Jose V. Yap Sr. Access Road
Jose V. Yap Sr. Access Road
Jose V. Yap Sr. Access Road
Date :
Project : Construction / Repair / Rehabilitation / Improvement of Various Infrastructure Net Length
including Local Projects Construction of Bypass and Diversion Roads (a) Road :
Jose V. Yap Sr. Access Road, Tarlac (b) Bridge :
Project ID : (c) Others :
Location : San Jose, Tarlac Target Start Date : upon approval
Station Limits : Total Project Duration : 270 C.D.
Appropriation : Php 100,000,000.00 No. of Pre-determined
Source of Fund : FY 2020 GAA (Augmentation) Unworkable Days :
Description of EQUIPMENT
% Total
Works to Be Done Description Required
A. Facilities for The Engineer 0.11% See Minimum Equipment Requirement
B. Other General Rquirements 0.85%
C. Earthwork 19.28%
D. Subbase and Base Course 15.06%
E. Surface Courses 24.21%
G. Drainage Structures 10.69%
H. Miscellaneous Structures 7.17%
I. Materials Details 22.64%
Total 100.00%
612(1) Reflectorized Thermoplastic Pavement Markings White sq.m. 539.00 758.51 408,836.89
Sub-Total of H 6,915,597.01
I Materials Details
715(1) Geotextile sq.m. 21,669.00 496.83 10,765,809.27
715(2) Separation Geotextile sq.m. 24,211.00 457.52 11,077,016.72
Sub-Total of I 21,842,825.99
Grand Total 96,500,000.00
Manpower 7
Sub-Total for A 540.13
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B.
Equipment
Manpower 9
Sub-Total for A 668.97
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B.
Equipment
a.) 150/50 kN/m High Strength Woven sq.m. 1.15 315.00 362.25
Separation Geotextile
(+15% Wastage & Overlap)