SCADA EMS Requirements
SCADA EMS Requirements
SCADA EMS Requirements
BCC -
NLDC – National Backup Control
Load Despatch Center
Center
Ch A Ch B Ch A Ch B Ch A Ch B Ch A Ch B
RTU
NLDC – SYSTEM ARCHITECTURE
IEC 60870-5-104
NLDC BCC
IDS/IPS IDS/IPS
Network Firewall Network Firewall
Network Switch Network Switch
Issues:
1. IP Management
CH-A CH-B 2. IP Routing
3. Network Security
RTU 4. Physical Security
NLDC – SYSTEM ARCHITECTURE
IEC 60870-5-104
NLDC BCC
FrontEnd Servers FE FE FrontEnd Servers
Network Firewall / IDS Network Firewall / IDS
Network Switch Network Switch
CH-A CH-B
Firewall
IP Address A IP Address B
Subnet 255.255.255.248 Subnet 255.255.255.248
Gateway IP Address A RTU Gateway IP Address B
NLDC – SYSTEM ARCHITECTURE
IEC 60870-5-104
NLDC BCC
MPLS
Multiprotocol Level Switching
CH-A CH-B
RTU
NLDC – SYSTEM ARCHITECTURE
IEC 60870-5-104
- TECHNICAL
REQUIREMENTS
GSO INTERFACING GUIDELINES FOR
SCADA/EMS SYSTEM - TECHNICAL REQUIREMENTS
GSO INTERFACING GUIDELINES FOR
SCADA/EMS SYSTEM - LSS SIGNAL LIST
APC
(Automatic Power
AHVC
(Automatic High
ADMIN
Curtailment) Voltage Control)
1. Point-to-point test
2. To ensure all signals can be transmitted and
received by both NLDC and PLANT
3. PIC:EMS Team @ NLDC
EMS TESTING
- PRE-ONLINE TEST & ONLINE TEST
Pre-online Test
To test all required logics implemented
correctly based on EMS technical
requirements before online can commence
PIC: EMS Team @ NLDC
Online Test
Testing commence at site as per APC & AHVC
commissioning plan
PIC: EMS Team @ LSS Plant
EMS TESTING
- APC Test Plan
EMS TESTING
- AHVC Test Plan
THANK YOU
Q&A