PROGRAM OF WORKS

PROJECT TITLE: Vision-Mission Corner Landscaping


SCOPE OF WORKS: 5 squaremeter corner of RAFI Building
SOURCE OF FUND: Internal Stakeholder
AMOUNT OF THE PROJECT: 15,000.00

I.D. NO DESCRIPTION UNIT QTY UNIT COST GRAND TOTAL

I. Materials
Garden soil Sack 10.00 250.00 2,500.00
Fox tail palm pieces 2.00 700.00 1,400.00
pandakaki pieces 4.00 150.00 600.00
snake plant pieces 30.00 15.00 450.00
lubi-lubi pieces 2.00 200.00 400.00
duranta pieces 10.00 20.00 200.00
bamboo poles length 15.00 150.00 2,250.00
angel jar pieces 1.00 1,000.00 1,000.00
hollow blocks pieces 15.00 25.00 375.00
cement bag 1.00 275.00 275.00
trapal meter 3.00 75.00 225.00
peebles bag 5.00 150.00 750.00
paint liter 4.00 175.00 700.00
Sub-total 8,625.00
I TOTAL MATERIALS COST 8,625.00
No. of
LABOR No. of Days Daily Rate
Personnel
3 3.00 300.00 2,100.00

II TOTAL LABOR COST 2,100.00


No. of
EQUIPMENT No. of Days Daily Rate
Equipment
none

III TOTAL EQUIPMENT COST 0.00


IV TOTAL PROJECT COST (I+II+III) 10,725.00

Prepared by: Funds Available

GINA G. OROSIO
Department Head Department Treasurer
Checked & Reviewed By:
Approved:

ARLENE D. BUOT, ED D
School Principal

1 of 1