Eart 03 003
Eart 03 003
Eart 03 003
1. SCOPE
This technical specification describes SPEN’s requirements for earthing and bonding systems at
secondary substations. This includes all HV/LV substations, HV switching stations, HV pole-mounted
installations and HV customer substations up to and including 11 kV.
It is intended for application to new build or existing substations where significant work is carried out
on site (e.g. switchgear replacement or transformer change), and is not retrospective.
This specification allows SPEN to demonstrate compliance with relevant national and international
standards as well as statutory legislation and licence conditions. This document has been issued to
align with latest releases of the ESQCR, BS EN 50522, ENA TS 41-24 and ENA EREC S34.
This document replaces EART-02-003.
2. ISSUE RECORD
This is a Reference document. The current version is held on the EN Document Library.
3. ISSUE AUTHORITY
4. REVIEW
This is a Reference document which has a 5 year retention period after which a reminder will be
issued to review and extend retention or archive.
5. DISTRIBUTION
This document is part of the Construction Virtual Manual maintained by Document Control but does
not have a maintained distribution list. This document also is published to the SP Energy Networks
website.
6. CONTENTS
1. SCOPE ....................................................................................................................................... 1
2. ISSUE RECORD ........................................................................................................................ 1
3. ISSUE AUTHORITY .................................................................................................................. 1
4. REVIEW ..................................................................................................................................... 1
5. DISTRIBUTION.......................................................................................................................... 1
6. CONTENTS ............................................................................................................................... 2
7. REFERENCE AND RELATED DOCUMENTS .......................................................................... 4
8. DEFINITIONS ............................................................................................................................ 5
9. FOREWORD .............................................................................................................................. 7
9.1 Legacy practice for earthing at secondary substations ................................................................................. 7
9.2 Modern practice for design of earthing at secondary substations ................................................................ 7
9.3 Standard Earthing Arrangements .................................................................................................................... 7
10. INTRODUCTION........................................................................................................................ 8
10.1 Earth Fault Current ........................................................................................................................................... 8
10.2 Earth Potential Rise (EPR)................................................................................................................................ 8
10.3 Touch Potential ................................................................................................................................................. 9
10.4 Step potential .................................................................................................................................................. 12
10.5 Transfer Potential ........................................................................................................................................... 12
10.6 Stress Voltage ................................................................................................................................................. 13
10.7 Equipment bonding ........................................................................................................................................ 13
10.8 Target Resistance ........................................................................................................................................... 13
10.9 Network Contribution ..................................................................................................................................... 14
10.10 Global Earthing System (GES) ............................................................................................................. 15
12. EPR LEVELS AND LIMITS FOR STEP AND TOUCH POTENTIALS ................................... 19
13. SUBSTATION EARTHING DESIGN PROCEDURE ............................................................... 23
13.1 Preliminary Design Approach ........................................................................................................................ 23
13.2 Design process flowcharts............................................................................................................................. 23
13.3 Ground mounted substations ........................................................................................................................ 27
13.4 Pole mounted installations............................................................................................................................. 27
13.5 Network Contribution ..................................................................................................................................... 27
13.6 Standard earthing scenarios .......................................................................................................................... 29
This specification makes reference to, or implies reference to, the following documents. This
document is intended to amplify and/or clarify the requirements of those documents where alternative
arrangements are permitted by those documents and/or where further information is required.
It is important that users of all standards, specifications and other listed documents ensure that they
are applying the most recent editions together with any amendments. For dated references, only the
edition cited applies. For undated references, the edition of the referenced document (including any
amendments) valid at the date of issue of this specification applies.
ENA TS 41-24 Guidelines for the design, installation, testing and maintenance of main earthing
systems in substations.
ENA EREC G12 Requirements for the application of protective multiple earthing to Low Voltage
networks
ENA EREC S34 A guide for assessing the rise of earth potential at electrical installations
ENA EREC S36 Identification and recording of 'hot' sites - joint procedure for Electricity Industry
and Communications Network Providers.
SWG-03-026 Specification for low voltage fuse boards and network pillars
8. DEFINITIONS
For the purpose of this specification, the following definitions shall apply and are reproduced in italic
font throughout this document:
Backup Protection Protection set to operate following failure or slow operation of primary
protection. (See Normal Protection also).
Bonding Conductor A protective conductor providing equipotential bonding between items
of metalwork.
Design Engineer Senior or Lead engineer whose responsibilities include, design,
construction and commissioning distribution substations, overhead lines
etc. The Head of Planning and Design for each District should
nominate a person to provide guidance on the design of Earthing
Systems at secondary substations.
Earth The conductive mass of earth whose electric potential at any point is
conventionally taken as zero.
Earth Electrode A bare conductor or group of bare conductors buried directly in the
earth to provide a direct electrical connection with the general mass of
earth. This includes earth rods driven into the ground, bare stranded
conductors, bare earth tape and mesh.
Earth Electrode Resistance The resistance of an Earth Electrode with respect to Earth.
Earth Fault A fault causing current to flow in one or more earth-return paths.
Typically, a single phase to earth fault, but this term may also be used
to describe two-phase and three-phase faults involving earth.
Earth Fault Current (IF) The worst-case steady state RMS current to earth, resulting from a
single phase to Earth Fault. Not to be confused with Ground Return
Current (IGR)
Earth Fault Current Fault current used to calculate the size of Earthing Conductors and
(Design) Earth Electrodes based on the system design limit of fault current.
Earth Potential Rise (EPR) The difference in potential which may exist between a point on the
(or UE) ground and a remote Earth in the event of an Earth Fault. Formerly
known as RoEP (Rise of Earth Potential).
Earthing Conductor A conductor connecting the Main Earth Bar of an installation to the
Earth Electrode system or connecting the Main Earth Bar to plant and
equipment.
Earthing Specialist A competent earthing designer as determined by knowledge, skills,
training and experience such that each earthing design is subject to a
technical check and professional review process.
Earthing System The complete interconnected assembly of Earthing Conductors and
Earth Electrodes.
Extremely High EPR A site with EPR exceeding 2.33 kV and requiring special measures (i.e.
special design and equipment) to ensure safety. (See section 12.1.3).
Global Earthing System An Earthing System of sufficiently dense interconnection such that all
(GES) items are bonded together and all rise in voltage together under fault
conditions. No true earth reference exists and therefore Step Potentials
and Touch Potentials are limited.
Ground Return Current The proportion of Earth Fault Current returning through soil via the
(IGR) general mass of earth.
High EPR An EPR greater than 430 V but not exceeding 2.33 kV. (See section
12.1.2).
Hot / Cold Site A Hot site is defined as one which exceeds EPR limits specified in
EREC S36. For secondary substations sites (with long clearance
times), if the EPR exceeds 430 V then it shall be classified as a Hot
Site.
Low EPR For the purposes of this document, this is defined as an EPR equal to
or less than 430 V. (See section 12.1.1)
Main Earth Bar Terminal or bar provided for connection of Earthing Conductors and
Earth Electrodes.
Normal Protection Clearance of a fault under normal circumstances. This includes relay
operating time and circuit breaker opening time for all foreseeable
faults. This time assumes that faults will be cleared by normal
upstream protection and does not allow for e.g. stuck circuit breakers or
other protection failures/delays.
Standard Earthing These are standard designs of typical ground-mounted substations and
Arrangement pole-mounted installations used in SPEN with a pre-designed layout of
Earthing System. The Step and Touch Potentials (as a % of EPR for
each standard layout) have already been established by modelling or
calculation.
Network Contribution The Earth Electrode effect of the wide area HV (and LV) interconnected
network. Large networks provide multiple parallel Earth Electrodes
which can provide a relatively low resistance path to earth.
Step Potential (US) Voltage between two points on the ground surface that are 1 m distant
from each other where 1 m is considered to be the stride length of a
person. (See section 10.4)
Stress Voltage Voltage difference between two segregated Earthing Systems, which
may appear) across insulators/ bushings or cable insulation etc. (See
section 10.6)
Target Resistance The resistance of the substation local Earth Electrode system
determined by policy or design.
Touch Potential (UT) Voltage appearing between a person’s hands and feet, or across both
hands. When conductive parts are touched simultaneously.
Transfer Potential Potential transferred by means of a conductor between an area with a
significant EPR and an area with little or no EPR and results in a
potential difference between the conductor and earth in both locations.
(See section 10.5).
9. FOREWORD
This specification replaces EART-02-003, “Earthing and bonding of plant and apparatus at secondary
substations”. The document has been revised to reflect significant changes in legislative and industry
standards and specifications relating to earthing and changes in equipment types currently employed.
The main changes that have led to the revision of this specification include:
If the combined Earth Resistance of the HV and LV Earthing Systems (including Network Contribution
from HV and LV cable sheaths) was less than 1 Ω, then it was permissible to combine the HV and LV
Earthing Systems. The “1 Ω Rule” practice was based on the requirements of The Electricity Supply
Regulations 1988.
No perimeter Earth Electrodes were installed around the substation. This approach relied heavily on
contributions from PILC cables radiating away from the substation, often passing under the operator’s
position. Since the lead sheath and steel armour/tapes of the cable are in contact with the ground
(even where hessian servings are used), these cables provided a degree of potential grading (thus
reducing Touch Potentials) as well as reducing the combined earth resistance of the substation.
The ESQCR state that the owner of the HV network shall ensure that, “the earth electrodes are
designed, installed and used in such a manner to prevent danger occurring in any low voltage
network as a result of any fault in the high voltage network”.
BS EN 50522 provides criteria for design, installation, testing and maintenance of Earthing Systems
of electrical power installations with nominal voltage above 1 kV. This standard is applicable to
substations and pole/tower installations and requires that the installation operates safely under all
conditions and ensures the safety of human life in any place to which persons have legitimate access.
ENATS 41-24 was revised in November 2018 to reflect the changes to earthing practice as outlined in
ESQCR and to align with BS EN 50522. This recognises that the “1 Ω Rule” no longer fully compliant
with UK standards so this practice has now been withdrawn.
The requirements of this specification are based on compliance with the latest issues of ESOCR, BS
EN 50522 and ENATS 41-24.
showing the Earthing System to be installed at typical ground-mounted substations and pole-mounted
installations are given in section 14.
This process allows the Design Engineer to choose a SPEN Standard Earthing Arrangement based
on particular scenarios such as substation location, system fault levels and Network Contribution. It is
anticipated that this procedure will be appropriate for the vast majority of situations.
However, there will be some situations where Standard Earthing Arrangements are not suitable, and it
is the responsibility of the Design Engineer to exercise a degree of judgement, and to seek help from
an Earthing Specialist if in doubt.
10. INTRODUCTION
An Earthing System shall be installed at every substation. The Earthing System shall be designed
such that in both normal and abnormal conditions there is no danger to persons.
The Earthing System shall be designed to avoid damage to equipment due to excessive potential rise
and potential differences within the earthing system and due to excessive currents flowing in auxiliary
paths not intended for carrying Earth Fault Current.
The term “Earthing” generally describes connection to the general mass of earth using a dedicated
Earth Electrode. The related term, ‘Bonding”, means connecting items together so they are at equal
potential. A well-designed Earthing System provides both Earthing and equipotential Bonding.
i. Limit the voltage rise (and voltage differences) on exposed metalwork under fault conditions
so as to reduce risk of shock to operators and members of the public who might be nearby.
ii. Ensure that any Earth Fault Current is carried safely back to the source substation without
causing damage to any equipment such that system protection operates quickly.
The Earthing Conductors and Earth Electrodes shall be able to withstand the maximum expected
Earth Fault Current as described in section 11.1.
Potential gradients develop in the surrounding ground area and these are highest adjacent to the
Earth Electrode. The EPR reduces to approximately zero (or true earth potential) at some distance
from the Earth Electrode. Figure 1 shows the potential gradient caused by an EPR (where one Earth
Electrode is installed).
The ESQCR require that danger will not arise on the LV system as a consequence of HV faults. If the
HV and LV Earthing Systems are connected, in event of HV earth faults, the resultant EPR will be
impressed on the LV neutral/earth (secondary transformer star point) and this voltage will ultimately
transferred to a customer’s LV earthing terminal. To avoid this danger, the HV and LV Earthing
Systems shall be separated if the EPR exceeds particular limits. (These limits are given in section
12.1.1).
The three main design parameters relating to the consideration of EPR when designing a substation
Earthing System are:
i. Touch Potential,
ii. Step Potential and
iii. Transfer Potential.
A person could be at risk if they can simultaneously contact parts at different potential, thus, in a well-
designed system, the potential differences between metallic items shall be kept to safe levels
regardless of the level of EPR.
The value of Touch Potentials is not only influenced by the EPR but also depend on the arrangement
of the Earthing System and buried Earth Electrodes. By comparing the Touch Potential gradient
shown in Figure 3 with the Touch Potential gradient shown in Figure 3, it can be seen the action of
installing a perimeter Earth Electrodes buried around the substation significantly reduces the potential
gradient of the EPR (i.e. kV/m) compared to an installation utilising a single Earth Electrode. This
solution reduces the maximum Touch Potential that staff (and members of public) may be exposed to.
Hand-to feet Touch Potentials can be further reduced by installing an Earth Electrode bonded to the
HV metalwork and buried at a relatively shallow depth immediately below the position that the
operator will stand when operating HV switchgear or other plant. This is often referred to as a “Earth
mat” or “Stance Earth”.
The permissible limits for Step Potential are usually much higher than for Touch Potential. As a
consequence, if a substation is safe against Touch Potential, it will normally be safe against Step
Potentials.
Figure 4 shows an example where staff or public can be exposed to Step Potentials.
For example, a long metal substation fence may export the an EPR out of the site to the end of the
fence, where it may pose an electric shock hazard to somebody standing on soil at true earth
potential. Similarly, a metallic water pipe or cable may import a zero-volt reference into a substation,
where local potential differences may be dangerous (see Figure 5). Bonding the cable or pipe to the
substation Earthing System may reduce risk in the substation but may create a problem elsewhere.
Isolation units or insulated inserts are typical solutions that may need to be considered.
In secondary substations, the consideration of Transfer Potentials is particularly important given that
LV neutral/earth conductors may be connected to, or close to, HV Earthing Systems and
consequently these conductors could export a Transfer Potential in to customer installations (e.g. on
to a customer’s LV earthing terminal).
The limits for permissible Transfer Potential relate to shock risk (Touch Potential and Step Potential)
and are given in sections 12.1.4. and 12.1.5.
Figure 5 – Example of risk of Transfer Potential (cable installed from substation to remote location)
If HV and LV Earthing System are combined, the Stress Voltage limits are unlikely to be exceeded in
the substation. If the HV and LV Earthing Systems are segregated, then the Stress Voltage includes
the difference in potential between the HV and LV Earthing Systems and may be assumed equal to
the EPR of the substation.
The limits for Stress Voltage Potential and typical equipment that may be exposed to this voltage are
described in section 12.1.6.
All normally accessible metalwork within a substation is connected together and to the Main Earth
Terminal, using a Bonding Conductor (or Earthing Conductor). This is to ensure that all adjacent,
exposed metalwork remains at a similar potential during fault conditions.
The size of Bonding Conductors that shall be employed is give in Section 14.3.
of the local substation Earth Electrode Resistance can be utilised that will provide compliance with
voltage limits for Step and Touch Potentials. The resistance specified for each case is termed “Target
Resistance”.
The Target Resistance is the measured resistance of the buried Earth Electrode system which has
been installed at the secondary substation being considered. This is the resistance without any
Network Contribution. (Section 10.9 describes the effect of Network Contribution which may be
provided from interconnected substations cables etc.)
This approach is intended to minimise calculation effort, based on normal (typical) scenarios. By
employing the Target Resistance approach, the local HV Earth Electrode system for the substation
shall have a sufficiently low resistance to ground to ensure reliable operation of the circuit protection
and to limit the EPR (and Touch and Step potentials) to acceptable levels. This technique is useful as
it is a readily understood parameter that can be achieved and tested by installers of the Earthing
System.
Once the HV cable sheaths / screens are connected to the substation local Earth Electrode, the
overall substation HV earth resistance will be reduced because any remote Earthing Systems from
the underground distribution network contribute in parallel with the substation local Earth Electrode.
Large networks provide multiple parallel electrodes which can provide a relatively low resistance path
to earth and the Network Contribution can be significant (i.e. providing a low resistance). A
representation of how interconnected secondary and primary substations (with parallel connected
Earth Electrodes) provide a Network Contribution that results in a lower overall HV network earth
resistance is shown in Figure 6.
In case of pole-mounted installations, it can generally be assumed that there will be no Network
Contribution and consequently no reduction in the overall HV network earth resistance. Therefore,
the EPR is calculated from the local Earth Electrode resistance only (i.e. the local Earth Electrode
system installed at that particular pole-mounted substation). This can also be the case for ground-
mounted substations which are fed from overhead line networks and depends if other secondary
substations are connected to the same section of HV cable as the substation being considered.
In a GES, the ground is saturated with metallic electrode contributions in the form of LV and HV
earthing systems, metallic cable sheaths or bare conductors (e.g. pipes) laid direct in soil. In such a
system, the soil surface potential will rise in sympathy with that of bonded steelwork under fault
conditions. The equivalent Earthing System created by the interconnection of local Earthing Systems
ensures that there are no dangerous Touch Potentials. Essentially this is the premise of Network
Contribution.
Networks within a GES by definition operate with combined HV /LV Earthing Systems.
i. Substations feeding city centre or densely built up areas with distributed low and high voltage
Earthing Systems.
ii. Substations feeding suburban area with many distributed Earth Electrodes interconnected by
protective conductors of low voltage system.
iii. Substation with a large number of nearby substations.
A representation of a GES is shown in Figure 7, where it can be seen that there is a large urban area
with multiple substations (and associated Earth Electrodes) interconnected by underground cables
offering a low resistance Network Contribution.
Section 10.9 describes how Network Contribution is considered and explains the impact of
interconnected primary and secondary substations. Table 8 gives typical criteria for networks which
can be considered a GES.
This section outlines what values of Earth Fault Current that shall be used when designing an
Earthing System. These are summarised in Table 1 and explained in detail in the relevant sub
sections.
Document
Design Criteria Earth Fault Current and duration
section
Functional Requirements
Rating of HV Earthing Maximum HV System Earth Fault Current (Design)
11.1
Conductors and HV Earth Backup Protection operation time of 3s
Electrodes
Safety Requirements Ground Return Current (IGR) based on % of maximum Earth
Calculation of EPR Levels Fault Current calculated for faults at the node point for
11.2
for Touch and Step secondary substation.
Potentials Normal Protection operating time of 1s
The Earthing System shall remain intact and be able to pass the maximum Earth Fault Current at any
fault location back to the system neutral. The design of the Earthing System shall ensure that the
passage of this Fault Current does not result in any thermal or mechanical damage to conductors or
insulation and facilitate correct operation of source circuit-breaker. This is the functional requirements
of an Earthing System.
Additionally, the Earthing System shall be able to pass Earth Fault Current whilst maintaining Touch
Potentials and Step Potentials within the permissible limits defined in sections 12.1.4 and 12.1.5. This
is the functional requirements of an Earthing System.
All above ground HV Earthing Conductors and buried HV Earth Electrodes shall be capable of
carrying the maximum HV System Earth Fault Current (Design), based on the Backup Protection
operation time, without any damage (i.e. the design shall take account of possible failure of the
primary protection system). The HV System Earth Fault Current (Design) levels that shall be used
when selecting the rating of HV Earthing Conductors are given in Table 2.
The buried Earth Electrode shall retain its functional properties at all times (i.e. both its current
carrying capability and its value of resistance to earth). For these reasons, the temperature rise of the
Earth Electrode and the density of current dissipation to the soil, during the passage of fault current,
needs to be considered. Thermal requirements are satisfied by appropriate choice of conductor
material and cross-sectional area. Surface current density requirements are satisfied by ensuring
sufficient surface area of the buried Earth Electrode.
Table 2– HV Earth Fault Current (Design) levels used to calculate size of HV Earthing/Bonding
Conductors and Earth Electrodes
Notes:
i. At ground-mounted secondary substations, the HV Earthing Conductor and buried HV Earth Electrode
shall be able to withstand the HV System Earth Fault Current (Design) level of 13.1 kA for a duration of
3 seconds. This shall include rural and urban locations.
ii. At pole-mounted secondary installations, a HV System Earth Fault Current (Design) level of 4 kA for a
duration of 3 seconds shall generally be employed for the vast majority of pole-mounted sites in SPEN.
This is based on these largely being situated in rural locations with low fault levels and the relatively
large impedance on overhead line conductors. The Design Engineer shall calculate the fault level at the
location to determine that fault level does not exceed this value.
iii. In cases where pole-mounted secondary installations are installed close to Primary Substations or at
locations where the Earth Fault Current may exceed 4 kA. In which case, the HV System Earth Fault
Current (Design) of 8 kA shall be employed.
11.2 Safety requirements (Calculation of EPR for Touch Potentials and Step Potentials)
An effective earthing system is essential to ensure the safety of persons in, and close to substations,
and to minimise the risk of danger on connected systems beyond the substation boundaries. The
most significant hazard to humans is that sufficient current may flow through the heart to cause
ventricular fibrillation. The basic criteria adopted in this specification for the safety of people are those
laid down in BS EN 50522.
The design of the Earthing System shall comply with the safety criteria (Touch and Transfer
Potentials) which are a function of Earth Fault Current and fault duration.
Note: This is not the same as the HV System Earth Fault Current (Design) levels used to
calculate the rating of HV Earthing Conductors and Earth Electrodes.
A conservative approach is to apply the maximum single-phase or three-phase fault level (whichever
is the highest) at the source Primary Substation as published in SPEN’s LTDS. Alternatively, at sites
remote from the source Primary Substation, the fault level calculated at the secondary substation site
may be used. In this case, a margin should be added to allow for future changes without detailed
assessment (e.g. typical 15% increase, unless more accurate information is available).
The fault duration used when considering acceptable EPR levels, shall be the Normal Protection
operating time of 1 s, rather than slow Backup Protection operation clearance time of 3 s. This is in
accordance with guidance given in ENATS 41-24 to meet safety criteria.
The remainder of Earth Fault Current will return through soil to the neutral connection at the primary.
Further guidance is given in ENA EREC S34. Only the component of Earth Fault Current returning to
source via the Earth Electrode into the soil is used to calculate the EPR. This called the Ground
Return Current (IGR) and is a fraction of total Earth Fault Current (IF).
For the standard earthing scenarios considered in Table 7 and Table 8 with complete underground
cable networks between primary and secondary substation, 30 % of the Earth Fault Current is
assumed to return to primary through the soil (i.e. IGR = 30 % x IF).
If any overhead line is introduced, or other measures to break sheath continuity, IGR will approach
100% of IF.
12. EPR LEVELS AND LIMITS FOR STEP AND TOUCH POTENTIALS
The design of the Earthing System must comply with the safety limits for Touch Potential and Step
Potential along with insulation withstand between different systems which will tend to restrict the
acceptable level of EPR. Where the EPR exceeds the Stress Voltage of equipment then mitigation is
required in the form of recognised specific and additional measures.
For pole-mounted transformers, the HV metalwork is placed out of reach to ensure that staff and
public are not exposed to hazardous Touch Potentials so a high EPR can be tolerated on the HV
steelwork. Additionally, the LV Earth Electrode system is separated from the HV Earth Electrode
system to avoid potentially dangerous voltages being transferred to a customer’s LV earthing
terminal.
In case of ground-mounted substations, the design of the Earthing System shall ensure that Touch
and Step Potentials are acceptable. These are ultimately some fraction of EPR. The EPR for a
secondary substation is calculated in the conventional manner by multiplying the Ground Return
Current (IGR) by the overall HV network earth resistance (RB). i.e.: EPR = IGR×RB.
The overall HV network earth resistance (RB) shall include the reduction in resistance provided by the
Network Contribution (if any) from the underground distribution network in parallel with the substation
Earth Electrode.
Touch Potential and Step Potential limits are dependent on the fault duration and hence the total fault
disconnection time including protection and circuit breaker operation. The additional foot contact
resistance presented by different types of surfaces (e.g. soil, concrete, etc.), will also affect the limits.
The fault duration used when considering acceptable EPR levels, shall be the Normal Protection
operating time of 1s, rather than slow Backup Protection operation clearance time of 3s.
Low EPR is defined in ENA TS 41-24 as an EPR less than 466 V. This is a limit imposed by various
standards and is the effective upper threshold for a Low EPR secondary substation as described in
ENA EREC S36. ENA TS 41-24 allows for a voltage transfer to LV systems of twice the permissible
Touch Potential limit. From Table 3, the permissible limit for Touch Potential is given as 233 V for 1
second faults (for a person standing on soil and wearing shoes). Thus, an EPR limit of 466 V is
acceptable for safety reasons.
In practice, this EPR would be impressed on the LV neutral/earth (distribution transformer star point).
The voltage that would be ultimately transferred to a consumer’s LV earth terminal would be less than
this, and the touch potential appearing within an installation would be even lower.
Additionally, ENA EREC S36 sets thresholds for maximum EPR to ensure that telecommunications
and other systems are not adversely impacted by substation EPR. For secondary substations (i.e.
with long clearance times), the EPR of must be limited to 430 V to be considered to be a “Cold Site”.
Otherwise special precautions must be employed.
The terms “Hot” and “Cold” have been used in the past as a convenience (on the basis that many
“Cold “sites will achieve safe step/touch limits) but do not relate directly to safe design limits for Touch
Potentials and Step Potentials in substations. Modern standards refer to High EPR and Low EPR
sites in an attempt to move away from the reliance on third party / telecommunications standards, and
so the terms are not used in this document.
SPEN has decided to utilise 430 V as a limit for Low EPR sites to provide an additional margin of
safety whilst still complying with telecoms requirements. For simplicity and interchangeability with
what is termed “Cold Sites” in ENA EREC S36, Low EPR is defined as an EPR equal to or less than
430 V in this document.
Where reasonably practicable, the EPR at ground-mounted sites shall be limited to 430 V, in which
case the HV and LV Earthing Systems can be combined.
Figure 8 - Close up of a typical HV/LV link inside LV cabinet (link in closed position)
High EPR is defined in ENA TS 41-24 as an EPR greater than twice the permissible touch potential
limit (e.g. greater than 466 V for faults of 1 s duration on soil). .
Where the EPR at ground-mounted substations is above 430 V, then the HV and LV Earthing
Systems shall be segregated.
In the case of pole-mounted installations or ground-mounted substations which are fed from overhead
lines there will be no benefit of cable sheath/screens for a proportion of Earth Fault Current to return
to the source Primary Substations. Therefore, the EPR may approach the system phase-earth
voltage. Extremely High EPR is defined in this specification as an EPR greater than 2.33 kV
An upper limit to EPR is imposed by the insulation withstand provided by insulation (and/or physical
separation) between the HV and LV Earthing Systems (i.e. Stress Voltage). This withstand capability
ensures that the LV system remains insulated from HV steelwork when the HV steelwork is raised to
an elevated potential during fault conditions. The limiting factor can be the insulation inside the LV
cabinet, transformer LV bushings, or the transformer windings themselves. The insulation on this
equipment experiences a voltage stress under HV fault conditions. See section 12.1.6 regarding
limits for Stress Voltage.
If the EPR at ground-mounted substations exceeds 2.33 kV, then the HV and LV Earthing Systems
shall be segregated.
Additional precautions shall also be taken at these sites, particularly where LV supplies are
brought into the substation. (See sections 14.5.4 and 16.2).
Touch Potential is calculated by multiplying the EPR by a % value which is based on the design of the
substation Earthing System. This % multiplier is influenced to a small degree by the depth of the
Earth Electrode and the proximity of other earthed metalwork, but for design purposes can be taken
as fixed for each layout.
SPEN Standard Earthing Arrangements with a perimeter Earth Electrode and corner electrodes is
designed to achieve a Touch Potential of 10% or less. of EPR. Therefore, if EPR is limited to 2.33 kV
(see section 12.1.2), the Touch Potential will not exceed 233 V.
The limits for Touch Potentials are set out in ENA TS 41-24 and summarised in Table 4 for standard
HV clearance times and typical surface coverings. In operational areas it can be assumed that
persons are wearing shoes. Therefore, based on a 1 s clearance time, and for substations with
outdoor concrete, a maximum Touch Potential of 233 V is appropriate.
The limits for Stress Voltage are based on the insulation withstand of the HV and LV equipment
employed in the substation. The insulation withstand levels of this equipment must be adequate to
ensure that, in event of a High EPR, the insulation does not breakdown causing the EPR on the HV
Earthing System to be transferred to the LV Earthing System.
For ground-mounted substations where the HV and LV Earthing Systems have been segregated, the
EPR will generally not exceed 2.33 kV. (See section 12.1.4). In this case, it is unlikely that the Stress
Voltage limits will be exceed.
For pole-mounted substations and in some ground-mounted substations with Extremely High EPR,
the EPR (and consequently the Stress Voltage imposed on the insulation of HV and LV equipment)
may approach the system phase-earth voltage (i.e. 6.35 kV for 11 kV system). The Design Engineer
shall ensure that the equipment employed in these installations is suitable for this application.
The typical equipment that may be exposed to a Stress Voltage in event of an Earth Fault at a
secondary substation and the insulation withstand limits that apply to his equipment is listed below
ducts. In some special circumstances (e.g. LV supplies to High EPR sites) additional ducts
may be required.
v. The electrical installation used for building services and auxiliary supplies. The LV
electrical installation forming part of the building services/ auxiliary services in substations
(e.g. heating, lighting, battery charger supplies etc.) shall be designed in accordance with BS
7671. BS 7671 specifies a stress voltage of 1.2 kV for such equipment.
This section describes the procedure to be used when carrying out a design of a secondary
substation Earthing System.
The design of the Earthing System for ground mounted equipment shall ensure that Touch and Step
Potentials are kept within acceptable limits. The Touch Potentials (based on a % of EPR have been
pre-calculated for SPEN Standard Earthing Arrangements (see section 14). So, provided certain
conditions are met and a pre-determined ‘Target Resistance’ value is employed, then this will ensure
Step and Touch Potentials are kept within permissible limits.
The procedure is appropriate for the majority of situations. However, at sites with extremely high fault
levels, overhead line sections, small Network Contribution or high soil resistivity can be particularly
onerous so may require an extensive and disproportionately expensive Earthing System. In such
cases, the more detailed approach for specific designs as outlined in section 22 shall be applied.
The flowcharts make reference to six considered scenarios described in section 13.6. It is expected
that the majority of normal (typical) installations will fit into these categories. Those which do not meet
relevant criteria will need more detailed assessment on an individual basis.
Figure 10 – Earthing design process –Substation fed via underground cable from primary substation
Figure 11 – Earthing design process–Substation fed via section(s) of overhead line from primary
substation
i. Choose a SPEN Standard Earthing Arrangement from section 14.5 based on the
standard earthing scenarios (location, fault levels and Network Contribution) given in
Table 8. (Ideally a scenario to achieve a Low EPR should be selected if conditions permit
this.)
ii. Select a Target Resistance of 10 Ω for the HV Earth Electrode and 20 Ω for the LV Earth
Electrode.
iii. Determine the extent to which a Standard Earthing Arrangement needs to be augmented
with additional Earth Electrodes.
i. Choose a SPEN Standard Earthing Arrangement from the types specified in section 14.6
based on the standard earthing scenarios (location, system fault levels and Network
Contribution) given in Table 8.
ii. Select a Target Resistance of 20 Ω for the HV Earth Electrode and 20 Ω for the LV Earth
Electrode.
iii. Ensure the HV Earth Electrode is installed (as far as reasonably practicable) away from often
frequented livestock areas.
However, in many cases a conservative estimate can be made to expedite the design process. This
section describes typical network scenarios which may provide the levels of Network Contribution
required to meet the safety requirements for Touch Potential limits.
The Design Engineer shall check the effective area of the network using cable records/ maps etc. In
areas where the soil resistivity is high (e.g. sand/ slate etc.) then the assumptions taken in the
standard earthing scenarios in Table 8 may not be applicable and it may not be possible to utilise a
Standard Earthing Arrangement.
Table 5 shows the maximum Network Contribution (i.e. that providing the lowest Earth Resistance
value) that may be expected based on particular soil types and provided that the radius of the area
exceeds the values given in Table 5.
Network
Effective Contribution
Soil Applicable
area Minimum
Application area Soil type resistivity scenario in
radius earth
(Ωm) Table 8
(m) resistance
(Ω)
Large urban area Loam / Chalk
100 1000 0.100 (1)
(e.g. City/large town) / Clay
Sand, Gravel,
Town 300 1500 0.170 (2)
Clay mix
Rural Area
(underground cable Loam/Chalk 100 <100 0.96 (3)
supply)
Rural Area
Sand, Gravel,
(underground cable 300 400 0.96 (3)
Clay Mix
supply)
Rural Area
(overhead line Loam/Chalk 100 200 0.62 (4)
supply)
Rural Area
Sand, Gravel,
(overhead line 300 500 0.62 (4)
Clay Mix
supply)
NOTES
“Underground cable supply” requires that the secondary substation is fed from a source primary
substation with underground cable without any intermediate overhead line sections.
Maximum Network Contribution results is a lower Earth Resistance
Measurement of Network Contribution recommended if network radius or soil resistivity is not
sufficient to achieve required earth resistance.
Different values of network area radii are given is section 22 for corresponding values of soil
resistivity. It can be seen that for denser rural networks with larger length of underground cables (i.e.
larger radius) higher values of soil resistivity can be tolerated. The Design Engineer shall check the
radius of the network and soil resistivity to ensure that the specified Target Resistance can be
employed.
For other intermediate values it will be necessary to consult an Earthing Specialist or to commission a
measurement of network resistance to confirm expectations.
Effective Network
No of No of Applicable
Area Contribution
Application area primary secondary scenario in
Radius Minimum Earth
substations substations Table 8
(m) Resistance (Ω) i)
Large urban area
3 150 1000 0.100 i) (1)
e.g. City/large town
Town 1-2 ii) 100 2000 0.170 i) (2)
Rural Area
(underground cable 1 i) 20 2000 0.96i) (3)
supply)
Rural area
(overhead line 0 30 500 0.62 i) iii) (4) iii)
supply)
NOTES
i. Network Contribution shall be determined by measurement or special assessment
ii. Close in primary substations may increase the applicable fault level.
iii. Network Contribution for scenario 4) relies on PILC cable network providing electrode effect
Target Resistance Ω 10 10 10 10 10 20
The earthing designs take cognisance of the installation practice using plastic sheathed cables
compared to legacy lead sheathed cables to meet the safety requirements. The EPR has been
estimated for the standard earthing scenarios described based on fault current at site and overall
earth resistance (see Table 7).
It is expected that the majority of typical installations will fit into these categories and therefore
Standard Earthing Arrangements can be employed. Where there is uncertainty or situations where
the basis of design is not applicable then specific earthing designs conducted by an Earthing
Specialist shall be conducted.
This section provides detailed arrangements and layouts for Standard Earthing Arrangements that
shall be employed in SPEN.
The Standard Earthing Arrangements have been developed to cover a range of typical ground-
mounted substations and pole-mounted installations used in SPEN. There will be some situations
where standard arrangements are not suitable, and it is the responsibility of the Design Engineer to
exercise a degree of judgement, and to seek help from an Earthing Specialist if there is any doubt that
the use of the Standard Earthing Arrangement is not appropriate at that site.
The Standard Earthing Arrangements have a known (pre-assessed) resistance in a given soil type
(see section 21). Where this resistance exceeds the Target Resistance required, it will be necessary
to add additional Earth Electrodes.
If it is particularly difficult to achieve the Target Resistance at a site due to particularly onerous ground
conditions or installation is not practicable, the design shall be refined using detailed parameters.
This shall follow the approach provided in ENA EREC S.34 (or Annex 2) and may require advice of an
Earthing Specialist.
The size of Earthing Conductors detailed allow for a maximum temperature rise of 250°C and are
appropriate for bolted connections. These are based on slow Backup Protection operation. All main
items of plant that may be subjected to HV Earth Fault Current (e.g. transformers, HV switchgear, HV
Metering Units, HV cable screens/sheaths etc.) shall be connected to the substation Main Earth
Terminal using suitably rated Earthing Conductors as described in Table 9. This may be achieved by
using a fully rated single conductor or duplicate conductors.
The minimum size of HV Earthing Conductors used in all ground-mounted secondary substations
shall be as given in row (1) in Table 9 based on being able to carry the Earth Fault Current (Design)
level of 13.1kA for a duration of 3 seconds.
The minimum size of HV Earthing Conductors used at pole-mounted secondary installations is based
on the HV System Earth Fault Current (Design) level applicable to the site (see section 11.1). A level
of 4 kA for a duration of 3 seconds can be employed for the vast majority of pole-mounted sites in
SPEN.
HV Earthing Conductors/
Bonding Conductors
HV Earth Fault Fault
Situation PVC covered Bare
Current (Design) duration
copper Copper
conductor tape
(1) Ground-mounted 13.1 kA 3s 120 mm2 40 x 4 mm
(2) Pole-mounted 8 kA 3s 70 mm2 N/A
(3) Pole-mounted 4 kA 3s 35 mm2 N/A
LV Earthing Conductors
LV cable
Situation PVC Insulated
size
Copper conductor
Ground-mounted N/A 70 mm2
185 mm2
Pole-mounted 70 mm2
(or larger)
Pole-mounted Up to 95 mm2 35 mm2
All other ancillary equipment (e.g. control units, RTUs, battery chargers etc.) shall be earthed to the
Main Earth Terminal using a minimum of 16 mm 2 insulated copper earthing conductor (or equivalent).
The purpose of such bonds is to form an equipotential zone, i.e. to eliminate hand-to-hand voltages,
but not to carry significant current.
Small extraneous parts not likely to attain any rise in potential (e.g. small window frames, handrails
etc.) need not be bonded at secondary substations.
HV Earth Electrodes have sufficient thermal rating to be able to carry fault currents up to the value of
HV Earth Fault Current (Design) for that system. The Earth Fault Current (Design) levels that shall be
used to determine the size of conductors used for Earth Electrodes to be used at secondary
substations are given in Table 11.
The HV Earth Electrodes used at ground-mounted substations shall have a sufficient thermal capacity
to be able to withstand the HV System Earth Fault Current (Design) level of 13.1 kA for 3s. This may
be achieved by using a fully rated single conductor. Alternatively, duplicate conductors can be used
(e.g. where a ring of perimeter Earth Electrodes are buried around the substation as shown in Figure
12 and Figure 14 and the size of single conductor can then be reduced accordingly.
The size and rating of buried LV Earth Electrodes that shall be utilised at secondary substation is
detailed in Table 12.
LV Earth Electrodes
Situation LV cable size Bare copper Earth rods Copper
conductor clad steel
Ground-mounted N/A 70 mm2 16 mm diameter
Pole-mounted 185 mm2 70 mm 2 16 mm diameter
(or larger)
Pole-mounted Up to 95 mm2 32 mm2 16 mm diameter
14.5.1 Overview
The Earthing System arrangement for ground-mounted substations is based on a buried Earth
Electrode system which includes a horizontal ring of bare copper conductor (“perimeter electrode”)
encapsulating all exposed metalwork to provide an area of lower Touch Potentials within the
substation. The perimeter electrode shall be installed at a depth of 0.6 m or greater to ensure it
remains in stable (wet/damp) soil.
The horizontal ring is supplemented by two earth rods located at the front or rear of the substation; or
four where necessary, located at each corner, primarily to reduce earth resistance. These rods may
be driven deeper, and extended, to reduce the substation resistance.
An Earth Electrode shall also be installed under the operator position (“Earth mat”) just below the
surface of the ground such and arranged that the HV switchgear can only be operated while standing
above the Earth Electrode.
In the Standard Earthing Arrangements, where the substation enclosure is non-metallic, the perimeter
electrode may be installed closely around the edge of the foundation. Special situations, where the
substation enclosure is metallic, (e.g. a pad mount substations) are not covered by the Standard
Earthing Arrangement and in these situations, the horizontal ring must be offset from the exposed
metalwork by up to 1 m to control Touch Potentials for the public.
Internal connections shall connect from the perimeter Earth Electrode to all items of plant. These
internal connections function as an Earthing Conductor if not in contact with soil, or an Earth
Electrode otherwise.
Touch Potentials may be further reduced by connection of horizontal reinforcing bars in the foundation
and by an additional loop of horizontal Earth Electrode in front of the substation in the areas where
doors open, and an operator is most likely to be present.
The main parameters that can be varied by the Design Engineer are the length of earth rods, and the
extent of any additional Earth Electrodes (if any) installed outside the footprint of the substation. No
other variations of the Standard Earthing Arrangements are permitted.
ALL SPEN standard ground-mounted designs achieve a Touch Potential of 10% or less of EPR. See
Table 13. The maximum EPR for these must in any case not exceed 2.33 kV, but will usually be
limited to lower values dependent on floor/ground covering
For substations with High EPR (e.g. Scenario 5 from section 13.6), or otherwise where the EPR
cannot be limited to 2.33 kV, there may exist a Touch Potential hazard if the steelwork (or anything
connected to it) can be touched from outside the substation. The highest risk will most likely be
members of public. In these situations, all equipment shall be housed within a GRP enclosure to
completely eliminate this risk to the public. The risk to operators with access inside the GRP
enclosure will be managed by the design of the Earthing System.
Standard GRP 10 23
Small Brick-built 10 18
Table 13 Touch and Step Potentials for Standard Secondary Substation Earthing Arrangements
Where the LV and HV Earthing Systems require to be segregated then separation between the HV
and LV Earthing Systems shall be provided by installing an insulated LV Earthing Conductor between
the substation and LV Earth Electrode system.
At High EPR, sites a minimum separation of 8 m in soil shall be provided between the HV and LV
Earthing Systems. At Extremely High EPR sites, a minimum separation of at least 20 m in soil shall
be provided. The insulated LV Earthing Conductor shall be kept separate from HV cables and HV
Earth Electrodes In line with normal practice, it is usual to route the LV Earthing Conductor in the
same trench as outgoing LV cables.
If separation cannot be achieved, the site shall be made Low EPR by installing additional Earthing
Electrodes as required. Alternatively, an earthing study shall be carried out to determine if a reduced
separation in soil is sufficient to prevent transfer of potentials from the HV Earthing System to the LV
Earthing System.
The Standard Earthing Arrangements for ground-mounted substations is based on the following
design criteria:
i. Touch Potentials and Step Potentials shall be below permissible limits (refer to sections
12.1.4 and 12.1.5 ).
ii. The EPR shall be limited to 430 V (see section 12.1.1) where reasonably practicable. Sites
which satisfy this requirement are defined as having a Low EPR. In which case, the HV and
LV Earthing Systems are combined. It is permitted to install a HV Earthing System only in
this case (see Figure 12). The HV/LV Earthing link inside the LV cabinet shall be closed.
iii. Where the EPR cannot be limited to 430 V, then reasonable steps shall be taken to limit the
EPR to 2.33 kV (see section 12.1.2). These sites are considered to be High EPR sites and
the HV and LV Earthing Systems shall be segregated in soil by at least 8 m. The HV/LV
Earthing link inside the LV cabinet shall be opened.
iv. In some exceptional situations (e.g. ground-mounted substations fed from overhead lines with
no Network Contribution), it may not be practicable to limit the EPR to 2.33 kV (see section
12.1.3). These sites are considered to be Extremely High EPR sites. In these cases, the HV
and LV Earthing Systems shall be separated in soil by at least 20 m. The HV/LV Earthing
link inside the LV cabinet shall be opened. A special substation design shall be chosen
capable of operating with an EPR up to 6.33 kV. Refer to (see section 14.5.4. for substation
design measures that shall be taken under these circumstances.
v. The HV Earth Electrode Resistance shall not exceed 10Ω. This value is necessary to provide
reliable and fast protection operation during Earth Faults.
vi. The LV Earth Electrode Resistance shall not exceed 20 Ω in accordance with EART-01-002.
vii. Earthing Conductors and Earth Electrodes shall be of sufficient size to safely carry the
maximum Fault Current (Design) of 13.1 kA for 3 s. (See sections 11.1 and 14.1).
14.5.2 GRP and brick-built substation with combined HV and LV Earthing Systems
The Standard Earthing Arrangement for GRP and brick-built unit substations with combined HV and
LV Earthing Systems (i.e. Low EPR site) is shown in Figure 12 and Figure 13. This is the usual and
preferred arrangement for urban areas (e.g. GEP locations).
The two HV earth rods locations shown may be varied to be connected at any two of the four corners
as required to suit site constraints (e.g. to avoid, rock, concrete etc. or to avoid having to drive deep
earth rods in locations where there may be buried services).
For this arrangement it is permissible to install an HV Earthing System and HV Earth Electrode
system only.
14.5.3 GRP and Brick Built Substation with segregated HV and LV Earthing Systems
The Standard Earthing Arrangement for GRP and brick-built unit substations with segregated HV and
LV Earthing Systems (i.e. High EPR site) is shown in Figure 14 and Figure 15. This arrangement
shall be employed where it is not possible to achieve a Low EPR.
The two HV earth rod locations shown may be varied to be connected at any two of the four corners
as required to suit site constraints (e.g. to avoid, rock, concrete etc. or to avoid having to drive deep
earth rods in locations where there may be buried services).
A separate LV Earth Electrode system segregated from the HV Earth Electrode system by at least 8m
(in soil) using an insulated cable shall be installed and connected to the LV neutral bar inside the LV
cabinet.
Figure 12 – Earthing Arrangement for GRP/ brick substation – Combined HV and LV Earths
Figure 13 - Earthing Arrangement for GRP/ brick substation – Combined HV and LV Earths (Front
Elevation view)
Figure 14 – Earthing Arrangement for GRP/ brick substation – Segregated HV and LV Earths
Figure 15 - Earthing Arrangement for GRP/ brick substation – Segregated HV and LV Earths (Front
Elevation view)
14.5.4 Special GRP ground-mounted substation for sites with an Extremely High EPR
The arrangement described in this section shall be used where it is not practicable to limit EPR to
below 2.33 kV (i.e. Extremely High EPR sites). It provides control of Touch Potentials to within
permissible levels and provides a minimum insulation withstand level of 7 kV between HV and LV
Earthing Systems. Only specifically approved plant type tested to a rated insulation withstand voltage
of at least 7 kV can be used in this application.
The Standard Earthing Arrangements described in the previous section may not be suitable for
application at High EPR sites and the Design Engineer shall consult an Earthing Specialist to ensure
that the design of the Earthing System is appropriate to control Touch and Step Potentials within
permissible limits. Soil resistivity studies will be required to determine the most effective Earthing
System design.
The following precautions shall also be taken at Extremely High EPR Sites:
i. A GRP substation enclosure shall generally be used in the first instance since the use of this
insulated enclosures significantly reduces the risk to public from being exposed to dangerous
Touch Potentials.
ii. Where it is not possible to utilise a GRP enclosure (e.g. due to planning constraints) then a
detailed earthing study shall be conducted by an Earthing Specialist to demonstrate that the
public will not be exposed to dangerous Touch Potentials.
iii. A dense metallic mesh bonded to HV switchgear shall be installed to provide an equipotential
zone (stance mat) around switchgear to control Step Potentials and Touch Potentials.
iv. All equipment inside the substation shall be bonded together.
v. The LV Earthing System shall be segregated from the HV Earthing System.
vi. Where LV supplies are installed within the substation then special precautions shall be
employed to ensure that the Stress Voltage of equipment inside the substation is not
exceeded which result in transfer of High EPR onto the LV network. (See section 12.1.6).
vii. Metallic LV street furniture in close proximity to the substation and HV Earth Electrode may be
exposed to hazardous EPR potentials which may present a danger to the public. Where
street furniture is located further than 20 m away from the HV Earth Electrode, the risk of
transferring hazardous EPR potentials is considered to be low. An earthing study shall be
carried out where existing street furniture is situated within 20 m of the HV Earth Electrode to
determine risk of public being exposed to hazardous EPR potential risk and appropriate
mitigation to control this risk. It is recognised that SPEN may not be in control of installation.
viii. Where lead sheathed cables are installed with 20 m of the HV Earth Electrode, an
assessment shall be undertaken to determine if this can lead to the transfer of hazardous
Transfer Potentials and appropriate measures shall be undertaken to control this risk.
ix. All LV cables and LV Earthing Conductor connecting to the LV Earth Electrode shall be PVC
covered and laid in plastic ducts for 20 m radius from substation.
The SPEN and Customer HV Earthing Systems shall be designed to meet the fundamental
requirements for an Earthing System as described in section 11.1 of this specification and shall satisfy
the requirements of ENA TS 41-24. These requirements shall be met independently of each other.
The Earthing Systems, their components and bonding conductors shall be capable of distributing and
discharging the fault current without exceeding thermal and mechanical design limits based on
backup protection operating time.
If this is satisfied, then the two Earthing Systems shall be connected together via two designated
connections that are duly labelled. Note that, if the combined Earthing System results in a High EPR
then the associated precautions shall be applied to both the SPEN and Customer sites. (e.g.
segregation of LV Earth/Neutral Earthing System at the customer substation, precautions to control
Transfer Potentials onto other metallic services, etc.).
Where it is not practicable to achieve the safety requirements for Touch Potential and Step Potential
limits, the SPEN Earthing System, the substation may rely on the Customer’s Earthing System,
providing that it is constructed to a similar standard to SPEN requirements. If the Customer’s
Earthing System is modified or removed in future the Earthing System of the SPEN substation shall
be reviewed.
14.6.1 Overview
The guidance in this section is based on the use of wood poles. Earthing of overhead equipment
using metallic poles, masts or towers is not covered by this specification and will require an
assessment by an Earthing Specialist.
At pole-mounted installations, it is not practicable to achieve Low EPR levels (see section 12.1.1).
Therefore, all HV steelwork shall be sited out of reach. Additionally, HV Earthing Conductors shall be
insulated and provided with mechanical protection for a minimum height of 3 m or above the height of
the anti-climbing device (whichever is greater). The Earthing Conductors shall also be insulated for a
minimum of 1 m below ground level to avoid damage from ploughing etc.
It is also a standard requirement that HV and LV Earthing Systems shall be segregated at all pole-
mounted substations. These precautions ensure that Touch Potential is less of an issue, therefore
the HV Earthing System serves three main purposes:
The HV Earth Electrode resistance (i.e. resistance from HV steelwork to the general mass of earth)
shall not exceed 20 Ω. Additionally, where surge arresters are installed, the HV Earth Electrode
resistance shall not exceed 10 Ω (see section 15.7). SPEN’s 11 kV network is directly earthed,
therefore a 20 Ω Earth Electrode system will allow sufficient Earth Fault current to flow back to the
primary substation to ensure the HV protection operates quickly enough. A 20 Ω earth resistance
also limits the likelihood of back flashover during lightning surges and resultant transformer winding
failure.
The HV Earth Electrode shall be installed at least 1 m below ground level to ensure as far as
reasonably practicable that Step Potentials directly above the Earth Electrode system remain below
permissible limits under Earth Fault conditions. The HV Earth Electrode may consist of bare
horizontal Earth Electrodes (i.e. bare copper conductor) laid in a trench, vertical earth rods or a
combination of the two. Sufficient Earth Electrodes shall be installed to achieve the required earth
resistance. The horizontal Earth Electrodes will be more effective where there is an underlying high
resistivity material such as rock. Vertical driven earth rods will be more effective where there is lower
resistivity material beneath the surface, e.g. wetter material below the water table.
All support steelwork and the transformer tank shall be connected using PVC insulated HV Earthing
Conductors sized in accordance with section 14.1. The HV Earthing Conductor shall be installed
down the pole and connected to a HV Earth Electrode.
All pole-mounted transformers currently being purchased by SPEN have a rated insulation withstand
voltage capability between the LV bushing and transformer tank of 7 kV in accordance with recent
SPEN specifications. This ensures that in the event of an HV fault, the resultant EPR will not be
sufficient to cause a flashover to the LV system (See section 12.1.6 covering Stress Voltage limits).
Note: Some older pole-mounted transformers may have a lower insulation withstand value of only 3
kV (see section 12.1.6 covering Stress Voltage limits. Pole-mounted transformers purchased before
2019 may have a lower insulation withstand value of only 3 kV and shall not be used unless it can be
established that the LV rated insulation withstand voltage of the transformer meets the 7 kV
requirement.
The LV Earth Electrode shall be installed a minimum of 20 m from the HV Earth Electrode (either by
installing the LV Earth Electrode at the first pole away from the pole-mounted transformer (see Figure
16) or by using an insulated conductor between the pole and the LV Earth Electrode system (see
Figure 17). This increased separation distance compared to ground-mounted substation reflects the
possible occurrence of a very high EPR being imposed on the pole-mounted steelwork and HV Earth
Electrodes as a result of an Earth Fault. Traditional practice in SPEN has been to provide an 8 m
separation, but a separation distance of 20 m is now employed based on computer modelling to
demonstrate that acceptable limits for LV transfer are not exceeded for typical soil resistivity
conditions.
If PILC type LV cables are installed on the pole, these usually cannot be isolated from earth and so it
is necessary to ensure that the HV Earth Electrode is sited more than 20 m from the pole and
insulated within this distance.
Consideration shall be given the effect of Step Potentials on horses and other livestock. Where
practicable the HV Earth Electrodes shall be located away from areas of high animal usage (e.g.
water troughs, milking parlours etc.). Where this is not possible a more detailed assessment of Step
Potentials and/or risk assessment is required by an Earthing Specialist.
The Standard Earthing Arrangements for pole-mounted is based on the following design criteria:
i. All pole-mounted substations shall be designed with separate HV and LV Earthing Systems
and shall be separated by at least 20 m.
ii. The HV Earth Electrode earth resistance shall not exceed 20 Ω in order to provide reliable
protection operation. (Where surge arresters are installed, the HV Earth Electrode earth
resistance shall not exceed 10 Ω).
iii. The LV Earth Electrode earth resistance shall not exceed 20 Ω to comply with ENA
Engineering Recommendation EART-01-002.
iv. The HV Earth Electrode and Earthing Conductors shall be of sufficient size and surface area
to safely carry fault current at that site (see sections 14.1 and 14.4).
v. EPR on pole-mounted steelwork can approach system phase-to-earth voltage, which in some
situations might be close to 6.33 kV. All LV equipment shall be suitably insulated and
separated from HV equipment to prevent flashover during HV fault conditions.
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1.
The separation between the buried HV and LV Earth Electrodes is effectively achieved by locating the
LV Earth Electrode at the base of the first LV pole positioned greater than 20 m away from the
transformer pole. The LV Earth Electrode shall be connecting to the overhead line neutral conductor
using an insulated Earthing Conductor with minimum cross section of 35 mm2.
* NOTE: HV Earthing Conductor and buried Earth Electrode at sites where HV fault level exceeds 4 kA shall be
70 mm2 (see section 14.1 and 14.4).
The LV neutral terminal of the transformer shall be connected to earth using an insulated LV Earthing
Conductor installed on the opposite side of the pole to the HV Earthing Conductor. (Where a H-pole
is used the HV and LV Earthing Conductors shall be installed on different poles). The insulated LV
Earthing Conductor shall be extended underground for a minimum of 20 m separation from the HV
Earth Electrode and connected to an LV Earth Electrode of bare copper with a maximum earth
resistance of 20 Ω.
The LV Earth Electrode system may be installed in the same trench as the LV cable and, in a similar
way to the HV Earth Electrode, a combination of horizontal and vertical electrodes may be used to
provide the required earth resistance of 20 Ω.
* NOTE: HV Earthing Conductor and buried Earth Electrode at sites where HV fault level exceeds 4 kA shall be
70mm2 (see section 14.1 and 14.4).
The LV Earthing Conductor shall have a minimum cross section of 35mm 2 for LV cable sizes up to 95 mm2. For
pole-mounted substations with LV cable sizes of 185 mm 2 or above, an LV Earthing Conductor with a minimum
cross section of 70 mm2 shall be installed. (See section 14.2).
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1.
The HV Earthing Conductor shall have a minimum cross-section of 70 mm2.
To ensure the effectiveness of the surge arresters, the HV Earthing Conductor shall be installed as
straight as possible down the pole avoiding sharp bends to a HV Earth Electrode with maximum earth
resistance of 10 Ω in accordance with section 15.7.
The Standard Earthing Arrangement for a hook stick operated ABSD and HV cable is shown in Figure
22.
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1
and shall have a maximum earth resistance of 10 Ω in accordance with section 15.7 The HV Earthing
Conductor shall have a minimum cross-section of 70 mm2.
In accordance with section 15.9, the HV Earth Electrode shall be installed at least 5 m away from the
pole at a location where the Operator will not be standing when carrying out any live HV switching
operations.
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1
and shall have a maximum earth resistance of 10 Ω in accordance with section 15.7. The HV
Earthing Conductor shall have a minimum cross-section of 70 mm2.
In accordance with section 15.9, the HV Earth Electrode shall be installed at least 5 m away from the
pole at a location where the Operator will not be standing when carrying out any live HV switching
operations.
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1
and shall have a maximum earth resistance of 10 Ω in accordance with section 15.7 The HV Earthing
Conductor shall have a minimum cross-section of 70 mm2.
In accordance with section 15.9, the HV Earth Electrode shall be installed at least 5 m away from the
pole at a location where the Operator will not be standing when carrying out any live HV switching
operations.
14.6.8 Hook stick operated Air Break Switch Disconnector (ABSD) and HV cable
The Standard Earthing Arrangement for a hook stick operated ABSD and HV cable is shown in Figure
22.
The HV Earth Electrode and HV Earthing Conductor shall be installed as described in section 14.6.1
and shall have a maximum earth resistance of 10 Ω in accordance with section 15.7 The HV Earthing
Conductor shall have a minimum cross-section of 70 mm2.
In accordance with section 15.9, the HV Earth Electrode shall be installed at least 5 m away from the
pole at a location where the Operator will not be standing when carrying out any live HV switching
operations.
15.1 General
Section 14 describes the Standard Earthing Arrangements and associated reference drawings. This
section provides additional guidance on construction aspects.
Where the soil is known to be acidic or alkaline (pH outside of the range 6 – 10) or otherwise
corrosive to copper then the electrode shall be surrounded with 150mm of imported neutral soil.
Joints shall be made using an Approved method. These are shown in Table 14.
The standard approach in SPEN is to use three single-core cables to connect into each cable box.
Each screen is connected via a bolted lug to a small earth bar inside the cable box, thus providing a
robust connection. This arrangement differs from that used by many other DNOs and IDNOs (and
which may be offered by switchgear manufacturers) where a single bolted connection is used for the
bunched sheaths. It is important that the more secure SPEN arrangement is used because the 11 kV
system in SPEN is directly earthed and Earth Fault Current can approach 13.1 KA unlike other UK
DNOs.33 Standard single bolted connections are not permissible for SPEN designs as they do not
offer the robustness and reliability necessary for SPEN’s solidly earthed network.
Due to the more onerous installation and ongoing maintenance requirements metallic fences should
be avoided where possible at High EPR secondary substation sites.
At High EPR sites an additional horizontal Earth Electrode ring shall be installed around the outside of
the fence and connected to the substation HV earth and fence. Ideally this should be offset from the
fence by between 0.5 m and 1 m if space permits. No third-party metallic fences shall be connected
to the substation fence unless continuity is broken, e.g. via a 2 m section of non-metallic fence or a
‘floating’ metallic fence section mounted either end on stand-off insulators.
The insulated HV Earthing Conductor shall be installed as straight as possible down the pole avoiding
sharp bends. NOTE: where an operator may carry out HV switching operations at that pole (see
section 15.9), the HV Earth Electrode shall be installed 5m away from the pole.
At pole-mounted installations with surge arresters, the HV Earthing Conductor shall have a minimum
cross section of 70mm 2.
15.8 Pole-mounted equipment with operating mechanisms accessible from ground level
Equipment such as PMARs, sectionalisers, and ABSDs with a low level earthed metallic control box
or switch mechanisms can present hazardous Touch and Step Potentials. For this reason, these
arrangements are no longer employed in SPEN and are not covered in this specification.
15.9 Pole-mounted equipment with operating mechanisms not accessible from ground level
It is generally considered that the probability of an Earth Fault occurring whilst an individual happens,
by chance, to be walking across the HV Earth Electrode at the same time, is extremely small and
therefore, in most circumstances no special precautions are required.
However, on poles with earthed equipment where an Operator may carry out HV switching operations
this may create unacceptable Step Potential hazards should this action result in an HV Earth Fault. In
such cases the HV Earth Electrode shall be installed at least 5 m away from the pole at a location
where the Operator will not be standing when carrying out any live HV switching operations.
Examples where this precaution is required include the following arrangements:
i. PMARs
ii. Soule switches
iii. Hook –stick operated ABSDs with HV cables
iv. HV fuse-units with HV cable
i. Close to areas where people may be expected to be barefoot and/or at wet locations such as
swimming pools, paddling pools, showers, schools/nurseries etc.)
ii. Close to concentrations of livestock (e.g. stables, milking parlours, pens etc.)
iii. Within 20 m of a fuel filling station.
At such sites special precautions may be justified to eliminate or minimise the risk. Such precautions
may involve careful site selection, positioning of the HV Earth Electrode in a direction away from the
area of concern or burying the electrode as deep as practicable.
Where possible, secondary substations shall not be installed near to such high-risk areas. If this is
unavoidable, then a detailed design assessment shall be undertaken by an Earthing Specialist to
optimise the location of the substation Earth Electrode to control the risk.
This includes situations where an external (i.e. remotely earthed) LV supply is brought into the
substation from the LV network or where the LV supply is taken directly from the local LV cabinet or
fuse-board. The insulation withstand of the equipment (i.e. Stress Voltage) shall be verified to ensure
that that breakdown between LV phase/neutral/earth to HV steelwork earth cannot occur internally.
Light switches, power sockets and conduits shall preferably be plastic. Alternatively, metallic light
switches, conduits and sockets shall not be installed within 2m of any metalwork bonded to the HV
Earthing system.
On LV cabinets fitted with a 13A socket, the LV isolator switch on the LV cabinet/LV fuse board
controlling the 13 A socket shall be opened and padlocked. Some older LV cabinets/fuse boards may
not be fitted with an isolator switch, and in this case, the 13A sockets shall be disconnected. If the
Design Engineer can establish by calculation that the EPR will not exceed 1.2 kV and the Stress
Voltage of the 13 A socket will not be exceeded (see section 12.1.6) then the isolator switch can be
left closed and socket can remain connected.
An isolation transformer shall be installed between the LV system and the substation building
service/auxiliary supply installation unless the Design Engineer can establish by calculation that the
EPR will not exceed 1.2 kV. SWG-03-026 provides details of isolation transformers and ratings to be
used at substations for providing building service and auxiliary supplies. Table 15 provides guidance
on rating of isolation transformer (where required) depending on EPR Level.
Secondary substations inside grid/primary substations shall not be used to supply customers.
Building or site lightning protection systems may be connected to the secondary substation HV
Earthing System providing that:
i. The lightning protection system has an independent earth resistance of 10Ω or lower (before
connection to the SPEN Earthing System);
ii. The substation is a Low EPR site.
If the above statements are not satisfied guidance shall be sought from an Earthing Specialist.
17.1 General
Measurements and inspection are required during installation and commissioning of a secondary
substation to ensure that the requirements of this specification have been met. In particular that the
earthing has been installed in accordance with the Standard Earthing Arrangement and that the
Target Resistance has been achieved.
17.2 Inspection
Following installation of the Earthing System a visual inspection shall be undertaken to check the
following aspects:
i. The standard HV Earth Electrode has been installed including horizontal ring electrode, earth
rods, additional electrode (as required), rebar connections, Main Earth Bar and equipment
connections.
ii. Ancillary metalwork bonded to Main Earth Bar including any metal doors.
iii. Correct earthing of any metallic fencing.
iv. At High EPR sites: The HV and LV Earthing Systems have been segregated and a separate
LV Earth Electrode installed.
v. At Low EPR sites: The HV and LV Earthing Systems have been combined.
vi. At Extremely High EPR site: Approved equipment, GRP enclosure and Touch/Step Potential
control measures, as described in 14.5.4.
Additionally, the value of resistance provided by the local network (i.e. Network Contribution shall be
measured by measuring the combined overall Earth Electrode Resistance (i.e. the total Earth
Electrode Resistance) of the complete installation once all HV cable sheath/screen connections have
been terminated.
It is important that the measurements are carried out using industry recognised methods and
equipment and results recorded. As a minimum, the following measurements shall be made:
Where the measured value of local Earth Electrode exceeds the design Target Resistance value,
additional Earth Electrodes shall be installed in accordance with section 23. If the measurement of
overall Earth Electrode Resistance exceeds design limits (see Table 7), then the Design Engineer
shall be consulted who shall confirm if criteria for standard earthing scenarios (and adoption of
Standard Earthing Arrangement) is still valid. Table 1
Where a Standard Earthing Arrangement is used, and typical assumptions are valid the Network
Contribution is selected from Table 5 or Table 6 and shall be recorded.
Where typical assumptions are not met, or in the case of one of the special situations described in
section 16, a report shall be retained that includes a summary of the design and calculations to
demonstrate compliance with the requirements.
For all secondary substations that will partly or fully adopted by SPEN or where SPEN staff will be
required to access, the third-party Designer shall demonstrate compliance with the general
requirements set out in this document.
The third-party Designer shall provide sufficient documented evidence for SPEN to assess
compliance prior to design approval being granted.
At IDNO sites which will be shared with SPEN (e.g. sites where SPEN own the HV RMU and IDNO
own the HV/LV transformer), the IDNO shall demonstrate that the substation Earthing System is
designed such that in both normal and abnormal conditions there is no danger to persons.
The IDNO shall confirm that the Earthing System is designed and installed to avoid damage to
equipment due to excessive potential rise and potential differences within the earthing system (Stress
Voltage), and due to excessive currents flowing in auxiliary paths not intended for carrying Earth Fault
Current.
All earthing designs shall comply with the requirements of ENA TS 41-24. The main requirements are
to satisfy Touch Potential limits, and NOT export dangerous potentials onto the LV network.
The justification below describes the Basis of Design applicable to the standard earthing scenarios
outlined in Table 8 and the Standard Earthing Arrangements described in section 14.
The basic design of secondary substations previously utilised by SPEN has been enhanced in this
specification to apply the design criteria in accordance with section 11.1 and 11.2 to develop an
earthing design that takes cognisance of the modern installation practice of using plastic sheathed
cables compared to lead sheathed cables. Previously Network Contribution was achieved through a
legacy practice of installing lead sheathed cables in contact with the surrounding soil that effectively
reduced the combined earth resistance of the substation, known as “cables with earth electrode
effect”. This effect also applies to modern cabled installations, whereby nearby substations are
conductively connected via sheaths or screens of cables as employed in polymeric distribution cables.
Whilst the majority of the network is still largely dominated by lead sheathed cables, the proportion is
reducing because plastic sheathed cables (e.g. PICAS) have been installed since 1980s. However,
new conurbations will still have a low resistance contribution from a plastic sheathed network albeit
the overall effect of nearby connected substations in parallel will be limited by the length of the
polymeric cabling and resultant impedance. Similarly, urban areas with many distributed Earth
Electrodes interconnected by the protective earth conductors of the low voltage system will also offer
a low resistance to earth. Hence, when relying on Network Contribution with a plastic sheathed cable
network then a measurement or special assessment may be required to ascertain the Network
Contribution.
The SPEN Standard Earthing Arrangements include some variants according to the local soil
conditions to ensure that tolerable Touch Potential levels are achieved using a Target Resistance and
expected Network Contribution based on a consideration of the network design. In accordance with
section 11.2 for safety requirements, significant parameters can be classified in order to determine the
EPR, and thereafter the appropriate mitigation measures can be utilised
It is expected that the majority of standard installations will fit into these categories and therefore
Standard Earthing Arrangements can be employed. Where there is uncertainty, or in situations where
the Basis of Design is not applicable, then specific earthing designs shall be conducted by an
Earthing Specialist.
The standard earthing scenarios discussed in section 13.6 are based on the Basis of Design
assumptions described below according to the applicable network configuration:
21.1 Scenario (1) - Dense large urban network (e.g. Cities and large towns) - all underground
modern cable network
For a secondary substation located within a city or large town that is connected via an all underground
cable network, the overall HV network resistance will be reduced by the Network Contribution to a
very low value. This dense large urban network is typically classified by location within 1 km of a
primary substation and connected via modern cable networks to typically three primary substations
and approximately 150 secondary substations.
This provides a Low EPR site when a 10 Ω local Earth Electrode resistance is employed.
The all underground modern cable network provides an overall HV network resistance to earth of 0.1
Ω or less (Network Contribution). This assumes an extensive lead sheathed network and a
reasonable soil model (deep uniform equivalent <= 100 Ω.m with radius 1 km or greater). Less
conductive soils will generally not provide an overall resistance lower than this even if they are larger,
although very dense interconnected networks will provide a further reduction in resistance due to the
conservative methodology used. A measurement of the network resistance should be taken if there is
doubt. If network resistance is higher, a detailed assessment shall be carried out using actual
calculated system parameters as described in section 22.
Generally, such networks are classed as Global Earthing Systems or GES, for which there is a further
reduction in Touch Potential due to the voltage smoothing effect of a distributed Earth Electrode
system. This additional benefit provides an extra margin of safety but has not been explicitly
considered /relied upon in the Basis of Design considerations.
It is assumed that the Earth Fault Current will not exceed 13.1 kA, and that only 30 % of this current
flows into the substation’s Earthing System. Connections to cable screens/ sheaths provide a reliable
connection to the existing network. For some older cable types, or very long runs, a slightly higher
proportion of current can flow via soil; but it is considered unlikely that greater than 30 % of 13.1 kA
will flow into the ground and thus contribute to EPR.
Also, it is assumed that protection will operate within 1 second. EPR will not exceed 430 V and
therefore it is safe to connect the HV and LV Earthing Systems on the basis that this is a Low EPR
site and the Touch Potential at customers’ premises will not exceed 50% of this value. A Touch
Potential of 233 V hand-to-feet is acceptable at customer premises for less than 1 second, based on
guidance in ENATS 41-24. This is informed by risk assessment based around fibrillation and makes
assumptions about footwear and floor/ground covering materials etc., and human body impedance. It
is also assumed that Step Potentials will be acceptable provided that the Touch Potential limits are
met.
The Standard Earthing Arrangement is suitable, since these all provide a Touch Potential of around
10% of EPR. (430 V x 10% = 43 V) which is well below the permissible limit for 1 second faults (233
V on soil, or 298 V on concrete / chippings). No assumptions have been made regarding ground
coverings, nor are they necessary for this EPR level.
For a radial connected substation in event of a lost/broken sheath connection, the local Earth
Electrode will be sufficient to operate protection and control Touch Potential. However, the EPR
could cause a hazard to individuals at the customer’s premises. In practice, LV cable sheaths and
other fortuitous metallic connections to the wider network will provide some additional EPR control but
may suffer damage if the resultant EPR exceeds the Stress Voltage level of the equipment. The risk
of such failures is considered acceptable (small) and justified within the industry.
It should be noted that this new design approach (using Standard Earthing Arrangements with Touch
Potential control) is an improvement over old (legacy) practice.
21.2 Scenario (2)- Smaller towns- all underground modern cable network
As per scenario (1) when the substation is located within a small town that is connected via an all
underground cable network, the overall HV network resistance will be reduced by the Network
Contribution to a low value. This urban network is classified by location within 2 km of a primary
substation and connected via modern cable networks to typically 100 secondary substations and one
primary substation.
This provides a Low EPR site when a 10 Ω local Earth Electrode resistance is employed.
As per scenario (1) when the substation is connected via an all underground modern cable network
with reliable network connections but with a reduced density / radius of surrounding network no
smaller than 1500 m.
The scenario is based on a maximum Earth Fault Current of 8 kA which is typical for sites in smaller
conurbations.
In this case a Network Contribution of at least 0.17 Ω is assumed. This requires a soil resistivity of
300 Ω.m or less, and a network radius of 1500 m or more. This also assumes a reasonably dense
network with connections radiating from the substation in various disparate directions. For sparser
networks, a soil resistivity of 100 Ω.m will be required to achieve a similar resistance. If in doubt, a
measurement should be performed.
For this scenario it is assumed that the source substation resistance is negligibly small and Ground
Return Current (IGR) will be 8 kA × 30% = 2.4 kA or less, and this will flow for less than 1 second. A
Network Contribution of 0.165 Ω or less will make the site Low EPR and practically rounding this to
0.17 Ω will not present any issues (EPR = 408 V) in terms of safety limits. The Touch Potential
around the site will remain close to 43 V under fault conditions, and transfer to the LV network will be
acceptable within premises that have appropriate PME equipotential bonding.
21.3 Scenario (3) - Rural ground-mounted substation - all underground modern cable
network
As per scenario (1) when the substation is located within a rural distribution system that is connected
via an all underground cable network, the overall HV network resistance will be reduced by the
Network Contribution. This rural network is classified by location within 2 km of a primary substations
and connected via modern cable networks to approximately 20 secondary substations.
This provides a High EPR site when a 10 Ω local Earth Electrode resistance is employed.
The design parameters here are similar to that for scenario (2) except the Network Contribution is
likely to be less (i.e. higher resistance), and the additional cost of making the site Low EPR is unlikely
to be justified (unless surrounding sites are Low EPR, and segregation cannot be achieved, in which
case making the site Low EPR may be the only viable option).
The maximum Earth Fault Current of 8 kA corresponds to a Ground Return Current of 2.4 kA,
assuming that 30% of the current flows into the ground. No reduction in fault level beyond the point of
connection is assumed (in practice the reduction may be used in design calculations; working with the
higher value provides a margin of safety).
This assumed Ground Return Current IGR produces an EPR less than 2.1 kV if the network provides a
resistance of less than 0.96 Ω and the local Earth Electrode system is less than 10Ω. Thus, a
relatively small network is sufficient to make safe on soil (Touch Potential of 10 % of EPR will be less
than 233 V despite site being a High EPR site.
It is assumed that sufficient area and/or soil type will achieve resistance as shown in Table 16 and
assumes uniform soil.
The Earthing Systems shall be segregated. If this is not possible (e.g. because of physical
constraints or existing arrangements), a bespoke design will be required.
Soil Resistivity
Radius for 0.96 Ω
(Ωm)
<100 <100m
200 200m
300 400m
400 500m
Table 16 – Assumed soil resistivity and network radius for scenario (3)
If the substation is surrounded by tarmac, or steelwork can only be touched from a dry (indoor)
position, an EPR closer to 3 kV may be acceptable and can give some design economy. The values
quoted above assume damp concrete or soil and are therefore conservative, providing an additional
margin of safety. In marginal cases it may be possible to accept a slightly reduced Network
Contribution if the dry ground covering Touch Potentials are acceptable, however this should be
justified only with design calculations and/or measurements to verify estimated values.
It is assumed also that all HV Earth Faults into this system will clear within 1 second.
This standard approach shall not be considered if the Earth Fault Current is greater than 8 kA or if the
ground return % is known to be greater than 30 %.
21.4 Scenario (4)- Rural ground-mounted substation (small town) fed from overhead line
with Network Contribution
This scenario considers a ground-mounted substation in a rural location where there is part overhead
line between the secondary substation and the source primary substation but the secondary
substation is connected to a reasonably large underground network providing some Network
Contribution. It assumes that the substation is connected via underground modern cable networks to
approximately 30 secondary substations within a 2 km radius.
This provides a High EPR site when a 10 Ω local Earth Electrode resistance is employed.
This scenario assumes that the 11 kV Earth Fault Current is limited to 4 kA which is typical in rural
areas fed from overhead lines. It also assumes that the current is limited by reactive impedances
(inductance) only which gives pessimistic (worst case) values. Adding overall HV network earth
resistance (assumed real) to the overall fault circuit gives a reduction in fault current.
It is assumed that all Earth Fault Current returns via ground, (i.e. IGR% = 100% x IE.)
A 2.33 kV EPR occurs when overall HV network resistance is around 0.58 Ω. Thus, for a 10 Ω
substation Earth Electrode, the neighbouring Network Contribution must be less than 0.62 Ω. This will
give a safe system on soil / wet concrete, for 1 second fault clearance time, provided Touch Potential
% is less than 10%.
It is assumed also that most of the surrounding network is PILC (meeting the conditions for ‘sparse’
networks), and that soil resistivity is low enough, and network size large enough, to provide the
required contribution which is provided for reference in Table 17 and assumes uniform soil:
Table 17 - Assumed soil resistivity and network radius for scenario (4)
A 1200 V EPR occurs when the overall HV network resistance is around 0.55 Ω; thus, for a 10 Ω
substation Earth Electrode, the neighbouring Network Contribution must be less than 0.62 Ω.
Applying this design limit would permit use of standard LV equipment with a stress voltage rating of
1200V.
21.5 Scenario (5) - Rural ground-mounted substation, all/part overhead fed, no Network
Contribution
In this scenario a 10Ω Earth Electrode is installed to achieve protection operation only.
This Earth Electrode will not significantly limit EPR and a voltage close to line voltage may appear
briefly on HV steelwork under fault conditions. In some cases (for raised operating voltage on 11kV
systems) this can approach 6.33 kV.
This situation is only permissible if special measures are in place as detailed in Section 14.5.4. These
measures shall ensure safety criteria is met.
Scenario 1 (i.e. in large urban areas like cities or large towns) with a large effective area and a
reasonable soil resistivity of 100 Ω.m. This offers a high Network Contribution that reduces the overall
substation HV earth resistance to less than 0.1 Ω. The effective area may be larger and soil resistivity
may be poorer providing a similar Network Contribution.
Scenario 2 (i.e. smaller towns with a smaller effective area) is based on a higher soil resistivity (i.e.
less effective) compared to Scenario 1. A soil resistivity of 300 Ω.m has been selected for this
scenario which is considered to be pessimistic to reflect a lower Network Contribution from Earthing
Systems of interconnected substation than scenario 1. It is considered that it is likely that a lower soil
resistivity will be available that will offer a further reduction in overall substation Earth Resistance (i.e.
higher Network Contribution. This will further reduce the overall substation HV earth resistance from
the required resistance value of 0.17 Ω.
In case of less dense networks than those covered in (e.g. Scenarios 3) a lower Network Contribution
may be provided given a higher network resistance value. Details are given in Table 19.
In rural areas, Scenarios 3 and 4 require that network resistances of less than 0.96 Ω and 0.62 Ω
respectively can be obtained from adjacent substations directly connected to the new substation
being considered. These values correspond to smaller network radii at lower soil resistivity as shown
in Table 19.
Different values of network area radii are given for corresponding values of soil resistivity. It can be
seen that for denser rural networks with larger length of underground cables (i.e. larger radius) higher
values of soil resistivity can be tolerated. The Design Engineer shall check the radius of the network
and soil resistivity to ensure that the specified Target Resistance can be employed.
Table 20 - Approximate network radius required in sparse / rural areas to achieve required resistances for
scenarios 3 and 4
For other intermediate values it will be necessary to consult an Earthing Specialist, or to commission
a measurement of network resistance to confirm expectations.
The Standard Earthing Arrangements and the corresponding Target Resistances given for standard
earthing scenarios in Table 8 make a number of assumptions covered by the Basis of Design as
described in section 21. They necessarily err on the side of caution to ensure that the design is safe.
In cases where the Standard Earthing Arrangements described are not be suitable for the application
being considered, the Design Engineer shall consult an Earthing Specialist to ensure that the design
of the Earthing System is appropriate to control Touch and Step Potentials within permissible limits.
Soil resistivity studies will be required to determine the most effective Earthing System design,
A specific design can be refined by more accurate calculation of Ground Return Current, and some
other parameters as described in Table 21. ENA EREC S34 provides detailed guidance together
with worked examples.
The most effective way is to measure the soil using a Wenner method as described in ENA TS 41-24.
However, this is usually carried out only in difficult or problem areas, or when designing a larger
(primary or grid) substation. Online data sources such as BGS (e.g. borehole records) can provide a
guide for design purposes.
The most effective way is to calculate the equivalent circuit of the resistance to earth is by calculating
the impedance of the connecting conductors and the resistance of each nearby substation earth
electrode. Alternatively, the Network Contribution can be measured using either a comparative earth
tester method or cable clamp method as described in ENA TS 41-24.
All foreseeable running arrangements should be considered, and/or appropriate factors applied to
allow for fault level growth etc.
If the standard design does not achieve the Target Resistance, additional Earth Electrodes shall be
installed to augment the Standard Earthing Arrangements. Typical options include laying bare
conductor in trenches or extending the rod electrodes. Where additional Earth Electrodes are
necessary to reduce the substation earth resistance, it may be installed as follows:
i. Extended substation earth rods. The length of the two substation earth rods may be
increased to reduce the earth resistance. This will be especially effective where the rods
penetrate into a soil layer of lower resistivity, for example where they extend beneath the
water table. The hardness of the ground will determine how far rods can practically be driven;
where the achievable depth is limited alternative methods will be required (see below). In
extreme circumstances, and where there is evidence of low resistivity material at greater
depths, installation of deeper rods may be considered but will be at increased cost.
ii. Extended horizontal Earth Electrode. An effective way to reduce earth resistance is to
extend the Earth Electrode beyond the substation using horizontal electrodes buried in a
trench. This may be cost-effectively achieved if the electrode can be laid beneath HV cables
while excavations are available. Horizontal electrodes are typically most effective over the
first two to three hundred metres. If two trenches are available (a minimum of 90 o apart) then
it is most effective to run two electrodes of length L in different directions than a single
electrode of length 2L in one direction. Horizontal HV Earth Electrodes must be kept away
from LV electrodes and metallic sheathed cables (by 8m or 20 metres for High EPR) if HV
and LV systems are segregated (e.g. High EPR or Extremely High EPR sites).
iii. Extended horizontal Earth Electrode with earth rods. Adding vertical earth rods to a
horizontal electrode can also be effective, especially where the rods penetrate into low
resistivity material. Where this arrangement is employed the rods should be spaced no closer
than twice their length.
Table 22 describes how the Target Resistance value required for secondary substations may be
achieved using the Standard Earthing Arrangement and how additional Earth Electrodes may be
supplemented to achieve the required Target Resistance depending on soil type
To aid the Design Engineer to identify the most practical solution indicative values for various
combinations of soil resistivity and different forms of additional Earth Electrodes have been calculated
in the following Tables.
Table 23 provides an indication of typical values of Earth Electrode Resistance that may be achieved
by extending the length of the substation earth rods and driving these deeper into the soil. Values of
Earth Electrode Resistance are given for different values of soil resistivity (assume uniform soil).
While earthing rods driven into a lower impedance soil deeper down offer a benefit when space is
limited, additional horizontal Earth Electrodes offer the most benefit. This effect is summarised in
Table 24. m
A combination of horizontal bare Earth Electrodes laid direct in tracks and earth rods driven into the
ground can provide an effective Earth Electrode system with low Earth Electrode Resistance. Table
25 provides different examples for different combinations of earth rods and horizontal conductor.
Soil Resistivity
Standard Design Additional Electrodes
Soil Type (Ωm)
Loam/Chalk 50 15 m loop If required
Clay 100 15 m loop 2 x 2.4 m rods
Sand, gravel, Clay 150 15 m loop 4 x 4.8 m rods
mix 200 15 m loop 25 m horizontal
300 15 m loop 50 m (Ideally 2 x 25 m)
horizontal
400 15 m loop 100 m (Ideally 4 x 25 m)
horizontal
500 15 m loop 150 m (Ideally 4 x 37 m)
horizontal
Slate, shale, rock >500 Specific design Specific design
Table 23- Typical values of resistance for vertically driven earth rods based on soil resistivity
Soil resistivity
Conductor
Length 25 Ωm 50 Ωm 100 Ωm 150 Ωm 200 Ωm 300 Ωm 400 Ωm 50 0Ωm
10m 3.6 7.3 14.6 21.9 29.2 43.8 58.3 72.9
25m 1.8 3.5 7.0 10.5 14.0 21.0 28.0 35.0
50m 1.0 2.0 3.9 5.9 7.9 11.8 15.8 19.7
100m 0.5 1.1 2.2 3.3 4.4 6.6 8.8 11.0
150m 0.4 0.8 1.5 2.3 3.1 4.6 6.2 7.7
200m 0.3 0.6 1.2 1.8 2.4 3.6 4.8 6.0
250m 0.2 0.5 1.0 1.5 2.0 3.0 4.0 5.0
Notes:
ii. Conductor resistance calculated using formulae R7 from ENA EREC S34 and Earth Electrode
resistance calculated using formulae R4 from ENA EREC S34
Table 24 – Earth Electrode Resistance for horizontal laid bare Earth Electrode laid direct in ground.
Table 25 - Earth Electrode options for achieving 1 Ω, 10 Ω and 20 Ω in different soil types