PETRONASCARIGALISDN.BHD.

INSPECTIONTESTRECORD(ITR) -A

LOW VOLTAGE CABLE E25-A


Project No. PCIHBV/2019/PD&T/2355
Project Title PROVISION OF LEASED POWER UNIT INCLUDING OPERATIONS AND MAINTENANCE FOR PETRONAS
CARIGALI IRAQ HOLDING B.V., GARRAF OPERATIONS
Facilities
INFORMATION
Tag no. System/ Sub System no. 500/570

Cable Core/Size 5C *1*240 mm2 /Phase Cable from DEG no.9


Cable to TR no.1 Ref. Drawing No. GF-LPU2-C-21-3341
Voltage 0.4 KV
INSPECTION/TEST OK N/A P/LNo
Documents required:
1 a) Cable layout drawing
b) Cable schedule and drum list.
Verify to ensure that all construction / installation activities have been
2
completed.
Cable Installed, identified, dressed and secured, cable rack / tray segregation
and bending radius as per project specifications and design. Verify and
3
confirm single core cables are using trefoil clamps, cable gland and gland
plate made of nonmagnetic material
4 Verify cable type and size in accordance with Cable schedule.
Cable gland type and size in accordance with Cable schedule. Confirm that
5
barrier glands are installed where required.
Verify and confirm that the lighting fixture cleats/supports are properly
6
installed and secured.
Verify and confirm that all unused cable entries are sealed using proper
7
sealing plugs.
The cable insulation resistance is to be checked using a 500V Megger. Each
cories to be tested against all other cores, and earth.

8 Test point Insulation Resistance Remarks


R-YBNE
Y-RBNE
B-RYNE
The cable continuity to be tested using a suitable multi-meter, set to ohms.
9 Measured resistance to be compared with the datasheet value. Measured
cable Resistance _Ohms
10 Gland body to earth path resistance (Max 0.1Ω)
PETRONASCARIGALISDN.BHD.

INSPECTIONTESTRECORD(ITR) -A

LOW VOLTAGE CABLE E25-A


Cable joints, if any are completed, identified and the location is marked in
11
cable schedule and relevant layout drawings.

12 Buried/underground sections of cables are properly marked using cable


markers as per project specifications.
13 Check and confirm all related red line markings are completed.
14 Record any defects/shortcomings in the system punch-list.
Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces are
15
clean.
Verify Instruments & its Accessories /Electrical equipment/Panel externally
16
clean.
COMMENT(S)AND ADDITIONALINFORMATION

COMPLETEDBY VERIFIEDBY ACCEPTEDBY


Designation Contractor Representative Inspector Discipline Engineer
Company ALMARWA PETRONAS CARIGALI PETRONAS CARIGALI
Name Haider J. Hassan
Signature

Date 11/09/2021