Method Statement LIT
Method Statement LIT
Method Statement LIT
: KAP2E2-MS-ELEC-GEN-1745-1
r, a
Method Statement
Lighting Fixtures
Signature:
1 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Method Statement
Installation & Termination of Exterior & Interior Lighting Fixtures
Document Control
Document Information
Information
Document ID BEC-KAP2E2
Document Owner Beijing Emirates International Construction Co.
Issue Date 21 August 2016
Last Saved Date 23 Feb 2017
Method Statement: Installation & Termination of Exterior &
File Name
Interior Lighting Fixtures
Document History
Version Issue Date Changes
[01] 23 Feb 2017 Submitted to NKY for approval
Document Approvals
Project Sponsor
M.O.I
Project Review Group
( P.M.O)
Ahmed AbouElGhar
Project Director
3 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Method Statement
Installation & Termination of Exterior & Interior Lighting Fixtures
Table of Contents
1- SCOPE OF WORK ..................................................................
2- REFERENCES .......................................................................
3- DEFINITIONS ......................................................................
4- RESPONSIBILITY……..............………………….....................
5- SPECIALIZED TOOLING EQUIPMENT……......................................
6- PRODUCT/MATERIAL………………………..............................
7- WORKFORCE………………………………….........................
8- PRIOR ACTIVITIES TO BE COMPLETED …......................................
9- HEALTH, SAFETY, & SECURITY ………........................................
10- ENVIRONMENT .....................................................................
11- QUALITY ASSURANCE/ CONTROL ................................................
12- PROCEDURES/ WORK METHODOLOGY …………............................
12.1 INSTALLATION OF INTERIOR LIGHTING FIXTURES
12.2 INSTALLATION OF EXTERIOR LIGHTING FIXTURES
4 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
1. SCOPE OF WORK
This Method Statement covers the nature and type of work for the Installation
& Termination of Exterior & Interior Lighting Fixtures by BEC-MEP to King
Abdullah Project (KAP2E2).
This method statement gives guidelines contained herein so as to ensure that
the job execution complies with the requirement of the specifications and the
authorities concerned and serves the intended purpose to satisfactory level.
This procedure is to be read in conjunction with the relevant ITP, outlining the
responsibilities and the quality verification to be performed by various parties.
2. REFERENCES
Contractor’s Quality Control Plan Set for Contract
Project Specification Section No. 16500, 16511, 16521, 16525
Project Health and Safety Plan
Approved Drawings & Material Submittal
Manufacturers Recommendation
3. DEFINITIONS
5 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
4. RESPONSIBILITIES
Project Manager
The project manager will have full authority and overall responsibility to
manage, supervise.
He will control the works and will have direct responsibility for ensuring safe
working practices and compliance with regulatory authority’s requirement.
He will coordinate with the engineers and the employer’s representative for
execution of the contract scope of works.
Implement the project quality systems to the satisfaction of the project
requirements.
Review changes and variations to evaluate impact of those on time and
schedule.
Project Engineer
Is responsible for ensuring that all works are carried out as per the
specifications, approved shop drawings and method statement as per
manufacturer’s instructions and coordinated with other works.
QA/QC Engineer/ Inspector
6 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Is responsible for monitoring the works are in fulfillment with the specified
requirements that all quality records related to the works are complete. He will
carry out all the inspections with the employer representative and notice will
be given to employer within 24 hours and ensure that no work will be
executed/covered up without inspection/testing.
Site Engineer
The site engineer shall coordinate all the site activities according to work
schedule, installation according to the project specifications, manufacturer’s
data sheet and approved shop drawings.
Shall liaise with site representatives and coordinate safety procedures with
site supervisors and site foremen.
Shall coordinate and explain the work to be carried out to the supervisors/ Site
Foreman.
Ensure the compliance of work with related approved quality control and
coordinate with BEC QA/QC Engineer/Inspector to advice for the areas to be
issued for internal external inspection.
The project team of experienced supervisors and foremen shall ensure the
quality of the installation work carried out, and shall also ensure that it is as
per the latest approved construction shop drawing issued for installation and
according to instructions received from the site engineer.
7 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
He will provide his subordinates adequate information to carry out their duties.
To ensure that he has adequate resources of machinery, labor, and materials
to carry out all the activities efficiently and to discuss with the site engineer.
To ensure safe and clean working environment to enforce a safe working
habit.
8 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
5. SPECIALIZED TOOLING/EQUIPMENT
Electrical Standard Tool Box
Measuring tape
Ladders/ Scaffolds
Marker
Drill Machine
Crimping Tools
Spirit Level
Multi-meter
Internal Resistance Tester
Lux Meter
Personal Protective Equipment
Crane Lifting
6. PRODUCT/MATERIAL:
9 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
7. WORKFORCE:
Construction team will ensure that manpower selected for the specified job is
well trained. Tool box talk shall be carried out before the work commences at
site to the involved workers through the supervisor and foremen in charge the
work, under the directives of in-charge engineer. The work procedure and
safety precautions should be clearly and concisely explained to the workers in
their own language so it is fully understood.
Storming procedure of the exterior & interior light fixture to be mentioned.
All staff will have a safety induction carried out by the contractor before
commencing any activities on site.
Prior to commencing any activity, labour force shall receive a tool box talk on
the project site safety regulations from the contractor safety officer on Daily
basis on topics appropriate to the activities being undertaken. A method
statement briefing will be given to all staff before the commencement of the
work and a record shall be kept.
Any process that is adopted that may have particular safety risk will be
assessed and addressed as required.
Safety officer should be full time stand by at site during the work.
Ensure all concerned personnel shall use PPE and all other items as required
and full specifications of equipment to be used.
Ensure adequate lighting and adequate space is provided in the working area
at night time.
Ensure that in all areas where there is a risk of falling from height preventative
measures will be taken and identify them.
Ensure service shaft opening are provided with barricade, tape, safety nets.
All BEC-MEP tradesmen, operators etc. are qualified and will have licenses
and their competency level issued by BEC.
Access/ Egress: BEC will provide scaffoldings assembly with attached step
ladder and rubberize wheel. Platforms will be provided on top of the
scaffolding assembly and circulated with tubular railings at adequate height to
protect the workers. Aluminum step ladders will be used in instances where
scaffolding is not permitted in the workplace and for alignment purposes of
installation. Safety personnel should be involved in preparation and approval
scaffolding assembly and ladders prior to use.
Housekeeping: The supervisor has the responsibility to ensure the site is kept
clean from any debris. Any material leftovers shall be collected and put into
designated disposal box. Unused materials shall be returned to proper
storage in every end of each day work.
12 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
10. ENVIRONMENT:
Any wasted generated to above work shall be segregated and disposed of
according to the Site and Authority Norms. Any chemical/cleaner used for the
job will be kept in container to avoid spillage on the ground.
13 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Site Engineer along with QA/QC inspector is responsible for all installation
activities for getting the work inspected/approved by consultant.
General Requirements for the Installation of Interior & Exterior Lighting Fixtures
Ensure interior and exterior lighting material receiving inspection is approved
before installation.
Make sure that the layout and detail drawings for lightings are approved.
Verify that the fixtures assembly parts and components shall be free of
damaged.
Verify that the fixtures assembly parts and components shall be new and
unused.
Ensure that the number of sockets connected to the circuit is correct.
All works shall be according to standard installation and manufacturer’s
recommendations.
Ensure that all civil works such as concrete foundations, floor/wall finishing,
false ceiling finishing etc. are completed prior to the installation of interior,
exterior, emergency lighting fixtures.
14 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Lighting fixtures and its components must be properly installed for ease of
maintenance and repairs of components.
Coordination shall be done during the installation of lighting fixtures and its
components with other trades.
15 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
16 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures
KAP2E2-MS-ELEC-GEN-1745-1 February 2017
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELEC-GEN-1745-1
Wiring on or within fixtures shall be neatly arranged and shall not be exposed
to any physical damaged.
Cables shall be arranged so that they are not be subjected to temperatures
above those for which they are rated.
Pendant luminaires shall be installed at a height from the floor as specified in
the approved drawings.
Check for any damages if any and replace it prior to energization.
12.4. Testing:
Perform Lux Testing
Include testing & commissioning procedure
13. ATTACHMENT:
13.1 Safety Risk Assessment
18 Method Statement: Installation & Termination of Exterior & Interior Lighting Fixtures