Final Deviation (MCH Bhadrak)
Final Deviation (MCH Bhadrak)
Final Deviation (MCH Bhadrak)
( GROUND FLOOR )
1 2 3 4 5 6 7 8 9 10.00
24 Plastic paint two coats with any approved paint over one coat of primer including cost and labour
etc. complete.
Qnty Vide MB - 4065
3479.93 Sqm per sqm 132.40 460,742.73
p-155
25 Finishing wall with 2 coat of Weather Coat over one coat of Primer etc. complete
Qnty Vide MB - 4065
899.62 Sqm per sqm 125.90 113,262.16
p-158
26 Providing & Fixing of Acoustical Mineral Fibre Board of RH-99 with microperforated,finely granulated surface texture , beveled tegular
edge with 6mm Black Revealed exposed grid Suspended False Ceiling System, with tiles of Humidity Resistance (RH) of 99%, NRC
Upto 0.5, αw value 0.6, CAC- 34dB ,Light Reflectance >85%, thermal Conductivity k = 0.052- 0.057 w/m K, Colour White, Fire
Performance Class- 0/ Class -1 (BS476 Part 6&7) in module size of 600 X 600 X 16 mm with Bio Block coating on the face of the tile,
suitable for Green Building application, with Recycled content of 63%, fixed to G.I.grids of system with 15mm white flanges
incorporating a 6mm central reveal in white/black colour and with a web height of 38mm , having stiches both perpedicular and
horizontal to make it stronger, and a load carrying capacity of minimum 15.68 Kgs/Sqm. The Main Runners & Cross Tees to have
mitred ends & “birdsmouth” notches to provide mitred cruciform junctions. The T Sections have a Galvanizing of 120 grams per SQM
& passed
Qnty through
Vide MB -5004065 hrs of Salt test. The Tile & Grid system used together should carry a 15 year warrantee. The main G.I. runner
spaced at 1200mm centre to centre739.462
p-160
Sqm
securely fixed to the per sqm
structural soffit using G.I. suspension system at 1200mm maximum1436.50
centr to 1,062,237.16
27 centre & not more than 150mm from spliced joints. The First/Last suspension system at the end of
Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and eveneach main runner should not be
greater
surface than 600mm
to receive from the
painting adjacent
including wall.
cost 1200mm long
of scaffolding crosscharges
staging tees to with
be interlocked between main
cost of all materials labourrunners at 600mm
T & P etc. as centre to
formdirection
per 1200 x 600 mm module.
of Engineer Cut cross
-In -charge. tees longer
in Ground Floorthan 600mm require independent support. 600 x 600mm modules to be formed
by fitting 600mm long cross tees centrally between the 1200 mm cross tees. The 1200mm cross tees to have central “birdsmouth”
notches to facilitate fitting of 600mm cross tees. Perimeter trim to be shadow wall angle (dimensions: 19x7x7x14mm), secured to
Qnty Vide MB - 4065
walls at maximum 450 mm C/C,complete 3210.79 in all respectSqm
with all cost ,labour,T & P,Taxes etc as per per sqm of the Engineer 62.00
direction - in - 199,068.98
p-162
charge.
28 Aerated Autoclaved fly ash (AAC) Bricks/masonory in filler /inside walls using A.A.C . Blocks of size
625mmx200mmx200mm Having compressive strength not less then 4N/mm square conforming to IS
2185(part-3)-2005 and IS - 6441-1972 In cement mortar of mix ( 1:6 )and screened and washed sand for
moartar for use in super structre including splays cutting , circular moulding , corbelling chamfering
and similar such type of works , watering & curing etc including cost conveyance , royalty loading ,
unloading and taxes of all materials ,cost of all labour scaffolding sundries , T&P required for the
works etc complete in all respect as directed by the Engineer -In-Charge
EXTRA ITEM
Providing and fixing Factory made Fiber Glass Reinforced plastic (FRP) Door Frames of size 75mm x 100
mm fabricated using E-glass chopped strand mat (GSM) U.V Stabilised inopathalic gel cost and
impreganted with inopathalic resin the thickness of the GRP skins shall not be less then 2.0mm the door
frame consist of four segment which are provided with plug in socket arrangement in situ-in-mould . The
segments are pluged in and are joined together by means of screw the GRP frame shall be provided with
wooden rainforcement on six locaction for high screw capacity for fixing metalic hold fast and shall be
concidered by filling with medium destity foam /plaster of paris with fibre rainforcement . six numbers of
260mm x 25mm x 5mm size 'S' shaped MS Flat hold fast shall be provided with the frame.all complete as
directed by the Engineer -in-charge.
C) Chajja
Qnty Vide MB - 4065 p-
/ Sqm.
112 1 22.27 @ Rs. 851.00 Rs. 18,951.77
D) Roof Beams
Qnty Vide MB - 4065 p-
/ Cum.
114 1 65.8 @ Rs. 11351.70 Rs. 746,941.86
E) ROOF SLAB
Qnty Vide MB - 4065 p-
/ Cum.
116 1 107.346 @ Rs. 9687.00 Rs. 1,039,860.70
F) Staircase
Qnty Vide MB - 4065 p-
/ Cum.
118 1 12.265 @ Rs. 10791.40 Rs. 132,356.52
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying the grills
and placing in position including cost of binding wire 18 to 20 gauge etc. complete
including all cost, conveyance, taxes etc. complete as directed by the Engineer-in-charge.
3 Providing, fitting, fixing up partition walling OEL aluminium anodized section No. 9210 and 9207 as single
groove and double groove respectively as horizontal and vertical member and OEL section 4660 as Tapered
clip for fixing up 12mm thickPrelaminated particle board (Novapan standard type) (I.S.I.) and jointing angle No.
1855 including all fitting ,cost of all materials, taxes, labour, T&P etc. complete.
9 Supplying, fitting & fixing of 10 mm thick & size of 600x600 mm Glazed Vitrified floor
tiles (GVT) of matt finish(WOODEN FINISH/RUSTIC FINISH) with veilcraft (VC )
shield( Scratch free/stain free) with water absorption limit between 0.08% to 3% and
conforming to IS : 15622:2006 (Group B Ib). laid on 20 mm thick cement mortar (1:4) (1
cement : 4 course sand) and filling joints with white cement of approved quality including
cost of all materials, labour T&P etc. required for the work all complete as per direction of
the
QntyEngineer-in-charge
Vide MB - 4065 (forp- New Work only )
Sqm
136 1 781.19 @ Rs. 1155.20 Rs. 902,430.69
10 Supplying, fitting & fixing of Granite Tiles of minimum Above 0.40 sqm. (20mm thick) of
approved make in floors laid on 20 mm thick cement mortar (1:4) (1 cement : 4 course
sand) and filling joints with slurry including cost of all materials, labour T&P etc. required
for the work all complete incl. rubbing as per direction of the Engineer-in-charge
13 12 mm thick Cement Plaster(OUTER SIDE+INNER SIDE) with cement mortar (1:6) including all
cost, conveyance, taxes, royalities etc. complete as directed by the Engineer-in-charge.
15 Supplying, fitting & fixing of Industrial vitrified tiles (30x30)cm in floors of approved make laid on 20 mm thick cement
mortar (1:4) (1 cement : 4 course sand) and filling joints with slurry including cost of all materials, labour T&P etc required
for the work all complete as per direction of the Engineer-in-charge
16 Supplying of M.S. Window grill / Fixed Grill / Grill gate made out of
M.S.angle, M.S. flat & M.S. square etc including cutting, welding etc
complete as per direction of Engineer-in-charge.
Qnty Vide MB - 4065 p-
kg
151 1 1978.77 @ Rs. 62.20 Rs. 123,079.49
17 Painting two coats with approved Enamel Paint on wood work and Steel
work
Qnty Vide MB - 4065 p-
Sqm
153 1 40.17 @ Rs. 130.80 Rs. 5,254.24
18 Plastic paint two coats to walls with over one coat of primer of approved shade on new
work to give an even shade including cost of paint
Qnty Vide MB - 4065 p-
Sqm
156 1 2562.23 @ Rs. 135.20 Rs. 346,413.50
19 Painting two coats with any approved colour of weather seal coat over a
coat of Water Bound Wall cement Primer to out side surface of wall in
Ground Floor
Qnty Vide MB - 4065 p-
Sqm
158 1 475.8 @ Rs. 130.50 Rs. 62,091.90
20 Providing & Fixing of Acoustical Mineral Fibre Board of RH-99 with microperforated,finely granulated surface texture ,
beveled tegular edge with 6mm Black Revealed exposed grid Suspended False Ceiling System, with tiles of Humidity
Resistance (RH) of 99%, NRC Upto 0.5, αw value 0.6, CAC- 34dB ,Light Reflectance >85%, thermal Conductivity k =
0.052- 0.057 w/m K, Colour White, Fire Performance Class- 0/ Class -1 (BS476 Part 6&7) in module size of 600 X 600 X
16 mm with Bio Block coating on the face of the tile, suitable for Green Building application, with Recycled content of 63%,
fixed to G.I.grids of system with 15mm white flanges incorporating a 6mm central reveal in white/black colour and with a
web height of 38mm , having stiches both perpedicular and horizontal to make it stronger, and a load carrying capacity of
minimum 15.68 Kgs/Sqm. The Main Runners & Cross Tees to have mitred ends & “birdsmouth” notches to provide mitred
cruciform junctions. The T Sections have a Galvanizing of 120 grams per SQM & passed through 500 hrs of Salt test. The
Tile & Grid system used together should carry a 15 year warrantee. The main G.I. runner spaced at 1200mm centre to
centre securely fixed to the structural soffit using G.I. suspension system at 1200mm maximum centr to centre & not more
than 150mm from spliced joints. The First/Last suspension system at the end of each main runner should not be greater
than 600mm from the adjacent wall. 1200mm long cross tees to be interlocked between main runners at 600mm centre to
form 1200 x 600 mm module. Cut cross tees longer than 600mm require independent support. 600 x 600mm modules to
be formed by fitting 600mm long cross tees centrally between the 1200 mm cross tees. The 1200mm cross tees to have
central “birdsmouth” notches to facilitate fitting of 600mm cross tees. Perimeter trim to be shadow wall angle (dimensions:
19x7x7x14mm), secured to walls at maximum 450 mm C/C,complete in all respect with all cost ,labour,T & P,Taxes etc as
per direction of the Engineer - in - charge.
21 Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even
surface to receive painting including cost of scaffolding staging charges with cost of all materials labour T & P etc. as per
direction of Engineer -In -charge. in Ground Floor
E) ROOF SLAB
Qnty Vide MB - 4065 p-
@ Rs. / Cum.
116 1 105.776 10756.70 1,137,800.70
F) Staircase
Qnty Vide MB - 4065 p-
@ Rs. / Cum.
118 1 6.955 12082.00 Rs. 84,030.31
2 M.S. Reinforcement for RCC works including cutting, bending, binding and
tying the grills and placing in position including cost of binding wire 18 to 20
gauge etc. complete including all cost, conveyance, taxes etc. complete as
directed by the Engineer-in-charge.
Qnty Vide MB - 4065 p-
122 1 367.953 @ Rs. 6204.50 / Qntl. Rs. 2,282,964.39
3 Providing, fitting, fixing up partition walling OEL aluminium anodized section No. 9210
and 9207 as single groove and double groove respectively as horizontal and vertical
member and OEL section 4660 as Tapered clip for fixing up 12mm thick B.W.R ply
board and jointing angle No. 1855 including all fitting ,cost of all materials, taxes,
labour, T&P etc. complete.
Qnty Vide MB - 4065 p-
125 1 76.58 @ Rs. 459.00 Sqm Rs. 35,150.22
4 Supplying fitting fixing 12mm thick Prelaminated particle board (Novapan standard type) (I.S.I.)
14 6 mm thick Cement Plaster with cement mortar (1:4) over RCC surface
including deep chiping & including all cost, conveyance, taxes, royalities etc.
complete as directed by the Engineer-in-charge.
Qnty Vide MB - 4065 p-
147 1 1830.87 @ Rs. 148.50 Sqm Rs. 271,884.20
15 Supplying, fitting & fixing of Industrial vitrified tiles (30x30)cm in floors of approved
make laid on 20 mm thick cement mortar (1:4) (1 cement : 4 course sand) and filling
joints with slurry including cost of all materials, labour T&P etc required for the work
all complete as per direction of the Engineer-in-charge
Qnty Vide MB - 4065 p-
149 1 88.68 @ Rs. 834.50 Sqm Rs. 74,003.46
DETAILED ESTIMATE FOR THE WORK "CONSTRUCTION OF 100 BEDDED MCH COMPLEX AT
DISTRICT HEAD QUARTER HOSPITAL(DHH),BHADRAK FOR THE FY 2017-18"
(SECOND FLOOR)
say 11,063,067.00
A) Column
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying
the grills and placing in position including cost of binding wire 18 to 20 gauge etc.
complete including all cost, conveyance, taxes etc. complete as directed by the
Engineer-in-charge.
10 Supplying, fitting & fixing of Granite Tiles of minimum Above 0.10 Sqm & up to 0.4 sqm
(10mm. thick) of approved make in dadoes laid on 12 mm thick cement mortar (1:3)
(1 cement : 3 course sand) and filling joints with slurry including cost of all materials, labour
T&P etc. required for the work all complete incl. rubbing as per direction of the Engineer-in-
charge
Qnty Vide MB - 4065 p-
141 1 46.51 @ Rs. 2316.9 Sqm. Rs. 107,747.43
11 Supplying, fitting & fixing of Germ free Ceramic wall tiles of premium grade of size
600x300mm having thickness 6.5mm to 6.7mm confirming to IS 13753 in dadoes,
skirting and risers of steps laid on 12 mm thick cement mortar (1:3) (1 cement : 3
course sand) jointed with slurry mixed with pigment to match the shades of the
tiles etc. complete including cost of all materials, labour T&P etc. required for the
work all complete as per direction of the Engineer-in-charge
14 Supplying, fitting & fixing of Industrial vitrified tiles (30x30)cm in floors of approved make laid on 20 mm
thick cement mortar (1:4) (1 cement : 4 course sand) and filling joints with slurry including cost of all
materials, labour T&P etc required for the work all complete as per direction of the Engineer-in-charge
15 Supplying of M.S. Window grill / Fixed Grill / Grill gate made out of M.S.angle, M.S.
flat & M.S. square etc including cutting, welding etc complete as per direction of
Engineer-in-charge.
Qnty Vide MB - 4065 p-
152 1 2127.78 @ Rs. 62.20 kg Rs. 132,347.92
16 Painting two coats with any approved enamel paint to new iron work including cost
of the primer and paint sand papering polishing the surface with cost conveyance
and taxes of all materials and labour with T&P required for the work etc complete
in all respect.
Qnty Vide MB - 4065 p-
154 1 43.19 @ Rs. 137.40 kg Rs. 5,934.31
17 Plastic paint two coats to walls with over one coat of primer of approved shade on
new work to give an even shade including cost of paint
Qnty Vide MB - 4065 p-
156 1 2613.29 @ Rs. 141.00 kg Rs. 368,473.89
DETAILED ESTIMATE FOR THE WORK "CONSTRUCTION OF 100 BEDDED MCH COMPLEX AT
DISTRICT HEAD QUARTER HOSPITAL(DHH),BHADRAK FOR THE FY 2017-18"
(THIRD FLOOR)
say 10,913,031.00
47,977,554.15
B) Lintel
Qnty Vide MB - 4065 p-
110 1 10.27 @ Rs. 12463.30 / Cum. Rs. 127,998.09
C) Chajja
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying the
grills and placing in position including cost of binding wire 18 to 20 gauge etc. complete
including all cost, conveyance, taxes etc. complete as directed by the Engineer-in-
charge.
G. TOTAL= 12,593,030.80
Tender premium- 11.67% less 1,469,606.69
TOTAL= 11,123,424.10
say 11,123,424.00
Sl. No.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
1 2 3 4.00 5.00 6 7 8 9.00
1 R.C.C. work of M 20 using 20mm and down graded hard granite Crusher broken
chips including laying, hoisting, Centring & shuttering with all cost, conveyance
etc. complete.
A) Column
Qnty Vide MB - 4065
1 50.97 @ Rs. 18848.80 / Cum.
p-108 Rs. 960,723.34
B) Lintel
Qnty Vide MB - 4065
1 10.65 @ Rs. 14073.30 / Cum.
p-111 Rs. 149,880.65
C) Chajja
Qnty Vide MB - 4065
1 23.35 @ Rs. 1459.80 / Cum.
p-113 Rs. 34,086.33
D) Roof Beams
Qnty Vide MB - 4065
1 67.482 @ Rs. 18848.80 / Cum.
p-115 Rs. 1,271,954.72
E) Roof Slab
Qnty Vide MB - 4065
1 101.402 @ Rs. 15396.80 / Cum.
p-117 Rs. 1,561,266.31
F) Staircase
Qnty Vide MB - 4065
1 6.85 @ Rs. 17687.00 / Cum.
p-119 Rs. 121,138.26
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying
the grills and placing in position including cost of binding wire 18 to 20 gauge
etc. complete including all cost, conveyance, taxes etc. complete as directed by
the Engineer-in-charge.
Sl. No.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
1 2 3 4.00 5.00 6 7 8 9.00
6 Supplying, fitting & fixing of 10 mm thick & size of 600x600 mm Glazed Vitrified floor tiles (GVT)
of matt finish(WOODEN FINISH/RUSTIC FINISH) with veilcraft (VC ) shield( Scratch free/stain
free) with water absorption limit between 0.08% to 3% and conforming to IS : 15622:2006
(Group B Ib). laid on 20 mm thick cement mortar (1:4) (1 cement : 4 course sand) and filling joints
with white cement of approved quality including cost of all materials, labour T&P etc. required for
the work all complete as per direction of the Engineer-in-charge (for New Work only )
12 Supplying, fitting & fixing of Industrial vitrified tiles (30x30)cm in floors of approved make laid on
20 mm thick cement mortar (1:4) (1 cement : 4 course sand) and filling joints with slurry including
cost of all materials, labour T&P etc required for the work all complete as per direction of the
Engineer-in-charge
Sl. No.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
1 2 3 4.00 5.00 6 7 8 9.00
Qnty Vide MB - 4065
1 38.730 @ Rs. 144.40 kg
p-154 Rs. 5,592.61
15 Plastic paint two coats to walls with over one coat of primer of approved shade
on new work to give an even shade including cost of paint
Sl. No.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
1 2 3 4.00 5.00 6 7 8 9.00
1 R.C.C. work of M 20 using 20mm and down graded hard granite Crusher broken
chips including laying, hoisting, Centring & shuttering with all cost, conveyance
etc. complete.
A) Column
Qnty Vide MB - 4065 p-
108 1 50.970 @ Rs. 21729.30 / Cum. Rs. 1,107,542.42
B) Lintel
Qnty Vide MB - 4065 p-
111 1 15.270 @ Rs. 15998.70 / Cum. Rs. 244,300.15
C) Chajja
Qnty Vide MB - 4065 p-
113 1 22.920 @ Rs. 1694.00 / Cum. Rs. 38,826.48
D) Roof Beams
Qnty Vide MB - 4065 p-
115 75.926 @ Rs. 21729.30 / Cum. Rs. 1,649,818.83
E) Roof Slab
Qnty Vide MB - 4065 p-
117 121.920 @ Rs. 17587.00 / Cum. Rs. 2,144,207.04
F) Staircase
Qnty Vide MB - 4065 p-
119 6.955 @ Rs. 20335.30 / Cum. Rs. 141,432.01
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying
the grills and placing in position including cost of binding wire 18 to 20 gauge etc.
complete including all cost, conveyance, taxes etc. complete as directed by the
Engineer-in-charge.
Providing and fixing of aluminum composite panel glazing fixed to wall surface of approved made &
quality with ACP indo bord 3mm thick mirror finish of exterior grade ,the size of outer aluminum sqare
frame as 100 x 44mm , inner aluminum sqare frame of 50 x 63mm . Accessories such a stainless steel
screw ,VHP tape 789 grade silicon ,colr etc .Complete including cost ,conveyance texes of all materials
labour ,tranceportation charges ,centering shuttering charges etc as per the specificaction & direction of
the Engineer -in -charge . The section are to be cut to will by means of sell expending screw etc.
complete.
Qnty Vide MB - 4065 p-
168 506.830 @ Rs. 7566.00 sqm Rs. 3,834,675.78
G. TOTAL= 19,363,572.47
Tender premium- 11.67% less 2,259,728.91
TOTAL= 17,103,843.56
say 17,103,844.00
DETAILED ESTIMATE FOR THE WORK "CONSTRUCTION OF 100 BEDDED MCH COMPLEX AT DISTRICT HEAD
QUARTER HOSPITAL(DHH),BHADRAK FOR THE FY 2017-18"
(SIXTH FLOOR)
Sl.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
No.
1 2 3 4.00 5.00 6 7 8 9.00
1 R.C.C. work of M 20 using 20mm and down graded hard granite Crusher broken chips
including laying, hoisting, Centring & shuttering with all cost, conveyance etc. complete.
A) Column
Qnty Vide MB - 4065 p-
110 11.560 @ Rs. 25178.50 / Cum. Rs. 291,063.46
B) Roof Beams
Qnty Vide MB - 4065 p-
115 11.232 @ Rs. 25178.50 / Cum. Rs. 282,804.91
C) Roof Slab
Qnty Vide MB - 4065 p-
115 17.950 @ Rs. 20207.80 / Cum. Rs. 362,730.01
2 M.S. Reinforcement for RCC works including cutting, bending, binding and tying the grills
and placing in position including cost of binding wire 18 to 20 gauge etc. complete including
all cost, conveyance, taxes etc. complete as directed by the Engineer-in-charge.
Sl.
Description of Item No. Length Breadth Height Quantity Unit Amount (In Rs.)
No.
1 2 3 4.00 5.00 6 7 8 9.00
12 Aerated Autoclaved fly ash (AAC) Bricks/masonory in filler /inside walls using A.A.C . Blocks of size
625mmx200mmx200mm Having compressive strength not less then 4N/mm square conforming to
IS 2185(part-3)-2005 and IS - 6441-1972 In cement mortar of mix ( 1:6 )and screened and washed
sand for moartar for use in super structre including splays cutting , circular moulding , corbelling
chamfering and similar such type of works , watering & curing etc including cost conveyance ,
royalty loading , unloading and taxes of all materials ,cost of all labour scaffolding sundries , T&P
required for the works etc complete in all respect as directed by the Engineer -In-Charge
Sl. No Description of Items No. Length Bredth Height Unit Quantity Rate Amount
1 Earth work in excavation of foundation trenches in hard soil including dressing and
levelling the bed upto the reqd. Depth and depositing the exavated materials with
all leads and lift T&P etc. complete per directionof engineer-in-charge.
Base
Qnty Vide MB - 4065
p-120 12.150 @ Rs. 4843.20 / Cum. 58,844.88
Wall
Qnty Vide MB - 4065
p-120 31.150 @ Rs. 9387.60 / Cum. 292,423.74
Slab
Qnty Vide MB - 4065
p-121 5.615 @ Rs. 8243.20 / Cum. 46,285.57
5 Providing High Yielding Strength Deformed rein forcement with all cost of
materials and labour T&P etc. complete as er direction of Engineer-in-Charge.
6 mm thick Cement Plaster with cement mortar (1:4) over RCC surface
6 including deep chiping & including all cost, conveyance, taxes, royalities
etc. complete as directed by the Engineer-in-charge.
Qnty Vide MB - 4065
p-148 226.800 @ Rs. 141.50 sqm 32,092.20
G. TOTAL= 1,165,835.88
Tender premium- 11.67% less 136,053.05
Total 1,029,782.83
say 1,029,783.00
PLINTH PROCTION
4 RC.C. work of M 20 using 20mm and down graded hard granite Crusher broken chips
including laying, hoisting, Centring & shuttering with all cost, conveyance etc. complete.
1 Earthwork in excavation in ordinary soil within 50m initial lead and 1.5m initial lift including
rough dressing and breaking clods to maximum 5cm to 7 cm and laying in layer not exceeding
0.3 m in depth etc complet as per the direction of Engineer-in-charge.
Base
Qnty Vide MB - 4065
p-120 23.800 @ Rs. 4843.20 / Cum. Rs. 115,268.16
Wall
Qnty Vide MB - 4065
p-121 58.190 @ Rs. 9387.60 / Cum. Rs. 546,264.44
Providing High Yielding Strength Deformed rein forcement with all cost of materials and labour T&P
etc. complete as er direction of Engineer-in-Charge.
5
Qnty Vide MB - 4065
p-124 59.922 @ Rs. 6160.80 qtl Rs. 369,167.46
6 6 mm thick Cement Plaster with cement mortar (1:4) including all cost, conveyance, taxes,
royalities etc. complete as directed by the Engineer-in-charge.
122,435,749.65
1 1 CIVIL WORK
Excavation of foundation in soil
with hydraulic excavator of 0.9
cum bucket capacity including
cutting and loading in tippers,
trimming bottom and side
slopes, in accordance with
requirements of lines, grades and
cross-sections, and transporting
to the embankment location with
a lift upto 1.5 m and lead upto
1000 m as per Technical -
Specification Clause 302.3 &
T&P required for the work
complete including cost of all
labour,labour cess,T&P,sundries
etc. as directed by the Engineer
in charge.
###
###
3.01 3.01 Building Proper Cum 2777.02 545.40 1514586.71 5300.9 2,891,110.86 1,376,524.15 90.88 Execution made according to###
3.02 3.02 RCC Drain Cum 17.28 545.40 9424.51 48.21 26,293.73 16,869.22 178.99 structural design of foundation###
3.03 3.03 plinth proction Cum 545.40 - - which is more than the estimate###
provision
3.04 3.04 perifery parking Cum 545.40 1338.09 729,794.29 729,794.29 100.00 ###
4 4 Providing and laying plain
cement concrete of proportion
(1:3:6) in foundation and floors
using 4 cm. size black hard
crusher broken granite stone
metal and screened and washed
sharp sand for mortar of
approved quality and from
approved quarry including
hoisting, lowering, laying
concrete, ramming, watering and
curing etc. complete to required 0.00 - -
levels laid in layers not
exceeding 15 cm. thick in each
layer including cost,
conveyance, royalties, of all
materials and cost of all
labours,labour cess, T&P etc
complete as per the direction of
the Engineer-in-charge.
###
4.01 4.01 Building Proper Cum 249.08 4420.20 1100983.42 198.03 875,332.21 225651.21 20.50 Completed ###
4.02 4.02 RCC Drain Cum 11.52 4420.20 50920.70 9.72 42,964.34 7956.36 15.63 ###
- Execution made according to site
plinth proction Cum 0.00 4420.20 0.00 - ###
requirment.
perifery parking Cum 0.00 4420.20 0.00 231.21 1,021,994.44 1,021,994.44 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
5 5 R.C.C. work of M-20 in
following works using 12 mm. to
20 mm. (½” to ¾”) size (20 mm.
not to exceed 25%) hard black
crusher broken granite stone
chips of approved quality from
approved quarry including
hoisting, lowering, laying and
compacting concrete, watering
curing, centering, shuttering and
finishing the exposed surfaces
smooth with cost, conveyance,
royalties of all materials with all
labour,labour cess and T & P
required for the work etc.
complete in all respect but - -
excluding the cost and
conveyance of M.S. rods or Tor
steel and binding wire of 18 to
20 gauge and labour charges for
straightening, cutting, bending,
binding and tying the grills and
placing in proper position and as
per the direction of the Engineer-
in-charge.
###
Execution made according to
514.675 2,492,673.96 45.76 structural design of foundation
6 6 Raft foundation Cum 948.80 4843.20 4595228.16 2102554.20
which is Less than the estimate
provision ###
###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
###
17.01 17.01 Building Proper Cum 211.01 4134.10 872336.44 93.649 387,154.33 485182.11 55.62 ###
plinth proction Cum 0.00 4134.10 0.00 - - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
18 18 Fly Ash brick masonry in
cement mortar (1:6) in super
structure using Fly Ash bricks of
25 x 12 x 8 cm size having a
crushing strength of not less than
75 kg./sqcm with dimensional
tolerance ± 2% including splays
cutting circular moulding
chamfering and corbelling and
similar such type of works with
all necessary projections
watering and curing after 0.00 - - 0.00
immersing the bricks in water at
least for six hours before use
including cost, conveyance,
royalties of all materials with all
labour,labour cess and T & P
required for the work complete
in all respect as per direction of
Engineer-in-Charge.
###
18.01 18.01 Ground Floor Cum 188.15 4172.50 785055.88 - 785055.88 100.00 ###
18.02 18.02 1st Floor Cum 178.57 4410.80 787636.56 - 787636.56 100.00 ###
18.03 18.03 2nd Floor Cum 214.08 4684.80 1002921.98 - 1002921.98 100.00 ###
18.04 18.04 3rd Floor Cum 206.13 5000.00 1030650.00 - 1030650.00 100.00 ###
Substitution of (A.A.C ) Block
18.05 18.05 4th Floor Cum 182.74 5362.40 979924.98 - 979924.98 100.00 ###
18.06 18.06 5th Floor Cum 215.83 5779.20 1247324.74 - 1247324.74 100.00 ###
18.07 18.07 6th Floor Cum 157.87 6258.60 988045.18 - 988045.18 100.00 ###
18.08 18.08 7th Floor Cum 95.08 6809.80 647475.78 - 647475.78 100.00 ###
- - ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
19 19 Fly Ash brick masonry in
cement mortar (1:4) in super
structure using Fly Ash bricks of
25 x 12 x 8 cm size having a
crushing strength of not less than
75 kg./sqcm with dimensional
tolerance ± 2% including splays
cutting circular moulding
chamfering and corbelling and
similar such type of works with
all necessary projections
watering and curing after - - 0.00
immersing the bricks in water at
least for six hours before use
including cost, conveyance,
royalties of all materials with all
labour,labour cess and T & P
required for the work complete
in all respect as per direction of
Engineer-in-Charge.
###
19.01 19.01 Ground Floor Cum 17.94 4368.30 78367.30 - 78367.30 100.00 ###
19.02 19.02 1st Floor Cum 14.00 4606.60 64492.40 - 64492.40 100.00 ###
19.03 19.03 2nd Floor Cum 12.82 4880.70 62570.57 - 62570.57 100.00 ###
19.04 19.04 3rd Floor Cum 17.35 5195.80 90147.13 - 90147.13 100.00 Substitution of (A.A.C ) Block
###
19.05 19.05 4th Floor Cum 30.49 5558.30 169472.57 - 169472.57 100.00 ###
19.06 19.06 5th Floor Cum 31.87 5975.10 190426.44 - 190426.44 100.00 ###
19.07 19.07 6th Floor Cum 31.87 6454.40 205701.73 - 205701.73 100.00 ###
- - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
20 20 Providing fitting and fixing up
partition walling OEL
aluminum anodized section
No.9210 and 9207 as single
groove and double groove
respectively as horizontal and
vertical member and OEL
section 4660 as Tapered clip
for fixing up 12mm thick pre-
laminated board (Nova pan
make) and jointing angle
- - 0.00
No.1855 etc. including cost,
conveyance, of all materials
(Excluding cost of 12mm
thick pre-laminated board)
with labour and T&P
complete in all respect as
direction of Engineer-in-
Charge.
###
20.01 20.01 Ground Floor Kg. 74.86 459.00 34360.74 268.33 123,163.47 88,802.73 258.44 ###
20.02 20.02 1st Floor Kg. 250.77 459.00 115103.43 160.25 73,554.75 41548.68 36.10 ###
76.58 35,150.22 22.51 Qnty.executed as per approved
20.03 20.03 2nd Floor Kg. 62.51 459.00 28692.09 6,458.13 ###
architectural design.
20.04 20.04 3rd Floor Kg. 114.66 459.00 52628.94 209.1 95,976.90 43,347.96 82.37 ###
20.05 20.05 4th Floor Kg. 187.62 459.00 86117.58 441.24 202,529.16 116,411.58 135.18 ###
21 21 Supplying, fitting and fixing
with 12mm thick Pre-laminated
Particle board(Standard type)
(ISI) fixed to the bottom portion
of door frame by means of
tapered clip No. 4660 including 0.00 - - 0.00
all cost of material, labour,
labour cess T&P etc. complete in
all respect as per direction of
Engineer in charge.
###
21.01 21.01 Ground Floor Sqm. 14.61 753.60 11010.10 52.21 39,345.46 28,335.36 257.36 ###
21.02 21.02 1st Floor Sqm. 48.94 753.60 36881.18 31.3 23,587.68 13293.50 36.04 ###
14.95 11,266.32 22.54 Qnty.executed as per approved
21.03 21.03 2nd Floor Sqm. 12.20 753.60 9193.92 2,072.40 ###
architectural design.
21.04 21.04 3rd Floor Sqm. 22.38 753.60 16865.57 40.84 30,777.02 13,911.46 82.48 ###
21.05 21.05 4th Floor Sqm. 36.62 753.60 27596.83 86.18 64,945.25 37,348.42 135.34 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
22 22 Providing and Fixing of
Structural Glazing approved
make to be febricated from roll
formed sections made of
prepainted steel(base steel as
per IS-513 of 0.6mm thick
'D'quality galvanized as per IS-
277 with zinc of120gm per
sqm) with primer of 5 -
75.7microns thick and finished
paint with po-lyster paint ( Black
/ Pearl white / Chocolatebrown)
of12-16microns along with the
alkydbacker at the back of 5-7
microns and thesizes of outer
frame being 46 x 52mm andwith
all vertical & horizontal 0.00 - - 0.00
mullions are of46 x 70mm and
fixed beading are of 18 x 25mm.
Sections for internal top and
bottomframes in the louvered
area should be 18 x40mm. Top
hung shutter should be
46x46mm. Accesories/ ed
beadings are of 18x25mm.
Accessories/ gaskets are to be
used as per the manufacturer's
supply and specification like
handle being made of high grade
aluminium powder coated and
with nylon recever and gasket
will be made of EPDM. All
corner brackets are to be made ###
of CRCA with zinc phosphating. 518.59 5,047,695.77 23.77
22.01 22.01 Ground Floor Sqm. 419.00 9733.50 4078336.50 969,359.27 do ###
The mullion caps and louvered-
clips should be glass filled
nylon. The sections are to be cut
to length jointed and assembled
by means of corner bracket and
frames are fixed to the concrete /
masonry walls by means of
self expanding screws and glass
to be used with safety laminated
glass of 12.38 mm thick with
0.76 mm inter layer Poly Vinyl
Butyral (PVB) lamination
between two glass with outer
being 6 mm thick toughened
reflective of Reflactsol series of
Saint Globain & inner glass
being of 6mm thick toughened
clear of Saint Gobain make etc.
complete.
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
23 23 Providing and fixing of Swing
Door of approved make to be
fabricated from roll formed
sections made of pre-painted
steel (base steel as per IS-513 of
0.6 mm thick “D” quality,
galvanized as per IS-277 with
zinc of 120 Gm/Sq.mtr) with
paint specification being with
primer of 5-7 microns and
finished paint with polyster paint
(Black /Pearl white/ Chocolate
Brown) of 12-16 microns
alongwith the alkyd backer at the
back of 5-7 microns and the
sizes of outer frame being of 33
x 57 mm and shutter being of 46 0.00 - - 0.00 do
x 52 mm and 46 x 46 mm and
lock rail should be of 23 x
130mm. Accessories / gaskets
are to be used as per the
manufacturer’s supply and
specification like handle, lock
and floor spring of approved
quality. Gasket will be made of
EPDM. All corner brackets are
to be made of CRCA with zinc
phosphating. The sections are to
be cut to length ,mitre joined
with corner bracket and frames
are fixed to the
concrete/masonry walls by
means of self expanding screws ###
and glass to be used of 6 mm 14.09 97,070.24 50.05
23.01 23.01 Ground Floor Sqm. 9.39 6889.30 64690.53 32,379.71 ###
23.02 23.02 1st Floor Sqm. 4.70 6889.30 32379.71 16.00 110,228.80 77,849.09 240.43 ###
23.03 23.03 2nd Floor Sqm. 4.70 6889.30 32379.71 22.09 152,184.64 119,804.93 370.00 Qnty.executed as per approved###
23.03 23.03 3rd Floor Sqm. 0.00 6889.30 0.00 12.00 82,671.60 82,671.60 100.00 architectural design. ###
23.03 23.03 4th Floor Sqm. 0.00 6889.30 0.00 8.72 60,074.70 60,074.70 100.00 ###
23.03 23.03 6th Floor Sqm. 0.00 6889.30 0.00 4.72 32,517.50 32,517.50 100.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
24 24 Providing & fixing of side hung
door of approved make to be
fabricated from roll formed
sections made of pre -painted
steel (base steel as per IS-513 of
0.60 mm thick "D" qualiyu,
galvanised as per IS-277 with
zinc of 120 gm/sqm)with paint
specification being with primer
of 5-7 microns thick & finished
paint with polyster paint
(Black/Pearl white/Chocolate
brown) of 12-16 microns along
with the alkyd backer at the back
of 5-7 microns & the size of
outer frame being of 46 x 52mm
and shutter being of 46 x 46 mm 0.00 - - 0.00 do
and lock rail and bottom rail
should be of 23 x 130mm.
Accessories/gaskets are to be
used as per the manufacturer's
supply & specifiction like handle
and lock of approved quality.
Hinges made up of 2.5mm thick.
Gasket will be made of EPDM .
All corner brackets are to be
made of CRCA with zinc
phosphating. The sections are to
be be cut to length, mitre joined
with corner bracket &frames are
fixed to the concrete/ masonry
walls by means of self
expanding screws & board to be ###
of 9mm prel-laminated etc. 51.19 250,569.93 34.76
24.01 24.01 Ground Floor Sqm. 78.46 4894.90 384053.85 133483.92 ###
24.02 24.02 1st Floor Sqm. 79.52 4894.90 389242.45 41.41 202,697.81 186544.64 47.93 ###
24.03 24.03 2nd Floor Sqm. 75.59 4894.90 370005.49 47.26 231,332.97 138672.52 37.48 ###
Completed
24.04 24.04 3rd Floor Sqm. 78.56 4894.90 384543.34 50.77 248,514.07 136029.27 35.37 ###
24.05 24.05 4th Floor Sqm. 91.80 4894.90 449351.82 55.47 271,520.10 177831.72 39.58 ###
24.06 24.06 5th Floor Sqm. 96.08 4894.90 470301.99 60.50 296,141.45 174160.54 37.03 ###
24.07 24.07 6th Floor Sqm. 100.31 4894.90 491007.42 114.09 558,459.14 67,451.72 13.74 Completed ###
- - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
25 25 Supply and fixing of Un-
plasticised Poly Vinyl Chloride
(UPVC) sliding windows of
FENESTA / NCL or equivalent
three track - only two glass
shutters sliding duly
manufactured using UPVC
reinforced profiles of 80mm x
52mm x 2.25mm or equivalent
for outer frames, 54mm x 38mm
x 2.25mm or equivalent for
sliding shutter frames capable of
mounting single glazing system,
structurally reinforced with hot
dip galvanized up to 50 microns
of minimum thickness of 1.2mm
prefabricated & welded through 0.00 - - 0.00
fusion welding the window sash
shall be fitted with 5mm thick
clear float glass (toughened) of
reputed make duly fixed with
EPDM weathering seal resistant
accessories like clipping locking
system made of aluminium 1
no., per set of sashes and the
system is to be installed at the
site using anchor fasteners,
silicon rubber sealant, easy
glazing / deglazing at site with
10 years manufactures warranty
for discoloration, wraping,
mechanical failures, shrinkages,
rotting, corrosion etc. with a ###
quality certificate from relevant 64.55 361,505.17 0.00
25.01 25.01 Ground Floor Sqm. 64.55 5600.39 361505.17 - 0.00 ###
25.02 25.02 1st Floor Sqm. 60.75 5600.39 340223.69 68.35 382,786.66 42,562.96 12.51 ###
25.03 25.03 2nd Floor Sqm. 60.75 5600.39 340223.69 71.39 399,811.84 59,588.15 17.51 ###
25.04 25.04 3rd Floor Sqm. 75.17 5600.39 420981.32 74.40 416,669.02 4312.30 1.02 Qnty.executed as per approved###
25.05 25.05 4th Floor Sqm. 59.99 5600.39 335967.40 66.07 370,017.77 34,050.37 10.14 architectural design. ###
25.06 25.06 5th Floor Sqm. 51.64 5600.39 289183.98 58.46 327,398.80 38,214.82 13.21 ###
25.07 25.07 6th Floor Sqm. 48.61 5600.39 272234.96 48.61 272,234.96 - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
26 26 Providing and fixing of Fixed
Glazing with part Top hung of
approved make to be fabricated
from roll formed sections made
of pre-painted steel (base steel as
per IS-513 of 0.6 mm thick “D”
quality, galvanized as per IS-277
with zinc of 120 Gm/Sq.mtr)
with paint specification being
with primer of 5-7 microns and
finished paint with polyster paint
(Black /Pearl white/ Chocolate
Brown) of 12-16 microns
alongwith the alkyd backer at the
back of 5-7 microns and the
sizes of outer frame being of
46x52 mm and with all vertical 0.00 - - 0.00
and horizontal mullions are of
46x70 mm and fixed beadings
are of 18x25 mm. Top hung
shutter should be of 46 x 46 mm.
Accessories / gaskets are to be
used as per the manufacturer’s
supply and specification like
handle being made of high grade
aluminium powder coated and
with nylon receiver and gasket
will be made of EPDM. All
corner brackets are to be made
of CRCA with zinc phosphating.
The mullion caps and louvered-
clips should be of glass filled
nylon. The sections are to be cut ###
to length ,mitre joined with 13.4 65,054.32 104.89
26.01 26.01 Ground Floor Sqm. 6.54 4854.80 31750.39 33,303.93 ###
26.02 26.02 1st Floor Sqm. 5.84 4854.80 28352.03 11.15 54,131.02 25,778.99 90.92 ###
26.03 26.03 2nd Floor Sqm. 5.12 4854.80 24856.58 9.46 45,926.41 21,069.83 84.77 ###
26.04 26.04 3rd Floor Sqm. 7.28 4854.80 35342.94 10.59 51,412.33 16,069.39 45.47 Qnty.executed as per approved###
26.05 26.05 4th Floor Sqm. 5.08 4854.80 24662.38 10.05 48,790.74 24,128.36 97.83 architectural design. ###
26.06 26.06 5th Floor Sqm. 5.46 4854.80 26507.21 10.05 48,790.74 22,283.53 84.07 ###
26.07 26.07 6th Floor Sqm. 2.52 4854.80 12234.10 22.62 109,815.58 97,581.48 797.62 ###
26.08 26.08 7th Floor Sqm. 4.36 4854.80 21166.93 4.36 21,166.93 - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
27 27 Providing 16 mm thick cement
plaster with cement mortar of
mix (1:6) with screened and
washed sharp sand for mortar
and finished smooth to the rough
surface of walls in all heights
after racking out joints including
watering and curing, rounding of
corners, providing grooves
where ever necessary with cost, 0.00 - - 0.00
conveyance, royalties of all
materials with cost of all
labour,labour cess, T&P, and
scaffolding required for the work
etc. complete in all respect as
directed by the Engineer in
charge.
###
27.01 27.01 Ground Floor Sqm. 5284.71 181.70 960231.81 - 960231.81 100.00 ###
27.02 27.02 1st Floor Sqm. 2430.37 186.10 452291.86 - 452291.86 100.00 ###
27.03 27.03 2nd Floor Sqm. 2213.48 190.60 421889.29 - 421889.29 100.00 ###
27.04 27.04 3rd Floor Sqm. 2460.45 195.30 480525.89 - 480525.89 100.00 Due to (A.A.C ) Block both side
###
are FACE Side. 16 mm plaster not
27.05 27.05 4th Floor Sqm. 2494.34 200.10 499117.43 - 499117.43 100.00 required. ###
27.06 27.06 5th Floor Sqm. 2504.94 205.10 513763.19 - 513763.19 100.00 ###
27.07 27.07 6th Floor Sqm. 2524.98 210.20 530750.80 - 530750.80 100.00 ###
27.08 27.08 7th Floor Sqm. 511.44 215.40 110164.18 - 110164.18 100.00 ###
- - ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
28 28 Supplying fitting & fixing of 10
mm thick & size of 600 x 600
mm Glazed Vetrified Tiles
(GVT) of matt finish
(WOODEN FINISH/RUSTIC
FINISH) with veilcraft (VC)
shield (Scratch free/stain free)
with water absorption limit
between 0.08% to 3% and
conforming to IS : 15622:2006
(Group B Ib), in floor laid on
20mm thick cement motar (1.:4) - - 0.00
(1 cement :4 course sand) and
filling joints with white cement
of approved quality including all
cost, labour, conveyance,T&P,
royality etc.all complete as per
direction of the Engineer-in-
charge.
###
28.01 28.01 Ground Floor Sqm. 839.68 1146.20 962441.22 1015.57 1,164,046.33 201,605.12 20.95 ###
28.02 28.02 1st Floor Sqm. 841.59 1155.20 972204.77 781.19 902,430.69 69774.08 7.18 ###
28.03 28.03 2nd Floor Sqm. 707.69 1164.50 824105.01 799.05 930,493.73 106,388.72 12.91 Qnty.executed as per approved###
28.04 28.04 3rd Floor Sqm. 745.95 1174.30 875969.09 745.14 875,017.90 951.18 0.11 architectural design. ###
28.05 28.05 4th Floor Sqm. 715.37 1184.60 847427.30 726.42 860,517.13 13,089.83 1.54 ###
28.06 28.06 5th Floor Sqm. 758.43 1195.50 906703.07 678.25 810,847.88 95855.19 10.57 ###
28.07 28.07 6th Floor Sqm. 772.08 1206.80 931746.14 724.167 873,924.74 57821.41 6.21 ###
29 29 Fixing Granite tiles of approved
dimension area above 0.4 sqm
(20mm thick) in floor, treads of
steps and landing on 20mm thick
bed of cement mortar (1:4)
jointed with neat cement slurry
mixed with pigment to match the
shades of the tiles including 0.00 - - 0.00
rubbing and polishing etc.
complete with cost, conveyance,
royalties of all materials
complete in all respects as per
direction of Engineer-in-Charge.
###
29.01 29.01 Ground Floor Sqm. 47.01 2174.40 102218.54 99.54 216,439.78 114,221.23 111.74 ###
29.02 29.02 1st Floor Sqm. 47.01 2183.30 102636.93 37.158 81,127.06 21509.87 20.96 ###
29.03 29.03 2nd Floor Sqm. 47.01 2192.70 103078.83 37.158 81,476.35 21602.48 20.96 ###
Qnty.executed as per approved
architectural design.
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
22.482 49,516.61 35.14 Qnty.executed as per approved
29.04 29.04 3rd Floor Sqm. 34.66 2202.50 76338.65 26822.05 ###
architectural design.
29.05 29.05 4th Floor Sqm. 33.42 2212.80 73951.78 22.482 49,748.17 24203.61 32.73 ###
29.06 29.06 5th Floor Sqm. 33.42 2223.60 74312.71 22.482 49,990.98 24321.74 32.73 ###
29.07 29.07 6th Floor Sqm. 33.42 2235.00 74693.70 22.482 50,247.27 24446.43 32.73 ###
30 30 Fixing granite tiles of approved
dimension area above 0.4 sqm
(20mm thick) in Dados, treads of
steps and landing on 12mm thick
cement mortar (1:3) jointed with
neat cement slurry mixed with
pigment to match the shades of
the tiles including rubbing and 0.00 - - 0.00 do
polishing etc. complete with
cost, conveyance, royalties and
taxes of all materials complete in
all respects as per direction of
Engineer-in-Charge.
###
30.01 30.01 Ground Floor Sqm. 53.13 2274.60 120849.50 60.167 136,855.86 16,006.36 13.24 ###
30.02 30.02 1st Floor Sqm. 53.13 2288.10 121566.75 53.974 123,497.91 1,931.16 1.59 ###
30.03 30.03 2nd Floor Sqm. 53.13 2302.10 122310.57 53.974 124,253.55 1,942.97 1.59 ###
46.505 107,747.43 55.07 Qnty.executed as per approved
30.04 30.04 3rd Floor Sqm. 29.99 2316.90 69483.83 38,263.60 ###
architectural design.
30.05 30.05 4th Floor Sqm. 29.99 2332.40 69948.68 46.505 108,468.26 38,519.59 55.07 ###
30.06 30.06 5th Floor Sqm. 29.99 2348.70 70437.51 46.505 109,226.29 38,788.78 55.07 ###
30.07 30.07 6th Floor Sqm. 29.99 2365.80 70950.34 46.505 110,021.53 39,071.19 55.07 ###
31 31 Fixing of Germ Free Ceramic
wall tiles of premium grade
having thickness 6.5mm to
6.7mm confirming to IS 13753
of size 600mm x 300mm in
dados skirting & riser of steps on
12mm thick cement plaster 1:3
joined with neat cement slurry
mixed with pigments to match
the shade of the tiles, including - - 0.00 do
rubbing & polishing etc.
complete including cost,
conveyance, royalties of all
materials, labour with T&P
complete in all respects as per
direction of Engineer-in-Charge.
###
31.01 31.01 Ground Floor Sqm. 944.88 1200.00 1133856.00 1424.84 1,709,808.00 575,952.00 50.80 ###
31.02 31.02 1st Floor Sqm. 1031.52 1213.40 1251646.37 1353.18 1,641,948.61 390,302.24 31.18 ###
###
32.01 32.01 Ground Floor Sqm. 597.97 128.20 76659.75 3,602.50 461,840.50 385,180.75 502.45 ###
32.02 32.02 1st Floor Sqm. 380.11 131.20 49870.43 2674.50 350,894.40 301,023.97 603.61 ###
32.03 32.03 2nd Floor Sqm. 377.10 134.30 50644.53 2761.51 370,870.79 320,226.26 632.30 ###
32.04 32.04 3rd Floor Sqm. 370.16 137.40 50859.98 2452.35 336,952.89 286,092.91 562.51 Due to (A.A.C ) Block both side
###
are FACE Side. 16 mm plaster not
32.05 32.05 4th Floor Sqm. 378.69 140.70 53281.68 2531.00 356,111.70 302,830.02 568.36 required. ###
32.06 32.06 5th Floor Sqm. 376.98 144.00 54285.12 2647.61 381,255.84 326,970.72 602.32 ###
32.07 32.07 6th Floor Sqm. 387.19 147.50 57110.53 2654.97 391,608.08 334,497.55 585.70 ###
32.08 32.08 7th Floor Sqm. 245.75 151.00 37108.25 1160.78 175,277.78 138,169.53 372.34 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
33 33 Providing 6 mm thick cement
plaster with cement mortar of
mix (1:4) with screened and
washed sharp sand for mortar
and finished smooth to R.C.C.
work after closed deep chipping
& slurry treatment including
watering and curing, rounding of
corners, providing grooves
where ever necessary with cost, - - 0.00
conveyance, royalties of all
materials with cost of all
labour,labour cess, T&P, and
scaffolding required for the work
etc. complete in all respect as
directed by the Engineer in
charge.
###
33.01 33.01 Ground Floor Sqm. 1290.71 141.50 182635.47 2205.59 312,090.99 129,455.52 70.88 ###
33.02 33.02 1st Floor Sqm. 1562.06 145.00 226498.70 1716.70 248,921.50 22,422.80 9.90 ###
33.03 33.03 2nd Floor Sqm. 1664.07 148.50 247114.40 1830.87 271,884.20 24,769.80 10.02 ###
33.04 33.04 3rd Floor Sqm. 1648.16 152.20 250849.95 1807.51 275,103.02 24,253.07 9.67 ###
33.05 33.05 4th Floor Sqm. 1655.64 156.00 258279.84 1767.50 275,730.00 17,450.16 6.76 Qnty.executed as per approved###
33.06 33.06 5th Floor Sqm. 1665.98 159.90 266390.20 1789.16 286,086.68 19,696.48 7.39 architectural design. ###
33.07 33.07 6th Floor Sqm. 1663.33 163.90 272619.79 2046.87 335,481.99 62,862.21 23.06 ###
33.08 33.08 7th Floor Sqm. 104.99 168.00 17638.32 328.73 55,226.64 37,588.32 213.11 ###
drain Sqm. 0.00 141.50 0.00 226.80 32,092.20 32,092.20 100.00 ###
33.08 33.08 perifery parking Sqm. 0.00 141.50 0.00 332.20 47,006.30 47,006.30 100.00 ###
34 34 Supplying, fitting and fixing
vetrified Industrial tiles in floors
of premium grade having
thickness 8mm to 10mm of size
300mm x 300mm confirming to
IS 4457 with colour / printed
series of approved make on
20mm thick bed of C.M. (1:4) - - 0.00
including cost of all materials,
taxes, labour, T&P etc. required
for the work in all respect as
directed by the Engineer in
charge.
###
34.01 34.01 Ground Floor Sqm. 57.63 816.30 47043.37 88.68 72,389.48 25,346.12 53.88 ###
34.02 34.02 1st Floor Sqm. 57.63 825.20 47556.28 145.68 120,215.14 72,658.86 152.79 ###
34.03 34.03 2nd Floor Sqm. 57.63 834.50 48092.24 88.68 74,003.46 25,911.23 53.88 Qnty.executed as per approved###
architectural design.
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
Qnty.executed as per approved
34.04 34.04 3rd Floor Sqm. 57.63 844.30 48657.01 88.68 74,872.52 26,215.52 53.88 architectural design. ###
34.05 34.05 4th Floor Sqm. 57.63 854.60 49250.60 88.68 75,785.93 26,535.33 53.88 ###
34.06 34.06 5th Floor Sqm. 57.63 865.50 49878.77 88.68 76,752.54 26,873.78 53.88 ###
35 35 Supplying, of M.S. grills, Grill
gates, M.S. gates, Garage door,
collapsible gates with top and
bottom rails, steel windows,
critical frames for windows, stair
case and parapet railing made
out of M.S Square bar/ flat
including stair case hand railing
with 40mm. dia G.I.pipe etc.
including painting two coats
- - 0.00
over a coat of redoxide primer as
per approved drawing and design
with cost of all materials &
labour, labour cess, T&P,
sundries etc. complete in all
respect as per specification &
direction of the Engineer-in-
Charge.
###
35.01 35.01 Ground Floor Kg. 2815.62 62.20 175131.56 5358.79 333,316.74 158,185.17 90.32 ###
35.02 35.02 1st Floor Kg. 1518.87 62.20 94473.71 1978.77 123,079.49 28,605.78 30.28 ###
35.03 35.03 2nd Floor Kg. 1500.00 62.20 93300.00 2076.02 129,128.44 35,828.44 38.40 ###
35.04 35.04 3rd Floor Kg. 1879.17 62.20 116884.37 2127.78 132,347.92 15,463.54 13.23 Qnty.executed as per approved###
35.05 35.05 4th Floor Kg. 1499.66 62.20 93278.85 1922.86 119,601.89 26,323.04 28.22 architectural design. ###
35.06 35.06 5th Floor Kg. 1541.41 62.20 95875.70 1567.45 97,495.39 1,619.69 1.69 ###
35.07 35.07 6th Floor Kg. 1215.34 62.20 75594.15 3155.20 196,253.44 120,659.29 159.61 ###
35.08 35.08 7th Floor Kg. 813.32 62.20 50588.50 726.82 45,208.20 5380.30 10.64 ###
36 36 Painting two coat with approved
synthetic enamel paint to new
wood & iron work including
cost, conveyances, royalties of
all materials and cost of all
labour with T&P required for the - - 0.00
work etc. complete as per
specification & direction of
Engineer in charge.
###
36.01 36.01 Ground Floor Sqm. 44.99 127.60 5740.72 60.21 7,682.80 1,942.07 33.83 ###
36.02 36.02 1st Floor Sqm. 30.38 130.80 3973.70 40.17 5,254.24 1,280.53 32.23 ###
36.03 36.03 2nd Floor Sqm. 30.38 134.00 4070.92 42.14 5,646.76 1,575.84 38.71 ###
36.04 36.04 3rd Floor Sqm. 75.17 137.40 10328.36 43.19 5,934.31 4394.05 42.54 ###
39.04 5,496.83 30.18 Qnty.executed as per approved
36.05 36.05 4th Floor Sqm. 29.99 140.80 4222.59 1,274.24 ###
architectural design.
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount Qnty.executed as per approved
architectural design.
36.06 36.06 5th Floor Sqm. 28.10 144.40 4057.64 38.73 5,592.61 1,534.97 37.83 ###
36.07 36.07 6th Floor Sqm. 24.31 148.10 3600.31 55.58 8,231.40 4,631.09 128.63 ###
36.08 36.08 7th Floor Sqm. 8.58 151.90 1303.30 11.08 1,683.05 379.75 29.14 ###
37 37 Painting two coats with plastic
emulsion paint over a coat of
Water Bound Wall cement
Primer to make an even finished
surface in all floors and heights
to wall surface of approved
make and shade including sand
papering, applying putty
wherever necessary & cost of - - 0.00
scaffolding, staging charges with
cost, conveyance, of all
materials, cost of all
labour,labour cess, T&P etc.
complete as per the direction of
the Engineer-in-charge.
###
37.01 37.01 Ground Floor Sqm. 5179.51 132.40 685767.12 3479.93 460,742.73 225024.39 32.81 ###
37.02 37.02 1st Floor Sqm. 2240.44 135.20 302907.49 2562.23 346,413.50 43,506.01 14.36 ###
37.03 37.03 2nd Floor Sqm. 1975.67 138.00 272642.46 2771.07 382,407.66 109,765.20 40.26 ###
37.04 37.04 3rd Floor Sqm. 2544.70 141.00 358802.70 2613.29 368,473.89 9,671.19 2.70 ###
Qnty.executed as per approved
37.05 37.05 4th Floor Sqm. 2560.51 144.00 368713.44 2716.98 391,245.12 22,531.68 6.11 ###
architectural design.
37.06 37.06 5th Floor Sqm. 2732.31 147.10 401922.80 3024.76 444,942.20 43,019.40 10.70 ###
37.07 37.07 6th Floor Sqm. 2608.84 150.30 392108.65 3065.183 460,697.00 68,588.35 17.49 ###
37.08 37.08 7th Floor Sqm. 511.44 153.60 78557.18 612.64 94,101.50 15,544.32 19.79 ###
38 38 Wall painting two coats with
Weather coat paint (1st quality)
exterior grade of approved make
& approved shade over a coat of
Water Bound Wall cement - - 0.00
Primer to make an even finished
surface in all floors and heights
with all scaffolding and staging ###
charges including cost, 899.62 113,262.16 50.45
38.01 38.01 Ground Floor Sqm. 597.97 125.90 75284.42 37,977.74 ###
conveyance of all materials, cost
38.02 38.02 1st all
of Floor
labours, labour cess, T & Sqm. 380.11 130.50 49604.36 475.80 62,091.90 12,487.55 25.17 ###
38.03 38.03 2ndsundries
P, Floor etc. as required for Sqm. 377.10 135.30 51021.63 475.8 64,375.74 13,354.11 26.17 ###
38.04 38.04 the
3rd work
Floor complete in all respect Sqm. 370.16 140.40 51970.46 475.8 66,802.32 14,831.86 28.54 ###
as per the direction of the Qnty.executed as per approved
38.05 38.05 4th Floor Sqm. 378.69 145.70 55175.13 475.8 69,324.06 14,148.93 25.64 ###
Engineer-in-Charge. architectural design.
38.06 38.06 5th Floor Sqm. 376.98 151.30 57037.07 475.8 71,988.54 14,951.47 26.21 ###
38.07 38.07 6th Floor Sqm. 387.19 157.20 60866.27 475.8 74,795.76 13,929.49 22.89 ###
38.08 38.08 7th Floor Sqm. 245.75 163.40 40155.55 876.87 143,280.56 103,125.01 256.81 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
39 39 Providing & Fixing of
Acoustical Mineral Fibre Board
of RH-99 with
microperforated,finely
granulated surface texture ,
beveled tegular edge with 6mm
Black Revealed exposed grid
Suspended False Ceiling System,
with tiles of Humidity
Resistance (RH) of 99%, NRC
Upto 0.5, αw value 0.6, CAC-
34dB ,Light Reflectance >85%,
thermal Conductivity k = 0.052-
0.057 w/m K, Colour White, Fire
Performance Class- 0/ Class -1
(BS476 Part 6&7) in module
size of 600 X 600 X 16 mm with - - 0.00
Bio Block coating on the face of
the tile, suitable for Green
Building application, with
Recycled content of 63%, fixed
to G.I.grids of system with
15mm white flanges
incorporating a 6mm central
reveal in white/black colour and
with a web height of 38mm ,
having stiches both perpedicular
and horizontal to make it
stronger, and a load carrying
capacity of minimum 15.68
Kgs/Sqm. The Main Runners &
Cross Tees to have mitred ends
& “birdsmouth” notches to ###
provide mitred cruciform 739.462 1,062,237.16 1098.87
39.01 39.01 Ground Floor Sqm. 61.68 1436.50 88603.32 973,633.84 ###
39.02 39.02 1st Floor Sqm. 0.00 1436.50 0.00 454.07 652,271.56 652,271.56 100.00 ###
39.03 39.03 2nd Floor Sqm. 25.35 1436.50 36415.28 673.69 967,755.69 931,340.41 2557.55 ###
39.04 39.04 3rd Floor Sqm. 0.00 1436.50 0 540.6 776,571.90 776,571.90 100.00 Qnty.executed as per approved###
architectural design.
39.05 39.05 4th Floor Sqm. 162.89 1436.50 233991.49 720.097 1,034,419.34 800,427.86 342.08 ###
39.06 39.06 5th Floor Sqm. 0.00 1436.50 0.00 672.897 966,616.54 966,616.54 100.00 ###
39.07 39.07 6th Floor Sqm. 445.31 1436.50 639687.82 714.263 1,026,038.80 386,350.98 60.40 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
40 40 Finishing plastered surfaces of
walls with cement based wall
putty (Water based) of approved
make and finishing the surface
smooth and even by sand
papering to receive painting in
walls, at all heights with staging
wherever necessary with cost,
conveyance, of all materials, - - 0.00
cost of all labour,labourcess, all
T&P etc. required for the work
complete in all respect as per the
direction of the Engineer-in-
charge.
###
40.01 40.01 Ground Floor Sqm. 5179.51 62.00 321129.62 3210.79 199,068.98 122060.64 38.01 ###
40.02 40.02 1st Floor Sqm. 2240.44 62.00 138907.28 2562.23 158,858.26 19,950.98 14.36 ###
40.03 40.03 2nd Floor Sqm. 1975.67 62.00 122491.54 2771.07 171,806.34 49,314.80 40.26 ###
40.04 40.04 3rd Floor Sqm. 2544.70 62.00 157771.40 2613.29 162,023.98 4,252.58 2.70 Qnty.executed as per approved###
architectural design.
40.05 40.05 4th Floor Sqm. 2560.51 62.00 158751.62 2716.98 168,452.76 9,701.14 6.11 ###
40.06 40.06 5th Floor Sqm. 2732.31 62.00 169403.22 3024.76 187,535.12 18,131.90 10.70 ###
40.07 40.07 6th Floor Sqm. 2608.84 62.00 161748.08 3065.183 190,041.35 28,293.27 17.49 ###
40.08 40.08 7th Floor Sqm. 511.44 62.00 31709.28 612.64 37,983.68 6,274.40 19.79 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
41 41 Providing & Fixing of Clip-in
Swing Down plain
(Mirror/Brush )finish Stainless
Steel (SS)ceiling System
consisting of 600x600 mm clip
in tiles of stainless steel in 0.5
mm thickness with bevel edge
in white colour (RAL 9010) with
Light Reflectance > 60% and
suitable for Green Building
application with Recycled
content of 25%. The product
must be conforming
EN13964:2004 standard. The
Clip-in Tile & Grid system used
together should carry a 15 year
warrantee.Comprising of Double - - 0.00
Frame System ,consisting of
3000mm long ‘C’ channels
spaced at 1200mm C/C securely
fixed to the structural soffit by
support clamp & approved
hangers. The last hanger at the
end of each "C" channel should
not be greater than 600mm from
the adjacent wall, using "C"-
channel connector for splicing
two pieces of "C"-channels.
4000mm Dp-12 Main carriers
(spring tee bars) shall be spaced
at 600mm C/C in a direction
perpendicular to the "C"-
channels and shall be secured at ###
every intersection with C 307.67 1,228,957.05 9.07
41.01 41.01 1st Floor Sqm. 282.08 3994.40 1126740.35 102,216.70 ###
41.02 41.02 2nd Floor Sqm. 94.55 3994.40 377670.52 102.55 409,625.72 31,955.20 8.46 qnty to be executed ###
41.03 41.03 3rd Floor Sqm. 183.53 3994.40 733092.23 162.13 647,612.07 85480.16 11.66 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
42 42 Supplying, fitting and fixing of
Stainless steel of 304 grade in
hand railing using 50mm dia of
2mm thick circular pipe with
Balustrade of size 32mm x
32mm x 2mm @ 0.90mtr. C/C
and stainless square pipe bracing
of size 32mm x 32mm x 2mm in
3 rows in stair case as per
approved design and Kg. 6874.86 287.10 1973772.31 7179.17 2,061,139.71 87,367.40 4.43 do
specification, buffing, polishing
etc with cost, conveyance of all
materials, cost of all
labour,labour cess, T&P etc.
required for the work complete
in all respect as per direction of
the Engineer-in-charge.
###
43 43 Providing 2.5cm thick Grading
Concrete over roof slab with
cement concrete (1:2:2) using
6mm size black hard granite
crusher broken chips and
screened & washed sharp sand
for mortar and finished smooth
to the rough surface of slab
including watering and curing - - 0.00
with cost, conveyance, royalties
of all materials with cost of all
labour, labour cess and T&P
required for the work etc.
complete in all respect as
directed by the Engineer in
charge.
###
43.01 43.01 6th Floor Sqm. 868.26 491.40 426661.98 1268.85 623,512.89 196,850.91 46.14 do ###
43.02 43.02 7th Floor Sqm. 102.01 549.40 56044.29 91.16 50,083.30 5960.99 10.64 do ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
44 44 Earth work in excavation of
foundation trenches in hard soil
including dressing of sides and
levelling the bed up to the
required depth and depositing
the excavated materials away
from the work site within 50m
initial lead & 1.5m initial lifts
with sundries & T&P required - - 0.00
for the work complete including
cost of all labour,labour
cess,T&P,sundries etc. as
directed by the Engineer in
charge.
###
44.1 44.1 RCC Drain Cum 138.24 167.80 23196.67 92.67 15,550.03 7646.65 32.96 ###
- Qnty.executed as per approved
44.02 44.02 Plinth proction Cum 0.00 167.80 0.00 - 0.00 ###
architectural design.
44.03 44.03 Periphery parking Cum 0.00 167.80 0.00 300.09 50,355.10 50,355.10 100.00 ###
111,833,914.49 ###
1 1 SUBSTITUDE ITEM - - 0.00 ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
Aerated Autoclaved fly ash
(AAC) Bricks/masonory in
filler /inside walls using A.A.C .
Blocks of size
625mmx200mmx200mm Having
compressive strength not less
then 4N/mm square conforming
to IS 2185(part-3)-2005 and IS -
6441-1972 In cement mortar of
mix ( 1:6 )and screened and
washed sand for moartar for use
in super structre including splays
cutting , circular moulding ,
corbelling chamfering and
- - 0.00
similar such type of works ,
watering & curing etc including
cost conveyance , royalty
loading , unloading and taxes of
all materials ,cost of all labour
scaffolding sundries , T&P
required for the works etc
complete in all respect as
directed by the Engineer -In-
Charge
###
Ground Floor Cum 4269.83 221.79 947,005.60 947,005.60 100.00 ###
1st Floor Cum 4329.19 205.27 888,652.83 888,652.83 100.00 ###
2nd Floor Cum 4397.46 201.99 888,242.95 888,242.95 100.00 ###
3rd Floor Cum 4475.97 175.09 783,697.59 783,697.59 100.00 ###
4th Floor Cum 4566.25 201.27 919,049.14 919,049.14 100.00 ###
5th Floor Cum 4670.08 208.62 974,272.09 974,272.09 100.00 ###
6th Floor Cum 4789.48 204.77 980,741.82 980,741.82 100.00 ###
7th Floor Cum 4926.80 109.19 537,957.29 537,957.29 100.00 ###
Execution made according to site
-
requirment. ###
Execution made according to site
-
requirment. ###
DEVIATION STATEMENT
NAME OF THE WORK: CONSTRUCTION 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTER HOSPITAL (D H H) BHADRAK.
AGREEMENT NO-108P , ( E E) 2019-2020 NAME OF THE AGENCY - DIVINE CONSTRUCTION.
less
ex
AS PER AGREEMENT AS PER EXECUTION Percentage of
Sl.
Description Of Item Excess Less Excess/Less From Remark
No. Aegreement
Units Quantity Rate Amount Quantity Amount
2 2 Providing and fixing Factory
made Fiber Glass Reinforced
plastic (FRP) Door Frames of
size 75mm x 100 mm fabricated
using E-glass chopped strand
mat (GSM) U.V Stabilised - - 0.00
inopathalic gel cost and
impreganted with inopathalic
resin the thickness of the GRP
skins shall not be less then
2.0mm the door frame consist of ###
four segment which are
provided with plug in socket rm 551.7 Execution made according to site
603.9 333,171.63 333,171.63 100.00
arrangement in situ-in-mould . requirment. ###
3 3 The segments
Supplying are pluged
, fitting & fixing in of
and
are joined together
Prepolished cement by concrete
means of
screw the
Paving GRP
tiles of frame
22-25shall
mm be
provided with wooden
thick of make ultra eurocornor
rainforcement on six locaction for
duracrete
high screw in floor offorsize
capacity with
fixing
applicaction
metalic hold fastof 20mm
and shallthick
be
cement
concidered mortar (1:4)
by filling and
with filling
medium
joint
destitywith
foamwhite
/plaster of paris - -
cement.including
with fibre rainforcement all cost,
. six
numbers of 260mm
conveyance, taxes,x 25mm x
royalities
5mmcomplete
etc. size 'S' shaped MS Flatby
as directed
holdEngineer-in-charge.
the fast shall be provided with
the frame.all complete as
directed by the Engineer -in-
charge.
###
sqm 877
1457.99 1,278,657.23 1,278,657.23 100.00 Execution made according to site
requirment. ###
118,601,073.87 34,495,199.35 27,728,039.97 ###
6,767,159.38 6,767,159.38 ###
EXTRA ITEM - ###
RATE ANALYSIS AS PER ( C S R ) ( Dt.0-26-11-2021 )
Providing and fixing of aluminum composite panel glazing fixed to wall surface of approved made & quality
with ACP indo bord 3mm thick mirror finish of exterior grade ,the size of outer aluminum sqare frame as 100 x
44mm , inner aluminum sqare frame of 50 x 63mm . Accessories such a stainless steel screw ,VHP tape 789
grade silicon ,colr etc .Complete including cost ,conveyance texes of all materials labour ,tranceportation
charges ,centering shuttering charges etc as per the specificaction & direction of the Engineer -in -charge . The
section are to be cut to will by means of sell expending screw etc. complete.
Executive Engineer
Junior Engineer Deputy Executive Engineer
Bhadrak(R & B) Section-1 Bhadrak (R & B) Sub Division Bhadrak ( R & B) Division
COMPRISION RATE OF EXTRA ITEMS AS PER CSR AND DERIVED RATE FROM AGREEMENT NO - 108 P, (C E )2019-20
(M.C.H BUILDING )
NAME OF THE WORK: CONSTRUCTION OF 100 BEDDED MCH COMPLEX AT DISTRICT HEAD QUARTERS HPSPITAL ( D H H ) BHADRAK.
Assistant Engineer Deputy Executive Engineer Executive Engineer Superintending Engineer Eastern
Bhadrak (R&B) section-I Bhadrak (R&B) Sub- Division Bhadrak (R&B) Division Circle [R&B] Balasore
GENERAL ABSTRACT
( REVISED )
A) Building Proper
i) Ground Floor Rs. 30,875,566.00 Rs 30,609,450.33 Rs 30,248,838.43
ii) First Floor Rs. 9,063,700.00 Rs 11,883,265.56 Rs 12,915,699.50
iii) Second Floor Rs. 9,475,100.00 Rs 11,979,779.21 Rs 12,524,699.02
iv) Third floor Rs. 9,698,300.00 Rs 12,717,257.30 Rs 12,354,841.05 As per Approved structural
v) Fourth floor Rs. 10,121,200.00 Rs 12,824,901.63 Rs 12,593,030.80 design estimate are
framed.
vi) Fifth floor Rs. 13,051,300.00 Rs 15,074,728.86 Rs 14,663,702.42
vii) Sixth floor Rs. 14,494,500.00 Rs 13,152,852.77 Rs 19,363,572.47
viii) Seventh floor Rs. - Rs 2,468,350.97 Rs 2,447,022.67
Sub.Total (A) 96,779,666.00 Rs 110,710,586.63 Rs 117,111,406.36
Whether the deviation is due to extra quantity and / or :- yes. The deviationis due to extra quantity of work
26 extra items of work
If the extra items of work , whether the rates approved :- No such case
27 (In comparison with the current S/R ) may be
indicated
Whether any audit para /draft para/AG para/vigilance :- No
28 case/court case
Whether recommended of E.E & S.E :- Yes , the E.E & S.E have reecommended for approval of Excess
29 deviation.
Authority competent to approve the deviation :- Since the netexcess deviation bellow 5% than the corresponding
30 agreement amount , it needs approval of C.E Building
Executive Engineer
Bhadrak (R&B) Division
LEAD STATEMENT
SL. NO. DESCRIPTION OF MATERIALS UNIT NAME OF QUARRY COST OF CARRIAGE CARRIAG
LEA E+ GRAND
D IN 1st 5km Extra Total ROYALTY ROYALT COST TOTAL
charge Carriage Y
1 2 3 4 5 6 7 8 9 10 11 12
1 A.A.C . Blocks of size 625mmx200mmx200mm Having compressive
strength not less then 4N/mm square conforming to IS 2185(part-3)- 192 nos cuttack (Tangi) 80 967.27 0 2739.00 0 3706.27 13359.51 17065.78
2005 and IS - 6441-1972
2 40mm size C.B.H.G. Metal (passing through 45mm sieve & retained Cum Bagudi 47 149.67 369.6 519.27 130 649.27 746.67 1395.94
on 26.5mm sieve)
3 20mm size C.B.H.G. Chips ( Minimum 65% passing through 19mm &
retained on 13.2mm but whole should pass through 26.5mm sieve) Cum Bagudi 47 149.67 369.6 519.27 130 649.27 1060 1709.27
4
12mm size C.B.H.G. CHIPS (Minimum 65% passing through 13.2mm Cum Bagudi 47 149.67 369.6 519.27 130 649.27 1096.19 1745.46
& retained on 9.5mm but whole should pass through 19mm sieve )
5
10mm size C.B.H.G. CHIPS (Minimum 65% passing through 9.5mm
& retained on 6.3mm but whole should pass through 13.2mm Cum Bagudi 47 149.67 369.6 519.27 130 649.27 1120 1769.27
sieve )
6 4.7mm size C.B.H.G. Chips (passing through 6.7mm sieve & retained Cum Bagudi 47 149.67 369.6 519.27 130 649.27 674.29 1323.56
on 2.36mm sieve)
7 Rough stone granite quarried Cum Bagudi 47 149.67 369.6 519.27 130 649.27 214.85 864.12
8 Sand for mortar Cum Rudhia 35 149.67 264 413.67 35 448.67 49.52 498.19
9 sand for filling Cum Rudhia 35 149.67 264 413.67 35 448.67 44.76 493.43
10 Steel oct-2018 MT Bhubaneswar 129 161.72 922.56 1084.28 0 1084.28 48347 49431.28
11 Cement (Excluding cost of empty cement bag) MT Bhadrak 5 161.72 0 161.72 0 161.72 5000 5161.72
12 All types of Tiles Sqm Bhadrak 5 5.37 0 5.37 0 5.37
13 Angular truss & purlin MT 0
14 Wood Cum local 5 129.38 0 129.38
Certified that, the leads providing in the estimate are correct and minimum to the best of my knoledge.
Cement (Excluding cost of empty cement bag)
e) P.H ( External ) :-
9,677,967.00
:- 1,500,000.00
f) W/M & Autoclave shredder L/S
:- 2,000,000.00
g) CC TV Intercome system
:- 196,156,704.00
Total (a to g)
:- 967,797.00
Quality Control @ 1%
:- 1,354,915.00
Contigency @1%
Prorota/ Departmental charges :-
:- 198,479,416.00
Total
Till to date position of allotment received , expenditure incurred and balance amount af allotments available with deviation ( Furnish the
4 information financial year wise )
Amount of actual payment mode to the concerned /contracter through different running bill execuction of this work .till to date
position of payment mode to the contracter (i.e. up to deviation statement to be furnished in the proforma furnished bellow )
5(A)
Cumulative Balance amount Avallable
Reference of Total amount of
Sl no Voucher no & date amount of running M.B. Date of Remark
running bill the running bills Page No
bills No Measurment
1 2 3 4 5 6 7 8 9
1 40/07-03-2020 1St R/A 6,225,225.00 6,225,225.00 4043 7
2 15/15-05-2020 2nd R/A 2,009,934.00 8,235,159.00 4043 15
3 18/21-07-2020 3rd R/A 4,138,915.00 12,374,074.00 4043 25
4 22/13-8-2020 4th R/A 3,941,216.00 16,315,290.00 4043 37
5 41/25-9-2020 5th R/A 8,172,642.00 24,487,932.00 4043
6 10/04-11-2020 6th R/A 7,063,368.00 31,551,300.00 4043
7 10/04-11-2020 7th R/A 2,462,764.00 34,014,064.00 4043
8 115/28-12-2020 8th R/A 10,867,406.00 44,881,470.00 4043
9 9th R/A 6,852,851.00 51,734,321.00 4043
Whether any amount is kept pending towards approval of deviation
5(B) :- Nill
statement by the higher authorites
18 If not ,state the present position of the work. :- The work is in progress likely to be comleted
Authority approved the tender (furnish the copy of the Lr. No. & date
26 :- L.r NO-34145, Date 14th aug' 2019
of the same )
Authority accepted the tender (furnish the copy of the Lr. No. & date
of the same )
27 :- L.r NO-34145, Date 14th aug' 2019
Reasons of deviation - furnish details along with all technical report As per structural design of Building . footing foundation
and other supporting documents to prove the reasons for deviation. adopted in place of Raft foundation, Hight of the building
:-
changed.and client requirement
32
Whether the case is Recommended by the Executive Engineer
concerned Yes , the E.E have reecommended for approval of Excess
33 :-
deviation.
:-
N B. Proforma prescribed for deviation statement and relative position of the tenderer of the work. Relative position of the tenders are
remained unchanged being it is a percentage basis.
N B.
Descripction of the item of works unit Accepted rate of the Provision as per the Agreement
SL NO tenderer
Qty. Amount
1 2 3 4 5 6
As per actual axecution Amount of Amount of less percentage of Agreement Sl Actual resons of deviation
Excess work (+) work (-) ve excess/less no.
ve
Qty Amount
7 8 9 10 11 12 13
Assistant Engineer
Executive engineer Superintending Engineer
Asst. Executive Engineer
Bhadrak [R&B] Eastern Circle [R&B]
Bhadrak [ R&B] Sub division
Bhadrak [R & B ] Division Balasore
Section-1
COST ABSTRACT
CONSTRUCTION OF 100 BEDED MCH COMPLEX AT DHH BHADRAK
sqm 10 507.87
Prepolished cement concrete paving tiles of
22-25 mm thick of make ultra @ rs60.00/sft
sand cum 0.21 49.52
cement qntl 0.744 509.04
Cement for slurry qntl 0.33 509.04
white cement qntl 0.076 1514.96
b) Labour
mason special each 2.16 453.4
man mulia each 2.16 303.4
sqm 10 5.37
Prepolished cement concrete paving tiles of
22-25 mm thick of make ultra @ rs60.00/sft
Sand cum 0.21 448.67
Cement cum 0.744 16.17
Cement for slurry cum 0.33 16.17
white cement cum 0.076 16.17
say
2 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of
cross-section 90 mm x 45 mm having single rebate of 32 mm x 15 mm to
receive shutter of 30 mm thickness .The laminate shall be moulded with
fire resistant grade unsaturated polyester resin and chopped mat. Door
frame laminate shall be 2 mm thick and shall be filled with suitable wooden
block in all the three legs. The frame shall be covered with fiber glass from
all sides. M.S. stay shall be provided at the bottom to steady]
the frame.
Factory made glass reinforced plastic door metre 5.00 330.00
frame 90x45 mm i/c carriage
LABOUR :
3 Supplying, fiting and fixing of big six A.C. sheet in roof including fixing of ridges &
wind ties
Roofing for etc. including cost of all fitings and drilling the holes in wind ties etc
9.30Sqm
(a) labour
Carpenter-Spl class 1.00 No 260.00
Man mulia 3.00 No 200.00
15% O.H charges and CP
T&P-2%
Total:
Rate for one Sqm
Rate for three Sqm
Cost of AC Sheet-3.00 Sqm 3.00 Sqm 250.00
Cost of iron angle(50x50x6mm) & wind ties (25x6mm)
Ironn Angle-50x50x6mm(3x1mtr= 3.00 Mtr @4.50kg/mtr=13.50Kg
Wind ties- (25x6mm)3x1mtr=3mtr@1.20Kg/mtr= 17.10 Kg 101.94
Total:
Rate per one Sqm
Add for Cess @1%
Say:
5078.70
10.40
378.73
167.98
115.14
5750.95
979.34
655.34
1634.69
553.92
553.92
53.70
94.22
12.03
5.34
1.23
166.52
8532.58
853.26
8.66
874.66
875.00 per/sqm
1650.00
68.01
45.51
1763.52
264.53
2028.05
260.00
600.00
129.00
17.20
1006.20
108.19
324.58
750.00
1743.17
2493.17
831.06
8.31
839.37
839.40
REVISED ABSTRACT
Rs 30,300,845.21
Rs 4,000,000.00
Rs 1,000,000.00
35,300,845.21
Rs 4,119,608.64
Rs 31,181,236.57
Rs 311,812.37
Rs 31,493,048.94
Rs 3,779,165.87
Rs 35,272,214.81
35,272,215.00
Executive Engineer
Bhadrak (R&B) Division
REVISED ABSTRACT
13,527,756.44
1,578,689.18
11,949,067.26
119,490.67
12,068,557.94
1,448,226.95
13,516,784.89
13,516,785.00
Executive Engineer
Bhadrak (R&B) Division