Bitumen Coarse

Bitumen Coarse is the top layer of pavement and the layer that comes in direct
contact with traffic. This layer should be able to withstand traffic and weather
(High and low temperature, Rain) without exhibiting various distress like cracking,
rutting etc. It may be composed of one or two layers as per the design.

Function
 Bitumen Coarse provides structural support to the pavement surface.
 This layer also transmits the load to the sub grade and sub base layer (DBM,
WMM, and GSB).

Material Required for Bituminous Concrete


1. Bitumen (Binder)
2. Coarse Aggregate
3. Fine Aggregate
4. Filler
5. Anti-stripping agent

The individual specifications are already given in the last article of (DBM Layer).

Grading Requirement for DBM


Grading I II

Nominal Aggregate
19mm 13.2mm
Size

Layer Thickness 50mm 30-40mm

OBC Min 5.2% Min 5.4%


Cumulative % by
Cumulative % by weight of
IS Sieve (mm) weight of total
total aggregate passing
aggregate passing

26.5 100 –

19.0 90-100 100

13.2 59-79 90-100

9.5 52-72 70-88

4.75 35-55 53-71

2.36 28-44 42-58

1.18 20-34 34-48

0.6 15-27 26-38

0.3 10-20 18-28

0.15 5-13 12-20

0.075 2-8 4-10


In case aggregate have specific gravity more than 2.7, minimum bitumen content
can be reduced proportionally.

Grading Requirement for BC

Requirements of Fines in DBM:


Dense Bitumen Macadam (MORTH V):

Fines Requirement  (75 mic


Layer Thickness Remarks
passing)

Grading 1 (MORTH V
40-50 mm               2-8 %
Table 500-17)

Grading 2 (MORTH V
30-40 mm             4-10 %
Table 500-17)

Plasticity Index≤ 4%                                      Sand Equivalent Value < 50%


Quality Control Tests Required for Bitumen and Aggregate
Testing and frequency will be same as of DBM. Therefore we can refer to the
given link.

Construction of BC Layer
Construction steps are same as given in DBM layer. Please refer to the link

Productivity
 BC Productivity              :     21000-25000 MT/month/team/day
 Paver Productivity        :     50 m³/hr     
 Roller productivity        :     40 m³/hr