Series NG 900 Road Pavements - Bituminous Bound Materials: Clause Title Clause Title
Series NG 900 Road Pavements - Bituminous Bound Materials: Clause Title Clause Title
Series NG 900 Road Pavements - Bituminous Bound Materials: Clause Title Clause Title
SERIES NG 900
ROAD PAVEMENTS – BITUMINOUS
BOUND MATERIALS
Contents
Clause Title Page Clause Title Page
NG 900 (05/18) General2 NG 929 (05/18) Dense Base and Binder Course
Asphalt Concrete (Design Mixtures) 28
NG 901 (05/18) Bituminous Pavement Mixtures 2
NG 930 (05/18) EME2 Base and Binder Course
NG 902 (05/18) Reclaimed Asphalt 3
Asphalt Concrete 31
NG 903 (05/18) Placing and Compaction of
NG 937 (05/18) Stone Mastic Asphalt (SMA)
Bituminous Mixtures 3
Binder Course and Regulating Course 31
NG 904 (05/18) Hot Rolled Asphalt Base 5
NG 938 (05/18) Porous Asphalt Surface Course 32
NG 905 (05/18) Hot Rolled Asphalt Binder Course
NG 942 (05/18) Thin Surface Course Systems 32
(Recipe Mixtures) 6
NG 943 (05/18) Hot Rolled Asphalt Surface Course
NG 906 (05/18) Dense Base and Binder Course
and Binder Course (Performance-Related
Asphalt Concrete (Recipe mixtures) 6
Design Mix) 37
NG 909 (05/18) 6mm Dense Asphalt Concrete
NG 945 (05/18) Weather Conditions for Laying of
Surface Course 6
Bituminous Materials 39
NG 910 (05/18) Hot Rolled Asphalt Surface Course
NG 948 (05/18) Ex Situ Cold Recycled Bound
(Recipe Mixtures) 6
Material39
#NG 911 (05/18) Hot Rolled Asphalt Surface Course
NG 954 (05/18) Method of Laboratory Determination
(Design Mixtures) 6
of Interface Properties Using the Modified
NG 912 (05/18) Close Graded Asphalt Concrete Leutner Shear Test 42
Surface Course 6
NG 955 (05/18) Ageing Profile Test Using a
NG 915 (05/18) Coated Chippings for Application Modified Rolling Thin Film Oven Test
to Hot Rolled Asphalt Surfacings 7 (MRTFOT)43
8 (05/18) A water absorption value of 2% or less for coarse aggregates is considered to indicate a satisfactory
aggregate source. (This value may be exceeded by fine aggregates.) When absorption values of coarse aggregates
exceed the recommended WA242, magnesium sulfate soundness tests should be carried out for compliance purposes.
BS EN 13043 indicates that the water absorption test is not applicable for blast furnace slag aggregates. Blast
furnace slag aggregates with absorption values up to 8% have been shown to have acceptable soundness. Therefore,
the durability of blast furnace slag aggregates should be determined by periodic measurement of soundness.
(05/18) Cleanness
9 (05/18) There is no current test procedure for cleanness other than the requirement for aggregates to meet the
specified BS EN 13108 requirements for the fraction passing the 0.063 mm sieve. Provided the aggregates meet
requirements for particle size distribution, based on the washing and sieving techniques of BS EN 933-1, it is
considered the cleanness aspect of the aggregates will be acceptable.
However, the coarse aggregates should be checked to ensure they are not coated with clay or silt after having gone
through the drying plant and before being coated with bitumen.
(05/18) Resistance to Polishing and Surface Abrasion
10 (05/18) The Design Manual for Roads and Bridges HD 36 (DMRB 7.5.1) gives guidance on aggregate
properties for new bituminous surfacing.
(05/18) Bitumen
1 (05/18) The purpose of this clause is to define the laying and compaction procedures that will maximise the
durability of the finished pavement. It has been drafted to ensure compatibility with the general specifications
for the transport, placing and compaction of asphalt mixtures given in BS 594987 and with other appropriate
Clauses (929, 930, 942 and 945) and should always be read in conjunction with the above documents as they relate
to the particular application.
2 (05/18) Certain key factors are important in maximising the durability of the finished pavement and should be
reviewed before work commences. These are as follows.
(i) Mechanical laying wherever practicable.
(ii) Bonding of layers.
(iii) Good compaction, particularly at joints.
(iv) Pre-planning of compaction process.
(v) Sealing of edges and joints to prevent water ingress.
3 (05/18) Clause 903 applies to the surfacing overlaying bridge decks but does not relate to laying waterproofing
systems. When laying hot paving materials on bridge deck waterproofing systems, care must be taken to follow
the guidance given in IAN 96/07. Appropriate measures should be taken to ensure that the bond system is fully
activated by sufficient heat but that the waterproofing system is not damaged by excessive heat.
(05/18) Laying
4 (05/18) Materials should be laid by paver unless there are small or inaccessible areas where hand laying is
the only practicable method. Pavers should be used with the minimum of hand raking and making up. The use
of automatic levelling devices should be encouraged and, where possible, greater emphasis should be given to
evenness rather than levels, provided that pavement thickness and clearances at structures are achieved. This
approach is particularly relevant when thick layers of base are being used to minimise the number of horizontal
interfaces.
5 (05/18) As far as practicable, the paver should work continuously without stopping. Stops can adversely affect
the ride quality of the finished pavement. Therefore, there should be sufficient mixed material on site when paving
commences to ensure that lack of supply will not stop operations. However, an excess number of delivery vehicles
should also be avoided as it can result in congestion on site and an extended time between mixing and laying for
each load.
(05/18) Compaction
6 (05/18) It is important that an effective compaction plan appropriate to the site circumstances is in place and is
understood by the paving crew. This is a requirement of sub-Clause 903.5.
7 (05/18) There is no conclusive evidence to show all vibratory rollers provide consistently greater compaction
than that achieved with conventional deadweight rollers. It is desirable that compaction should be maximised so
site trials of vibratory rollers, proposed as an alternative to conventional deadweight rollers, may be beneficial. The
trial should not only determine the required number of passes of the vibratory roller, but also the frequency and
amplitude of the vibrating rolls and roller speed. Additional advice is included in TRRL Report LR 1102. Where
evidence is provided by the Contractor to indicate a proposed vibratory roller will achieve adequate compaction,
the evidence should be representative of the conditions likely to be encountered in the works. Factors which are
relevant include types of compacted material and source of aggregate, the thickness and temperature of layers
and the condition of the proposed roller compared with that previously used. Site trials are not required to prove
vibrating rollers where the final density or air voids is measured as compaction is then a controlled parameter.
8 (05/18) If compaction trials have been carried out, the frequency and amplitude of vibrating rollers and
travelling speed of the roller which have been found to be satisfactory should be used. The Contractor can use
equations [1] and [2], to select the paving and rolling rates to achieve the minimum number of roller passes
required before the surfacing has cooled to the minimum temperature for compaction:
Rolling length (m) = average paving speed (m/min) x T (min) … [1]
Roller passes = (Rolling rate/Paving Rate) x No of Rollers … [2]
where:
Rolling rate (m²/min) = Roller width (m) x Roller speed (m/min)
Paver rate (m²/min) = Paver width (m) x Paver speed (m/min))
T = time required for compaction (usually 10 min for HRA and 8 min for mixtures without pre-coated chippings)
9 (05/18) When reliance is placed on a method specification for the control of compaction of bituminous mixtures,
close attention should be paid to the temperature of the material. BS 594987 lays down minimum temperatures
at which compaction should be substantially complete. It will, therefore, be necessary to commence rolling at
temperatures exceeding the minimum, making due allowance for weather conditions, which may affect the rate of
cooling of the laid material. NG 945 for cold weather working gives useful advice. For hot weather, TRL Report
494 ‘The Behaviour of Asphalt in Adverse Hot Weather Conditions’ gives useful advice on the subject. For all
practical purposes where material is tested for adequacy of compaction in accordance with Clauses 929, 930 and
937, the requirements should have been achieved above the minimum rolling temperature. Any subsequent rolling
at temperatures below the minimum should only be necessary to remove roller marks and regulate the surface.
(05/18) Inter-layer Bond
10 (05/18) Inter-layer bond is essential to prevent ingress of water and resultant deterioration of the pavement. It is
also important to ensure that the pavement acts as a homogenous structure. BS 594987 and Clause 920 give explicit
and comprehensive requirements that should be followed. It is difficult to overestimate the importance of bond.
Generally, it is good practice to lay bases in thicker lifts to minimise the number of layers and, hence, interfaces
(giving due consideration to the maximum layer thicknesses given in BS 594987).
(05/18) Joints
11 (05/18) However, a joint in a bituminous layer is constructed, it will always be the weakest part of the pavement.
Therefore, it is good practice, wherever possible, to minimise the number of cold joints by, for example, using wide
screeds and/or paving in echelon.
12 (05/18) Joints should always be located in low stress areas of the pavement wherever practicable, as indicated
in sub-Clause 903.21. However, where an existing road surface is being replaced, it is permitted to locate the
longitudinal joints within the surfacing material in the middle of a traffic lane. This position should only be selected
if positioning the joint under the lane edge or lane marking would result in significant areas of sound surface course
material being unnecessarily replaced. Joints should never be placed in the wheel-track zones.’
13 (05/18) Compaction at joints with unsupported edges will never be as good as in the body of the mat. This is
recognised in the air void content requirements in sub-Clauses 903.24, 929.15 and 930.15.
14 (05/18) To guard against ingress of water at joints, Sub-Clause 903.22 requires binder to be applied to the
vertical face prior to laying the adjacent mat in order to improve bond and Sub-Clause 903.25 requires overbanding
to seal the surface of the joint.
15 (05/18) To ensure that water does not enter the pavement from the side, sub-Clause 903.26 requires sealing the
edges of the finished pavement. This is always required for the high side of the elevation. Sealing of the low side
is conditional on whether it is necessary to let water out or stop water getting into the pavement. The selection is a
design issue and should be specified in Schedule 4 of contract specific Appendix 7/1.
NG 906 (05/18) Dense Base and Binder Course Asphalt Concrete (Recipe Mixtures)
1 (07/19) The mixture designation should be chosen to suit the thickness of the layer as indicated in BS 594987
Table 1A.
#NG 911 (05/18) Hot Rolled Asphalt Surface Course (Design Mixtures)
1 (05/18) The special requirements included in contract specific Appendix 7/1 may include specific mix
designations, binder grade and for 30% and 35% stone content mixtures, the required properties of coated
chippings in accordance with Clause 915.
2 (05/18) The method for determining the design binder content for surface course is described in BS 594987
Annex H. The target binder content in the mixture will normally be the higher of the design binder content and the
minimum binder content indicated in BSI PD6691 Annex C Table C 2A or C 2C as appropriate.
3 (05/18) The Contractor may usually be permitted to use either type C or type F mixtures.
4 (05/18) In the past, Marshall properties, such as stability and flow, were used as indicators of resistance to
permanent deformation, but this is no longer included as an option in the BS EN 13108 standards. In very heavily
trafficked situations, where resistance to permanent deformation is of high importance, it is recommended that
performance related Hot Rolled Asphalt to Clause 943 is used.
NG 915 (05/18) Coated Chippings for Application to Hot Rolled Asphalt Surfacings
1 (05/18) Generally, 14/20mm chippings are required to achieve an initial texture depth of 1.5mm and maintain a
suitable texture under traffic. For low speed applications, particularly high stress areas such as roundabouts, lower
rates of application and 8/14mm chippings combined with lower requirements for texture depth are appropriate.
2 (05/18) The condition of the binder film at the time of application is critical in achieving good adhesion to the
asphalt. The hot sand test in BS EN 12697-37 and the requirement in BS EN 13108-4 and BSI PD6691 C.2.8.4
provide a means for establishing their suitability.
3 (05/18) Thebinder film can be adversely affected in the following ways:
• excessive mixing temperature leading to hardening;
• storage of hot or warm chippings in large stockpiles resulting in ‘coking’ (to prevent this, chippings
should be cooled as quickly as possible after mixing and should be stored in stockpiles no more than
one metre in height);
• contamination with dirt and dust.
4 (05/18) It is good practice to sheet chipping stockpiles on site in the winter to stop them becoming too cold,
particularly in frosty conditions as this can make achieving adhesion more difficult.
7 (05/18) Basic details of the tendered design for each site should be completed in the Design Proposal and TAIT
certificates for similar sites provided.
8 (05/18) If any site is considered by the tenderer to be unsuitable for Slurry Surfacing this should be stated in the
Design Proposal. There may be sections where the existing road surface is considered not suitable for treatment or
the performance requirements are too onerous to be achieved in practice.
9 (05/18) When preparing the instructions for tendering it is essential that the compiler includes the following
information and instructions adapted as necessary to suit the particular conditions of contract and form of contract:
(i) Tenderers’ attention is drawn to the requirement that Tenderers intending to sub-contract Slurry
Surfacing must nevertheless provide with their tender all the information required by Clause 918 and
contract specific Appendix 7/7.
(ii) In determining the award of the Contract, regard will be had not only to the price tendered but also to the
following criteria:
(a) the Contract time period entered in the Form of Tender by the Tenderer;
(b) the requirements of contract specific Appendix 7/7 assessed as follows:
Contract Duration All tenders will be evaluated against the lowest submitted Contract period.
Design Life All tenders will be evaluated considering the Estimated Design Life stated in the TAIT
Certificate.
Any tender not complying with the submission of the following information in accordance with the contract will
not be considered:
• QA registrations.
• Method Statement.
• Design Proposal.
• Declaration(s) of Performance.
• Traffic Management.
• Contingency Plans.
• Test Results.
• Previous Applications.
10 (05/18) Contractors should recognise the need for best practice as described in the Road Surface Treatments
Association (RSTA) Code of Practice for Slurry Surfacing.
11 (05/18) The Estimated Design Life is required in order to assist in the assessment of tenders on a value for
money basis; it is often the case that more expensive designs last longer. The end of the Design Life is the time at
which the surfacing should no longer be expected to provide the surface properties required at the site in question.
(This is a separate consideration from the guarantee period and does not imply a guarantee that the life will always
be attained). Further guidance on the Design Life of Surface Treatments including Slurry Surfacings has been
published by RSTA and ADEPT.
12 (05/18) The responsibility for the provision of information upon which to base the design should be set out
in the contract, but it is expected that the compiler would provide the traffic data, the classification of the site in
accordance with HD 36 (DMRB 7.5.1) and the minimum requirements for aggregate properties. The compiler
should set out any limitations on the availability of a site in contract specific Appendix 1/13. These limitations
could include requirements to avoid the site at rush hours, on market days or for particular events already planned
at the time of writing the contract. When the Contractor makes his site visit for the purposes of tendering he should
make a visual assessment of the road surface and traffic category and bring any anomalies about the site to the
attention of the Overseeing Organisation.
13 (05/18) For the purposes of the contract, monitoring will stop at the end of the guarantee period, or for novel or
innovative materials, after one-third of the stated Estimated Design Life, but in order to check the proposed Design
Life against the actual achieved life, monitoring should continue for the whole life of the Slurry Surfacing. On
heavily trafficked roads this can most conveniently be done by means of the texture output from TRACS (TRAffic-
speed Condition Survey) surveys, which are currently carried out on all trunk roads every 2 years and SCRIM
surveys, which are carried out annually. For other roads volumetric patch technique or use of the mini texture meter
or other device calibrated against glass spheres values as Glass Spheres Patch Equivalent values, may be more
convenient.
14 (05/18) The Vialit pendulum test should be carried out using BS EN 13588 on the recovered binder used to
manufacture the Slurry Surfacing. The minimum binder cohesion at peak measured using the Vialit Pendulum
should be reported. The range of temperature for modified binders for a value of 1.0 J/cm2 provides another
parameter for evaluation of the modification.
15 (05/18) Penetration, softening point, Fraass Brittle point, toughness, tenacity, and other viscosity measurements
are not in themselves sufficient as product identification tests, although they may be useful as quick or low cost
Quality Assurance tests to check consistency from load to load of the binder. The Contractor’s Design Proposal
should provide a declaration of performance giving at least the information specified. In order to set a standard
the contract compliance test has been standardised using the results from a dynamic shear rheometer of complex
shear (stiffness) modulus and phase angle as specified in BS EN 14770. If the supplier considers that other tests
would identify his binder more precisely then he may provide the results of these additional tests in addition to the
requirements of sub-Clause 918.7 and add them to the Binder Data Sheet in contract specific Appendix 7/7.
Other recovery test methods may be used to provide residual binder for subsequent testing and these may be
convenient for quality control purposes, however, the definitive test is Clause 955 and results for BS EN 14770 and
BS EN 13588 for contract compliance purposes will be based on recovered binder from Clause 955.
16 (05/18) The compiler should specify the minimum PSV required for a particular site together with the maximum
AAV. Guidance on the levels to specify is given in HD 36 (DMRB 7.5.1); over specification should be avoided
in order to conserve scarce resources. Where coloured Slurry Surfacing is used on the carriageway, even in small
areas like ‘village gates’ they should have adequate skidding resistance. As they are usually fairly thin it is not
possible to provide deep macrotexture.
17 (05/18) Repairs to the existing road in preparation for Slurry Surfacing (for example, patching), should be
carried out well in advance of the works. They should be carried out in such a manner that the hardness and
macrotexture of the remedial work is sufficiently similar to the rest of the road to avoid problems of variable
appearance and behaviour in the completed Slurry Surfacing for at least the duration of the maintenance period.
The existing road variability and surface characteristics have a bearing on the achievable levels of performance
that may be specified. If the existing surface is hot rolled asphalt then the patches will ideally be laid with hot
rolled asphalt. Thin asphalt surfacings should be repaired with stone mastic asphalt of similar consistency and
highly textured variable substrates should be treated with a polymer modified Bond Coat. Patches should not have
a horizontal sealing strip applied as this will show through thin Slurry Surfacing reducing macrotexture, similarly
binder-rich soft materials used to seal cracks similar to stress absorbing membrane interlayers (SAMIs) should not
be used, especially longitudinally in the wheel tracks.
18 (05/18) The minimum and/or maximum thicknesses at which the Slurry Surfacing is to be laid should only be
specified where there are specific reasons for so doing. If the Slurry Surfacing is being laid purely to restore surface
characteristics such as skid resistance and macrotexture depth, the choice of thickness should not be restricted. One
reason for specifying a minimum thickness is to improve the profile. For rut filling this is often accomplished by the
application of two layers, sometimes using different materials. This should be described in the Design Proposal.
19 (05/18) Cleanliness of the existing surface is extremely important. The Slurry Surfacing will adhere only to the
top layer of the material on which it is placed and if this is mud or dust then the surfacing will fail, lacking bond
with the underlying structure. It may be found necessary in some circumstances to use high pressure washing to
remove strongly adherent material. The masking of street furniture should be carried out very carefully as any cover
must not be rendered immovable. In order to give a clean straight joint at the beginning and end of the work all
start and finish points should be masked with a suitable material about 1 m wide for machine laid work and 0.5 m
for hand laid work, or an alternative, documented, procedure producing a similar outcome may be used.
20 (05/18) General weather limitations should be covered by the Contractor’s Quality Plan. Any site specific
weather limitations should be specified under ‘Special restrictions’ in contract specific Appendix 7/7.
21 (05/18) Traffic control immediately after Slurry Surfacing is critical to the production of a good quality surface.
The surface should not be trafficked at all until the Slurry Surfacing has set sufficiently to enable it to take the
traffic stresses that will be imposed. Too early opening will lead to damage and loss of material, which will require
additional remedial work before the Contractor may leave the site. The surface should be monitored closely
during early trafficking and if there are signs of distress due to inadequate curing the traffic control regime should
be altered to keep the traffic off the Slurry Surfacing until it has gained adequate strength. Strength gain will be
particularly slow in conditions of high humidity and/or low temperatures, i.e. those conditions where the rate of
evaporation of the water from the Slurry Surfacing is reduced. Traffickability time and mixture cohesion tests are
relevant in this context.
22 (05/18) As part of the normal traffic control mechanism for high-speed roads there should be a mandatory
temporary speed limit in place for the duration of the work. Therefore, if Slurry Surfacing is being used in this
situation (assuming a design is produced and approval given) it should be designed to be opened to traffic travelling
at the temporary speed limit on completion of initial sweeping. There should follow a number of days of trafficking
at this speed with the traffic management being organised in such a manner that all lanes have at least 48 hours
of speed limited trafficking within a minimum of 72 hours of first opening the carriageway to controlled traffic.
This period, or such other, longer period, that either the compiler states in contract specific Appendix 7/7 or the
Contractor requires for his process should be included within the works programme. The Overseeing Organisation
will not normally require a longer period than this but may do so if the traffic on the section of road is unusually
light or the work is required to be carried late in the season, i.e. during October. The Contractor will determine the
need for a longer period from experience with the particular process that is proposed. All loose aggregate should be
removed from any traffickable part of the carriageway or hard shoulder prior to removing the temporary contract
speed limit from the works.
23 (05/18) Care should be taken to ensure that the Slurry Surfacing bonds adequately to the underlying surface
as with these relatively thin materials it is absolutely essential for there to be a good bond if early failure is to
be avoided. Although bond may be checked using a suitable test any unbonded areas are likely to fail within the
guarantee period and will be identified during the final visual assessment. Bond coats should normally be used.
24 (05/18) When incorrectly manufactured or laid Slurry Surfacing has poor durability. For Slurry Surfacing
placed in a single layer less than about 8 mm thick the assessment of areas of total loss of material at the end of the
guarantee period should be a sufficient performance measure.
25 (05/18) It is important to ensure that all access covers are unmasked and if necessary reset as soon as possible
after completion of laying so that their owners may find and use them if required. This is particularly important for
fire hydrants, as public safety may be dependent on their visibility and accessibility. It is also easier to match the
Slurry Surfacing with additional material if needed and make level adjustments while the Slurry Surfacing team is
close-by.
26 (05/18) Macrotexture is measured in the nearside (inside) wheel track where the lane width and traffic are
sufficient for this to be identified; for low traffic category sites the track carrying the most traffic (wear) is tested,
this may be the outside wheel track for narrow lanes where tyre paths in both directions overlap. High-speed
sensor measurements should be used for measuring macrotexture depth on high-speed and heavily trafficked roads
because of the amount of macrotexture depth measurement to be undertaken. This form of measurement avoids the
need for additional lane closures, which use of volumetric patch technique or the mini texture meter would require.
Other methods may be used, but the results should be reported as Patch Equivalent values. Lightly trafficked
roads should be assessed for cleanliness and cleaned if necessary before measurements are made. This would not
normally be necessary on roads carrying heavy or fast traffic. The use of high-speed measurements also enables
long term monitoring as part of the routine TRACS surveys. The macrotexture depth for Slurry Surfacing on high-
speed heavily trafficked roads (Clause 942 would normally be used to specify slurry surfacing on these roads) at the
end of the guarantee period would normally be specified at 1.5 mm measured by the volumetric patch technique.
Depending on traffic levels, lower macrotextures at the end of the guarantee period may be specified in contract
specific Appendix 7/7 for lower speed roads.
TABLE NG 9/1: (05/18) Minimum Patch Macrotexture Depth Requirements (or Volumetric Patch
Equivalent) in the Nearside Wheel Track at the End of the Guarantee Period
Traffic cv/lane/day Speed limit 50 mph or 60 mph Speed limit 40 mph or lower Patch
Patch Macrotexture (mm) Macrotexture (mm)
50 to 250 1.0 0.8
10 to 50 1.0 0.7
Below 10 1.0 No requirement
More than 250 (or speed limit Not Applicable to this Clause, see Clause 942: Thin Surface Course Systems
greater than 60 mph)
27 (05/18) Visual assessment of defects should be carried out in accordance with BS EN 12274-8. It is anticipated
that because Slurry Surfacing defects are usually obvious the need for a full assessment procedure will be rare.
The visual assessment of area defects is classified in Table NG 9/2. The category appropriate to the site should be
specified in contract specific Appendix 7/7.
The visual assessment of linear defects is classified in Table NG 9/3. The class appropriate to the site should be
specified in contract specific Appendix 7/7.
28 (05/18) Where a bond coat is proposed in the Design Proposal it shall comply with Clause 920. If the bond
between layers is to be assessed then the torque bond test shall be carried out in accordance with Clause 951.
29 (05/18) Materials failing to set or setting too rapidly are caused by defects in workmanship or laying in
inappropriate weather conditions. Work should stop and should not recommence until the any application faults
have been rectified and the weather conditions are suitable. If the material has not been manufactured in accordance
with the design proposal it may not set either adequately or at all and will need removal and replacement.
30 (05/18) Surface irregularity is measured in two ways as described in Clause 702, but as Slurry Surfacing is laid
in a different manner to the method assumed in that Clause, Slurry Surfacing should meet the appropriate class
given in Table NG 9/4 for transverse regularity and Table NG 9/7 for longitudinal irregularity. The class limits are
given in Table NG 9/5 for the former and in Table NG 9/7 for the latter.
31 (05/18) The guarantee period stated in the specification should be clearly stated as applying to the Slurry
Surfacing. An appropriate Special Requirement should be included in the Conditions of Contract drawing particular
attention to the guarantee period.
Note: The reproducibility has been allowed for when setting these minimum levels and the average value of
the peak cohesion for polymer modified binders is likely to be at least 0.3 J/cm2 above the minima given in
Table NG 9/8.
* For conventional binders where 0.7 is not consistently achieved, 0.5 over a minimum temperature range of 15oC
has been found to provide satisfactory performance.
7 (05/18) Product Identification Test: Penetration, softening point, Fraass Brittle point, toughness, tenacity, and
other viscosity measurements are not in themselves sufficient as product identification tests, although they can
be useful as quick or low cost Quality Assurance tests to check consistency from load to load of the binder. The
Contractor should provide a Binder Data Sheet giving at least the information specified. In order to standardise, the
product identification test has been based on the results from a dynamic shear rheometer of complex modulus and
phase angle (see BS EN 14770). If the supplier considers that other tests would better characterise his binder then
he may provide the results of these tests in addition to the requirements of sub-Clause 919.3.
8 (05/18) The binder sprayer should be checked for accuracy of transverse distribution using the test method
stated. This assesses the ability of the spraybar in real working conditions and may be carried out quickly using the
correct binder. The Depot Tray test to BS 1707 averages the rate of spray over 60 seconds in a static condition and
therefore does not simulate site conditions such as the influence of varying spraybar height above the road, or any
tendency to pump or pressure surging. The performance of the binder sprayer is classified in accordance with the
value of the coefficient of variation (Cv) for the regularity of transverse distribution. The category required for the
sprayer, to be specified in contract specific Appendix 7/21, should be selected from Table NG 9/9.
* this Cv and category is appropriate when carpet tiles 100 mm wide and at least 200 mm long are used for the
test, where the surface is very even, on dual carriageways and motorways there is a case for specifying category 3.
Where 50 mm wide trays are used each two adjacent trays should be averaged before calculating the Coefficient of
variation (Cv).
9 (05/18) The compiler should specify the minimum PSV required for a particular site together with the maximum
AAV. Guidance on the levels to specify is given in HD 36 (DMRB 7.5.1); over specification should be avoided in
order to conserve scarce resources.
10 (05/18) The chipping spreader should be checked for accuracy of transverse distribution using the stated
method. With multi-layered surface dressings it is very important to obtain the correct rate of spread of the larger
chipping as under or over chipping will reduce the quality of the dressing and may result in it failing to perform as
a multi-layered system. Particular attention should be paid to the rate of spread in the vicinity of the overlaps in the
chipping spreader mechanism as the performance, particularly of worn spreaders, can be significantly different in
these areas from the rest of the spreader. The performance of the chipping spreader is classified in accordance with
the value of the coefficient of variation (Cv) for the regularity of transverse distribution. The category required for
the spreader to be specified in contract specific Appendix 7/21 should be selected from Table NG 9/10. The rate
of spread for secondary chippings is less important and an excess is usually beneficial so that spreading with, for
example, two tail board gritters in echelon are often satisfactory.
11 (05/18) Remedial work to the existing road, for example, patching, should be carried out prior to surface
dressing. It should be carried out in such a manner that the hardness and macrotexture of the remedial work is
sufficiently similar to the rest of the road to avoid problems of variable appearance and behaviour in the completed
surface dressing for at least the duration of the maintenance period; for example, patching using close textured
bitumen macadam should be carried out in the previous summer otherwise it will absorb bitumen into the voids and
chip loss may ensue. If the existing surface is hot rolled asphalt then the patches will have to be laid with hot rolled
asphalt and preferably sufficiently far in advance of the works for the binder to wear off the surface otherwise
there will be excess binder in that area. Patches should not have a horizontal sealing strip applied as this will show
through the dressing very rapidly and has been known to initiate fatting failure. The use of binder rich materials
should not be used to pre-seal areas especially longitudinally in the wheel tracks as the dressing will fat up and
macrotexture will be lost.
12 (05/18) Cleanliness of the existing road surface is extremely important. The binder will adhere only to the top
layer of the material on which it is sprayed and if there is mud or dust then the surface dressing will fail rapidly,
through the lack of bond with the underlying structure. It may be necessary in some circumstances to use high
pressure washing to remove strongly adherent material. The masking of street furniture should be carried out with
care as the interface between the furniture and the surrounding surface should be sprayed in order to exclude water
from the road structure, but any cover must not be rendered immovable.
13 (05/18) The mode of operation of surface dressing contracts can necessitate the adoption of techniques requiring
equipment for traffic management and safety over and above that normally required by static works. For example,
where traffic lights are required as part of the traffic management scheme, in order to facilitate the relocation of the
lights, some sites may require the provision of additional sets over and above the minimum necessary, so that the
work progresses with a minimum of interruption and disruption to road users.
14 (05/18) General weather limitations should be covered by the Contractor’s Quality Plan. Any site specific
weather limitations should be stated in contract specific Appendix 7/21. Further guidance may be obtained from
HD 37 (DMRB 7.5.2).
15 (05/18) In order to ensure that only the binder is overlapped on transverse joints the chipping application should
stop short of the end of the binder film wherever possible. When spraying from a completed section some hand
canning and masking of the end is necessary in order to abut the joint without forming a ridge.
16 (05/18) Longitudinal joints should have slightly overlapped binder films obtained by leaving a wet edge
approximately 100 mm wide. Care should be taken to ensure that double chipping does not take place as this will
form a ridge. As the binder overlap is generally in a lightly trafficked location the additional thickness of binder
film is unlikely to be a problem. Quartering (spraying of a part bar) should be avoided wherever possible, but may
be necessary at tapers and other similar locations. An overlap (up to 300 mm) should be provided to ensure full rate
of spread of binder at all points.
17 (05/18) The frequency of testing for rates and accuracy of spread of binder and chippings should be stated in
contract specific Appendix 1/5. The rate of testing should be reduced once the Contractor has demonstrated his
ability to consistently meet the requirements. The more consistent a Contractor is in his work the lower the rate of
testing that can be employed, a minimum rate of 1 test per day could be reached if the contract is large enough. The
Overseeing Organisation may carry out testing at audit frequency, typically at about 10% of the specified frequency
for the Contractor. If the results from this audit testing are significantly different from those of the Contractor, for
example, by more than the reproducibility of the test, then the Overseeing Organisation and the Contractor should
work together to determine the source of difference. With this type of specification it is important that all the
required testing is carried out, preferably under supervision, as it is not possible to assess the rate of spread of either
binder or aggregate subsequent to the spreading of those materials.
18 (05/18) The allowable tolerance on the design rate of spread of binder is dependent on the site and is classified
in Table NG 9/11. The category or categories appropriate to the site should be specified in contract specific
Appendix 7/21.
19 (05/18) The allowable tolerance on the design rate of spread of chippings is dependant on the site and is
classified in Table NG 9/12. The category or categories appropriate to the site should be specified in contract
specific Appendix 7/21.
20 (05/18) Both types of rollers specified are suitable for rolling surface dressing. The aim should be to orientate
the chippings and place them in contact with the binder rather than provide compaction. There is some consensus
that vibration assists in the break of emulsion binders and a re-roll can help where the ‘cheesy’ stage of an
emulsion is prolonged. The ability of the rollers to spray water on to the drums or tyres should be checked before
commencement of any work. Although water may not be needed all the time, when it is, it is needed urgently.
Heavy steel wheeled rollers tend to crush chippings and their use should not be permitted.
21 (05/18) Traffic control immediately after surface dressing is most crucial in the production of good quality
surface dressing. On high speed roads the best way of doing this is to introduce convoy vehicles into the traffic
stream in order to keep speeds low. The deployment of 10 mph signs, when permitted, is an extremely useful
method of inducing caution in the road user. If possible cones should be used to vary the lane position so that
as much of the dressing as possible is subjected to slow speed traffic. The lane should be suction swept prior to
removal of the convoying vehicles from the traffic stream, care being taken not to remove chippings, which would
otherwise become part of the mosaic. With multi-layered surface dressing it may not be necessary to sweep, unless
there are windrows which should be removed. If the work has been carried out correctly there will be no loose large
chippings. Provided there are no loose large sized chippings it may be useful to gradually increase the speed of the
convoying vehicles to disperse excess small chippings to the side of the lane for subsequent removal.
22 (05/18) It is essential that the dressing is monitored for some time after opening to traffic, particularly in hot
weather when using cutback binders, as at high temperatures the binder cohesion is low when using emulsions in
humid or cool weather, the binder takes longer to gain cohesion. Both conditions result in lower initial resistance to
traffic forces and the mosaic may be destroyed. Should this happen the Contractor should be prepared to re-impose
traffic control and have on site a suitable “dust” ready to use. The ideal “dust” is light coloured, absorbent and
about 4 mm to 1 mm in size. Oolitic limestone and blastfurnace slag are particularly good although other materials
available locally may have to be used.
NG 920 (05/18) Bond Coats, Tack Coats and Other Bituminous Sprays
(05/18) Bond Coats and Tack Coats
1 (05/18) This Clause specifies tack coats and bond coats for asphalt concrete, hot rolled asphalt and stone mastic
asphalt binder course and regulating course. Bond coats and tack coats are applied prior to laying of bituminous
mixtures in order to promote the development of a homogeneous pavement structure and to prevent ingress of
water. The structural design of pavements assumes that the bond between layers is complete. Bond is particularly
important in highly stressed areas. The use of tack or bond coat is a universal requirement when placing bituminous
material on any new or existing bound substrate, under Clause 903.4. Further information can be found in
BS 594987. The use of tack and bond coats under Thin Surface Course Systems is covered by Clause 942.
2 (05/18) BS 594987 gives recommended application rates of tack and bond coats. Clause 903 converts these
recommendations into requirements. A bond coat is more appropriate where greater bond strength or better sealing
is required. An example is where materials are to be laid less than 30 mm thick, or where a particular site has a
binder lean substrate and permeability is considered a problem. Advice on the choice of tack coat or bond coat is
provided in BS 594987. Traditionally a tack coat using C40B4 or C60B3 emulsion has been used to add a little
extra binder to an existing surface and is often adequate to initiate adhesion between layers. Bond coats generally
have a higher binder content containing modifiers and are usually used at a higher rate of spread thus promoting
improved adhesion with some waterproofing capability, important to prevent water ingress below porous or
permeable materials. Additional information is provided in HD 37 (DMRB 7.5.2).
3 (05/18) Bond coats may sometimes need to be partially covered with aggregate, to prevent them from being
picked up when being walked on or driven over, especially during periods of hot weather. A typical rate of
application of chippings is approximately 3 to 5 kg/m2. Alternatively, ‘non-tack’ bond coats, which are available
from some suppliers, may be used. When these emulsions break, sometimes accelerated using proprietary breaking
agents, the residual binder is not as tacky or sticky, only becoming so at the high temperatures associated with the
asphalt overlay when they melt at the interface, thereby achieving a bond. These materials are useful for work in
urban areas where foot traffic is sometimes unavoidable.
4 (05/18) Rates of spread of binder should follow the recommendations of BS 594987 or the manufacturer’s
instructions, as appropriate. Rates of spread may need to be altered for varying macrotexture and porosity of
the existing road and an increased rate at the kerb or road edge is beneficial to minimise water ingress where
compaction by traffic is least.
5 (05/18) Particular care is required when applying a bituminous surfacing to an existing concrete road as not
all emulsions adhere well to concrete. It is likely that one specially formulated for this application will be needed.
The adhesion of a bituminous surfacing to newly laid concrete is a special case and evidence of a satisfactory bond
should be provided.
6 (05/18) Pendulum Class 4 (previously known as “Intermediate grade”) bond coats or bituminous sprays have a
Vialit Pendulum Peak Cohesion minimum value of 1.0 J/cm2 on the recovered binder prepared using Clause 955
when measured using BS EN 13808. Pendulum Class 5 (previously known as “Premium grade”) bond coats or
bituminous sprays have a Vialit Pendulum Peak Cohesion minimum value of 1.2 J/cm2. Pendulum Class 4 or 5
bond coats are recommended when overlaying highly variable surfaces or those of high porosity. Pendulum Class 5
bond coats are recommended for sealing under porous asphalt or for improved bond in highly stressed areas.
7 (05/18) The spread rates for tack and bond coats on hydraulically bound substrates may need to be higher than
those required for bituminous substrates.
Bituminous Sprays
8 (05/18) Bituminous sprays may be used to seal and protect earthworks, drainage media, recycled material and
cementitious materials including cement-stabilised soil. The primary purpose is not necessarily to promote bond
with an overlay, but to limit the evaporation or ingress of water and in cementitious materials, to facilitate proper
curing. Cementitious surfaces are alkaline and in warm summer conditions anionic emulsions may be more suitable
than cationic emulsions. Anionic emulsions have an alkaline water phase and can penetrate the surface before
breaking. It is important that the coverage of residual binder is uniform. Even small areas that remain unsealed will
increase evaporation of water and, in cementitious materials, cause premature drying that will inhibit curing. The
surface of the sprayed area should normally be covered with light coloured aggregate to reduce the absorption of
heat from the sun’s rays and reduce water loss.
(05/18) General
9 (05/18) To enable the Overseeing Organisation to identify each product the Contractor is to supply the
declaration of performance for each product and the other information required in Sheet 2 of contract specific
Appendix 7/4.
NG 922 (05/18) Surface Dressing: Design, Application and End Product Performance
1 (05/18) The specification is not of the conventional recipe/method type. It contains elements of performance-
related testing of materials for contract compliance, quality control of the process and end product performance and
reference should be made to: BS EN 12271, HD 37 (DMRB 7.5.2), Road Note 39 and British Standards Published
Document PD 6689. The principal differences from a recipe specification are that responsibility for the design of
the dressing is transferred to the Contractor and that there is performance measurement of the Surface Dressing,
measured at intervals throughout a guarantee period specified in the contract. The guarantee period is normally two
years for motorways, trunk roads and heavily trafficked or highly stressed roads, and one year for other roads.
2 (05/18) The specification allows considerable freedom for the Contractor in the design of the Surface Dressing
provided it complies with BS EN 12271. BS EN 12271 is a harmonised standard under the Construction Products
Regulation and as such the surface dressing is required to be CE marked and the manufacture is obliged to make a
declaration of performance. The evaluation of conformity requirements in BS EN 12271 include the Type Approval
Installation Trial (TAIT).
3 (05/18) Low noise emission Surface Dressings may be specified by limiting the designs to double or multi-
layered dressings and/or the maximum macrotexture depth in contract specific Appendix 7/3.
4 (05/18) Tenderers are expected to visit all the sites, to assess the parameters required, and in conjunction with
those given in the appendices, to design a suitable surface dressing.
5 (05/18) Basic details of the tendered design for each site should be completed in the Design Proposal and
declaration of performance provided.
6 (05/18) If any site is considered by the tenderer to be unsuitable for surface dressing this should be stated in the
Design Proposal. There may be sections where the existing road surface is considered not suitable for treatment or
the performance requirements are too onerous to be achieved in practice, see HD 37 (DMRB 7.5.2).
7 (05/18) When preparing the instructions for tendering it is essential that the compiler includes the following
information and instructions adapted as necessary to suit the particular conditions of contract and form of contract:
(i) Tenderers’ attention is drawn to the requirement that Tenderers intending to sub-contract surface
dressing must nevertheless provide with their tender all the information required by Clause 922 and
contract specific Appendix 7/3.
(ii) In determining the award of the Contract, regard will be had not only to the price tendered but also to the
following criteria:
(a) the Contract time period entered in the Form of Tender by the Tenderer.
(b) the requirements of contract specific Appendix 7/3 assessed as follows:
Contract Time Period All tenders will be evaluated against the lowest submitted Contract period.
Durability All tenders will be evaluated considering the durability categories stated in the
declaration of performance.
QA Certification Any tender submitting QA registrations which are not valid in the context of this
scheme will not be considered.
Method Statement All tenders will be evaluated in respect of the submitted method statement and any
that do not fully comply with all the constraints contained in the Contract documents
will not be considered.
Design Proposal Any tenderer submitting design proposals which do not fully comply with the
constraints contained in the Contract Documents will not be considered.
Declaration of Performance Any tenderer failing to submit the declaration of performance for the surface dressing
will not be considered.
Traffic Management Any tenderer failing to submit his proposals for traffic control and aftercare as
detailed in contract specific Appendices 7/3 and 1/17, or not fully complying with all
the constraints contained in the Contract Documents, will not be considered.
Contingency Plans Any tenderer failing to submit his details of contingency plans as detailed in contract
specific Appendix 7/3 will not be considered.
Previous Applications Any tenderer failing to submit the details of previous applications, personnel,
technical and managerial multiple layer dressing expertise as detailed in contract
specific Appendix 7/3 will not be considered.
8 (05/18) It is expected that the design would normally be carried out based on Road Note 39 although alternative,
documented, design procedures may be used provided they take into account the particular requirements of the
site. Contractors should recognise the need for best practice as set out in Road Note 39, BSI PD 6689 and in Road
Surface Treatment Association (RSTA) documents. Durability characteristics are required in order to assist in the
assessment of tenders on the expected design life of the surface dressing on a value for money basis; it is often the
case that more expensive designs last longer. The end of the design life is when the dressing no longer provides
the surface properties required at the site in question. Further guidance on the design life of Surface Treatments
including Surface Dressing has been published by RSTA and ADEPT.
9 (05/18) The responsibility for the provision of information upon which to base the design should be set out
in the contract, but it is expected that the compiler would provide the traffic data, the classification of the site in
accordance with HD 36 (DMRB 7.5.1), the minimum requirements for aggregate and binder properties, and records
of road surface hardness measurements carried out in accordance with Road Note 39. The compiler should set
out any limitations on the availability of a site in contract specific Appendix 1/13. These limitations could include
requirements to avoid the site at rush hours, on market days or for particular events already planned at the time
of writing the contract. There are problems with hardness measurements in that they need a lane closure and are
best carried out when the road temperature is above 15°C, (Road Note 39), therefore it may be necessary for the
Overseeing Organisation to carry out measurements during the preceding summer. When the Contractor makes his
site visit for the purposes of tendering he should make a visual assessment of the road hardness and traffic category
and bring any obvious anomalies about the site to the attention of the Overseeing Organisation.
10 (05/18) For the purposes of the contract, monitoring will stop at the end of the guarantee period, or for novel
materials, after one third of the stated estimated design life, but in order to check the proposed design life against
the actual achieved life, monitoring should continue for the whole life of the dressing. On heavily trafficked roads
this can most conveniently be done by means of the macrotexture output from TRACS surveys, which are currently
carried out on all trunk roads every 2 years and SCRIM surveys, which are currently carried out every 3 years. For
other roads volumetric patch tests or use of the Mini Texture Meter or other device calibrated against volumetric
patch values as Volumetric Patch Equivalent values, may be more convenient.
11 (05/18) The Vialit pendulum test should be carried out using BS EN 13588. The minimum binder cohesion at
peak measured using the Vialit Pendulum for four grades of binder are given in Table NG 9/13. Guidance as to
the choice of binder is given in HD 37 (DMRB 7.5.2). The range of temperature for premium and intermediate
binders for a value of 1.0 J/cm2 for heavily trafficked roads or highly stressed sites, provides another parameter for
evaluation of the modification together with peak value (see HD 37 (DMRB 7.5.2).
Note: The cohesion test has a significant reproducibility. This has been allowed for when setting these minimum
levels and the average value of the peak cohesion for polymer modified binders is likely to be at least 0.3 J/cm2
above the minima given in the Table.
* For conventional binders where 0.7 is not consistently achieved, 0.5 over a minimum temperature range of 15°C
has been found to provide satisfactory performance.
12 (05/18) Penetration, softening point, Fraass Brittle point, toughness, tenacity, and other viscosity measurements
are not in themselves sufficient as contract compliance tests, although they may be useful as quick or low cost
Quality Assurance tests to check consistency from load to load of the binder. The Contractor’s Design Proposal
should provide a declaration of performance for the binder giving at least the information specified.
13 (05/18) The binder sprayer should be checked for accuracy of transverse distribution using BS EN 12272-1.
This assesses the ability of the spraybar in real working conditions and may be carried out quickly using the correct
binder. The Depot Tray test to BS 1707 averages the rate over 60 seconds in a static condition and therefore does
not simulate site conditions caused by varying spraybar height, wind effects and pump or pressure surging. The
performance of the binder sprayer is classified in accordance with the value of the coefficient of variation (Cv) for
the regularity of transverse distribution. The category required for the sprayer, to be specified in contract specific
Appendix 7/3, should be selected from Table NG 9/14.
(05/18) * The Cv and category is appropriate when carpet tiles 100 mm wide and at least 200 mm long are used
for the test, where the surface is very even, on dual carriageways and motorways there is a case for specifying
category 3. Where 50 mm wide trays are used each two adjacent trays should be averaged before calculating the
Coefficient of variation (Cv).
14 (05/18) The compiler should specify the minimum PSV required for a particular site together with the maximum
AAV. Guidance on the levels to specify is given in HD 36 (DMRB 7.5.1); over specification should be avoided in
order to conserve scarce resources.
15 (05/18) The chipping spreader should be checked for accuracy of transverse distribution using the stated
method. With multi-layered surface dressings it is very important to obtain the correct rate of spread of the larger
chipping as under or over-chipping will reduce the quality of the dressing and may result in it failing to perform as
a multi-layered system. Particular attention should be paid to the rate of spread in the vicinity of the overlaps in the
chipping spreader mechanism as the performance, particularly of worn spreaders, can be significantly different in
these areas from the rest of the spreader. The performance of the chipping spreader is classified in accordance with
the value of the coefficient of variation (Cv) for the regularity of transverse distribution. The category required for
the spreader to be specified in contract specific Appendix 7/3 should be selected from Table NG 9/15. The rate of
spread for secondary chippings is less important and an excess is usually beneficial so that spreading with two
tail-board gritters in echelon is acceptable.
16 (05/18) Repairs to the existing road, in preparation for Surface Dressing, (for example, patching) should be
carried out well in advance of the works. They should be carried out in such a manner that the hardness and
macrotexture of the remedial work is sufficiently similar to the rest of the road to avoid problems of variable
appearance and behaviour in the completed dressing for at least the duration of the maintenance period; for
example, patching using close textured bitumen macadam should be carried out in the previous summer otherwise
it may absorb bitumen into the voids and chipping loss may ensue. The existing road variability and surface
characteristics have a bearing on the achievable levels of performance that may be specified; further information is
available in HD 37 (DMRB 7.5.2). If the existing surface is hot rolled asphalt then the patches will have to be laid
with hot rolled asphalt and preferably sufficiently far in advance of the works for the binder to wear off the surface
otherwise there will be excess binder in that area and fatting may occur. Thin surface course systems should be
repaired with stone mastic asphalt of similar consistency and highly textured variable substrata should be sealed
with a pad coat. Patches should not have a horizontal sealing strip applied as this will show through the dressing
very rapidly and has been known to initiate fatting failure. Binder-rich soft materials to seal cracks similar to stress
absorbing membrane interlayers (SAMIs) should not be used especially longitudinally in the wheel tracks, as the
Surface Dressing will fat up.
17 (05/18) Cleanliness of the existing road surface is extremely important. The binder will adhere only to the top
layer of the material on which it is sprayed and if this is mud or dust then the Surface Dressing will fail rapidly,
lacking bond with the underlying structure. It may be found necessary in some circumstances to use high pressure
washing to remove strongly adherent material. The masking of street furniture should be carried out very carefully
as the interface between the furniture and the surrounding surface should be sprayed in order to exclude water from
the road structure, but any cover must not be rendered immovable.
18 (05/18) Traffic safety and management. The mode of operation of Surface Dressing contracts can necessitate
the adoption of techniques requiring additional equipment over and above that normally required by static works.
For example, where traffic lights are required as part of the traffic management scheme, some sites may require
the provision of additional sets of traffic lights over and above the minimum necessary in order to permit work to
progress with a minimum of interruption and disruption to road users.
19 (05/18) General weather limitations should be covered by the Contractor’s Quality Plan. Any site specific
weather limitations should be specified under ‘Special restrictions’ in contract specific Appendix 7/3. Further
guidance may be obtained from HD 37 (DMRB 7.5.2).
20 (05/18) In order to ensure that only the binder is overlapped on transverse joints the chipping application should
stop short of the end of the binder film wherever possible. When spraying from a completed section some hand
canning and masking of the end is necessary in order to abut the joint without forming a ridge.
21 (05/18) Longitudinal joints should have slightly overlapped binder films obtained by leaving at least a 100 mm
wide wet edge. Care should be taken to ensure that double chipping does not take place as this will form a ridge.
As the binder overlap is generally in a lightly trafficked location the additional thickness of binder film is unlikely
to be a problem. Quartering (spraying of a part bar) should be avoided wherever possible, but may be necessary at
tapers and other similar locations, sufficient overlap (up to 300 mm) should be implemented in order to ensure at a
minimum the full rate of spread of binder at all points.
22 (05/18) The frequency of testing for rates and accuracy of spread of binder and chippings should be stated in
contract specific Appendix 1/5. The rate of testing should be reduced once the Contractor has demonstrated his
ability to consistently meet the requirements. The more consistent a contractor is in his work the lower the rate of
testing that may be employed; a minimum rate of 1 test per day on motorways and trunk roads might be attained
if the contract is large enough. The Overseeing Organisation will carry out testing at audit frequency, typically at
about 10% of the specified frequency for the Contractor. If the results from audit testing are significantly different
from those of the Contractor, for example, by more than the reproducibility of the tests, then the Overseeing
Organisation and the Contractor should work together to determine the source of difference. For roads other than
trunk roads or motorways the frequency of testing detailed in the Quality Plan and the Sector Scheme for the
Supply and Application of Surface Treatments to Road Surfaces should be used.
23 (05/18) The permitted tolerance on the design rate of spread of binder is dependent on the site and is classified
in Table NG 9/16. The category or categories appropriate to the site should be specified in contract specific
Appendix 7/3. These categories have been taken from BS EN 12272-1 for surface dressing.
24 (05/18) The permitted tolerance on the design rate of spread of chippings is dependent on the site and
is classified in Table NG 9/17. The category appropriate to the site should be specified in contract specific
Appendix 7/3. These levels have been taken from BS EN 12272-1 for surface dressing.
25 (05/18) The aim of rolling should be to orientate the chippings and place them in contact with the binder rather
than provide compaction. There is some consensus that vibration using a rubber coated vibratory steel-tyred roller
assists in the break of emulsion binders and a re-roll can help where the ‘cheesy’ stage of an emulsion is prolonged.
The ability of the rollers to spray water on to the drums or tyres should be checked before commencement of any
work. Although water may not be needed all the time, when it is, it is needed urgently. Heavy steel-wheeled rollers
(12 tonnes) tend to crush chippings and their use should not be permitted.
26 (05/18) Traffic control immediately after Surface Dressing is most crucial in the production of good quality
Surface Dressing. On high speed roads the best way of doing this is to introduce convoy vehicles into the traffic
stream in order to keep speeds low. The deployment of 10 mph or 20 mph signs, when permitted, is extremely
useful and warn the road user. If possible cones should be used to vary the lane position so that as much of the
dressing as possible is subjected to slow speed traffic. The lane should be suction swept prior to removal of the
convoying vehicles from the traffic stream, care being taken not to remove chippings that would otherwise become
part of the mosaic. With multi-layered surface dressing it may not be necessary to sweep initially unless there
are windrows which should be removed. If the work has been carried out correctly there will be no loose large
chippings. Provided there are no loose large sized chippings it may be useful to gradually increase the speed of the
convoying vehicles to disperse excess small chippings to the side of the lane for subsequent removal.
27 (05/18) On motorways and heavily trafficked dual carriageways it is not normally possible to convoy traffic
through the works at a speed of 20 mph which would normally be done on other roads to consolidate the Surface
Dressing prior to final sweeping and opening to unrestricted traffic. As part of the normal traffic management for
motorway work there is generally a mandatory 50 mph speed restriction in place for the duration of the work.
Therefore, instead of the normal slow speed trafficking and convoying as part of the aftercare, the Surface Dressing
should be designed to be opened to 50 mph traffic after completion of initial suction sweeping. Suitable designs
include double and multi-layered dressings using polymer modified emulsion binders and racked-in dressings
using polymer modified cutback binders with lightly coated chippings for the primary layer. There should follow
a number of days of trafficking at the restricted speed limit (generally 50 mph) with traffic management being
organised in such a manner that all lanes have at least 48 hours of speed limited trafficking. A minimum of
72 hours of restricted speed limit control after opening the whole carriageway to traffic should be included in the
works programme. This period may be extended as stated by the Overseeing Organisation in contract specific
Appendix 7/3 or as detailed by the Surface Dressing Contractor in his Design Proposal. The period will not
normally be extended except when the traffic on the section of motorway is unusually light or the work is to be
carried out late season, for example in August. The Surface Dressing Contractor will determine the need for a
longer period based on his experience with a particular process that is proposed. All loose chippings should be
removed from any traffickable part of the carriageway or hard shoulder prior to removal of the speed restriction.
28 (05/18) It is essential that the dressing is monitored for some time after opening to traffic, particularly in hot
weather when using cutback binders as at high temperatures the binder cohesion is low. When using emulsions,
humid or cool weather, results in a similar problem as the binder takes longer to gain cohesion. These conditions
result in lower initial resistance to traffic forces and the mosaic may be destroyed. The Contractor should be
prepared for these eventualities and have on site, ready to use, a suitable ‘dust’, if this is required, and be prepared
to re-impose traffic control. The ideal ‘dust’ is light coloured, absorbent and about 4 mm to 1 mm in size. Oolitic
limestone and blastfurnace slag are particularly good although other materials available locally may have to be
used.
29 (05/18) Macrotexture is measured in the nearside (inside) wheel track where the lane width and traffic are
sufficient for this to be identified; for low traffic category sites the track carrying the most traffic (wear) is tested,
this may be the outside wheel track for narrow lanes where tyre paths in both directions overlap. High-speed
sensor measurements should be used for measuring macrotexture depth on trunk roads and motorways because of
the amount of macrotexture depth measurement to be undertaken. This form of measurement avoids the need for
additional lane closures, which the use of volumetric patch technique or the Mini Texture Meter would require.
Other methods may be used, but the results should be reported as Glass Spheres Patch Equivalent values. Lightly
trafficked roads should be assessed for cleanliness and cleaned if necessary before measurements are made. This
would not normally be necessary on roads carrying heavy or fast traffic. The use of high speed measurements
also enables long term monitoring as part of the routine TRACS surveys. The macrotexture depth for high speed
roads at the end of the guarantee period would normally be specified at 1.5 mm measured by the volumetric patch
technique. Depending on traffic levels, lower macrotextures at the end of the guarantee period may be specified
in contract specific Appendix 7/3 for lower speed roads and for certain Surface Dressing product types as shown
in Tables NG 9/18 and NG 9/19. The macrotexture requirements are reduced for double and multiple-layered
surface dressings, which are more durable especially when the binder is modified, as the rate of embedment (loss of
macrotexture with time) is lower. These dressings have lower initial macrotexture and a greater number of points of
contact to tyres and they are used to reduce tyre noise emission in areas where this is important such as urban roads
or trunk roads and motorways close to a conurbation. Macrotexture levels specified should be achievable depending
on the variability and surface characteristics of the existing road and traffic category; guidance is available in
HD 37 (DMRB 7.5.2).
TABLE NG 9/18: (05/18) Minimum Glass Spheres Patch Macrotexture Depth Requirements
(or Glass Patch Equivalent) in the Nearside Wheel Track for Single and Racked-in Surface
Dressings at the End of the Guarantee Period
Traffic cv/lane/day Speed limit 50 mph or higher Glass Speed limit 40 mph or lower Glass
Spheres Patch Macrotexture (mm) Spheres Patch Macrotexture (mm)
More than 2000 1.5 1.5
250 to 2000 1.5 1.2
50 to 250 1.2 1.0
Less than 50 1.0 0.8
TABLE NG 9/19: (05/18) Minimum Glass Spheres Patch Macrotexture Depth Requirements
(or Glass Spheres Patch Equivalent) in the Nearside and Offside Wheel Tracks for Double
and Multiple-layered Surface Dressings at the End of the Guarantee Period
Traffic cv/lane/day Any Speed Limit Glass Spheres Patch Macrotexture (mm)
Over 3250 1.2
250 to 3250 1.0
Less than 250 0.8
The decrease in macrotexture between 12 and 24 months is a guide to the life of the dressing, the lower the value
the longer the life, unless other failure mechanisms intervene. A maximum reduction in macrotexture of 40%
should be specified in contract specific Appendix 7/3. Double and multiple-layered dressings using modified
binders normally show reduced loss of macrotexture with time. An increase in macrotexture depth over time
indicates that the surface is losing chippings.
30 (05/18) It is anticipated that because Surface Dressing defects are usually obvious the need for a formal
assessment procedure using the quantitative method in BS EN 12272-2 will be rare. All defects are measured
in 100 m sections. The visual assessment of fatting up, tracking and bleeding P1, expressed as a percentage of
area, is categorised in Table NG 9/20. The category appropriate to the site should be specified in contract specific
Appendix 7/3 provided that the levels are achievable depending on the traffic category and existing road surface
characteristics, see HD 37 (DMRB 7.5.2).
TABLE NG 9/20: (05/18) Defect Category: Fatting Up, Tracking and Bleeding
The visual assessment of scabbing and tearing, (P2), expressed as a percentage of area using BS EN 12272-2, is
categorised in Table NG 9/21. The category appropriate to the site should be specified in contract specific
Appendix 7/3.
The visual assessment of fretting, (P3), expressed as a percentage chipping loss using BS EN 12272-2, is
categorised in Table NG 9/22. The category appropriate to the site should be specified in contract specific
Appendix 7/3.
The visual assessment of streaking, (P4), expressed as length of streaking using BS EN 12272-2, is categorised in
Table NG 9/23. The category appropriate to the site should be specified in contract specific Appendix 7/3.
31 (05/18) The guarantee period stated in the specification should be clearly stated as applying to the Surface
Dressing. For trunk roads and motorways this period should normally be two years, for other roads such as lightly
trafficked single carriageways the guarantee period may be one year. An appropriate Special Requirement should be
included in the Conditions of Contract drawing particular attention to the guarantee period.
installation of the system. Further guidance on when to treat freshly laid asphalt using different systems is provided
in the RSTA Code of Practice for High Friction Surfacings.
7 (05/18) On occasion cracking which extends into the surface course can be induced by the application of
high friction surfacing. The risk of this occurring is much greater when the surface course is newly applied and
untrafficked. Provided the high friction surfacing is well bonded to the substrate and with the agreement of the
Overseeing Organisation, the cracking may be sealed using a suitable epoxy or similar resin and the high friction
surfacing made good. Any cracks in excess of 0.5 mm are the liability of the Contractor under the terms of the
guarantee required in sub-Clause 924.7.
8 (05/18) The minimum polished stone value of the aggregate used in high friction surfacing systems, determined
in accordance with BS EN 1097-8, to be specified in contract specific Appendix 7/1 can be obtained from HD 36
(DMRB 7.5.1). The only aggregate type which consistently delivers 70+ psv is calcined bauxite. Further guidance
on Aggregate Specification for High Friction Surfacing is contained within the Code of Practice for High Friction
Surfacings. Currently suppliers offer a two year warranty for their products.
TABLE NG 9/24: (05/18) High Friction Surfaces: Area of Application by Type Classification*
NG 929 (05/18) Dense Base and Binder Course Asphalt Concrete (Design Mixtures)
1 (05/18) The requirements in Clause 929 are now based on the European Asphalt Standard BS EN 13108-1 as
detailed in BSI PD6691 and BS 594987. This has implications for the verification and validation of mixtures as
described below.
2 (05/18) Clause 929 requires that designed dense base and binder course asphalt concrete mixtures meet
the example requirements of BSI PD6691 Annex B. It is the responsibility of the asphalt producer to provide
verification of these properties for each mixture in the form of a Type Test Report, in accordance with
BS EN 13108-20. However, the producer is obliged to supply only the declaration of performance. This verification
may have been carried out in accordance with a protocol given in BS 594987 Annex C. The protocol is based on
the job mixture approval trial procedure specified previously in earlier editions of the Specification for Highway
Works Clause 929, is technically equivalent and provides the same information.
3 (05/18) For most contracts, the information from the declaration of performance and CE Marking, should
be sufficient to demonstrate that the mixture complies with the requirements of Clause 929. Under these
circumstances, there is no need for an additional job mixture approval trial. On particularly large or critical projects,
there may be a benefit in undertaking validation trials as part of the contract. Where required, these should be
carried out as contract compliance testing and in accordance with BS 594987 Annex C and the requirement clearly
indicated in contract specific Appendix 1/5. It should be noted that this additional testing should only be specified
where there is reasonable justification to do so.
4 (05/18) If required, mix volumetrics can be monitored in the permanent works by determining void contents of
cores compacted to refusal. This can provide an indication of deformation resistance. It should be noted however,
that resistance to permanent deformation assessed by wheeltracking forms part of the Type Test Report. Monitoring
void content at refusal will generally only be practicable only on larger contracts. If void content at refusal is to be
monitored in the permanent works, this should be clearly indicated in Schedule 5 of Appendix 7/1.
5 (05/18) Verification of wheel tracking properties for each mixture will be recorded in the form of a Type Test
Report in accordance with BS EN 13108-20. This verification may have been carried out in accordance with a
protocol given in BS 594987 Annex D. Requirements appropriate to traffic and stress condition should be selected
from Table NG 9/25.
6 (05/18) On particularly large or critical projects it may be appropriate to monitor resistance to permanent
deformation in the permanent works. If required, this should be clearly indicated in Schedule 5 of Appendix 7/1
along with the site classification.
7 (05/18) When specifying resistance to permanent deformation information is given in the note to BSI PD6691
Table B4.
8 (05/18) Sub-clause 6 requires a minimum stiffness category of 1800 MPa for mixtures containing 40/60 grade
binder and 2800 MPa for mixtures containing 30/45 grade binder. This is a minimum default value for these
mixtures and should not be confused with the design stiffness. Further information on design stiffness can be found
in HD 26 (DMRB 7.2.3). There is no protocol covering stiffness determination for dense base and binder asphalt
concrete mixtures in BS 594987. Therefore, the following Type Testing protocol should be adopted:
‘Following the general protocol in BS 594987 Annex C, take an additional, three adjacent core pairs as described
in C.3.2. Cut test specimens from these cores and determine stiffness in accordance with BS EN 12697-26
(ITSM method 20oC). The mean of the set of six values shall not be less than 1800 MPa for mixtures containing
40/60 grade binder and 2800 MPa for mixtures containing 30/45 grade binder.’
9 (05/18) Indirect density gauges, including nuclear density gauges, are specified for compaction control. It is
important that these are calibrated across an appropriate range of densities as required by BS 594987. Such gauges
have a penetration depth of approximately 80 mm and where layer thicknesses exceed this it is especially important
that cores are visually inspected to ensure that they are uniformly compacted.
10 (05/18) A new requirement for density control close to joints has been introduced. Experience has shown that in-
situ void content requirements in the wheeltracks are generally achieved. Therefore, the frequency of testing in this
position has been reduced. Compaction at joints is considered to be a primary factor in affecting the durability of
asphalt pavements and testing at this location has therefore been introduced. Contractors may need to adopt special
measures of joint compaction in order to comply with this requirement.
11 (05/18) Where dense asphalt concrete base and binder course mixtures are to run on directly by normal highway
traffic (due to traffic management requirements) it is recommended that they be surface dressed to prevent water
ingress and to provide adequate skid resistance.
IA & As I and II, above, but with contraflow anticipated during summer
IIA months
F Approaches to and across major junctions (all limbs) BSI PD6691 Table B4 Classification 2 (60°C)
III G1 Gradient 3% to 10%, longer than 50 m
L Roundabout
30
Notes for Guidance on the Specification for Highway Works Road Pavements – Bituminous Bound Materials
Series NG 900
Volume 2 Series NG 900
Notes for Guidance on the Specification for Highway Works Road Pavements – Bituminous Bound Materials
NG 937 (05/18) Stone Mastic Asphalt (SMA) Binder Course and Regulating Course
1 (05/18) The requirements in Clause 937 are based on BS EN 13108-5 as detailed in BSI PD6691 and
BS 594987. This has implications for the verification and validation of mixtures as described below.
2 (05/18) Clause 937 requires the volumetric properties of SMA binder course and regulating mixtures to
comply with BSI PD6691 Annex D. It is the responsibility of the asphalt producer to undertake verification of
these properties for each mixture in the form of a Type Test Report, in accordance with BS EN 13108-20. This
verification will have been carried out in accordance with a protocol given in BS 594987 Annex G. The protocol
is based on the job mixture approval trial procedure specified previously in earlier editions of the Specification for
Highway Works, is technically equivalent and provides the same information.
3 (05/18) The means to specify resistance to permanent deformation for SMA binder courses, previously given in
Clause 952, are now contained within this Clause. Requirements appropriate to traffic and stress condition should
be selected from Table NG 9/26. Verification of wheel tracking properties for each mixture will be recorded in the
form of a Type Test Report in accordance with BS EN 13108-20. This verification will have been carried out in
accordance with a protocol given in BS 594987 Annex G.
4 (05/18) On particularly large or critical projects it may be appropriate to monitor resistance to permanent
deformation in the permanent works. If required, this should be clearly indicated in Schedule 5 of contract specific
Appendix 7/1 along with the site classification.
5 (05/18) When specifying resistance to permanent deformation information is given in the note to BSI PD6691
Table B4.
1 (05/18) Thin surface course systems are bituminous products with suitable properties to provide a surface
course that is laid at a nominal depth between 20mm and 50 mm. This classification refers to hot-mixed asphalts in
accordance with the BS EN 13108 family of materials, primarily Parts 1, 2 and 5. Acceptance requirements for the
material relate to CE marked products with the required declaration of performance and valid CE marking. These
cover only the manufacture of the product and not its installation. Additional in-situ performance requirements are
also specified to cover aspects of the installation not covered by the declaration of performance.
2 (05/18) In order to demonstrate that the ‘as installed’ thin surface course system is able to meet the specification
requirements a System Installation Performance Trial (SIPT) is required. This requires third party assessment of the
installed system when constructed and over a period of two years. The SIPT is part of the evidence to be provided
to determine system acceptability and is not to be part of the contact specific works.
3 (05/18) The Contractor is required to guarantee the system for five years. The performance of the system is
required to be maintained throughout the five year period. The compiler should ensure that the contract conditions
and documentation cover the guarantee requirements.
4 (05/18) CE marking by producers is certificated by Notified Bodies in accordance with the requirements of the
relevant standard.
5 (05/18) The UK National Highways Sector Scheme 16 provides interpretation of BS EN ISO 9001 Quality
Management Scheme requirements in relation to asphalt laying and registration is required for the laying of asphalt
mixes in Clause 901.
6 (05/18) The SIPT is certificated by a Certification Body (CB) which is UKAS accredited for product approval to
BS EN 45011. The SIPT will be observed by an inspection panel made up of, at least, a lead auditor and two other
competent inspectors. The personnel are required to have appropriate technical knowledge and experience.
7 (05/18) Those supervising the works should ensure that they receive the declaration of performance and the
SIPT documentation and check that they identify that the stated performance requirements are met by the chosen
materials.
8 (05/18) Completion of the SIPT does not automatically mean that the particular system is suitable for every
situation where a thin surface course system is required.
9 (05/18) New materials that have not undergone a SIPT may be considered for use, these would need to be
considered using the departures from standard process. Such materials would need to be monitored for at least two
years and be in the process of being progressed for a completed SIPT.
Full details of the monitoring arrangements and details of intervention contingency plans must be included in the
departures from standards submission. The surface macrotexture performance guarantee period should be extended
to three years in these circumstances.
10 (05/18) A distinction should be drawn between limitations set for the properties of thin surface course systems
recorded for the SIPT and requirements placed on the work being carried out. The former are based on results from
past works and identify what the system achieved for the trial, whilst the latter identify what the system is required
to achieve in this case.
15 (05/18) Premature cooling in adverse cold weather could be overcome either by use of a thicker surfacing or by
pre-heating of the substrate.
16 (05/18) Retention of thin layers of existing material after planing should be avoided. There is a significant risk of
such thin layers failing prematurely.
17 (05/18) The nominal thickness at which to lay the material has to be selected by the Contractor with due
allowance for the constructional tolerance. If both a minimum and a maximum thickness are specified, the
difference between the maximum and minimum thicknesses should be at least 20% of their average. The System
Installation Method Statement should state the absolute installed minimum thickness at any point.
18 (05/18) The range of nominal installation depth at which a thin surface course system can be laid will be specific
to the system. If systems are specified to be laid at nominal depths other than those identified, then the desired
performance may not be achieved.
(05/18) Design – Mixture Selection
19 (05/18) The compiler should state whether each section of road is only suitable for thin surface course systems
with an upper (D) aggregate size of 10mm or less in contract specific Appendix 7/1.
20 (05/18) The minimum polished stone value of the coarse aggregate should be selected from Table 3.1 in HD 36
(DMRB 7.5.1). Separate maximum aggregate abrasion values should be given for thin surface course systems using
the appropriate information from Table 3.2 in HD 36 (DMRB 7.5.1).
35 (05/18) Noise assessment is an additional optional declaration for a SIPT and should only be specified for sites
of specific noise concern.
36 (05/18) Permitted Road/Tyre Noise Levels are given in Table 9/17. Levels 2 and 3 are necessary in noise-
sensitive areas. In the interest of sustainability Level 3 should only be specified in very noise sensitive areas.
37 (05/18) Level 0 must not be specified at sites with existing noise barriers or earth bunds, where the latter have
been specifically installed as a noise mitigation measure, and must not be used at locations that have been identified
as an Important Area, either with or without First Priority Locations, in any of England’s Noise Action Plans
published by DEFRA in March 2010.
38 (05/18) Road/Tyre Noise Levels are demonstrated by the optional value stated in the SIPT.
(05/18) Deformation Resistance
39 (05/18) The deformation resistance of thin surface course systems can be set in terms of wheel tracking level
stated in the declaration of performance. For trunk roads including motorways, Level 3 is usually required (see also
Table NG 9/26).
40 (05/18) If other levels of deformation resistance are required, this shall be specified in contract specific
Appendix 7/1, with due consideration of the classifications given in Table NG 9/26.
41 (05/18) Deformation resistance data should be declared under the CE Marking declaration of performance. If
cores are taken from a SIPT site for the purposes of checking deformation resistance of the installed material, the
following protocol should be used.
42 (05/18) A minimum of six cores should be taken from a 100 m length of the SIPT at nominally even spacing
along a diagonal line across the lane width in accordance with BS EN 12697-27: 2001. The cores need to be
maintained at a temperature of 15° ± 10°C during transportation to the test laboratory and for up to 96 hours once
delivered. If wheel tracking testing has not commenced within 96 hours of coring, the specimens are to be placed in
storage and maintained at a temperature 5° ± 2°C until commencement of the testing procedure.
43 (05/18) The cores should be tested in accordance with BS EN 12697-22: 2003.
44 (05/18) The wheel-tracking levels of the thin surface course system are required to be Level 3 unless otherwise
specified in contract specific Appendix 7/1. The required level should be stated in contract specific Appendix 7/1.
TABLE NG 9/26: (05/18) Classification of Sites by Traffic and Stress Condition for Resistance to
Permanent Deformation of Thin Surface Course Systems
Site Site Definition Traffic at Design life (Commercial vehicles per lane per day)
Cate
Up 251 501 1001 1501 2001 2501 over
gory
to – – – – – – 4001
250 500 1000 1500 2000 2500 4000
A Motorway (main line) 0 1 2 3
Dual carriageway (all
B purpose) non-event
sections
Dual carriageway (all
I & II D
purpose) minor junctions
Single carriageway non-
C
event sections
Single carriageway minor
E
junctions
As I and II, above, but with 0 1 2 3
IA &
contraflow anticipated during
IIA
summer months
Approaches to and across 0 1 2 3
F
major junctions (all limbs)
III Gradient 3% to 10%,
G1
longer than 50 m
L Roundabout
As III, above, but with contraflow 0 1 2 3
IIIA anticipated during summer months
or in a south-facing cutting uphill
G2 Gradient steeper than 0 1 2 3
IV G2
10%, longer than 50 m
As IV, above, but with contraflow 0 2 3
IVA anticipated during summer months
or in a south-facing cutting uphill
Approach to roundabout, 0 2 3
traffic signals, pedestrian
J/K
crossings, railway level
crossings and similar
47 (05/18) Calibration trials and checks should be undertaken at the start and during the course of work to derive
and confirm a relationship between the volumetric patch method and the Measured Texture Depth (SMTD).
48 (05/18) In the event of a dispute, or discrepancy between the two methods, only results obtained using the
volumetric patch method will be considered for compliance purposes.
49 (05/18) Calibrations carried out on site are only applicable to that site and that surfacing.
50 (05/18) SMTD is numerically different from macrotexture measured by the volumetric patch technique.
Volumetric patch macrotexture depth is a measurement of the average depth of hollows in the surface below
general level of peaks. SMTD is the standard deviation of the sample height measurements.
(05/18) Surface Macrotexture – After 2 Years
51 (05/18) The performance levels of macrotexture depth for use on the strategic road network are given in
Table 9/14 of Clause 942. Research has shown that hot applied thin surfacings with an upper (D) aggregate size
of 10mm or 14mm maintain adequate high speed skid resistance with these levels of texture. For hot applied
thin surfacings with an upper (D) aggregate size of 6mm, current techniques for assessing texture depth do not
satisfactorily explain the skid resistance characteristics. These materials will require a supplementary assessment
from a System Installation Performance Trial (SIPT) to provide evidence verifying adequate high-speed friction
performance. Evidence must be provided that a SIPT has been carried out or a SIPT must be included in the
proposal for the departure from standard.
NG 943 (05/18) Hot Rolled Asphalt Surface Course and Binder Course (Performance-Related
Design Mixtures)
1 (05/18) This Clause is for the specification of hot rolled asphalt mixtures that have been designed to achieve
controlled levels of resistance to permanent deformation (rutting) measured by the wheel tracking test. These
mixtures are used as both surface course and binder course. They are particularly suitable as a regulating binder
course under thin surfacings and as a binder course over bridge deck waterproofing. When used as surface course
they must be chipped to provide a skid resistant surface.
2 (05/18) Using hot rolled asphalt surface course to this Clause will ensure a good level of resistance to permanent
deformation within the surface course itself. Designers should be aware that significant rutting often occurs in the
lower layers of the pavement and use of a performance designed surface course on an inadequate substrate will not
protect against this. To provide adequate resistance to deformation, binder course and base designed in accordance
with Clauses 929, 930 or 937 should be used, particularly in the top 100 mm of the pavement.
3 (05/18) In almost all cases, the use of a modified binder or binder modifier will be required in order to achieve
the more onerous (Class 2) performance level. Since these are generally proprietary products, sub-Clause 5 requires
the submission of information to the Overseeing Organisation for approval. If there is evidence of successful use of
a modified binder/modifier in similar conditions, the presumption should be of approval.
4 (05/18) Verification of wheel tracking properties for each mixture will be recorded in the form of a Type
Test Report in accordance with BS EN 13108-20. This verification will have been carried out in accordance
with a protocol given in BS 594987 Annex F. This protocol is based on the job mixture approval trial procedure
specified previously in earlier editions of Clause 943, is technically equivalent and provides the same information.
Requirements appropriate to traffic and stress condition should be selected from Table NG 9/27 and included in
contract specific Appendix 7/1.
5 (05/18) On particularly large or critical projects it may be appropriate to monitor resistance to permanent
deformation in the permanent works. If required, this should be clearly indicated in Schedule 5 of contract specific
Appendix 7/1 along with the site classification.
6 (07/19) When specifying resistance to permanent deformation, it will be necessary to take into account the
transitional problems brought about by the change in the wheel tracking test method from BS 598 Part 110 to
BS EN 12697-22, which uses similar equipment but different duration and loading. Further information is given
in the note to BSI PD6691 Table C3. Work is in hand to establish criteria for the new method, but in the interim,
requirements should be based on the BS 598 test but with data provided to show the values for the same mix tested
to the BS EN 12697 method.
38
Notes for Guidance on the Specification for Highway Works Road Pavements – Bituminous Bound Materials
Series NG 900
Volume 2 Series NG 900
Notes for Guidance on the Specification for Highway Works Road Pavements – Bituminous Bound Materials
2 (05/18) The aggregate component should be of a quality generally suitable for use in cement bound material
or asphalt. However, given the nature of the operation, which involves processing arisings from existing road
pavements, some discretion should be applied. The emphasis should be on ensuring that deleterious materials, such
as clay lumps and badly weathered aggregate are excluded from the recycled material.
3 (05/18) When determining the grading of materials containing asphalt planings, samples should be dried to
constant mass at 40oC and care should be taken not to break down the aggregated particles of asphalt unnecessarily.
4 (05/18) It is good practice to undertake mix design evaluation in advance of works on site, but it must be
recognised that this is not always practicable, particularly for small projects. Additionally, there will not always
be time for the full design procedure and, in particular, the curing stage to be carried out in advance of the works.
Where this is the case, information from earlier works with the same process or accelerated curing regimes should
be taken into consideration.
The components used in the mix design stage should represent the materials available in the permanent works.
Where a representative component is unavailable, the Contractor should use a replacement component of similar
properties in the mix design stage.
The laboratory prepared aggregate should be thoroughly mixed with measured proportions of the bitumen binder,
cementing binder and adhesion agent(s). The type and grade of the bitumen and adhesion agent(s) used in the trial
mixtures shall be the same as those used in the finished works.
For QVE, the Contractor should declare the Indirect Tensile Stiffness Modulus in accordance with BS DD 213.
For SVE it is recommended that an accelerated curing regime is used involving curing at 60oC for 72 hours and
then determining Indirect Tensile Stiffness Modulus. However, the values obtained in this way should not be
expected to reflect in situ performance in the same way as for the other material types.
For QH and SH materials the Contractor should declare the minimum performance class achieved according to
the direct measurement of Dynamic Modulus and Flexural Strength after conditioning; where these values are not
directly measurable, suitable alternative apparatus and transfer functions may be utilised as described below.
If information is required on the moisture sensitivity of the mixtures, additional sets of specimens can be made up
and tested after 24 hours soaking in water. The soaked specimen should not show any signs of cracking or swelling
and the modulus or strength values should be at least 75% of the un-soaked values.
Declaration using alternative test methods for hydraulic mixtures should be dealt with as follows:
Using compressive strength tests in accordance with prEN13286 Part 41 and using relationships from Croney
(1991):
log f f + 0.773
Edyn =
0.0301
f f = 0.11 f c
Using the indirect tensile strength and stiffness in accordance with prEN13286 Part 42
Edyn = 11 + 0.84EITSM
ff = 1.33 fit
Where Edyn is elastic dynamic stiffness in GPa, EISTM is the ISTM in GPa, ff is the flexural strength in MPa, fc is the
compressive strength in MPa, fit is the indirect tensile strength in MPa.
This declaration shall include the direct value from laboratory tests and also a predicted 360 day value. Factors can
be used to relate the laboratory test values with 360 day test values. Based on current knowledge, the following
factors are suggested; other factors may be used supporting evidence. These factors should be applied to the test
results prior to any transfer functions.
TABLE NG 9/29: (05/18) Factors to Link Laboratory Test Values and 360 Day Values
The Contractor should also justify this design with appropriate references to design charts or if requested by the
Overseeing Organisation, carrying out analytical pavement design.
5 (05/18) It is recommended that a trafficking trial be performed as part of the mixture approval trial and is a
best-practice approach to ensure that excessive deformation will not occur in the permanent works. It should be
noted that a trafficking trial cannot guarantee deformation resistance in the permanent works and it can be a time-
consuming method of approving a foundation.
As a general rule, the ‘Quick’ mixtures, which include cement, are less likely to be susceptible to rutting, as are
those with a stable, angular, granular aggregate content. Particular care should be taken if there is a high proportion
of rounded gravel.
A trafficking trial may not be necessary if:
• evidence is available to show that the proposed construction (materials, construction and thicknesses)
has performed well at other sites under the same moisture conditions; or
• the type of construction is of a type that is unlikely to be susceptible to deformation.
The experience of the Contractor with this type of work and evidence of satisfactory application of the same
techniques on similar sites in the past should be taken into consideration.
Deformation may also result from weak underlying foundations which may be exposed during recycling operations.
This should be taken into account by those responsible for the design of the works. Whether a trafficking trial is
performed or not, it is important to ensure that the foundation meets the specified requirements in the permanent
works.
If the construction is to be trafficked by special, very heavy vehicles, additional consideration should be given to
the proven performance of the material approval trial under trafficking in relation to these vehicles.
6 (05/18) The plant used for ex situ stabilisation should be capable of achieving controlled batching by weight or
volume. The plant should have hoppers and tanks appropriate for the component materials to be mixed. The mixing
plant shall be located close enough to the site to enable placing of the material within the appropriate setting time.
7 (05/18) It is important to establish a testing regime for end performance properties (stiffness, tensile strength)
appropriate to the nature of the works. It is recommended, given the precision of the testing the results are assessed
for conformity in sets of six. This does not, however, mean that a full set of six specimens needs to be made up at
one time.
For works of a reasonable size, it is recommended that specimens are prepared at an overall frequency of three per
1000 tonnes, with a minimum of three per working day. Conformity should be assessed on a rolling basis.
It may be possible to relax this requirement for small and intermittent jobs.
40kg of material is required for each sample to have sufficient material for the three test samples (PRD, Cylindrical
and Moisture Content) to be produced. PRD samples require a minimum of 5kg of material; Cylindrical samples,
4kg; Moisture Content samples, 3kg; as well as three PSD tests from a bulk sample of six individual samples.
8 (05/18) A PRD or other other suitable mould may be used. Where long-term storage of materials is required, the
use of an inexpensive mould such as plastic soil pipe is advised.
9 (05/18) The criteria in this sub-Clause represent the minimum permitted end-product compliance criteria;
however, they can be supplemented by other laboratory and non-destructive in situ test methods as agreed with the
Overseeing Organisation. For VE materials, particularly those containing asphalt planings, analysing for bitumen
content is unlikely to be of value. This aspect of process control is better controlled through tank reconciliation.
A description of the supplementary test methods and expected outcomes of the testing can be including in the
Material Quality Plan declaration. Supplementary testing can be of value to both the Contractor and the Overseeing
Organisation and should be viewed as good practice. For example, a non-destructive falling weight test device can
in certain circumstances be used to show the in situ performance of the layer and also show that curing is occurring.
It is advised that any agreed supplementary testing is used as a tool for ‘acceptance’ (as opposed to ‘rejection’) so
that along with practical evidence at other sites these may be used to resolve non-compliance issues should they
occur.
NG 954 (05/18) Method for Laboratory Determination of Interface Properties Using the Modified
Leutner Shear Test
1 (05/18) The test method is intended to assess the bonding between adjacent asphalt pavement layers using
cylindrical samples. It is also appropriate for asphalt applied to concrete.
2 (05/18) The peak shear stress at the interface between asphalt layers measured using the Modified Leutner Shear
Test should not be less than 1MPa for an interface within the top 75 mm of the pavement structure and not less than
0.5MPa for interfaces at or below the top 75 mm.
3 (05/18) Clause 954 incorporates by dated or undated reference, provisions from other publications. These
normative references are cited at the appropriate places in the text, and the publications are listed in Appendix F.
For dated references, subsequent amendments to or revisions of any of these publications apply to this Clause
only when incorporated in it by amendment or revision. For undated references the latest edition of the publication
referred to applies (including amendments).
4 (05/18) The Leutner shear test was developed in Germany in the late 1970s as a simple means of undertaking
a direct shear test on a bond between two pavement layers. The test is performed on 150 mm diameter cores
comprising at least two layers (with a bond between them) taken either from a pavement or produced in the
laboratory. The principle of the test is to apply a shear displacement rate across the interface under investigation
and monitor the resulting shear force. No normal force is applied to the specimen. The standard loading rate is
50 mm/min and the test is typically carried out at 20°C. It should be noted that a 5mm gap is introduced in this
modified version of the shear test, as shown in Figure 9/2, in order to give a certain level of tolerance for interface
alignment to the shear plane.
5 (05/18) With reference to sub-Clause 954.4, shear test apparatus is commercially available. Various sizes of
standard shearing rings are also available, necessary in order to incorporate some variation in specimen diameter.
It should be noted that these standard shearing rings require modification to introduce a 5 mm gap over the shear
plane (see sub-Clause 954.3 above).
6 (05/18) It is recommended to use a servo-hydraulic universal testing machine with an incorporated data logging
system. However, other loading frames (such as the Marshall apparatus) can also be used, providing they fulfil the
requirements of sub-Clause 954.4 (ii).
7 (05/18) The data logging system described in sub-Clause 954.4 (iii) shall to be capable of collecting around
40 data points per second.
8 (05/18) The recommended material for the metal extension is aluminium.
9 (05/18) The recommended diameter of the cored specimens is 150 ± 2 mm. It is recommended to have a range
of shearing rings and metal extensions to cover the range of specimen diameters.
10 (05/18) The thickness of the layer below the interface to be tested shall be sufficient to ensure a secure grip is
maintained on the specimen during the test (Figure 9/2 B). 60 mm is recommended as the minimum thickness.
11 (05/18) The thickness of the layer above the interface shall be sufficient to ensure a proper contact with the
upper shearing ring (Figure 9/2 C). The minimum recommended thickness of the layer above the interface is
15 mm. If the thickness of the layer above the interface is between 15 and 30 mm, a metal extension shall be glued
on the top of the layer above the interface.
12 (05/18) It is recommended that the shearing rings are selected to form a loose fit around the specimen. For
example, if the specimen diameter is 150.1 mm, 151 mm shearing rings shall be selected.
13 (05/18) It is recommended that the metal extension selected shall have a diameter slightly larger than the
diameter of the specimen (the difference shall not be more than 2 mm). When a metal extension is used, it is
recommended that the shearing rings are selected to form a loose fit around the metal extension. For example, if the
metal extension diameter is 151 mm, 152 mm shear rings shall be selected.
14 (05/18) The sample support shown in Figure 9/2 B needs to be tightened using a hand spanner to give a firm
grip. However, care is necessary to avoid over tightening and consequent damage to the specimen.
15 (05/18) It is necessary to carefully inspect both sections of the sheared specimen. Crushed coarse aggregate on
the specimen edge could indicate misalignment of the specimen interface in the shear plane.
NG 955 (05/18) Ageing Profile Test Using a Modified Rolling Thin Film Oven Test (MRTFOT)
1 (05/18) The MRTFOT uses screws to continually stir and mix polymer modified bituminous binders in the
sample cans so they may be aged without the problems of skinning and polymer phase separation.
The air jetted into the glass bottles normally used in the RTFOT has sometimes caused polymer binders to creep out
of the bottles, because of the return air flow. The MRTFOT uses the screws to pull binder to the back of the cans as
they rotate in the carousel and this counteracts the air flow to the front. If the RTFO carousel rotates anticlockwise,
viewed from the front, screws with a right-hand thread are required and if the carousel rotates clockwise, screws
with a left hand thread are required. The screws also help in the mixing and binder film exposure accelerating
oxidation. Glass bottles do not have screw tops so removal of the whole sample is difficult. To further aid the
removal of binder, the MRTFOT uses PTFE coated cans which also assists with the cleaning. Glass bottles do not
have precision made walls and in order for the screws to uniformly scrape the internal walls, aluminium PTFE
coated cans were designed. A heavy stainless steel screw with a flat edge was developed to enhance scraping
and pressure at the interface and a semi-circular thread incorporated to maximise binder movement. The design
(unthreaded shank) also minimises the opportunity for the screw to worm itself out of the orifice. The stainless steel
screws are manufactured from high quality surgical steel so that they are resistant to corrosion, which is particularly
a problem with emulsions. The screws, produced to a ‘fine machined finish’, and the sample cans manufactured
to the dimensions stated, with screw top lids, are all commercially available. A certificate of conformity should be
obtained. It is convenient to have the PTFE coating a contrasting colour to the binder (e.g. green) so that the binder
sample can be clearly identified.
2 (05/18) The MRTFOT can be used as an alternative to PAV85 (BS EN 14769), to evaluate ‘ageing’ of the binder
on the road. The MRTFOT does not require a Pressure Ageing Vessel (PAV) apparatus, which is considered to be a
greater safety hazard when using emulsions or fluxed binders containing highly volatile oil. In static tests such as
the PAV, the trays used in BS EN 14769 (3mm thick sample) may result in skinning and heterogeneous ageing. The
combination of the screw continually mobilising the binder film and the rotation of the specimen in the air stream
in the MRTFOT reduces the test time whilst maintaining a homogeneous sample. This is particularly relevant for
heavily polymer-modified binders and is one reason why 135ºC was selected. The protocol minimises the possible
phase separation of the polymer from the base binder.
3 (05/18) Binder samples may lose volatile oil, but may increase in weight due to the products of oxidation, so
care should be exercised in evaluating weight changes.
4 (05/18) Binder samples for test from other apparatus (e.g. recovered binders from roads) may be loaded into the
sample cans without carrying out the RTFOT at 163ºC.
5 (05/18) Binders that have been tested in accordance with BS EN12607-1 in a separate RTFOT apparatus using
conventional glass bottles do not necessarily result in identical ‘Short-term Aged Binder’ after the MRTFOT. This
may be the case when the binder is heavily modified, where skinning is likely to occur and the binder does not roll
exposing fresh binder faces for oxidation to take place, as originally intended in the ASTM D2872 test, which was
designed for unmodified bitumen.
6 (05/18) The test method produces around 10g of material per sample can. This is sufficient for testing using
rheology (see BS EN 14770) or Vialit Pendulum Cohesion (see BS EN 13588). For other tests, sufficient sample
cans should be used and the binder combined prior to testing.
7 (05/18) Polymer modified binders may need to be heated and stirred prior to testing in other apparatus to ensure
that internal stresses are not present in the test specimens. This thermal history is to be reported.
(05/18) Asphalt Binders
8 (05/18) The Ageing Profile test provides a plot, generally of complex stiffness (shear) modulus G* and phase
angle d, using a Dynamic Shear Rheometer in accordance with BS EN 14770. The change in properties provides
an indication of how the binder will age in the road pavement and a plot is much superior to just two points:
‘Short-term Aged’ and ‘Long-term Aged’. The ‘Long-term Aged’ condition represents the near end-life of asphalt
and, since most binders asymptote to similar stiffness after that amount of ageing, it does not reveal a great deal
of information; conversely, early-life points can show the rate of loss of beneficial characteristics. The correlation
between ageing in road pavements and laboratory ageing methods is not far advanced and this procedure is able to
generate a large number of samples at a realistic price to study durability. Longer periods of test providing larger
volumes of aged binder, such as generated by the RCAT, may have greater precision, but the cost of this specialist
equipment and the time taken to complete the test (a couple of hundred hours), supports the argument for more
rapid tests such as the Ageing Profile test to be used.
9 (05/18) Hard grade bitumens to BS EN 13924 may be assessed using the Ageing Profile test. The viscous elastic
transition temperature may be plotted and some correlation with cracking of both stone mastic asphalt and high
modulus asphalt has been determined.
(05/18) Bituminous Emulsions and Fluxed Binders
10 (05/18) The initial stage of the MRTFOT is able to drive off water from polymer modified bituminous emulsions
rapidly at a comparatively low temperature of 85ºC. This is because the stainless steel screws continually disturb
the binder and there is a controlled nitrogen gas flow over the binder surface encouraging a homogenous break
without skinning. This is important, as higher temperatures would drive off the volatile oils too quickly and/or
destroy the microstructure of the binder, which would not, therefore, simulate the residual binder on the road. Some
polymer microstructures are more sensitive to temperature than others and this should be considered when heating
samples for subsequent testing.
11 (05/18) Nitrogen gas is used, rather than air, to minimise ageing of the binder and to increase safety, especially
with some emulsions (containing some very light oils) and also for fluxed binders.
12 (05/18) The second stage of the test method uses nitrogen gas at 135ºC for 30 minutes (after ramping the RTFO
temperature up from 85ºC to 135ºC) to remove most of the highly volatile oil left within the sample after the first
stage. This process results in a ‘Recovered Binder’ equivalent to that obtained by the recovery process described
in BS EN 13074-1. These recovery methods simulate the state of a binder film soon after application using
conventional spraying or mixing equipment; the method is not intended to drive off all the volatile components, but
to enable testing of recovered binder properties as detailed in BS EN 13808 for emulsions. The test method may
also be used for conventional unmodified emulsions.
13 (05/18) The ‘Recovered Binder’ from the sample cans may be conveniently scraped onto a non-adhesive sheet
or dish (e.g. PTFE or silicone) in order to collect enough material for a test. Care should be taken to minimise
volatile oil loss and opportunity for oxidation by ensuring a quick transfer to a suitable storage pot or test apparatus.
14 (05/18) The percentage loss of weight should be recorded as an indicator of water and/or volatile oil loss and
compared to the binder content of an emulsion or the percentage volatile flux.
15 (05/18) Recording sample history is important as the method of sampling, whether from spraybar or storage tank
or just after manufacture, may affect the properties of the binder. The sample size and its subsequent treatment in
terms of, for example, re-heating, exposure to frost and regular stirring, may make a considerable difference to the
result for water or volatile oil loss.
(05/18) Preservatives
16 (05/18) These may be solvent based materials (typically 50% solvent) with hard base binders, or sometimes
resin based systems. Other components are used to improve the aged bitumen in road pavements (e.g. to replace
the lost maltene phase). It is the solvent based preservatives that require careful attention to the laboratory protocol,
hence the use of nitrogen and fume cupboards. The RTFOT also needs proper venting.
17 (05/18) The protocol provides binder samples that may be tested using rheology to compare ageing of the
control against ageing of the preservative treated aged control binder. The use of the screws ensures mixing so the
improvement is the maximum potential that could possibly be expected.
18 (05/18) After initial addition, preservatives provide improvement of the properties of the binder, because they
soften the aged bitumen. However, after subsequent ageing, some preservatives show hardening, which, unless
the treatment is repeated on a regular basis, might be detrimental to the performance of the surface of the road
pavement. Data are required to correlate test results to field performance.
19 (05/18) The test provides product identification and an indication of performance, so that any changes in
formulation may be detected and accommodated and also consistency of supply may be established.
20 (05/18) Some preservatives are emulsion systems and may be polymer modified binders. These binders improve
the aged control bitumen in the test, but it has not yet been demonstrated that they can penetrate the road surfaces
sufficiently to provide the same benefit in situ.
MRTFOT MRTFOT
163ºC 163ºC
45min 15min
135ºC
Aged6 Binder
Characteristic e.g. G* at 25 ºC and 0.4Hz
6h 135ºC Air
Aged4 Binder
4h 135ºC Air
Aged2 Binder
2h 135ºC Air
RTFOT
163ºC Air
Sample 45min
Total 60min
Time
85ºC 135ºC
Aged22 Binder
22h 135ºC Air
Characteristic e.g. G* at 25°C and
Aged5 Binder
5h 135ºC Air
Aged3 Binder
3h 135ºC Air
Recovered Binder
135ºC in N2
85ºC in N2 30min
75min
0.4Hz
Time
MRTFOT
Control binder - Sample MRTFOT
Transition Procedure
135°C Air jet at 4000ml/min
Aged Control
45min 4h
Binder
Stainless steel screws Stainless steel screws
Sample after MRTFOT Sample of aged control
Weight loss reported Weight loss reported
135ºC
Addition of Preservative
Remove stainless steel screws
Remove some binder and replace with preservative (keeping the residual weight constant),
swirl/coat,
Cool to ambient on side at 20°C (ambient) for 24 hours in fume cupboard
Weight loss reported
MRTFOT
50°C
2h (no screws)
Nitrogen gas jet at 4000ml/min
Sample
Weight loss reported
Test Simulates
After MRTFOT
Aged binder in asphalt after 3 to 5
Sample of aged bitumen (originally years
40/60 penetration grade) prepared as a
homogenous thin film in PTFE coated
aluminium can
Addition of Preservative
30
25
Viscous Elastic Transition Temperature
20
10
0
Short Term Control after laboratory ageing Improvement with Comparison of
Aged equivalent to 3 to 5 years Preservative applied Preservative treated
40/60 pen aged Control after further
Control laboratory ageing
equivalent to 5 to 10
years
TABLE NG 9/1TS: (05/18) Criteria for the Stability and Flow of Rolled Asphalt Surface Course
(Design Mixtures)
TABLE NG 9/1WG (05/18) Criteria for Stability and Flow of Rolled Asphalt Surface Course
(Design Mixtures)
6 (05/18) High Stone Content Asphalt (HSCA) has successfully been used as a surface course throughout North
Wales for over 25 years. HSCA will only be approved within speed limits of 30mph or less where microtexture is
the main contributor to skidding resistance.