Saes Q 004
Saes Q 004
Saes Q 004
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations .................................... 2
3 References ........................................................ 2
4 Pile Marking and Installation Records ............... 3
5 Pile Installation Planning ................................... 5
6 Driven Pile Installation ....................................... 7
7 Drilling ............................................................. 15
8 Insert or Grouted Piles .................................... 18
9 Grouting........................................................... 19
10 Conductors and Conductor/Piles ..................... 25
Revision Summary .................................................. 25
1 Scope
This standard presents the basis for installation of piles for use in offshore structures
and coastal zones. This specification does not apply to onshore pile installation.
This standard describes the equipment, materials, personnel and procedures that shall be
used to install offshore structure piles and conductors. The intent of this specification is
to provide minimum installation requirements for offshore pile foundations, including
anticipated problems and recommended remedial action that may be required in the
event that pile installation does not proceed as expected.
2.1 Any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs), Materials System Specifications (SAMSSs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Consulting Services Department of
Saudi Aramco, Dhahran.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below, unless otherwise noted.
Page 2 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Piles and added lengths of pile in excess of the water depth shall be marked with
12 mm wide stripes on 0.25 m centers. Stripes are to be painted with oil-based
paint to cover at least 50% of the pile perimeter. Every fourth stripe shall be
marked with the corresponding meter number, measured from the tip of the pile.
Page 3 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
A complete set of pile installation records shall be prepared by the contractor's site
engineer. All records shall be made available to Saudi Aramco Representatives
immediately on completion of pile installation. Items that must be included in the
records for each operation are listed in the following subsections.
4.2.1 Driving
4.2.2 Drilling
The following records shall be kept for all drilling operations: date, time,
bit size, centralizers spacing, hole penetration, pile tip penetration (if
applicable), type, bit weight, torque, drill string rotation, hole penetration
rate, weight and viscosity of drilling fluid, and interruptions during
drilling. Any unusual phenomena or difficulties related to the drilling
program shall also be recorded. This includes drilled hole collapse, drill
bit plugging, equipment breakdown, and withdrawal from drilled hole.
Page 4 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
4.2.4 Grouting contractor shall provide for all grouting operations: date, time,
grout mix, setting time, and unit weight of grout samples, grouting
pressure, ability to establish static head, volume change, compressive
strength, seafloor leakage, interruptions or other problems encountered
during grouting, time and number of each grout sample taken, and any
unusual conditions observed during the grouting operation. If there is
any reason to believe that the mud at the bottom of the hole is not
completely displaced by the grout the same should be reported. In such
cases, the end bearing capacity shall not be considered.
4.2.5 Distribution
5.1 The project specification for each individual job shall include penetrations of
piles and conductors, lengths of concrete plugs or any other specific construction
requirements to supplement the general requirements of this SAES.
Commentary:
Procedures used to install piles to achieve the specified design capacity shall be
selected on the basis of the results from the geotechnical site investigation
performed at the site, pile drivability analyses, and pre-installation planning.
Page 5 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
All piles shall be installed by driving into existing undisturbed soil, except where
sound rock strata greater than three (3) pile diameters thick is located within 20 m
of the seafloor, or where pile refusal occurs above terminal penetration.
Jetting shall NOT be permitted either on the inside or on the outside of any pile.
Pile installation procedures that are acceptable for use in Saudi Aramco
operating areas are listed in Table 1. The same procedures can be adopted while
taking remedial action in case of pile refusal. Alternative installation procedures
shall be subject to review and approval by Supervisor, Offshore Engineering
Group, CSD.
A Job Safety Analysis (JSA) shall be carried out in accordance with the Loss
Prevention Department Safety Management Guide (SMG) 06-003-2013.
Page 6 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Contractor shall stab all piles or pile sections in all corner legs of the
platform and predrive by putting the hammer weight on each pile.
However, if the contractor wishes to adopt a different procedure,
he shall obtain prior approval of Saudi Aramco. The sequence of
stabbing should attempt to follow a diagonal pattern to reduce sideways
drift. The expected penetration under pile weight plus hammer weight
shall be analyzed prior to installation as part of the pre-installation
planning work effort.
Then the jacket shall be leveled and the top of the jacket leg shall be
attached to the driven pile or pile section with a temporary welded
connection. The remaining piles shall then be driven to design
penetration. Finally, (if required) the first pile shall be spliced and
redriven. During driving, every effort shall be made to maintain the
jacket top at the specified elevation.
Page 7 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
The test pile is used to prove pile capacity and setup at the site.
Dynamic measurements and CAPWAP (CAse Pile Wave Analysis
Program) type analysis are performed on the pile after at least 12 hours of
setup. Saudi Aramco Representative shall approve the DMS (Dynamic
pile Monitoring)/CAPWAP report. Based on the driving characteristics of
the test pile the Contractor and Saudi Aramco Representative shall
re-evaluate the splicing schedule, the soil stratigraphy, and pile design
parameters. Such revision shall be reviewed and accepted by Supervisor,
Offshore Engineering Group, CSD.
Unless specified otherwise, the Contractor shall have available at the site
a minimum 12 m long section of piling for each pile, in addition to the
design length of piling. This extra length shall be available to cover the
possibility of having to drive piles deeper than the design penetration.
Closure devices are used on the lower end of the jacket columns and pile
sleeves to provide buoyancy. They shall be designed to avoid
interference with the installation of the piles.
Guides shall be designed to support the full weight of the add-on pile
section prior to welding the pile sections together. If bare cages are
used, it shall be ensured that they do not interfere with the DMS gauges.
Page 8 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Lifting eyes and weld-on lugs used for pile handling shall be designed to
accommodate stresses associated with initial pile pickup, stabbing, and
impact loads as may occur during the handling of the pile.
Where lifting eyes and weld-on-lugs are used to support the initial pile
section from the top of the jacket, each eye or lug should be capable of
resisting the entire hanging weight.
In all cases, the padeyes should be designed to resist all possible out-of-
plane bending loads.
Where lifting eyes and/or weld-on-lugs are on lengths of pile that will
remain in service, they should be removed by torch cutting 6 mm from the
pile steel surface and subsequently be ground smooth to prevent damage
to internal jacket leg elements such as packers during pile driving.
Contractor shall supply all equipment and experienced personnel for driving
piles in accordance with plans and specifications.
All pile driving equipment shall be in good operating condition when brought to
the work site and shall be approved by the Saudi Aramco PMT Representative at
the site.
Contractor shall select suitable pile hammers to drive the piles to the
design penetration, based on the drivability analyses performed as part of
the pre-installation planning. Only hydraulic hammers should be
mobilized. If the contractor wishes to mobilize diesel hammers, he
should obtain specific approval of Saudi Aramco before mobilization.
Pile hammer guides shall provide a close fit to the pile wall and must
hold the hammer properly in line with the pile.
Page 9 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
All pile installations shall be monitored as per ASTM D4945 with dynamic
monitoring system (DMS), operated by trained personnel and analyzed by
engineers.
Page 10 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
6.3.2.2 The SRD for piles in compression shall be taken as the sum of
shaft resistance and end bearing. SRD so calculated from the
restrike test (or by applying the setup calculated from the
restrike tests) shall be taken as the static ultimate compression
pile capacity.
Page 11 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Page 12 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Setup or restrike tests shall be carried out 12 or 24 hours after end of initial
drive. Offshore Engineering Group, CSD shall be consulted for deciding on
necessity of another restrike test if the required capacity is not achieved in the
initial or subsequent restrike test(s). Pile installation procedure shall be
submitted by the contractor before fabrication of the piles.
In cases where it is not possible to perform a restrike test due to bad weather
conditions, the setup may be assessed based on driving data before and after
waiting periods.
The setup shall be derived based on skin friction and should be applied to skin
friction only.
Suitable complete backup pile hammers shall be supplied and readily available,
especially when driving through soil layers that will develop increased driving
resistance (setup) during delay periods.
Design penetration shall be based on the static axial pile capacity and
lateral load requirements for each site, calculated in accordance with the
procedures presented in SAES-M-005.
In the event that the pile refuses at a penetration less than the design
penetration and the calculated static axial capacity is less than the design
Page 13 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Pile driving refusal shall be defined as per Section 12.5.6 of API RP 2A,
21st edition. Properly operating hammer is defined as the hammer
providing a transferred energy equal to or greater than the energy
considered in the drivability report.
Any splice made to a pile extending more than 5 m into clay layers at
penetrations of more than 15 m below the seafloor will probably
experience sufficient increases in driving resistance (set-up) to make the
continuation of driving difficult. Therefore, splice locations shall be
chosen to minimize the possibility of refusal due to the increase in
driving resistance.
When the soil plug is drilled out of the pile and the pile re-driven or a
predrilled hole is used to facilitate driving, a grout plug must be placed to
develop end bearing of the pile. The pile should first be cleaned out as
described in paragraph 7.2.7 and the grout plug placed in accordance
with paragraph 9.3.7. The length of the grout plug shall be specified for
each specific job.
Page 14 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
7 Drilling
The Contractor shall supply all equipment, materials and experienced personnel
required to drill soil plug from inside piles, drill pilot holes, and drill holes or
pre-drill holes for insert or grouted piles. Before arriving at the site, all
equipment shall be approved by Saudi Aramco PMT Representative and shall be
in good operating condition.
The drill rig shall be either a rotary type, power swivel or turbo drill.
The rated torque for these units shall not be less than 8,100 N.m.
(6,000 ft. lbs).
The support equipment to accompany the drill rig shall include the
following:
(1) As a minimum, a supply of drill pipe that is at least 125 mm
diameter to drill to design penetration, including pup joints and
cross-over subs with a 100% reserve.
(2) An adequate supply of drill collars to provide bit manufacturer's
recommended weight to drill bit and bumper subs for use from
floating barge.
(3) Stabilizers of appropriate size and number to keep drill string
aligned in hole.
(4) Two roller type bits with jets of each size required.
(5) Positive displacement pump(s) capable of providing at least
1100 liters per minute to the bit together with suction and discharge
hoses.
(6) Small tools and spare parts for rig and pump repairs to maintain
equipment in good working order.
(7) Air lift equipment for removing cuttings.
Page 15 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
7.1.4 Specifications
All drilling equipment shall be mobilized at the job site in time to allow
testing at least one day prior to earliest need.
7.1.6 Personnel
7.2.1 Purpose
Page 16 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
The soil plug can be removed from a pile using a bit with a diameter
slightly less than the inside diameter of the pile. If plug is removed,
reassessment of pile capacity shall be carried out.
Drilling to remove a soil plug should stop one pile diameter or at least
1.5 m above the tip of the pile, whichever is greater.
A predrilled pilot hole to assist driving shall stop two pile diameters or
2 m above terminal penetration whichever is greater. The diameter of
the pre-drilled hole shall be less than 75% of the outside diameter of the
pile when mostly in clay and, less than 50% of the outside diameter of
the pile when mostly in sand.
Where pilot holes are used the axial pile capacity shall be re-evaluated to
account for the reduction in insitu soil stress caused by the drilling. In all
cases the driven pile skin friction and end bearing unit values in disturbed
zone shall be reduced by at least 25%. In addition, the unit skin friction
values shall be reduced by 25% along the length of the already driven pile
for a distance of at least five (5) pile diameters above the pile tip.
For anchor piles subject to lateral loads only, the diameter of the predrilled
hole may be increased to the outside diameter of the anchor pile.
Predrilled holes for grouted insert piles or grouted piles should provide at
least a 76 mm clear space around the pile to be grouted to the full design
penetration.
Seawater with an air assist can be used as drilling fluid to remove drill
cuttings in stable clays, rock and sand layers of limited thickness. Drilling
mud shall be used to pre-drill holes in unstable clays and sand deposits
greater than 4.5 m thick. Mud-loss and hydraulic fracture assessment
should be carried out. Specifications for drilling mud are given below:
Page 17 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
7.2.7 Stabilizers
7.2.8.1 Internal Grout Plug - After drilling out the internal soil plug
and re-driving the pile to an acceptable penetration and prior to
installing the grout plug, all loose soil shall be removed from
the inside of the pile.
7.2.8.2 Pilot Hole - After drilling the pilot hole and re-driving the pile
to an acceptable penetration, all loose soil shall be removed
from inside the pile prior to placing the grout plug.
Insert or grouted piles shall be of the size and length indicated in the Pile
Installation Specification and drawings for a specific job.
Page 18 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
8.2 Centralizers
Piles shall be placed in the predrilled holes and should advance into the hole
under self-weight plus the weight of a pile hammer, if necessary. No blows
shall be applied to any pile to be grouted. The tip of pile shall be 30 cm above
bottom of predrilled hole.
9 Grouting
Contractor shall provide all equipment, materials and experienced personnel required to
grout structure piles in jacket sleeves, structure piles to insert piles and structure or
insert piles to foundation formations. All equipment shall be in good operating
condition when it is brought to the job site and shall be approved by the Saudi Aramco
PMT Representative at the site.
Page 19 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
Page 20 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
9.1.4 Personnel
9.2 Materials
The cement used for grouting shall be ASTM C150, type V (Sulfate
Resistant Portland Cement) with 30% Fly ash. Fly ash shall comply with
ASTM C618.
The grout mix shall have high fluidity to ensure flow during grouting
process. Chemical admixtures complying with ASTM C494 can be used
to achieve the required fluidity of the grout mix. The maximum water to
cement ratio (water/ cement + Fly ash) shall not exceed 45%.
High Sulfate-resisting Portland Cement or API standard well cement
grouts shall be used. In general, Portland cement grouts should be used
with or without inert fillers mixed with either seawater or fresh water.
Any water used to mix grout should be free of hydrocarbons and other
deleterious matter. The 28 day grout strength shall be minimum
17.25 MPa (2,500 psi) as per Section 8.4.1 of API RP 2A.
9.2.4 Quantities
When ordering materials, the contractor shall consider that grout seals
are normally imperfect, that grout loss can occur in the formation and at
Page 21 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
the seafloor.
Contractor shall submit the grouting procedure for approval of Saudi Aramco.
9.3.1 Purpose
9.3.3 Sampling
The annulus between pile and jacket leg should be filled with grout
where it is required by design as per SAES-M-005 after the pile has been
installed to grade and is completely shimmed and welded to the jacket.
Sealer plates should be omitted until after grouting. The grouting
procedure shall be as follows:
(1) Try to establish circulation by pumping seawater through the lower
Page 22 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
grout line.
(2) If circulation can be established and the returns are approximately
equal to pumped quantity, pump 0.14 m³ slug of grout followed by
a sufficient volume of water to clear hoses and grout lines plus
300 liters. Slurry used for grout plug should be monitored to
ensure a minimum weight of 1,860 kg/m³.
(3) If partial or no circulation is obtained, add lost circulation material
to cement slurry, pump slug as in Step 2, allow sample to set two
hours, and try to establish circulation using seawater. If water level
in leg holds for 5 minutes proceed with Step 5. If water level will
not hold, use divers to place bagged cement around jacket leg to
seal obvious flow channels, then repeat Step 3.
(4) An alternate procedure for setting grout plug is to run a 25 mm
(1 inch) grout pipe inside the annulus between jacket and pile and
pump a grout plug consisting of 0.14 m³ plus volume needed for
grout lines followed by sufficient volume of water to clear hose and
grout lines plus 300 liters. Check water level as in Step 3.
(5) Allow four hours for plug to harden, then fill remainder of annulus
using upper grout line. Grouting should be continued until returns
at the jacket leg are 1,860 kg/m³ grout.
(6) Fill any empty space that occurs from grout settling with hand-
mixed grout within 24 hours and install sealer plates.
Grouting insert piles to formation and initial pile section shall be done
after the insert pile with centralizers is placed in the predrilled hole. Two
pressure heads and a 75mm (3 inch) grout pipe shall be provided by
fabricator for contractor's use. The stepwise grouting procedure of insert
piles shall be as follows:
(1) Run grout pipe to 1 m above the tip of the pile. The length of grout
plug will be specified in pile installation specification for
individual projects or shown on the drawings.
(2) Connect pressure head and weld to cover top of insert pile.
(3) Hook-up lines to pressure head and pump seawater until all air in
insert is displaced through exhaust valve, then close exhaust valve.
(4) Pump 0.4 m³ to 0.6 m³ low density grout, 1,280 kg/m³ to serve as a
scouring medium ahead of structural grout.
Page 23 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
9.3.6 Grouting of Drilled and Grouted Piles to the Formation and Jacket Leg
Placing a grout plug in a driven pile shall follow the stepwise procedure
given below:
(1) Run the grout line to the top of the soil plug.
(2) Connect the grout lines and pump a quantity of grout adequate to
Page 24 of 25
Document Responsibility: Offshore Structures Standards Committee SAES-Q-004
Issue Date: 18 December 2016
Next Planned Update: 30 June 2019 Installation of Piles and Conductors for Offshore Structures
fill all grout lines and to provide the required length of grout plug
in the pile plus 0.3 m³ and lift grout line.
(3) Wait four hours, then measure top elevation of the grout plug.
If not adequate, repeat Steps 1 and 2.
10.1 Conductors are used as part of the oil drilling and/or production operations and
are not used to provide axial or lateral foundation support to the structure.
Conductor/piles serve a dual use and are depended upon and designed to provide
axial or lateral foundation support in addition to serving oil production and
drilling functions. The use of conductor/piles is generally not recommended
except for minimum structures.
10.2 Conductor/piles shall be installed using the techniques given in this standard for
piles. All requirements for grout should be met and detailed procedures and
materials used for installing conductor/piles should be approved at least two
months prior to installation by Supervisor, Offshore Engineering Group, CSD.
Revision Summary
5 July 2010 Revised the “Next Planned Update”. Reaffirmed the contents of the document, and reissued
with editorial changes.
30 June 2014 Revised Next Planned Update, reaffirmed the content and reissued as major revision since it
has not been reviewed for 5 years.
18 December 2016 Major revision. Sea water is being allowed for mixing grout. Personnel requirements for pile
testing has been changed. References to API RP 2A, 21st Edition and API RP 2GEO have
been added.
Page 25 of 25