Ntroduction: 400 KV Sub-Station
Ntroduction: 400 KV Sub-Station
Ntroduction: 400 KV Sub-Station
COMMISSIONING CHRONOLOGY
GENERAL
• In general if everything is normal then the shift staff has to fill the operation
records as listed in enclosure.
• All readings must be taken at proper time as per OS norms.
• There should not be any over writing or cutting on Log Books.
• Readings of switch yard equipments, A/C plant, DG set, F/F system, Auxiliary
system must be taken locally.
Normally there should not be any alarm on control panel windows in C/R, A /C plant
control panel, DG control panel and F/F system Control panel. In case any alarm appears
then try to reset the same and inform to maintenance In-charge.
In case of above there will not be any flag on Main-1 / Main-2 panel & fault
locator will not give any reading. Follow steps 1 to 5 as in the section “Line
auto recloses successfully”.
i) In case of over voltage take permission from CPCC if voltage has come
down. Consult other end and Charge/Synchronize the line.
In case over voltage stage-2 operates then inform S/S In-charge for further
restoration of the feeder.
ii) Bus reactor has hand reset type of trip relay, so when ever Bus reactor
trips, clearance is to be taken from S/S In-charge and then reset the relay
by pressing push button.
iii) In case direct trip signal receives, consult other end if they find out the
reason for tripping after that code may be taken for charging and
synchronization of line.
LBB (local breaker back up) or BFR will operate when main protection
has operated and tripping has been extended to trip relay and CB fails to trip due
to mechanical problem etc. It is delayed protection if the current to the LBB or
BFR persists for 200 ms then only relay will operate. Setting of ABB relay
RAICA) is 200mA and that of ALSTOM relay CTIG 1.2 amps for phase element
& 0.4 amp for neutral element with 1000/1 A CT. The tripping relays for both
these protection are common and are located in bus bar Panel. In case of operation
of these protection either B/B-I or B/B-II connected all CB’s will trip and B/B
will become dead.
STEPS TO BE TAKEN
• Do not charge the Bus or line till clearance is given by S/S In-charge and CPCC.
• After inspection and clearance is accorded by S/S In-charge and ask for code from
CPCC.
• Reset the B/B trip relays by pressing the push button in B/B panel.
• Without resetting the B/B trip relays, CB’s cannot be closed because closing
command for CB goes through the contact of this relay.
• If code is given by CPCC charge the B/B by closing CB’s and record time and
other parameters
SHUTDOWN PROCEDURES
A Avail permission code from CPCC for shut down of the line. Pass on the
same code to remote end.
B Note down the system parameters of all lines/ICTS.
C Open the Main CB of the line.
D Open the Tie CB of the line.
( If the remote end opens the line from their end, Main CB & Tie CB will
open automatically)
E Put the Auto Reclose switch (A/R) of the line in “NON AUTO” position.
F Open the line Isolator *89L.
G Open the Main Bay Isolator *89A & Tie Bay Isolator *89A & *89B.
H Open Bus side Isolator *89 & Reactor isolator *89R.
I Check physically for proper opening of all Isolators done in F, G, H.
J Ensure that line Isolator at the other end is open.
K Get permission from other end to earth the line.
L Close the earth switch of the line Isolator *89LE and inform other end.
M Ensure that the line is earthed at the other end.
N Attach “DO NOT OPERATE” board at the control panel of the line bay.
O Issue PTW (Permit To Work) on the line and individual equipment.
A. Avail permission code from CPCC for shut down of the BUS 1/ BUS 2.
B. Open all the CB’S connected to BUS-I/ BUS 2.
C. Put the Auto Reclose switches (A/R) of all the above CB’s in “NON AUTO”
position.
D. Open all the Isolators of the bays connected to BUS 1/ BUS 2.
E. Check physically for proper opening of all Isolators done in D.
F. Ensure that the BUS-I/ BUS-2 voltage is around 10KV (due to induction).
G. Close Bus-I/ Bus-2 earth switch 1389E / 1589E Bus side respectively.
H. Ensure that the Bus selection switch of voltage / frequency is on Bus-II/ Bus-I
respectively.
I. Ensure that the bus selection latch relay is correctly operated and MW, MVAR
and Current of all feeders are matching.
J. Ensure that all the energy meters of feeders & ICTs are running
K. Issue the PTW (PERMIT TO WORK) on individual equipment.
A. Ensure all permits issued are returned and cancelled. (i.e. Line,
Switchyard, CP/RP Maintenance)
B. Check for removal of all men and material from S/Y physically.
C. Physically check for removal of earthing done at working site, both
permanent and temporary.
D. Ensure that all S/Y equipments of the line on which PTW’S were cleared,
are in operating condition.
E. Check for SF6/ OIL pressure of Main & Tie CB.
F. Ensure local/remote switch of CB’s are in “Remote” position.
G. Ensure that all relay flags are reset.
H. Check for no annunciation pending on window and do lamp test OK.
I. Ensure that D/R,E/L, F/L are in service.
J. During charging of the line from BALLABGARH end the A/R selection
switch of both Breaker must be kept in NON AUTO mode to avoid auto
re-closure of switch on to fault. After successful synchronizing same may
be kept in 1 PH mode.
• ICT shall be charged preferably from 220 KV side and synchronized from
400 KV side in normal condition.
• In case of Auto transformer has undergone major overhaul or oil has been
exposed to the atmosphere, values of BDV, PPM shall be taken before
charging the transformer.
SEQUENCE OF OPERATIONS
A. Confirm the removal of earthing at BBMB end, if any, and give clearance
for closing the 220 KV line isolators at their end.
B. Close 220 KV side Autotransformer isolator L*489.
C. Close all the 400 KV side isolators of Main & Tie Bay.
D. Check physically the closing of all isolators done B & C.
E. Inform the readiness to CPCC.
F. Take permission from CPCC for charging the ICT-I from 220 KV side.
G. Note down all parameters of ICT’s and lines.
H. Check physically the healthy ness of transformer.
I. Close 220 KV Breaker of ICT. As such the Auto- transformer is charged
from 220 KV side.
J. In case the Auto transformer trips on fault, second attempt MUST NOT be
made until ICT is properly tested and reason for tripping is ascertained.
K. Close 400KV Main and Tie CB’s of ICT as per requirement. In no case
check synchronizing relay should be bypassed.
L. After synchronizing the ICT note down the readings and check the current
in all the three phases and inform to CPCC.
M. Check all relay and control panels and equipments in the switch yard for
any abnormalities and inform S/S In-charge.
SEQUENCE OF OPERATION FOR CHARGING BUS-1/ BUS-2
GENERAL OPERATING INSTRUCTIONS
A. Ensure all permits issued are returned and cancelled. (i.e. Bus-1/ Bus-2,
Switchyard, CP/RP Maintenance).
B. Check for removal of all men and material from S/Y physically.
C. Physically check for removal of earthing done at working site, both
permanent and temporary.
D. Ensure that all S/Y equipments on which PTW’S were cleared, are in
operating condition.
E. Check for SF6/ OIL pressure of all the CBs.
F. Ensure local/remote switch of CB’s are in “Remote” position.
G. Ensure that all relay flags are reset.
H. Ensure that Event Logger is in service.
Switchgear Equipment :
Switchgear covers a wide range of equipment concerned with switching and interrupt
currents under both normal and abnormal conditions. It includes switches, fuses, circuit
breakers, relays and other equipment. A brief account of these devices is given below.
A. Switches : A switch is a device which is used to open or close an electrical circuit
in a convenient way. It can be used under full-load or no-load conditions but it
cannot interrupt the fault contacts. This is particularly true for circuits of high
voltage and large current capacity. The switches may be classified into air
switches and oil switches. The contacts of the former are opened in air and that of
the latter are opened in oil.
i. Air-break switch : It is an air switch and is designed to
open a circuit under load. In order to quench the arc that
occurs on opening such a switch, special arcing horns
are provided. Arcing horns are pieces of metals
between which arc is formed during opening operation.
As the switch opens, these horns are spread farther and
farther apart. Consequently, the arc is lengthened,
cooled and interrupted. Air-break switches are
generally used outdoor for circuits of medium capacity
such as lines supplying and industrial load from a main
transmission line or feeder.
ii. Isolator or disconnecting switch: It is essentially a knife
switch and is designed to open a circuit under no load.
Its main purpose is to isolate one portion of the circuit
from the other and is not intended to be opened while
current is flowing in the line. Such switches are
generally used on both sides of circuit breakers in order
that repairs and replacement of circuit breakers can be
made without any danger. They should never be opened
until the circuit breaker in the same circuit has been
opened and should always be closed before the circuit
breaker is closed.
iii. Oil breaker: The content of such switches are opened
under oil usually transformer oil. The effect of the oil is
to cool and quench the arc that tends to form when the
circuit is open. These switches are used for circuit of
high voltages and large current carrying capacity.
B. Fuses : A fuse is a small piece of wire of thin strip which melt when excessive
current flow through it for sufficient time. It is inserted in the circuit in the series
to be protected. Under normal operating condition the fuse element it at a
temperature below its melting point. Therefore it carry normal load current
without overheating. However, when a short-circuit or overload occur, the current
to the fuse element increases beyond its rated capacity. This raises the
temperature and the fuse element is melt, disconnecting the circuit protected by it.
C. Circuit Breaker: Circuit Breaker is an instrument which can open or close a circuit
under all conditions viz no load, full load, or fault condition. It is so designed that
it can be operated manually under normal condition or automatically in faulty
condition. For the latter operation, a relay circuit is used with the circuit breaker.
The circuit breaker essentially consists of moving and fixed contacts enclosed in
strong metal tank and immersed in oil, known as transformer oil.
Under normal operating conditions, the contacts remains closed and the circuit
breaker carries the full-load current consciously. In this condition, the emf in the
secondary winding of current transformer(C.T.) is sufficient to operate the trip
coil of the breaker but the contacts can be opened by manual or remote control.
When a fault occurs, the resulting over current in the C.T. primary winding
increases the secondary emf. This energies the trip coil of the breaker and moving
contacts are pulled down, thus opening the contacts and hence the circuit. The arc
produced during the opening is quenched by the oil. It is interesting to note that
relay performs the function of detecting a fault whereas the circuit breaker does
the actual circuit interruption.
D. Relay: A relay is a device which detects the fault and supplies information to the
breaker for circuit interruption. It is divided into three parts viz.
i. The primary winding of a current transformer which in
series with the circuit to be protected. The primary
winding often consists of the main conductor itself.
ii. The second circuit is the secondary winding of C.T.
connected to the relay operating coil.
iii. The third circuit is the tripping circuit which consists of
source of supply, trip coil of circuit breaker and the
relay stationary contacts.
Under normal load conditions, the emf of the secondary winding of C.T. is small
and the current flowing in the relay operating coil is insufficient to close the relay
contacts. This keeps the trips coil of the circuit breaker unenergised. Consequently, the
contacts of the circuit breaker remain closed and it carries the normal load. When a fault
occurs, a large current flows through the primary of C.T. This increases the secondary
emf and hence the current through the relay operating coil. The relay contacts are closed
and the circuit breaker is energised to open the contacts of the circuit breaker.
MAINTENANCE OF 400 KV SUB-STATION
In order to ensure smooth & safe operation of the substation, it is essential to keep all the
equipments of switchyard, protection relays and auxiliaries in healthy condition all the
time so that we can attain high level of availability which is more than 98.5%. There are
various maintenance activities for different equipments in order to keep them in healthy
condition. Details of various schedule maintenance activities are as given below:
CIRCUIT BREAKER:
i) Checking of oil leaks from grading capacitors.
ii) Checking of oil leaks in hydraulic circuit.
iii) Checking of hydraulic oil level & replenishment/ topping up of oil (if
necessary).
CURRENT TRANSFORMER:
PROTECTION SYSTEM:
i) Testing of DR/EL with Time Synchronisation Unit.
CIRCUIT BREAKERS:
CIRCUIT BREAKER:
i) Checking of Hydraulic oil pressure drop/ air pressure drop during duty
cycle operation check.
ii) Checking of auto-starting/ stopping of oil pump/ air compressor.
iii) Dew point measurement of operating air at the outlet of Air
Dryer for
ABCB breaker.
iv) CB operating timings (Main, PIR, Aux.)
v) Checking of Pole Discrepancy relay.
vi) Functional checks, duty cycle operation including rapid re-closing
(O-0.3s-CO).
vii) Checking of all operation lockouts.
viii) Checking of all interlocks.
ix) Checking of pressure settings.
x) Cleaning of Breaker interrupter, support insulators, PIRs and grading
capacitors.
xi) Checking of close/trip coil currents.
xii) Checking of healthiness of Operation Counter.
xiii) Checking of tightness of all cable terminations in MB.
xiv) Checking of door sealing gaskets and replacement, if necessary.
xv) Checking of space heaters.
CURRENT TRANSFORMER:
i) Thermovision scanning of CT and Top dome.
ii) Checking of space heaters & illumination in CT MB.
iii) Checking the tightness of all connections including earthing.
iv) Cleaning of marshalling box and junction box.
i) Visual checking of earthing HF point (in case it is not being used for
PLCC).
ii) Checking for any breakage or cracks in cementing joint.
iii) Cleaning of CVT capacitor stacks and tightness of terminal
connections.
iv) Thermovision scanning of capacitor stacks and EMU.
v) Checking of space heaters & illumination of MB.
vi) Checking and tightness of all connections including earth connections.
vii) Cleaning of MB and junction box & checking the healthiness of
gaskets.
SURGE ARRESTOR:
i) Cleaning of LA insulator.
ii) Testing of counters.
iii) Checking of leakage current (Third harmonic Resistive current).
8. WAVE TRAP;
i) General inspection / cleaning of tuning unit.
ii) Tightening & cleaning of wave trap.
9. PROTECTION SYSTEMS:
i) Checking of DC logic circuit for trip and annunciations including
timers by simulation.
ii) Checking of voltage for relays.
iii) Reach checks for all 4 zones of Distance protection.
iv) Time measurement for the same.
v) Power swing blocking check for Distance protection.
vi) SOTF checking for Distance protection.
vii) VT fuse failure check for Distance protection.
viii) Checking of trip contacts and annunciations.
ix) Check for carrier send.
x) LBB and STUB protection testing.
xi) Auto Reclose test.
xii) Checking of DR & EL initiation.
xiii) Checking of fault locator initiation.
xiv) Checking of Over voltage relay.
xv) Checking of all aux. relays.
xiv) Checking of Reactor back up impedance.
xv) Checking of Buchholz, PRV OTI, WTI in reactor and transformer.
xvi) Checking of differential protection of reactor and transformer.
xvii) Checking of REF Protection of reactor and transformer.
xviii) Checking of Over Fluxing and over load relay in transformer.
xix) Checking of PLCC system for return loss, transmitter/ receiver
check, power supply measurement and alarms.
TWO YEARLY MAINTENANCE OF EQUIPMENTS (S/D ACTIVITY):
CIRCUIT BREAKER:
i) Static Contact Resistance measurement.
ii) Dynamic contact Resistance measurement.
CURRENT TRANSFORMER:
i) Measurement of C & tan delta.
CIRCUIT BREAKER:
i) C & Tan delta measurement of grading capacitor.
ii) Dew point measurement of SF6 gas (3Y).
CAPACITOR VOLTAGE TRANSFORMER:
i) C & Tan delta measurement (3Y).
CIRCUIT BREAKER:
i) SF6 gas/ Air pressure leakage test.
ii) Repainting of metallic part.
CURRENT TRANSFORMER:
i) IR measurement.
ii) Measurement of CT secondary resistance, CT ratio test.
iii) Magnetization characteristics.
iv) DGA and other parameters of oil.
DG SET:
i) Sequence test for annunciation in Control room panel for fire alarm
system.
ii) Smoke test and cleaning of detectors.
iii) Checking / replacement of air filters of compressor.
iv) Checking of auto starting of diesel engine.
v) Checking of oil level of diesel engine, top up if required.
vi) Check leakage and lubrication of all the pumps.
vii) Checking of operation of all the pumps and compressor.
D.G.SET:
i) Cleaning of HP tank.
ii) Cleaning of NRVs.
iii) Checking/replacement of fuel oil filter, lub oil filter, air filter of Diesel
engine.
iv) Checking of alignment of all pump sets.
v) Checking of pressure of the hydrant system at the remotest end, auto-
starting of pumps, diesel engine etc.
vi) Operation of Deluge system, check outlet pressure check alarm, check
starting of diesel/ electrical pump.
vii) Cleaning and tightening of terminals of electrical panels.
viii) Painting of pipes, air lines MB.
DG SET:
MAINTENANCE OF FACTS:
FACTS installed on 400 KV BLB-KNP line is first project on any 400 KV lines
in India. For the maintenance of FACTS some precautions has to be taken as capacitor
bank and all other equipments are installed on a platform, charged at 400 KV.
PRECAUTIONS TO BE OBSERVED WHILE WORKING ON THE HIGH
VOLTAGE PLATFORM
1. Bypass the capacitor bank permanently (both earth switches will be closed under
this condition, both capacitor isolators are open, bypass isolator and BPCB is
closed).
2. Open the fence door observing all capacitor isolator interlock protocol.
3. Using an earth rod, manually earth all incoming tube connections from line for all
the phases. Also, earth all the platforms manually by earthing rod. Keep the earth
rod permanently connected on that platform on which work will be undertaken.
5. After completing work on platform remove earthing rod, ladders, loose hardware
and working tools lying on platform or inside platform mounted equipment.
Ensure all doors of platform mounted equipment are properly closed.
Note: Visual inspection need to be carried out after each line fault at the first
available opportunity.
YEARLY MANITENANCE:
YEARLY MANITENANCE:
I. Check for cleanliness and any mechanical damage to the enclosure, support
insulators.
II. Check for burning mark on the surface of copper and graphite electrodes. (In case
of burning marks/ pitting they are to be smoothed by using a file and grinding
cloth and then cleaned by wiping with cloth.)
III. Check for tightness of bolted connections.
IV. Check for oil leakage in the voltage divider capacitor.
V. Measurement of capacitance of voltage divider capacitor to check voltage divider
ratio.
VI. Measurement of resistance of damping resistors.
YEARLY MANITENANCE:
I. Visual inspection and cleaning of housing to remove any dust, dirt etc.
II. Checking of oil level.
III. Testing of oil.
IV. Checking colour of silica gel and replace silica gel if discoloration is observed.
I. Visual inspection of the equipment and check if the arms of the top/bottom
spiders have become loose from the winding.
II. Check top and bottom of the winding for possible abnormalities such as
carbonization, arc marks etc.
III. Check top of the winding and the cooling ducts for foreign particles, in particular
for bird’s nests and remove them.
IV. Check inside and outside surface of the reactor winding for possible tracking
marks. If such marks are found notify before re-energisation.
V. Check tightening torque of the bolts of the support structure. If bolts are found to
be loose, re-tighten all the bolts.
VI. Check surface of the reactor and insulators for contamination. Clean reactors if
necessary.
VII. Check status of the protective paint of the reactor. Local imperfections or paint
peeling to be touched-up. (For usual environmental conditions it is recommended
that the reactor is r-coated after 10 years of operation).
राम पकाश मनोज गोयल
1
2
34
56