fuel ash’)
Gvxx volumetric expansion category
IBI immediate bearing index
Immxx immersion category
IBIxx immediate bearing index category
LA Los Angeles coefficient
NR no requirement
OWC optimum water content
PTR Pneumatic tyred roller
Rc compressive strength
t time (hours) at constant temperature in defining maturity for calculating the construction period
TºC ambient air temperature in defining maturity for calculating construction period
3 (01/20) The strength class for RCC shall be a minimum mean strength C40/50 in accordance with
sub- Clauses 1059.9 to 1059.13.
4 (01/20) RCC shall be tested in accordance with contract specific Appendix 1/5, Clause 1059 and the test
methods specified in the following Clauses.
5 (01/20) Before work commences, the Contractor shall submit a statement to the Overseeing Organisation that
includes:
(i) the information detailed in the ‘Designation and Description’ clause of the relevant BS EN Standard
for the specified RCC, confirming compliance with the requirements of this Series and contract specific
Appendix 7/1;
(ii) target proportions of constituents, including optimum moisture content;
(iii) mixture design details and results, in accordance with Clause 1060.
(iv) Method statement for the trial length and the main works, in accordance with Clause 1056.

Amendment – January 2020 42


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1052 (01/20) RCC Constituents


(01/20) Cement and combinations
1 (01/20) The permitted cement and combinations and the required minimum cement content or combination
content are listed in Table 10/13. RCC mixture proportions used for production shall be based on a laboratory
mixture design procedure in Clause 1060.
TABLE 10/13: (01/20) Minimum Cement or Combination Content for RCC

Cement and combinations Minimum Cement or Combination


Content
(a)  Portland cement CEM I conforming to BS EN 197-1 270 kg/m3
(b)  Portland-slag cement CEM II/A-S and CEM II/B-S conforming 270 kg/m3
to BS EN 197-1

(c)  Portland-fly ash cement CEM II/A-V and CEM II/B-V


conforming to BS EN 197-1

(d)  Pozzolanic cement CEM IV/A (V) conforming to BS EN 197-1

See NOTE 1
(f)  A BS 8500-2 combination of Portland cement CEM I 270 kg/m3
conforming to BS EN 197-1 with not more than 35% fly-ash for use
as a cementitious component in structural concrete conforming to
BS EN 450-1    (SEE NOTE 2)
NOTE 1:

     CEM II/A-V has a maximum siliceous fly ash content of 20%

     CEM II/B-V has a maximum siliceous fly ash content of 35%

     CEM IV/A (V) has a maximum siliceous fly ash content of 35%

NOTE 2: Siliceous fly ash conforming to EN 14227-4 may be used where it meets the BS 8500-2:2015 Annex A
compressive strength requirements.
For materials required to comply with BS EN 197-1 and/or BS EN 450-1 the Contractor shall submit the relevant
material declarations of performance to the Overseeing Organisation prior to the inclusion of the materials into
the works. The declarations of performance shall demonstrate that the materials meet the requirements for the
specification.
(01/20) Aggregates

2 (01/20) The aggregates used in RCC shall comply with BS EN 13242 and have declared values for the
requirements listed in Table 10/14. The Contractor shall submit the declaration of performance for the aggregate to
the Overseeing Organisation prior to the inclusion of the aggregate in the works. The declaration of performance
shall demonstrate that the aggregate meets the requirements for the specification.

Amendment – January 2020 43


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

TABLE 10/14: (01/20) Aggregate Requirements for RCC

Reference Declared Values for aggregate properties


Crushed or broken particles in coarse and fine C100/0 (crushed gravels, manufactured and recycled
aggregate aggregates are not permitted)
Resistance to fragmentation of coarse LA35 or as specified in contract specific Appendix 7/1
aggregate
Magnesium sulfate MS18
Total sulphur content S1 (Where the Contractor is able to provide evidence
of mixture stability over an extended period then the
Overseeing Organisation may consider the use of higher
limits.)
Acid-soluble sulfate content AS0.2 (Where the Contractor is able to provide evidence
of mixture stability over an extended period then the
Overseeing Organisation may consider the use of higher
limits.)
Fines quality Aggregate passing 425 µm shall be non-plastic as defined by
and tested in compliance with BS 1377-2

1053 (01/20) Storage of RCC Constituents


1 (01/20) Aggregates shall be stored on a firm and clean substrate avoiding contamination with other constituents.
2 (01/20) Cement, and dry FA shall be stored in silos.
3 (01/20) Wet (conditioned) to BS EN 450-1 FA shall have no agglomerations greater than 10 mm size.
4 (01/20) Wet (conditioned) FA shall be stored at the source or at the production location for at least 72 hours
before use, and have a minimum water content of 10%.

1054 (01/20) General Requirements for Production and Layer Construction


(01/20) Production
1 (01/20) RCC shall be produced by the mix-in-plant method using batching by mass, in accordance with
Clause1055. RCC shall be produced in plants which operate a production control quality management system
which follows the guidance in BS EN 14227-1 Annex B.
(01/20) Layer Construction
2 (01/20) Construction of layers and any reworking and reuse shall be completed within the maximum
construction period specified of 30 °C hours. The time shall be measured from the addition of binder to completion
of compaction.
3 (01/20) The construction period, in degree hours, shall be the summation of the products of the average air
temperature above 3ºC (T ºC) and time for each period (t hours): i.e. construction period limit =Σ(T.t). If the air
temperature during the interval, t, fluctuates by more than 4ºC, interval t shall be re-calculated.
4 (01/20) Mixtures shall be batched by mass and paver laid in a single lift. The mixture must be placed using a
paver with a high compaction screed used in accordance with the method demonstrated on the Trial Length. The
paver must be capable of attaining the thickness, lines and grades indicated on the plan, and produce consistent
compaction and compliance with surface level tolerance.

Amendment – January 2020 44


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

5 (01/20) Laying shall be carried out in a way that avoids segregation and drying of the surface. Curing shall
be undertaken in accordance with sub-Clause 1054.19 as soon as practicable, and the curing compound shall be
applied prior to drying of the surface.
6 (01/20) Compaction of RCC shall be carried out by rollers to achieve the design compaction as demonstrated in
the installation trial.
7 (01/20) The minimum compacted thickness shall be 150 mm.
8 (01/20) Making-up of level after initial compaction is not permitted.
9 (01/20) The edge of hardened RCC material shall be vertical and straight before fresh RCC material is laid
against it within the permitted construction period in sub-Clauses 1054.2 and 1054.3. To ensure adequate bond
between wet joints compaction shall be completed before drying and within the permitted construction period in
sub-Clauses 1054.2 and 1054.3.
10 (01/20) Compaction of RCC layers by a method proven in the Trial Length (or by previous satisfactory
experience on similar projects) to provide the required density and finished profile shall be completed without
drying out and before setting of any part of the layer. Testing, controls and checking of RCC shall be carried out in
accordance with the requirements in Clause 1059.
11 (01/20) On completion of compaction the surface shall be closed, free from ridges, cracks, loose material,
visible voids, ruts, shear planes and other defects.
12 (01/20) Reworking and re-compaction of the layer to achieve the required surface finish shall only be
permitted within the construction period set out in sub-Clauses 1054.2 and 1054.3 and only when the water
content requirements of the reworked material are maintained within the limits stated in the method statement.
If rectification is not completed within the specified time period the defective area shall be removed to the full
thickness of the layer and new mixture machine laid and compacted. The minimum length of full depth replacement
shall be 15m and full width of a traffic lane.
13 (01/20) The exposed uncompacted edges of the longitudinal and transverse day joints shall be cut back to a
minimum 1.5 times the layer thickness.
14 (01/20) Transverse and longitudinal day joints shall be formed before commencing further work by sawing
vertically to the full depth.
15 (01/20) Unless otherwise specified in contract specific Appendix 7/1, all longitudinal joints shall be formed
outside wheel path zones.
16 (01/20) Longitudinal day joints shall be subject to density testing procedures 300mm from the edge. The density
shall be within 95% of that measured for the relevant test section.
17 (01/20) During cold weather:
(i) the temperature of RCC shall not be less than 5ºC at the time of laying;
(ii) RCC shall not be laid on a frozen surface;
(iii) laying of RCC shall cease when the air temperature falls below 3ºC, and laying shall not be resumed
until the rising air temperature reaches 3ºC.
18 (01/20) In the case of heavy or persistent rain, production shall cease and any laid material shall be compacted
immediately. The above also applies for light rain that results in any roller pick up and/or ponding of water on the
uncompacted RCC.

Amendment – January 2020 45


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

(01/20) Curing, Protection and Use of Surfaces by Traffic and Construction Plant
19 (01/20) On completion of compaction the layer shall be cured to prevent loss of water by the following.
(i) Application of a bitumen emulsion spray complying with Class C40B4, as specified in the National
Foreword to BS EN 13808 to produce an even and complete coverage of at least 0.2 kg/m2 of residual
bitumen. Before spraying commences, the surface shall be free of all loose material and standing water.
The curing membrane shall be protected from any damage until the construction of the overlaying layer.
(ii) Application shall be by metered mechanical spraying equipment, spray tanker or spraying device to
ensure consistent and adequate cover rate. The machine spread rate shall be calibrated using the method
in BS 594987. The spraying equipment used shall not cause permanent deformation in the surface. For
small or inaccessible areas, application may be by hand held sprayer.
20 (01/20) RCC shall not be trafficked within 7 days of laying unless test specimens made at the time of
construction as required in Clause 1059 and cured under the same conditions as the in-situ RCC achieve 20 N/mm2.
21 (01/20) Should the RCC when trafficked exhibit signs of damage, trafficking shall cease immediately and shall
only resume once the layer has gained sufficient stability to resist damage.
22 (01/20) Surface contamination shall be avoided as far as is practicable and any unavoidable contamination shall
be removed prior to overlaying.
(01/20) Rectification
23 (01/20) Before overlaying the finished pavement, high spots shall be removed by fine milling, grinding or bump
cutting. Milling, grinding or bump cutting shall only be carried out after 7 days or when the material has achieved
a strength of 20 N/mm2. No visible damage shall be evident to the upper section of the layer. Damage can include
delamination, cracking and/or spalling of the surface.
24 (01/20) Depressions which exceed the permitted level tolerances under Clause 702 shall be removed and
replaced to the full depth of the layer. Any loose material shall be removed and replaced to the full depth of the
layer. The minimum length of the full depth replacement shall be 15m and full width of a traffic lane.
(01/20) Daily Records
25 (01/20) Daily record sheets shall be included in the Health and Safety file at the completion of the works and
shall include the following information:
(i) suppliers’ details including name/company name and address;
(ii) mixing plant production batch record results (to include: date of production, aggregate content, cement
content, added water, time of completion of mixing, vehicle identification);
(iii) records that demonstrate that the constructed layer is within the permitted tolerances;
(iv) density test measurements;
(v) sample and test locations;
(vi) site construction period records showing the time(s) of arrival, vehicle identification, time(s) of
completion of compaction and time(s) of application of curing membrane;
(vii) construction period calculated in accordance with sub-Clauses 1054.2 and 1054.3;
(viii) weather records at point of laying.

Amendment – January 2020 46


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1055 (01/20) Production of Roller Compacted Concrete Mixtures


1 (01/20) The RCC shall be produced in a static mixing plant that batches by mass and mixes in a forced-action
mixer, to produce a homogenous mixture.
2 (01/20) The mixing plant shall have an automated recording and data collection system.
3 (01/20) A minimum of two aggregate fractions shall be used each with a separate feed hopper.
4 (01/20) RCC shall be transported directly to the point where it is to be laid. RCC shall be protected from the
weather during transit and whilst awaiting tipping.
5 (01/20) Results of routine compressive strength testing and moisture content of aggregate, during normal
production shall be used by the Contractor to make any necessary prudent adjustments to the mix design. The
Contractor shall inform the Overseeing Organisation of any changes made to the mix design when the change is
implemented.

1056 (01/20) Method Statement and Trial Length


(01/20) Method Statement
1 (01/20) At least 10 days prior to constructing the trial length specified in sub-Clauses 1056.4 to 1056.6 and when
a trafficking trial is required sub-Clauses 1056.8 to 1056.10, the Contractor shall provide a full method statement
to the Overseeing Organisation. The statement shall detail the operatives, plant, materials and procedures for
the construction of the trial length(s) and of the works. The statement shall also include procedures for induced
cracking, and the procedures to be applied during inclement weather, plant breakdowns and other unscheduled
events.
2 (01/20) The method statement shall include the intended mixture proportions with supporting data from trial mix
results carried out in accordance with Clause 1060 and/or historic records to justify the proportions.
3 (01/20) The method statement shall include a sample record sheet for the submission of the data required by
sub-Clause 1054.25
(01/20) Trial length
4 (01/20) Prior to the commencement of the main works, the Contractor shall construct a trial length of at least
800 m2 conforming to the submitted method statement. The trial length shall include a longitudinal joint, transverse
end-of-day joint and a trafficking trial included should immediate trafficking be required. The trial length may be
accepted into the permanent works where the work meets the specified requirements. Where the Contractor can
produce documentary evidence of similar work carried out to this specification during the previous 6 months, the
Overseeing Organisation may allow the works to proceed without the trial length.
5 (01/20) The trial length shall include crack induction at the spacing specified in Clause 1057.1. The effectiveness
of the crack induction procedure used shall be checked within 28 days of construction, by recovering four evenly
spaced 150 mm diameter cores from the line of the induced cracks and assessing each core for compliance with
Clause 1057.1.
6 (01/20) The depth of the crack induction shall be measured versus the requirements of Clause 1057.2. Should
the average depth of the induced cracks be less than the specified depth, then a further demonstration shall be
completed with a revised method to verify compliant full width sections of RCC. Non-compliant sections shall be
removed.
7 (01/20) The mixture constituents, proportions, laying and compaction plant and construction procedures used for
the trial length shall not be changed unless the Contractor lays a further trial length or the changes are agreed by the
Overseeing Organisation.
8 (01/20) The method statement shall include the proposed method by which the density compliance shall be
achieved.

Amendment – January 2020 47


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

1057 (01/20) Induced Cracking of RCC


1 (01/20) Transverse cracks shall be induced at 2.5 m longitudinal spacing with a tolerance of ± 300 mm.
2 (01/20) Cracks shall be induced in fresh material after initial compaction. The transverse cracks shall be
induced by grooving the fresh material to form straight vertical grooves not more than 20 mm wide, to a depth of
between one quarter and one third of the layer thickness over the full width of the pavement. Bitumen emulsion
shall be poured or sprayed into the grooves prior to final compaction, to form a crack inducing membrane. The
bitumen emulsion shall comply with Class C40, as specified in the National Annexes to BS EN 13808. During final
compaction of the mixture, the surface of the groove shall be fully closed throughout its full length. The bitumen in
the groove shall be fully encased and remain continuous. The plant and methodology shall be approved as part of
the Method Statement and Methodology trial under Clause 1056.
3 (01/20) The depth of bitumen emulsion membrane in the compacted layer shall be sufficient to reduce the
effective cross-sectional area of the layer by between one quarter and one third, and shall be a minimum depth
specified in the method statement based on the requirements of sub-Clause 1057.2. The effectiveness of the
procedure shall be checked as part of the trial length as described in Clause 1056.
4 (01/20) Longitudinal cracks shall be induced, using the procedure specified in sub-Clause 1057.2, under
each lane line and the edge line between the nearside lane and a hardshoulder. A longitudinal induced crack is
not required between the nearside lane and a 1 metre hard strip. Unless otherwise specified in contract specific
Appendix 7/1, longitudinal joints in all layers shall be situated outside wheel track zones.
5 (01/20) Saw cutting of the hardened RCC as an alternative to induced cracking is not permitted.

1058 (01/20) Roller Compacted Concrete Mixtures


1 (01/20) With the exception of mixture grading RCC mixtures shall comply with BS EN 14227-1, and have
binder constituent proportions complying with the requirements of Clause 1052.
2 (01/20) Aggregates shall comply with the requirements of Clause 1052 and shall have a grading that complies
with a grading envelope in Table 10/15 for a 0/14 or 0/20 aggregate mixture. The aggregate gradings in Table 10/15
exclude the binder constituent proportion.
Table 10/15: (01/20) Aggregate Grading for RCC Mixtures (Excluding binders)

Sieve Percenatge passing by mass


mm minimum maximum minimum maximum
0/14 0/20
31.5 100 100 100 100
20 100 100 90 100
14 86 100 78 94
10 72 95 62 86
8 68 90 56 80
4 52 74 38 59
2 41 61 28 48
1 30 50 19 39
0.5 20 37 15 31
0.25 11 26 9 23
0.125 6 15 6 15
0.063 2 10 2 10

Amendment – January 2020 48


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

3 (01/20) The mixture strength after immersion shall be at least 80% of the non-immersed strength, when tested in
accordance with the laboratory mixture design requirements specified in Clause 1060.
4 (01/20) The method of construction shall be in accordance with Clause 1054.
5 (01/20) The laboratory performance of the mix shall comply with the requirement of contract specific
Appendix 7/1, when sampled and tested in accordance with Clause 1059.

1059 (01/20) Testing, Control and Checking of RCC


(01/20) General
1 (01/20) Tests, controls and checks shall be carried out in accordance with the requirements in Table 10/16 and
the following sub-Clauses at locations stated in contract specific Appendix 1/5. Testing shall be carried out in
compliance with the requirements of Clause 1055 and be undertaken by an organisation accredited in accordance
with BS EN ISO/IEC 17025 for the test method.
(01/20) Sampling
2 (01/20) Sampling shall be in accordance with BS 1924-1. Where a bulk sample of RCC is taken from a layer,
it shall be taken from the full depth of the layer, used without further mixing, and not combined with other bulk
samples.
(01/20) Measurement of In-situ Wet Density
3 (01/20) With the exception of a trial length the normal method for determining density shall be by
non- destructive methods.
4 (01/20) A correlation shall be established for each mix and each measuring device from the trial length.
5 (01/20) The density shall be measured routinely at a distance of 0.8 to 1.2m from the edge of the slab if a spot
measurement process is chosen with a minimum frequency of one reading per laid area of 1000 m2.
6 (01/20) Density measurements shall be taken at the locations at which material is placed that has been sampled
for cube testing.
7 (01/20) The average in-situ wet density of an area 1000 m2 specified in sub-Clause 1059.6 shall be not less than
95% of the average wet density of the test specimens taken to determine the laboratory mechanical performance of
the same area.
8 (01/20) The result of each single determination of in-situ wet density shall be not less than 92% of the wet
density of the RCC cube made with the sample from the same location.
(01/20) Laboratory Mechanical Performance
9 (01/20) A bulk sample of RCC shall be taken from each location specified for the determination of in-situ wet
density, as sub-Clause 1059.5
10 (01/20) For conformity assessment the 28 day strength shall be determined in accordance with BS EN 13286-41
on specimens made from each bulk sample in accordance with BS EN 13286-51, using vibratory compaction.
The minimum-mean average strength of RCC shall be C40/50, which shall be
a) 40 MPa as determined from 150mm diameter 2:1 cylinder specimens, or
b) 50 MPa where determined for either 150mm cubes or 150mm diameter 1:1 cylinder
11 (01/20) The requirement specified in contract specific Appendix 7/1 shall be deemed to be satisfied if the
average compressive strength of the group of specimens is equal to or greater than C40/50 and no individual test
result is less than C27/34N/mm2.

Amendment – January 2020 49


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

TABLE 10/16: (01/20) Requirements for Testing, Control and Checking of RCC

Test/control/check Test frequency Test reference


Constituents Aggregates – BS EN 13242 Declaration of –
performance to be submitted for each aggregate
used prior to the commencement of RCC work.

Cement – Declaration of performance to be


submitted prior to the commencement of RCC
work.

Slag – Certificates to be provided weekly


to confirm the declared values required by
BS EN 14227-2, Clause 5.

Fly ash – Certificates to be provided weekly to


confirm compliance with the requirements of
BS EN 14227-4.

Other constituents (that do not fall under the


scope of the Construction Products Regulation)
– certificates to be provided weekly to confirm
compliance with the specification agreed as part
of the factory production control system for the
mixture.
Batching records for Continuously using the automated surveillance and –
‘mix-in-plant’ method of data collection system
construction using batching
by mass
Aggregate grading Not less than 2 per day BS EN 933-1
Water content at final Not less than 2 per day BS 1924-2, Clause 1.3
compaction
In-situ wet density 1 per 1000 m2 or part thereof laid each day Sub-Clause 1059.5
(measured at the locations detailed in
sub- Clause 1059.5)
Laboratory mechanical 1 per 1000 m2 or part thereof laid each day As required by Table 10/17
performance (with test specimens prepared from a bulk sample
taken from each of the locations detailed in
sub- Clause 1059.5)
Strength after immersion in Laboratory mixture design procedure Sub-Clause 1060.7
water

Amendment – January 2020 50


Volume 1 Series 1000
Specification for Highway Works Road Pavements – Concrete Materials

Table 10/17: (01/20) Laboratory Mechanical Performance Testing Requirements for RCC

Clause Mixture Curing regime Curing Test method Age at test


temperature
28 days
or other age
BS EN 12390 RC – agreed by the
1059.5 RCC 20°C
Water at 20ºC BS EN 13286-41 Overseeing
Organisation
(see Note)
NOTE:
For site control purposed, RCC may be assessed on the basis of 7 days strength (or other agreed age) where the Contractor so requests,
provided that a robust correlation is established between 7 days and 28 days strength using representative samples of the aggregates and
binder used in the works.

12 (01/20) Compliance of the area specified in sub-Clause 1059.5 shall be assessed using the results for test
specimens that are cured and tested in accordance with Table 10/17 using compression testing to the class of
mechanical performance specified in contract specific Appendix 7/1.
For the purposes of this specification, any reference to ‘characteristic strength’ in BS EN 14227-1 shall be
superseded by the requirements of this sub-Clause.

1060 (01/20) Laboratory Mixture Design Procedure


1 (01/20) Prior to the commencement of the work or any change in mixture constituents, the Contractor shall
determine the target proportions of the constituents, including water, for the specified RCC, based on the mixture
design procedure described in this Clause.
2 (01/20) The mixture design procedure shall determine the properties of the RCC at a minimum of 3 values of
binder contents, and a minimum of 2 values of water content for each value of binder content.
3 (01/20) The optimum water content (owc) and maximum bulk density of the mixture shall be determined using
the vibrating hammer method detailed in BS EN 13286-4.
4 (01/20) RCC mixtures shall be classified in accordance with BS EN 14227-1 by compressive strength with
specimens manufactured in accordance with EN 13286-41, at the age of 28 days.
5 (01/20) In order to establish strength development characteristics, compressive strength shall be reported at
7 and 28 days.
6 (01/20) The strength after immersion in water shall be assessed in accordance with sub-Clause 1060.7. The test
temperature shall be (20 ± 2) °C.
(01/20) Resistance to Water – Strength After Immersion
7 (01/20) The strength after immersion in water shall be assessed by comparing the average strength and condition
of:
(i) 3 specimens initially cured in a sealed condition for 14 days at the test temperature; and then removed
from their moulds and immersed in aerated water for 14 days at the same test temperature;
(ii) 3 specimens cured in a sealed condition for 28 days at the same test temperature; and then removed from
their moulds and immersed in aerated water for 14 days at the same test temperature.
The immersed specimens shall be unconfined and have water in contact with all surfaces. On completion of the
immersion stage of the test the specimens shall show no signs of cracking or swelling.
8 (01/20) The test temperature shall be (20 ± 2) ºC.

Amendment – January 2020 51F

You might also like