Year 4 - Sem 7 / Multiple Choice Questions (MCQ) - Unit II
Year 4 - Sem 7 / Multiple Choice Questions (MCQ) - Unit II
Year 4 - Sem 7 / Multiple Choice Questions (MCQ) - Unit II
NOTE: the questions are suggestive only and not an end to the number of
questions
2. The term _________, in a botanical sense, refers to a tree that sheds its leaves annually.
a) Evergreen
b) Pine
c) Deciduous
10. Which of the following tree form will belong to coconut tree?
a) Vase
b) Columnar
c) Fountain
11. Which of the following tree form will belong to Neem tree?
a) Spread
b) Round
c) Fountain
19. Which of the following fuel sources are used for the fire place?
a) Propane
b) Gas line
c) Both A & B
21. Which of the following is the one of the oldest material for pavements?
a) Stone
b) Clay pavers
c) Concrete pavers
28. What is the thickness of decomposed granite laid for vehicular movement?
a) 2-4 inches
b) 5-7 inches
c) 8-10 inches
30. What is the important point to be considered for using water body in landscaping?
a) Water splashed to be treated
b) Pumps and equipment
c) Both A & B
37. In addition to the visual effect plant material can be planned for_________
a) Sound and smell
b) Tactile characteristics
c) Both A & B
39. Spaces while moving gives mass view frame or new spaces opening, which will change
its role in landscaping is called as______
a) Enframement
b) Sequential space
c) Spatial enclosure
45. At Site Level, Surface flow is caused to flow around rather than through the building.
This is achieved by creating ______
a) Grading
b) Trench
c) Subtle swale
47. Stone filled baskets of wire mesh or wickers used as slope retention are called______
a) Gabions
b) Mortar bag
c) Rubbles
48. A laid up crib of interlocking woods or metal filled with rock ballast used as slope
retention are called________
a) Pilling
b) Cribbing
c) Mulching
49. Dumped or placed fragments of broken stones used as slope retention are called______
a) Rubble
b) Gabions
c) Pilling
2. Pick up the item of work not included in the plinth area estimate
A. Wall thickness
B. Room area
C. Verandah area
D. Courtyard area.
3. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
A. 2.00%
B. 2.50%
C.4.00%
D. 5.0%.
12. While estimating the qualities for the construction of a building, the correct metric unit is
A. Metre for length
B. Cubic metre for area
C. Square metres for volume
D. Litre for capacity
20. The measurement is made for stone work in square metre in case of
A. Wall facing
B. Columns, lintels, copings
C. Dressed stones in Chajja
D. All the above.
27. Pick up the correct statement regarding the centre line method of estimating a building
A. Product of the centre line of the walls and area of cross-section of any item, gives total
quantity of the item
B. The centre line is worked out separately for different sections of walls of a building
C. The centre line length is reduced by half the layer of main wall joining the partition wall
D. All the above.
29. In long and short wall method of estimation, the length of long wall is the centre to centre
distance between the walls and
A. breadth of the wall
B. half breadth of wall on each side
C. One fourth breadth of wall on each side
D. None of these.
31. The total length of a cranked bar through a distance (d) at 45? in case of a beam of effective
length L, is
A. L + 0.42 d
B. L + 2 x 0.42 d
C. L - 0.42 d
D. L - 2 x 0.4 d.
32. While estimating a reinforced cement structure, the omitted cover of concrete is assumed
A. at the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar
B. in thin slabs, 12 mm minimum or diameter of the bar whichever is more
C. for reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar
which is more
D. All the above.
35. The expected out turn of brick work in cement mortar in foundation and plinth per mason per
day, is
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3.
36. The expected out turn of half brick partition wall per mason per day is
A. 1.5 m3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2.
37. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
A. 1.5 rn3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3.
38. The expected out turn of 12 nun plastering with cement mortar is
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
39. The expected out turn of 2.5 cm cement concrete floor per manson per day
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm.
40. The expected out turn for earth work in excavation in ordinary soil per mazdoor per day is
A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum.
41. Pick up the correct statement from the following: All pipes and fittings are classified
according to their diameters
A. The diameter of the pipes is the nominal diameter of internal bore
B. All pipes are measured along the centre line of the pipes in metres
C. Lead caulked joints are enumerated separately
D. All the above.
44. In case of laying gullies, siphons, intercepting traps, the cost includes
A. Setting and laying
B. Bed concreting
C. Connection to drains
D. All of these.
45. The concrete work for the following part of the building of specified thickness is measured in
square metres
A. Root slabs
B. Floors
C. D.P.C.
D. All the above.
47. Brick walls are measured in sq. in if the thickness of the wall is
A. 10 cm
B. 15 cm
C. 20 cm
D. None of these.
51. For 12 mm thick cement plastering 1 : 6 on 100 sq. in new brick work, the quantity of cement
required, is
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3.
52. For 100 sq. m cement concrete (1 : 2 : 4) 4 cm thick floor, the quantity of cement required, is
A. 0.90 rn3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3.
54. A revised estimate is usually prepared when the original estimate has exceeded by more than
A. 1%
B. 2%
C. 10%
D. 100%
59. Of the total estimated cost of a building, electrification usually amounts for
A. 1%
B. 2%
C. 8%
D. 15%
60. Of the total estimated cost of a building, sanitation and water supply works usually amounts
for
A. 1%
B. 2%
C. 8%
D. 15%
61. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
A. 2%
B. 2.5%
C. 4%
D. 5%
62. To make out an estimate for a work the following data are necessary-Drawing, Specification
and ___________
A) materials
B) rates
C) labours
D) transportation
64. Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as
Rs. 10 lakhs.
A) True
B) False
65. The approx. cost of 10 km length of irrigation channel of 3 cu m per sec. capacity @
Rs.70000/- per km works out as Rs.7 lakh.
A) True
B) False
66. Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span
comes to 3*50*30000 = Rs. 45 lakhs.
A) True
B) False
67. __________ is prepared on the basis of plinth area of building, the rate being deducted from
the cost of similar building having similar specification, heights and construction, in the locality.
A) cube rate estimate
B) supplementary estimate
C) maintenance estimate
D) plinth area estimate
68.________________ is the amount provided in the estimate and bill of quantities for some
specialised work to be done by a specialised firm; whose details are not known at the time of
preparing estimate.
A) Prime cost
B) Provisional sum
C) Capital cost
D) Building cost index
69. In this method approx. total length of walls is found in running metre and this total length
multiplied by the rate per running metre of wall gives a fairly accurate cost.
A) Annual repair
B) Item rate estimate
C) Approximate quantity method estimate
D) Cubical content estimate
70. _______________ estimate is a detailed estimate and is prepared to maintain the structure or
work in proper order and safe condition.
A) Supplementary and revised estimate
B) Maintenance estimate
C) Item rate estimate
D) Revised estimate
71. A large work or project may consists of several building or small works and each of these
work is known as ___________
A) sub-work
B) sub-project
C) sub-head
D) sub-construction
72. The term ______________ is used to denote a procedure of costing or valuing an item of
work on the basis of actual labourers and materials required.
A) prime cost
B) hour-work
C) day-work
D) sub-work
1. Type of a technical drawing that provides power and light details for engineering and
architectural projects.
a) Plumbing drawing.
b) Electrical drawing.
c) Centerline drawing.
d) Structural drawing.
2. ___________ provides a dimensioned graphical information that can be used by contractors
to construct the work in the site.
a) Working drawing.
b) Electrical drawing.
c) Centreline drawing.
d) Structural drawing.
a) Plumbing drawing.
b) Electrical drawing.
c) Centreline drawing.
d) Structural drawing.
5. The concept and principles of the architectural designs are defined by a _________________.
a) Centreline drawing.
b) Schematic drawing.
c) Working drawing.
d) Structural drawing.
6. Centre line plans helps you understand the exact position of ___________ on site.
a) Beam
b) Column
c) Wall
d) Area
7. _____________ is the most common type of stairs found in both residential and commercial
properties.
a) Spiral staircase
b) Straight staircase
c) Quarter turn staircase
d) Steel staircase
8. _____________ beam is used in the middle or on the sides to support the non RCC staircase.
a) Plinth
b) Simply supported
c) Cantilever
d) Stringer
a) L – angle
b) Tee profile
c) I – Section
d) C – section
10. The line joining all the nosing is called ____________
a) Thread line
b) Riser line
c) Pitch line
d) All the above
11. ___________ wall carries the weight of a house from the roof and upper floors to the
foundations on its own.
a) Stone wall
b) Shear wall
c) Load bearing wall
d) Non load bearing wall
12. In residential building, tread nosing to be ___________ for the safety purposes.
a) Splayed
b) Rounded
c) Squared
d) All the above
13. In a traditional cavity wall, what is the ideal width of the cavity required in the center is
________________
a) 100 mm
b) 50 mm
c) 5 mm
d) 25 mm
a) R Value
b) U Value
c) T value
d) All the above
a) R Value
b) U Value
c) T value
d) Thermal mass
a) U – Value
b) R – Value
c) T – Value
d) None of the above.
a) 2 W/m2K
b) 1.5 W/m2K
c) 0.8 W/m2K
d) 2.1 W/m2K
18. What is an ideal cement mortar thickness while plastering the wall ___________
a) 10 mm
b) 12 mm
c) 18 mm
d) 25 mm
19. Which drawing helps us understand the center to center distance of columns?
a. Centreline drawing
b. Setting out drawing
c. Skin section
d. Elevation
20. Which drawing is used to give a detailed section through an individual external wall to
indicate any cladding etc.?
a. Centreline drawing
b. Setting out drawing
c. Skin section
d. Elevation
21. Which of the following lines should be used for indicating centerline
a. ____________
b. ___ _ ___ _ __
c. …………………
d. ----------------
22. Which of the following lines is used for indicating section line
a. ____________
b. ____ _ _____
c. ___ . ___ . __
d. ----------------
23. Which of the following lines can be used for hidden lines?
a. ____________
b. ____ _ _____
c. ___ . ___ . __
d. ----------------
24. If you had to start construction on site which drawing would you have to consult?
a. Centreline drawing
b. Setting out drawing
c. Skin section
d. Elevation
25. How many reference points do we need to provide in a setting out drawing.
a. 1
b. 2
c. 3
d. 4
26. What is the need for the second reference point _____________
a. To confirm
b. To start construction
c. To speed up the process
d. Vaastu
29. The Contractor is placing a horizontal member over a large opening to support the load
above in a wall he’s building. What is that horizontal member called?
a) Beam
b) Keystone
c) Lintel
d) All the above
a. 0.8mm to 1.25mm
b. 5mm to 10mm
c. 15mm to 20mm
d. None of the above
32. When it comes to quality of paint, which of the following best describes what to look for?
a. Durability
b. Uniformity of color
c. Both
d. None of the above
33. ___________ a term which is used to indicate the covering of entire or part of the exposed
surface of Plywood by means of Veneers.?
a. Rebating
b. Veneering
c. Studding
d. All the above
36. Which of the following drawing conveys the concept of the project?
a) Schematic drawing
b) Centerline drawing
c) Working drawing
d) Set out plan
a) Graphic symbols
b) Abstract
c) Pictures
d) All the above
39. What is the next stage after schematic design stage in a design process?
a) Centerline drawing
b) Working drawing
c) Design development stage
d) None of the above
a) Parallel
b) Running
c) Chain
d) All the above
a) Architectural
b) Structural
c) Electrical and plumbing
d) All the above
42. ___________ is the readable map depicting the plot of the land where, building is
constructed
a) Road plan
b) Floor plan
c) Site plan
43. The process of transferring conceptual drawing into architectural drawing is _________
a) Schematic plan
b) Working drawing
c) Setting out plan
44.Developing physical position at the corners of the site for constructing building is called
_________
a) Schematic plan
b) Working drawing
c) Setting out plan
a) Schematic plan
b) Working drawing
c) North point
46.Which gives the graphical representation of size and distance in the architectural drawing?
a) scale
b) Working drawing
c) North point
AR8721 – ARCHITECTURAL DESIGN DETAILING (UNIT 2 – MCQ):
1. Mention the energy rating system developed by The Energy and Research Institute for
buildings in India.
a) Leadership in Energy and Environmental Design
b) Green Rating for Integrated Habitat Assessment
c) Indian Green Building Council
d) Energy Conservation Building Code
2. Calculate the wavelength of the body for the wavelength for temperature 270C.
a) 10 micro metre
b) 100 micro metre
c) 1 milli metre
d) 0.1 micrometre
10. The Purpose of green building is to __________ of resources such as energy, water and
minerals.
a) Normalize efficiency
b) Reduce Efficiency
c) Increase efficiency
d) Make no change
13. What is the standard rating system for construction for a green building in Singapore?
a) LEED, Green Globes
b) BREEAM
c) Green Star
d) Green Marks
18. The facture that light transmission depends inside a building are
a) Location
b) Orientation
c) Nature of building operation
d) All the above
19. The parameter that determine energy conservation in artificial lighting is artificial
lighting is
a) Light transmission
b) Solar factor
c) U-value
d) All the above
20. The rate of heat transfer which is also called as U-value can be changed by
a) Tinted glazing
b) Double Glazing
c) Laminated glazing
d) All the above
22. The percentage of heat gain that solar factor contributes inside a building is _____
a) 80%
b) 40%
c) 100%
d) 60%
23. The contributing factors for the energy performance of a building are
a) Solar factor or SHGC
b) Light transmission
c) U-Value
d) All the above
27. The process of converting used materials to new products to reduce consumption of fresh
raw materials is ___________
a) Reusing
b) Recycling
c) Manufacturing
d) Reduction
28. Which of the following are the benefits of material resource optimization?
a) Lower energy and raw materials savings
b) Increased cost savings for business and consumers
c) Higher material disposal needs and costs
d) All the above
29. The factors for selection of glass for green building are
a) Climate type
b) Orientation
c) Glazing type
d) All the above
34. High performance glazing is one of the main objectives of optimizing building design to
a) Increase conventional energy demand
b) Increase material usage
c) Reduce conventional energy demand
d) Reduce renewable energy demand
37. Key objectives of optimizing building design to reduce conventional energy demand are
a) Optimize window area
b) Solar passive building design measures
c) Efficient artificial lighting
d) All of the above
39. List out the criteria requirements of the GRIHA rating systems
a) Optimize building design to reduce conventional energy
b) Use of low energy materials in interior
c) Optimize energy performance of building in specified limits
d) All of the above
40. ___________ will reflect more daylight that dark coloured surfaces
a) Metallic sunshade
b) Reflective glazing
c) Light coloured surfaces
d) Clear glass
41. Which of the following is used between double glazed unit to redirect sunlight?
a) Argon gas
b) Laminated glass
c) Louvers
d) Venetian blinds
42. ___________ will redirect brightness of sunlight into deeper areas of the building
a) Metallic sunshade
b) Reflective glazing
c) Light coloured surfaces
d) Clear glass
43. To maximise daylight, _____________ can be used in the proposed building to allow
natural light into interiors of the building.
a) Skylight
b) Glass façade
c) Louvers
d) All the above
45. Which of the following types of glass will be ideal for the building?
a) Glass with SHGC 0.57 and U-value 4.8
b) Glass with SHGC 0.60 and U-value 2.5
c) Glass with SHGC 0.45 and U-value 3.7
d) Glass with SHGC 0.25 and U-value 1.8
52. Hot bodies emit electromagnetic radiation in the form of __________ radiation
a) Ultraviolet
b) Infrared
c) Visible light
d) All the above
--------------------------------------------------x--------------------------------------------------------------------------
1. Mention the energy rating system developed by The Energy and Research Institute for
buildings in India.
a) Leadership in Energy and Environmental Design
b) Green Rating for Integrated Habitat Assessment
c) Indian Green Building Council
d) Energy Conservation Building Code
2. Calculate the wavelength of the body for the wavelength for temperature 270C.
a) 10 micro metre
b) 100 micro metre
c) 1 milli metre
d) 0.1 micrometre
10. The Purpose of green building is to __________ of resources such as energy, water and
minerals.
a) Normalize efficiency
b) Reduce Efficiency
c) Increase efficiency
d) Make no change
13. What is the standard rating system for construction for a green building in Singapore?
a) LEED, Green Globes
b) BREEAM
c) Green Star
d) Green Marks
18. The facture that light transmission depends inside a building are
a) Location
b) Orientation
c) Nature of building operation
d) All the above
22. The percentage of heat gain that solar factor contributes inside a building is _____
a) 80%
b) 40%
c) 100%
d) 60%
23. The contributing factors for the energy performance of a building are
a) Solar factor or SHGC
b) Light transmission
c) U-Value
d) All the above
27. The process of converting used materials to new products to reduce consumption of fresh
raw materials is ___________
a) Reusing
b) Recycling
c) Manufacturing
d) Reduction
28. Which of the following are the benefits of material resource optimization?
a) Lower energy and raw materials savings
b) Increased cost savings for business and consumers
c) Higher material disposal needs and costs
d) All the above
29. The factors for selection of glass for green building are
a) Climate type
b) Orientation
c) Glazing type
d) All the above
34. High performance glazing is one of the main objectives of optimizing building design to
a) Increase conventional energy demand
b) Increase material usage
c) Reduce conventional energy demand
d) Reduce renewable energy demand
37. Key objectives of optimizing building design to reduce conventional energy demand are
a) Optimize window area
b) Solar passive building design measures
c) Efficient artificial lighting
d) All of the above
39. List out the criteria requirements of the GRIHA rating systems
a) Optimize building design to reduce conventional energy
b) Use of low energy materials in interior
c) Optimize energy performance of building in specified limits
d) All of the above
40. ___________ will reflect more daylight that dark coloured surfaces
a) Metallic sunshade
b) Reflective glazing
c) Light coloured surfaces
d) Clear glass
41. Which of the following is used between double glazed unit to redirect sunlight?
a) Argon gas
b) Laminated glass
c) Louvers
d) Venetian blinds
42. ___________ will redirect brightness of sunlight into deeper areas of the building
a) Metallic sunshade
b) Reflective glazing
c) Light coloured surfaces
d) Clear glass
43. To maximise daylight, _____________ can be used in the proposed building to allow
natural light into interiors of the building.
a) Skylight
b) Glass façade
c) Louvers
d) All the above
45. Which of the following types of glass will be ideal for the building?
a) Glass with SHGC 0.57 and U-value 4.8
b) Glass with SHGC 0.60 and U-value 2.5
c) Glass with SHGC 0.45 and U-value 3.7
d) Glass with SHGC 0.25 and U-value 1.8
52. Hot bodies emit electromagnetic radiation in the form of __________ radiation
a) Ultraviolet
b) Infrared
c) Visible light
d) All the above
ANSWER KEYS
1B 8C 15 C 22 A 29 D 36 A 43 D 50 B
2C 9A 16 D 23 A 30 D 37 D 44 A 51 C
3B 10 C 17 B 24 A 31 A 38 C 45 C 52 B
4D 11 D 18 D 25 B 32 C 39 D 46 C
5C 12 A 19 D 26 D 33 A 40 C 47 C
6C 13 D 20 B 27 B 34 C 41 C 48 B
7D 14 A 21 B 28 B 35 D 42 A 49 B
-----------------------------------------------------------x-----------------------------------------------------------------
27. What are the characteristics of the American grid planning systems
a) Historical
b) Walkable
c) Sustainable
d) All of the above
29. One of the main advantages of the grid plan was _________
a) Allowed the rapid subdivision
b) Check the orientation of non-development areas
c) Centralized plan
d) None of the above
30. In American grid planning systems Costs for streets depend largely on _________
a) Four Variables
b) Eight Variables
c) Nine Variables
d) Twelve Variables
31. Is urban phobia is another name for anti-urbanism
a) No
b) May be
c) Yes
d) None of the above
32. Anti-urbanism is a discourse of fear of the city, produced and reproduced via a variety of
_________
a) Negative representations of urban places
b) Positive representations of urban places
c) Space for recreational
d) None of the above
33. _________ was one of the force which triggered anti-urban representations
a) Industralization
b) Migration
c) New catalyst formation
d) None of the above
34. The idea of the picturesque in urban design is the idea of looking at the environment as a
_________
a) Picture or a collection of 'pictures
b) Picture
c) Collection of 'pictures
d) All of the above
35. In the visual arts, architecture and urban design a sequence is a series of images
expressing a thought or feeling_________
a) Space-time experience
b) Non sequential spaces
c) Haptic experiences
d) All of the above
42. In city Nuovo the industrial hub was located around a_________ which was the railway
station that connected with other cities
a) Transit nodes
b) Green belt
c) Residential neighborhood
d) All of the above