SUBSEA CONTROLS PROJECT

REFERENCES
INTRODUCTION
Proserv has been manufacturing control systems in the UK since 1976 and has considerable
experience in subsea production system engineering and subsea control system design.

As the industry technology has advanced into locating much of the production equipment on the
seabed so Proserv has developed control, monitoring and safety shutdown systems which are able to
operate in this equipment either from the surface, or the subsea environment.

Early involvement in the Subsea arena began for Proserv in the 1980’s with the design and prototype
manufacture of our own subsea control module, using our in-house spool-type control valves. These
whilst initially adapted and evaluated for subsea use did not show the degree of durability of the
carbide shear seal type valves used in our subsea control systems today.

A number of subsea hydraulic systems for short step-outs and SSIV controls were made, but it was
the development of our Wellcon multiplexed electronic programmable control modules employing
shear-seal valves that established Proserv presence in the subsea market.

In 1992 our first complete multiplexed Electro-Hydraulic subsea control system was developed and
the first full system deployed the following year.

In 1999 the Artemis subsea control system was developed adding deep water ROV deployment to
the product line.

The inclusion of the Sicom OCC modem technology in 2007 enabled open and high performance
subsea network availability.

In 2014 Proserv launch the latest generation subsea electronics Artemis 2G (A2G) which provides
operators with a reliable, more accessible and flexible system with increase data and power
performance and full compliance with latest SIIS, IWIS, ISO and API specifications

With much more reliance on oil and gas field life extension and brownfield expansion of older field the
Artemis and A2G technology from Proserv now provides an alternative to using the original
Equipment Manufacture with the Augmented Controls Technology (ACT) provided by Proserv subsea
controls technology.

In 2017 the latest OCX modem from Proserv provides greater communication processing, extended
bandwidth and inbuilt configuration tools to provide our solutions with up to 4Mbps data speeds over
distance on powerline copper for use with MPFM instrumentation and subsea video on installations.
PROJECT PROFILES

Zennor Finlaggan ..................................................................................................................................................... 5


Premier Bison, Iguana & Gajah Puteri Development (BIGP) ................................................................................... 6
Talos Boris & Tornado SCM Refurbishment - ACT .................................................................................................. 7
CNR Ninian .............................................................................................................................................................. 8
Apache Callater........................................................................................................................................................ 9
BP Shah Deniz ....................................................................................................................................................... 10
Statoil Visund (ACT) ............................................................................................................................................... 11
Hess Bergading Development................................................................................................................................ 12
EnQuest Scolty Crathes ......................................................................................................................................... 13
Apache Far North Triassic ..................................................................................................................................... 14
EnQuest Ythan ....................................................................................................................................................... 15
Hess Stampede Development................................................................................................................................ 16
Apache Aviat Development .................................................................................................................................... 17
Petrobras Drill Pipe Riser (DPR) ............................................................................................................................ 18
Nobel Gunflint Development .................................................................................................................................. 19
Talos Phoenix Development .................................................................................................................................. 20
CNR Toni Development ......................................................................................................................................... 21
Taqa Cladhan Development .................................................................................................................................. 22
Talisman Montrose Cayley and Shaw .................................................................................................................... 23
Iona Orlando Field Development............................................................................................................................ 24
Iona Kells Field Development ................................................................................................................................ 24
Ithaca Anglia ACT .................................................................................................................................................. 25
Maersk Flyndre and Cawdor Field Development ................................................................................................... 26
Anadarko Lucius .................................................................................................................................................... 27
Hess Tubular Bells ................................................................................................................................................. 28
Premier Dua Field Development ............................................................................................................................ 29
Perenco Well 53/02A-14A Tie Back ....................................................................................................................... 30
Petrobras Early Production Riser (EPR) ................................................................................................................ 31
Shell Princess ........................................................................................................................................................ 32
Statoil Snorre B ...................................................................................................................................................... 33
CNR Lyell ............................................................................................................................................................... 34
EnQuest Knightsbridge Ardmore............................................................................................................................ 35
Valiant Causeway .................................................................................................................................................. 36
Statoil Heidrun........................................................................................................................................................ 37
Ithaca Athena ......................................................................................................................................................... 38
Statoil Åsgard ......................................................................................................................................................... 39
Chevron Jack & St. Malo ........................................................................................................................................ 40
BG Gaupe .............................................................................................................................................................. 41
GDF Juliet .............................................................................................................................................................. 42
Apache Bacchus .................................................................................................................................................... 43
EnQuest Don Fields Chemical Metering Project .................................................................................................... 44
Anadarko Caesar Tonga ........................................................................................................................................ 45
KEI Terang Batur Sirasun ...................................................................................................................................... 46
ATP Telemark ........................................................................................................................................................ 47
Perenco Bure North ............................................................................................................................................... 48
Centrica Seven Seas Wells Development .............................................................................................................. 49
Talisman Auk North Field Development ................................................................................................................. 50
RWE Topaz Well Development .............................................................................................................................. 51
Bridge Resources Durango Well Development ...................................................................................................... 52
Petrofac Don Field Development ........................................................................................................................... 53
Tullow Wissey ........................................................................................................................................................ 54
Granby / Mosaic Tristan NW .................................................................................................................................. 55
CNR Lyell Multiphase Flowmeter Multiplexer ......................................................................................................... 56
Maersk Dumbarton SSIV Multiplexer ..................................................................................................................... 57
GDF Minke ............................................................................................................................................................. 57
Perenco Davy East ................................................................................................................................................ 58
BG Miskar .............................................................................................................................................................. 59
BG Maria ................................................................................................................................................................ 59
CNR Banff Phase II ................................................................................................................................................ 60
Addax Okwori ......................................................................................................................................................... 61
Water Oil Ewing Bank ............................................................................................................................................ 62
BP Faragon ............................................................................................................................................................ 63
BG North West Seymour ........................................................................................................................................ 64
DONG Stine ........................................................................................................................................................... 65
Talisman Duart ....................................................................................................................................................... 66
Talisman Ross Field............................................................................................................................................... 67
Marathon Braemar East ......................................................................................................................................... 68
Talisman Hannay ................................................................................................................................................... 68
Talisman Kildrummie.............................................................................................................................................. 69
Brovig Chestnut...................................................................................................................................................... 69
Centrica Rose ........................................................................................................................................................ 70
Talisman Hannay Field Development .................................................................................................................... 71
Ranger Kyle Phase 2 Field Development .............................................................................................................. 71
Amerada Hess Flora & Fife Field Developments ................................................................................................... 72
Amerada Hess Angus Field ................................................................................................................................... 72
Conoco MacCulloch ............................................................................................................................................... 73
Kerr McGee Janice and James .............................................................................................................................. 74
Petrobras MacManifold .......................................................................................................................................... 75
Petrobras P27 ........................................................................................................................................................ 76
Petrobras P33 / P35 ............................................................................................................................................... 76
Shell Gannet E & F Field Development .................................................................................................................. 76
Amerada Hess Durward and Dauntless ................................................................................................................. 77
Conoco Banff ......................................................................................................................................................... 77
BP Newsham ......................................................................................................................................................... 78
Emerald Extension Well & Satellite Choke Base.................................................................................................... 79
Sovereign Emerald................................................................................................................................................. 79
Total North Alwyn Subsea Project.......................................................................................................................... 80
Placid L10-S1 ......................................................................................................................................................... 81
Project Zennor Finlaggan
Client Zennor Petroleum
Completion Date In Production
Water Depth Shallow North Sea
Step out Distance 20km
No. of SCMs 2
System Artemis 2G
Intervention Method ROV using Running Tool
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Zennor Petroleum required a flexible solution capable of
Background using a number of host facilities as that was not determined
when the project was first sanctioned
The A2G subsea controls solution provided supports both
Solution the longer and shorter step out requirements determined by
the eventual host facility
Full Subsea Control System, including topside MCS, HPU
and TUTU. Subsea; SSIV Instrumentation, Manifold Subsea
Scope of Supply
Chemical Metering and Instrumentation, 2 Production SCMs
and Tree Instrumentation, and SCM Running Tool rental
The tailored approach of the SCM mounting base to the tree
enabled the successful integration of the Proserv controls
Conclusion onto the GE subsea Xmas Tree and therefore the selection
of the preferred XT vendor and Controls vendor without the
need to compromise either contracts
Premier Bison, Iguana & Gajah Puteri Development
Project
(BIGP)
Client Premier Oil
Completion Date In Production
Water Depth 80m
Step out Distance 21km
No. of SCMs 3
System Artemis 2G
Intervention Method ROV Self-Aligning
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location Indonesia
Premier had a complex host platform arrangement with 2
subsea wells powered from the Pelican platform and 1 from
the Naga platform. Both platforms are normally unmanned
Background (NUI) and control is from a third host platform Gajah Baru.
This is then further complicated by Pelican and Naga having
no safe area for EPU or Subsea Comms, and Gajah Puteri
th
(GP) requiring control from a 4 platform AGX.
The complex surface controls required distributed power and
controls systems with fibre optic connections between
platforms. The hazardous area required distributed explosion
Solution
proof EPU solution. Subsea, the tree instrumentation also
required front mounted connections on the SCM to avoid
mounting base penetrators.
Full Subsea Control System, including topside SCU, HPU
Scope of Supply and EPU on each platform, 3 Production SCMs and Tree
Instrumentation
The topside controls distributed between 4 platforms and the
requirement for SCM housing mounted instrumentation
Conclusion
connections required an ingenious solution without including
excessive complexity
Project Talos Boris & Tornado SCM Refurbishment - ACT
Client Talos
Completion Date 2017
Water Depth 760m
Step out Distance 10.5km
No. of SCMs 6 x GE Modpod A2G upgrades - ACT
System A2G
Intervention Method ROV
Xmas Tree Supplier GE
Control Method Electro-Hydraulic
Location Gulf of Mexico
After reports of the system of failing the operator was told by
OEM that much of the installed subsea equipment was
Background obsolete. Upgrades using replacement OEM equipment
were considered by Talos as too expensive.

Proserv provided a solution to integrate both Typhoon and


Boris fields into the existing Phoenix field already controlled
by Proserv. Proserv replaced the OEM canister with Proserv
A2G SEMs in each ModPod SCM and the Topside
Solution expansion unit to hold communications and power units to
integrate with existing Proserv control system. The first
upgraded SCM install used coexist technology with the OEM
subsea power as source. Further SCMs will use the Proserv
EPUs to provide subsea power.
Topside Expansion MCS within the existing MCS PLC rack
with EPU and TPCUs for the system.
Scope of Supply
6 retrofit SCMs A2G SEMs complete with new running tools
and test stand
Successful coexist testing and integration of the A2G SEM
Conclusion into the OEM SCM has enabled long term support for this
project and later expansion.
Project CNR Ninian
Client CNR
Completion Date 2017
Water Depth 132m
Step out Distance 0.5km
No. of SCMs 2
System Artemis 1G
Intervention Method Diver
Xmas Tree Supplier N/A
Control Method Multiplexed Electro-Hydraulic
Location UK North Sea
The Ninian Central Platform (NCP) is located in the Central
North Sea approximately 240 miles North East of Aberdeen
and has been on-stream since 1982. The Oil and Gas
pipelines are protected by Subsea Emergency Safety Valves
Background
(SSESVs) which are controlled by a GEC Avionics control
system (built by Brisco Engineering now part of Proserv),
supplied in 1990.The system was at the end of its 25 year
design life and was no longer supported.
Proserv replaced the previous two GEC SCMs with a single
Solution field proven Artemis SCM with internal dual redundant
SEMs; thus minimising system complexity.
Replacement MCS, EPU, Umbilical and Subsea Control
Scope of Supply Module with flying leads for SSIV control

Working closely throughout the project life-cycle with the


Conclusion client CNR International has ensured requirements and
expectations are clearly understood and managed.
Project Apache Callater
Client Apache North Sea
Completion Date 2017
Water Depth Shallow North Sea
Step out Distance 12.5 km
No. of SCMs 2
System Artemis 1G
Intervention Method Diver
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Greenfield extension to the Beryl Alpha platform using new
MCS and HPU topside. Central field Manifold controls
Scope of Supply
including SCM. Initially 1 Tree SCM and controls set with
extension for 7 others
Design of new SCMs based on the Bacchus, Aviat and FNT
Comments projects and interchangeable throughout using backward
supported A1G technology
Project BP Shah Deniz
Client BP Exploration
Completion Date 2017
Water Depth 600m
Step out Distance N/A
No. of SCMs N/A
System Direct Instrumented
Intervention Method ROV
Xmas Tree Supplier N/A
Control Method Direct Instrumented
Location Azerbaijan
Hydrate Remediation System used to tie in either side of a
recognised hydrate formation managed the pressure drop
either side and inject chemicals.
Scope of Supply
Scope include manifold and mudmat with choke, isolation
valves, injection valves, and instrumented pressure /
temperature including surface monitoring system
System is mobile in nature using workover umbilical for
Comments
surface monitoring and ROV operator manifold valves
Project Statoil Visund (ACT)
Client Statoil
Completion Date 2016
Water Depth 335m
Step out Distance 900m
No. of SCMs 1 refurbishment ACT SCM
System Replacement A2G SEM
Intervention Method ROV
Xmas Tree Supplier Aker
Control Method Electro-Hydraulic
Location Norwegian North Sea
Statoil had a requirement to refurbish older Aker 4G SCM
modules that had obsolescence and fault issues, particularly
Background with the internal electronics (SEM)
The OEM was unable to support the system or provide spare
parts
Provide an Augmented Control Technology (ACT) system
Solution with new electronics and existing external hardware

Refurbish the used Aker 4G SCM module by installing a


Proserv A2G SEM with redundant power and communication
Scope of Supply Reuse all hydraulic parts and sensors, replace only where
necessary. Interface to topside Siemens DCS by legacy
MODBUS map
Proserv provided a cost effective solution in 6 weeks using
A2G technology and pre-purchased SEM. This gave high
Conclusion bandwidth and open topside interface with redundant power
supply and communication and greater instrumented inputs
that was not available from the OEM
Project Hess Bergading Development
Client Hess Malaysia
Completion Date 2016
Water Depth
Step out Distance 250m
No. of SCMs N/A
System Direct Instrumented
Intervention Method Diver Only
Xmas Tree Supplier N/A
Control Method Direct Hydraulic
Location Malaysia
SSIV control system for infield and gas export pipelines.
Surface HPU and control panel with monitoring provision,
Scope of Supply
surface umbilical termination, subsea umbilical and
termination, and flying leads to SSIVs
UK design and fabrication with final assembly, termination
Comments
and testing completed in Proserv site in Malaysia
Project EnQuest Scolty Crathes
Client EnQuest
Completion Date 2016
Water Depth 105m
Step out Distance 25km
No. of SCMs 2
System Artemis 1G
Intervention Method Diver
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location North Sea
2 well subsea control system in two drill centres; Crathes at
18km and Scolty at a further 7km. Each controlled using tree
Scope of Supply
mounted SCM and manifold mounted distribution system.
Surface HPU, MCs and TUTU included on Kittiwake platform
Proserv initially reviewed the specification and agreed
changes to rationalise the control system to reduce cost and
schedule impact
Comments Proserv responsibility for interface management between
rd
client, and other 3 party contractors as well as controls.
Proserv Interface Engineer specifically allocated for this
project
Project Apache Far North Triassic
Client Apache North Sea
Completion Date Q1 2016
Water Depth 110m
Step out Distance 4.7
No. of SCMs 2
System Artemis 1G
Intervention Method Diver
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Scope of Supply MCS, HPU, TUTU, Jumpers
Utilises the SCM and XMT from the Bacchus project with
Comments new surface equipment mounted on the Berryl Bravo
platform
Project EnQuest Ythan
Client EnQuest
Completion Date 2015
Water Depth 170m
Step out Distance 17km
No. of SCMs 1
System Artemis
Intervention Method Diver
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Distribution system designed to be diver handled under the
Scope of Supply protective structure of the XMT. Distribution provided to 3
wells from single XMT
Comments Don System Extension
Project Hess Stampede Development
Client Hess
Completion Date Currently In Manufacture
Water Depth 3700 ft
Step out Distance 24km
No. of SCMs 13
System Artemis 2G
Intervention Method ROV
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location GOM
Subsea Control System for the development of 12 subsea
Scope of Supply
wells
SCM on-board accumulation design negates the requirement
Comments
for separate tree mounted SAM
Project Apache Aviat Development
Client Apache
Completion Date 2015
Water Depth
Step out Distance 24km
No. of SCMs 3
System Artemis 1G
Intervention Method Diver with active mounting base
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Subsea Control System for 2 trees based on the Aviat field
Scope of Supply
24k from the Forties Alpha platform
The SCM design is identical and interchangeable with the
Comments
Apache Bacchus SCM
Project Petrobras Drill Pipe Riser (DPR)
Client Weatherford
Completion Date 2015
Water Depth 2500m
Step out Distance -
No. of SCMs 10
System Artemis 2G
Intervention Method ROV
Xmas Tree Supplier Multiple
Control Method Multiplexed Electro-Hydraulic
Location South America
Deep Water IWOCS system designed for operation on
multiple Mobile Drilling Units and service in country Brazil.
Scope of Supply Scope includes Zone 1 Hazardous Area control room ,
separate HPU and subsea DPR frame with on board
accumulation
40 function SCM with dual A2G SEM. Subsea scope based
Comments on EPR supply from 2 years early with improvements to
topside control cabin and HPU.
Project Nobel Gunflint Development
Client Nobel Energy
Completion Date 2015
Water Depth 1,860 m
Step out Distance 38 km
No. of SCMs 3
System Artemis 2G
Intervention Method ROV
Xmas Tree Supplier
Control Method Multiplexed Electro-Hydraulic
Location Gulf of Mexico
Surface MCS with remote station, HPU and TUTA. Subsea
Scope of Supply UTA and Distribution including Mudmat. Dual SEM SCM with
Fibre Optic communications to OCH
Uses dual A2G SEMs with SIIS L2 instrumentation and fibre
Comments
optic communications to dual OCH
Project Talos Phoenix Development
Client Talos
Completion Date 2015
Water Depth 650 m
Step out Distance 4.7 km
No. of SCMs 4
System Artemis
Intervention Method ROV
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Gulf of Mexico
MCS with remote operating terminal, HPU, TUTA. Subsea
Scope of Supply
UTA with dual SEM SCM mounted on UTA
Fast reaction project from limited specification requirements.
Comments Client relies heavily on Proserv expertise to specify and
design subsea control system
Project CNR Toni Development
Client CNR
Completion Date 2015
Water Depth
Step out Distance 11 km
No. of SCMs 2
System Artemis
Intervention Method ROV
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location North Sea
New MCS and OCH to co-exist with current system used on
Scope of Supply
Toni. Include two new well control SCMs
Upgrade the existing CNR Cameron supplied control system
on the Toni Field. Key requirement included the
incorporation of in-well instrumentation using an Open
Comments
Communications Hub (OCH) and 2 additional Subsea
Control Modules (SCMs). The existing topology utilised
separate communications and power.
Project Taqa Cladhan Development
Client TAQA
Completion Date 2015
Water Depth 160 m
Step out Distance 16.5 km
No. of SCMs 4
System Artemis
Intervention Method ROV
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Surface MCS, HPU and TUTU with SSIV control in HPU.
Subsea Distribution with 2 sets of Production Tree
Scope of Supply
equipment and 1 Water Injection Tree equipment including
SCM, SCMMB, Pressure and Temperature Tx and GLFM
SCMMB includes mounting for the Tree Pressure
Transmitters to allow ease of access for diver replacement if
Comments
necessary
Project Talisman Montrose Cayley and Shaw
Client Talisman
Completion Date 2015
Water Depth 95 m
Step out Distance 10 & 17.5 km
No. of SCMs 7 plus 5 OCH
System Artemis
Intervention Method Diver
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
MCS, HPU, 3 SSIV Panels, 3 TUTUs. Each drill centre
Scope of Supply includes SDU, OCH, Manifold mounted SCMs, pressure,
temperature transmitters, GLFM, WIFM
Fibre Optic communications system. Open Communications
Comments Hub on each manifold enabling high speed communications
to manifold mounted MPFM and SCMs
Project Iona Orlando Field Development
Client Iona Energy
Completion Date On hold
Water Depth 142 m
Step out Distance 11 km
No. of SCMs 2
System Artemis
Intervention Method Diver
Xmas Tree Supplier GE
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Surface MCS and HPU shared with Kells project, Subsea
Scope of Supply
Manifold mounted SCMs and SCMMB
SCM designed to be compatible with the Kells project which
Comments includes functionality to monitor and control Xmas Trees
from three different manufacturers

Project Iona Kells Field Development


Client Iona Energy
Completion Date On hold
Water Depth 135 m
Step out Distance 14 km
No. of SCMs 2
System Artemis
Intervention Method Diver
Xmas Tree Supplier Cameron and FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Surface MCS, HPU and TUTA, Subsea Manifold mounted
Scope of Supply
SCMs and SCMMB
System is designed to operate two different subsea tree
designs from separate manufacturers. The SCM includes
Comments
functionality to operate both trees and instrumentation which
differs on each.
Project Ithaca Anglia ACT
Client Ithaca
Completion Date 2015
Water Depth 50m
Step out Distance 5km
No. of SCMs 2
System A1G ACT
Intervention Method Diver
Xmas Tree Supplier GE
Control Method Electro-Hydraulic
Location North Sea
A remote unmanned platform in the North Sea supports two
subsea production wells linked to a host platform. The
subsea control system is over 20 years old, is unsupported
Background
by the OEM and has suffered from repeated failures,
unscheduled shutdowns, and limited remote support leading
to a significant loss of production
Proserv provided a retrofit solution using the existing Subsea
Control Module (SCM) hydraulic and mechanical hardware
but replacing the Subsea Electronic Module (SEM) for a
Solution more reliable and fully supported unit. This provided a
replacement solution with the incumbent Subsea Control
Modules (SCMs) and thus an upgrade path to improve
availability and support and system capability.
A study was undertaken to consider the implications of SEM
replacement within each SCM, including the use of existing
inductive couplers that are inherent in the system. Each
SCM was disassembled, pre tested, retrofitted and FAT
Scope of Supply
tested with new Proserv electronics. The surface control
system was also replaced with a new MCS to replace the
OEM system and provide communications to the retrofit
SCMs
Significantly less expensive than a replacement
Significantly greater technical performance and reliability
Enables Production from an otherwise unproductive field
Conclusion Higher reliability and availability
Optimised uptime
State of the art electronics and connectivity
Remote connectivity
Project Maersk Flyndre and Cawdor Field Development
Client Maersk Oil and Gas
Completion Date 2015
Water Depth 70 m
Step out Distance 25.1 km
No. of SCMs 3
System Artemis
Intervention Method Diver
Xmas Tree Supplier
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Surface MCS, HPU and TUTA, Subsea Manifold mounted
Scope of Supply
SCMs and SCMMB
Each SCM includes an electrically latched fail closed valve
on the LP header to vent Tree valve controls in the event of
Comments
an ESD, improving the closure time against an hydraulic
ESD equivalent
Project Anadarko Lucius
Client Anadarko
Completion Date Delivered May 2013
Water Depth 7000ft
Step out Distance 65000ft?
No. of OCHs 2 SMIM’s 1 x Compact SMIM
System OCH (Open Communication HUB)
Intervention Method ROV
Xmas Tree Supplier Aker
Control Method Fiber Optic and Powerline Communications
Location GOM
Topside Control Cabinet and Communications Server
Scope of Supply 2 x 6 output Subsea Meter Interface Modules - SMIM
1 x 2 output Subsea Meter Interface Modules - cSMIM
This Project required 2 retrievable high bandwidth and high
power subsea modules using FO communications. Each
controlled up to 6 MPM multiphase flow-meters at each drill
Comments
centre. Additionally a further step-out requiring 1 smaller
compact module controlling up to 2 MPM meters was
provided using Proserv power-line technology.
Project Hess Tubular Bells
Client Hess Corporation
Completion Date 2014
Water Depth 1370 m
Step out Distance 13 km
No. of SCMs 6
System Artemis
Intervention Method ROV Lift Line Installation
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Gulf Of Mexico
Surface MCS, HPU and TUTA, Subsea Tree mounted SCMs
Scope of Supply and SCMMB with ROV recoverable SAM and Tree
Transmitters in scope
5 HP 15Ksi functions with 5Ksi LP functions taking the full
system to 26 Functions. Dual SEM SCM with each SEM
Comments
supporting serial external transmitters and dual DHG cards
(4 cards in each SCM)
Project Premier Dua Field Development
Client Premier Oil Vietnam Offshore (POVO)
Completion Date Delivered 2013
Water Depth 93 m
Step out Distance 17 km
No. of SCMs 4
System Artemis
Intervention Method Diver
Xmas Tree Supplier GE Vetco
Control Method Multiplexed Electro-Hydraulic
Location Vietnam (Nam Con Son Basin)
Surface MCS, HPU and TUTA, Subsea Manifold mounted
Scope of Supply SCMs and SCMMB with CMV on each SCMMB

Subsea Control System is mounted on manifold SDU sub


structure. Each SCMMB includes chemical isolation valves
Comments
and metering valve. Common manifold functions control and
monitored from any one of 4 SCMs
Project Perenco Well 53/02A-14A Tie Back
Client Perenco
Completion Date Delivered 2013
Water Depth
Step out Distance 9 km
No. of SCMs 1
System Artemis
Intervention Method Diver
Xmas Tree Supplier GE Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern North Sea

Scope of Supply 1 Well Subsea Control System

System manufactured utilising some equipment which had


Comments been mothballed and stored following cancellation of the
Bure North project in 2009
Project Petrobras Early Production Riser (EPR)
Client Weatherford
Completion Date Delivered 2013
Water Depth 2500m
Step out Distance -
No. of SCMs 1
System Artemis
Intervention Method ROV
Xmas Tree Supplier Cameron plus others later in project
Control Method Multiplexed Electro-Hydraulic
Location South America
EPR Control System for WOCS in 2500m water. 40 EH
Scope of Supply functions using three pressure levels. Topside control cabin
with HPU and LER
Dual SEM, in-SCM flow meters, twin lockdown drive, deep
Comments
water operation accumulation on separate pressure systems
Project Shell Princess
Client Shell
Completion Date Delivered 2012
Water Depth 1100 m
Step out Distance 5 km
No. of OCH’s 1
OCC communication on power line co-exist with FMC KOS
System
150
Intervention Method ROV Installation
Xmas Tree Supplier FMC Kongsberg Subsea
Control Method Multiplexed Electro-Hydraulic
Location GoM
Provide communication from topside system to the subsea
via power line communication co-exist with FMC KOS 150
modems.
Scope of Supply Provide topside AC Power Control for the system. Transform
AC high-voltage to DC and provide power management
subsea to all instruments. Integrate ATS and DTS on 1
downhole fiber
Comments Achieved bandwidth approx. 320kb/sec
Project Statoil Snorre B
Client Statoil
Completion Date Delivered 2012
Water Depth 335m
Step out Distance 1 km
No. of EDU’s 6
Proserv Powerline communication technology (OCC)
canisters integrated in Vetco GE POD to establish electrical
System
power and communication infrastructure to Downhole
Control Modules
Intervention Method ROV Installation
Xmas Tree Supplier GE Oil and Gas
Control Method Multiplexed Electro-Hydraulic
Location North Sea – Norwegian sector

Scope of Supply Spare parts

The initial system was delivered to Snorre B in year 2000


Comments
including 27 smart well (DIACS).

From
Platform
500 VAC
Power cable

EDU II

DIACS Electrical Power and


Distribution Unit Modem and
Diplexor
(DIACS EDU - OCH) Unit

Power 12 V DC
supply
5 V DC

1 atm N2
Oil
System A
System B

RS485 RS485 RS485


RS485
230 V AC

230 V AC

230 V AC

230 V AC DCM
Project CNR Lyell
Client Framo Engineering / CNR
Completion Date Delivered 2012
Water Depth 200 m
Step out Distance 8.5 km
No. of OCH’s 1
System OCC communication on power line
Intervention Method Diver Installation
Booster Pump Supplier Framo Engineering
Control Method Multiplexed Electro-Hydraulic
Location North Sea – British sector
Open Communication HUB for 1 Subsea Multiplexer system
with Power Line modem Communication, for interfacing of
Scope of Supply process transmitters and control of direct control valves on
the Lyell Subsea Multiphase Booster Pump. Non-redundant
system, topside TPCU rack.
OCH – version with 1 input power and communication and 2
Comments
output/inputs with interfaces to the booster pump.
Project EnQuest Knightsbridge Ardmore
Client EnQuest
Completion Date Currently In Commissioning
Water Depth 90 m
Step out Distance 4 km
No. of SCMs 10
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
9 well control system over two umbilicals from the Usi Gorm
Scope of Supply
FPSO
The subsea control system is designed for control and
Comments monitoring on the manifold and Production Xmas Trees
using tree mounted SCMs
Project Valiant Causeway
Client Valiant Petroleum
Completion Date Installed 2012
Water Depth 150 m
Step out Distance 16 km
No. of SCMs 3
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
3 well control system over two umbilicals from the Cormorant
Scope of Supply
Platform
Production wells include ESP in well. Both umbilicals are
installed with 3.5kV power cables in with the controls cables.
Comments Communications is copper rather than fibre based with
signals having to work with the noise generated by the ESP
power cables
Project Statoil Heidrun
Client Statoil
Completion Date October 2011
Water Depth 360 m
Step out Distance 6.2 km
No. of OCH’s 1
No. of SeaHawk’s 2
Open Communication Hub (OCH) with SeaHawk subsea
System
video camera’s connected on the subsea template
Intervention Method ROV Installation
Xmas Tree Supplier FMC Kongsberg Subsea
Control Method Multiplexed Electro-Hydraulic
Location North Sea – Norwegian sector
Provide communication from topside system to the subsea
via broadband DSL communication to an OCH. The OCH
has 4 open power and communication outputs with DSL and
Scope of Supply Ethernet communication, 240 VAC and 24 VDC power.
Delivery of 2 subsea cameras for observation of possible
leakage on template. Special monitoring leak during gas lift
operation.
Comments Achieved bandwidth approx. upto 10 Mb/sec
Project Ithaca Athena
Client Ithaca Energy UK Ltd
Completion Date 2011
Water Depth 132 m
Step out Distance 2 km
No. of SCMs 6
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Up to 8 well subsea control system with 5 wells developed in
Scope of Supply
the first phase.
Manifold includes a multiphase flowmeter tied back through
Comments the SCS. Compact FPSO turret requires bespoke topside
equipment designs
Project Statoil Åsgard
Client Statoil
Completion Date 2011
Water Depth 280 m
Step out Distance Installed on several templates (5-20 km)
No. of SeaHawk’s 1
SeaHawk subsea video camera connected on the subsea
System
template
Intervention Method ROV Installation
Xmas Tree Supplier FMC Kongsberg Subsea
Control Method Multiplexed Electro-Hydraulic
Location North Sea – Norwegian sector
Provide communication from topside system to the subsea
via broadband DSL communication direct to a SeaHawk
Scope of Supply
subsea camera unit for observation of possible leakage on
template.
Comments Achieved bandwidth approx. up to 15 Mb/sec

Common
SeaHawk™
server
Project Chevron Jack & St. Malo
Client MPM / Cameron / Chevron
Completion Date 2011
Water Depth 3050 m
Step out Distance 27 km
No. of OCH’s 4
Open Communication Hub (OCH) with fiber optic and power
System
line communication
Intervention Method ROV Installation
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location GoM
4 off Subsea Meter Interface module (SMIM) for connection
to 4 MPFM Flowmeters.
4 topside cabinets for power and communication to up to 40
Scope of Supply
MPM flowmeters.
TCS – redundant Topside Controller Station for storage and
data handoff to PAS.
Comm. interface – MPFM:
Ethernet (Modbus over TCP/IP)
Comments Typical comm. Speed on 27 km umbilical:
100 Mbps (fiber) or 40 kbps – modulated on power-
line
Project BG Gaupe
Client BG Group
Completion Date 2011
Water Depth 100 m
Step out Distance 8 km
No. of SCMs 2
System Artemis
Intervention Method ROV Installation
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
2 wells in Norwegian waters tied back to a UK platform with
Scope of Supply
subsea distribution and manifolding at it’s base.
Wells include NORSOK standard designs with smart in hole
Comments
multi-zone completions operated from the well SCM
Project GDF Juliet
Client GDF Suez
Completion Date 2011
Water Depth 60 m
Step out Distance 28 km
No. of SCMs 4
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Dril-Quip
Control Method Multiplexed Electro-Hydraulic
Location Southern North Sea

Scope of Supply 2 well subsea control system plus manifold SCM

Tie back to unmanned platform and utilising an existing


Comments
HPU/control room facility with minimal space for MCS
Project Apache Bacchus
Client Apache North Sea Limited
Completion Date 2011
Water Depth 100 m
Step out Distance 8 km using pipeline bundle
No. of SCMs 5
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
4 well subsea control system plus manifold SCM in a
Scope of Supply
pipeline bundle step out.
Fast track project with caisson riser and pipeline bundle
Comments
connection system
Project EnQuest Don Fields Chemical Metering Project
Client Enquest
Completion Date Nov 2010
Water Depth 170 m
Step out Distance 17 km
No. of SCMs N/A - 2 data modules used
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier N/A
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
2 manifolds retrofitted with Skoflo chemical metering valves
Scope of Supply
controlled from existing subsea control system
Each manifold has a replacement roof section manufactured
Comments with subsea data module, controls valves and all cabling and
tubing for installation
Project Anadarko Caesar Tonga
Client Anadarko
Location Gulf of Mexico
Completion date 2010
Water depth 1500 m
Step out distance 25 km
Topside voltage ~700 VAC
Subsea voltage range 250 – 500 VAC
No of subsea modules 2
System OCH (Open Communication HUB)
2 subsea modules for up to 8 flowmeters
Scope of supply 1 topside cabinet for data handoff and storage
Test equipment
Power and fiber-optic communication system for 4 Framo
multiphase flowmeters. Topside data handoff with MODBUS
System description interface.
Fully redundant system with power management and internal
diagnostics.
OCH INSTALLED ON SDU & MUD
MAT Project
KEI Terang Batur Sirasun
Client Kangean Energy Indonesia
Completion Date 2010
Water Depth 250 m
Step out Distance 32.5 km to Sirasun East
No. of SCMs 6 in Phase 1
System Artemis
Intervention Method ROV Installation
Xmas Tree Supplier DrilQuip
Control Method Multiplexed Electro-Hydraulic
Location Indonesia
Two phase project with Terang manifold installed in the first
Scope of Supply phase of 5 wells and the extension to Batur and Sirasun
included in the second phase of another 4 wells
Wet Gas flow metering included within scope of supply. Site
Comments Integration Testing and local storage provided by Proserv in
region and in country.
Project ATP Telemark
Client Bluewater Industries
Completion Date 2009
Water Depth 1400 m
Step out Distance 30 km
No. of SCMs 1
System Artemis
Intervention Method ROV Installation
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Gulf Of Mexico
Single well subsea control system. Proserv stock SCM and
Scope of Supply Mounting Base modification to suit project requirements
allowing a fast track delivery.
ROV Deep Water Installation with 15,000 psi HP
requirement and Smart Well hydraulics.
Comments HPU and TUTA manufactured in Proserv Kingwood Houston
Office with subsea manufacturing completed in Great
Yarmouth.
Project Perenco Bure North
Client Perenco
Completion Date Project Cancelled 2009
Water Depth
Step out Distance 12 km
No. of SCMs 1
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea

Scope of Supply Upgrade EPU and SCM with SUTU and jumpers

SCM to communicate on existing umbilical already utilised


Comments for Aker solutions control system. Testing completed but
project cancelled due to dry well before installation
Project Centrica Seven Seas Wells Development
Client Centrica
Completion Date 2009
Water Depth 30m
Step out Distance 14.2 km
No. of SCMs 3
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Subsea Multiplexed Electro-Hydraulic Control System with 3
Scope of Supply SCMs including replacement for current BP Newsham
system
Comments SCMs have Dual SEMs to avoid single point failure
Project Talisman Auk North Field Development
Client Talisman
Completion Date 2009
Water Depth 150m
Step out Distance 11 km
No. of SCMs 4
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Subsea Multiplexed Electro-Hydraulic Control System with 4
Scope of Supply
SCMs, HPU, MCS, EDU and Subsea Distribution
Controls Umbilical installed within same trench Power Cable
for 3 off ESPs. Communications systems operates using
Comments
copper modems and digitally filters specific noise
frequencies from HV cable proximity.
Project RWE Topaz Well Development
Client RWE
Completion Date 2008
Water Depth 40 m
Step out Distance 19 km
No. of SCMs 1
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Dril-Quip
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Single well SCM control system XT set c/w subsea XT
Scope of Supply
transmitters.
SCM supplied from stock for SIT in order to meet fast track
Comments
delivery required for XT installation.
Project Bridge Resources Durango Well Development
Client Technip
Completion Date 2008
Water Depth 11 m
Step out Distance 14 km
No. of SCMs 1
System Artemis
Intervention Method Diver Installation
Xmas Tree Supplier Dril-Quip
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Single well SCM control system c/w topside HPU, MCS and
Scope of Supply
subsea XT transmitters.
SCM installed onto existing design XT requiring special
design slim-line SCM to meet restricted space requirement.
Comments
XT transmitters and tree mounted SCMMB delivered within 9
weeks to meet schedule.
Project Petrofac Don Field Development
Client Petrofac
Completion Date Installed 2008
Water Depth 170 m
Step out Distance 17 km
No. of SCMs 12
System Artemis
Diver Installation and Intervention with SCM base stab
Intervention Method
connectors
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central Sector North Sea
6 Slot Subsea Distribution within over-trawl protective
Scope of Supply structure. Surface control system on Northern Producer FPF.
SCMs located on FMC trees.
Subsea interface into water-cut meters
Comments Separate Signal and Power
Subsea Chemical Metering Valves
Project Tullow Wissey
Client Tullow
Completion Date Installed 2009
Water Depth 40 m
Step out Distance 11 km
No. of SCMs 2
System Artemis
Diver Installation and Intervention with SCM base stab
Intervention Method
connectors
Xmas Tree Supplier Dril-Quip
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Tie into the Horn and Wren platform for a single well control
Scope of Supply system.

Subsea Hydraulic Intensifiers used to generate HP fluid in


SAM.
Comments Closed loop hydraulic fluid control system
Combined safe area HPU and MCS for use on an unmanned
platform with limited access and power.
Project Granby / Mosaic Tristan NW
Client Bluewater Industries
Completion Date 2007
Water Depth 40 m
Step out Distance 15.1 km
No. of SCMs 1
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Extension to Perenco Davy system with Subsea SUT,
Scope of Supply
Jumpers and SCM
Comments Although North Sea application, client based in Houston
Project CNR Lyell Multiphase Flowmeter Multiplexer
Client CNR
Completion Date 2007
Water Depth 150 m
Step out Distance 8.5 km
No. of SDMs 1
System Artemis
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Data Module Only
Location North Sea
Surface Control Unit and Subsea Data Module for MPFM and
Scope of Supply
Analogues
Multiplexing required for Multiphase Flowmeter data and
Comments
associated analogues
Project Maersk Dumbarton SSIV Multiplexer
Client Maersk
Completion Date 2007
Water Depth 150 m
Step out Distance 200 m
No. of SDMs 1
System Artemis
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Data Module Only
Location Central North Sea

Scope of Supply Surface Control Unit and Subsea Data Module

Subsea Data only required for monitoring of SSIV position


Comments
and local pressure using limited existing umbilical cables.

Project GDF Minke


Client Gaz De France Britain
Completion Date 2006
Water Depth 45 m
Step out Distance 15 km
No. of SCMs 2
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
MCS, EPU
Scope of Supply
Hydraulic and Electrical Jumpers, SCM
Controlled from a Dutch sector platform the Minke single
Comments
well is actually in the UK sector.
Project Perenco Davy East
Client Perenco
Completion Date 2006
Water Depth 50 m
Step out Distance 7 km
No. of SCMs 1
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
MCS, EPU, HPU Modifications to existing system,
Scope of Supply
Hydraulic and Electrical Jumpers, SCM, SDU
Local client supported directly from our Great Yarmouth
Comments
office.
Project BG Miskar
Client BG Tunisia
Completion Date 2006
Water Depth
Step out Distance 3 km
No. of SCMs 4
System Artemis
Intervention Method ROV Guide Wire Running Tool Installation and Intervention
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Mediterranean
Topside MCS, EPU, HPU, TUTU
Hydraulic and Electrical Jumpers, SCM, SCMMB, SDU,
Subsea
Subsea Instrumentation
Project includes integration of Framo Multiphase Flow Meter
Comments
and Roxar Down Hole Pressure and Temperature Gauge.

Project BG Maria
Client BG International
Completion Date 2006
Water Depth
Step out Distance 12 km
No. of SCMs 3
System Artemis
Intervention Method ROV Guide Wire Running Tool Installation and Intervention
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside EPU, HPU Modifications to NW Seymour, TUTU
Subsea Hydraulic and Electrical Jumpers, SCM, SCMMB, SDU,
Subsea Instrumentation
Project includes integration of Framo Multiphase Flow
Comments
Meter.
Project CNR Banff Phase II
DSND later completed by PGS
Client
Operator later changed to CNR
Completion Date 1997 and then extended 2001, and 2004
Water Depth 90 metres
Step Out Distance 2-3 km
No. of SCMs 7
System Wellcon
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Dril-Quip and FMC
Control Method Multiplexed Electro-Hydraulic
Location North Sea
Hydraulic Power Unit Master Control Station Electronic
Power Unit Test Stands and Test Hydraulic Power Unit
Scope of Supply
Subsea Electro-Hydraulic Distribution Subsea Control
Modules Electro-Hydraulic Jumpers
Extensively extended the Ramform Banff system now has
increased services and the addition of the Kyle control
Comments system. With 24 hydraulic functions for Production and
Injection Well Control the SCMs are the most populated
Wellcon SCM produced
Project Addax Okwori
Client Subsea 7
Completion Date 2006
Water Depth 150 m
Step out Distance 4 km
No. of SCMs 2
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location West Africa - Nigeria
Topside MCS, EPU, HPU Modifications, TUTU
Hydraulic and Electrical Jumpers, SCM, Subsea Mud Mat
Subsea
and Protective Frame
Comments Each SCM operates two production wells
Project Water Oil Ewing Bank
Client Walter Oil
Completion Date 2005
Water Depth 750 m
Step out Distance 30 km
No. of SCMs 1
System Artemis
Intervention Method ‘Fly to Place’ ROV Guided Installation and Intervention
Xmas Tree Supplier Dril-Quip
Control Method Multiplexed Electro-Hydraulic
Location Gulf of Mexico
Topside MCS, EPU
Subsea SCM, SCMMB
Comments System operates simplex hydraulics and electrical supplies
Project BP Faragon
Client Vetco
Completion Date 2005
Water Depth N/A
Step out Distance N/A
No. of SCMs -
System -
Intervention Method N/A
Control Method N/A
Location Central North Sea
Topside Hydraulic Power Unit
Subsea -
Proserv supply of compact split HPU for location in limited
Comments
footprint on Andrew platform
Project BG North West Seymour
Client BG International
Completion Date 2005
Water Depth
Step out Distance 10 km
No. of SCMs 2
System Artemis
Intervention Method ROV Guide Wire Running Tool Installation and Intervention
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU, TUTU
Hydraulic and Electrical Jumpers, SUTU, SCM, SCMMB,
Subsea
SDU, Subsea Instrumentation
Later expanded to include Maria system and SCM modified
Comments
for compatibility across systems.
Project DONG Stine
Client DONG
Completion Date 2004
Water Depth
Step out Distance 9.4 km
No. of SCMs 3
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Cameron
Control Method Multiplexed Electro-Hydraulic
Location Danish Sector North Sea
Topside MCS, EPU, HPU, TUTU
Hydraulic and Electrical Jumpers, SUTU, SCM, SCMMB,
Subsea
SDU, Subsea Instrumentation
ROV intervention on SUTU for installation of jumpers,
Comments
however SCM is diver installed.
Project Talisman Duart
Client Talisman
Completion Date 2006
Water Depth
Step out Distance 9 km
No. of SCMs 1
System Wellcon
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS Hardware and Software Modifications
Subsea Hydraulic and Electrical Jumpers, SCM
Comments SCM kept compatible across Duart, TNT and Ross fields

Project TALISMAN - Tartan North Terrace


Client Talisman
Completion Date 2005
Water Depth
Step out Distance 3.4 km
No. of SCMs 1
System Wellcon
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU
Subsea Hydraulic and Electrical Jumpers, SCM
SCM modified from the earlier Ross system to include a dual
DHPT interface within the SEM. A software switch allows
Comments
different tools to be accessed and maintains compatibility with
the Ross field.
Project Talisman Ross Field
Client Coflexip Stena Offshore
Completion Date 1999 then extended in 2001 and 2002
Water Depth 115 metres
Step Out Distance Up to 5 Km on four separate drill centres
No. of SCMs 13
System Wellcon
Intervention Method Diver
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Master Control Station, EEx’p’ Zone 1 rated Electronic Power
Units, Hydraulic Power Unit, SCM Teststand, Test HPU
Electro-Hydraulic Distribution Units, Umbilical Termination
Scope of Supply
Units, Electro-Hydraulic Jumpers, 10 off Subsea Control
Modules, Subsea Accumulator Modules, Subsea
Instrumentation.
The Talisman Ross field remains the most complex and
numerous system Proserv has produced. The system
operates with four drill centres served from 3 umbilicals. One
Comments drill centre has piloted hydraulic shutdown, while another is
served with electrical and hydraulic services from separate
locations. Limitations on turret design required the EPUs to be
installed in the Zone 1 area of the turret.
Project Marathon Braemar East
Client Marathon Oil
Completion Date 2003
Water Depth
Step out Distance 12.5 km
No. of SCMs 2
System Artemis
Intervention Method ROV Guide Wire Running Tool Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU, TUTU
Hydraulic and Electrical Jumpers, SCM, SCMMB, Subsea
Subsea
Instrumentation
Comments First permanently installed Artemis system

Project Talisman Hannay


Client Talisman
Completion Date 2002
Water Depth -
Step out Distance 14 km
No. of SCMs 2
System Artemis
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU, TUTU
Subsea Hydraulic and Electrical Jumpers, SCM
System originally installed as Wellcon system and changed
Comments out for Artemis using equipment from the abandoned
Kildrummie project.
Project Talisman Kildrummie
Client Talisman
Completion Date 2002
Water Depth -
Step out Distance -
No. of SCMs -
System Artemis
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU, TUTU
Subsea Hydraulic and Electrical Jumpers, SCM
System never installed and equipment later used for Hannay,
Comments
and TNT projects.

Project Brovig Chestnut


Client Brovig
Completion Date 2001
Water Depth -
Step out Distance -
No. of SCMs 1
System Artemis
Intervention Method ROV Guide Wire Running Tool Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
Location Central North Sea
Topside MCS, EPU, HPU, TUTU
Subsea Hydraulic and Electrical Jumpers, SCM, SCMMB
System had to be fitted into a restricted control room space.
Comments Supplied as a rental system and recovered from subsea after
one year production.
Project Centrica Rose
Client Centrica
Completion Date 2003
Water Depth 25 m
Step out Distance 10 km
No. of SCMs 1
System Wellcon
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier Vetco
Control Method Multiplexed Electro-Hydraulic
Location Southern Sector North Sea
Topside MCS, EPU, HPU, TUTU
Hydraulic and Electrical Jumpers, SCM, SCMMB, UTDA Tree
Subsea
Instrumentation
Due to the restricted space on the host Amethyst platform the
HPU, MCS, EPU and some of the third party ESD and PCS
system upgrades were contained within an integrated
Comments
package. This not only saved space but allowed the
installation and pre-commissioning to be completed onshore
thus saving time on this unmanned platform.
Project Talisman Hannay Field Development
Client Stolt Offshore
Completion Date 2001
Water Depth 120 metres
Step out Distance 14 km
No. of SCMs 1
System Wellcon
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
Subsea Control Modules – incorporating smart well
technology, Electro-Hydraulic Termination and Distribution
Scope of Supply Units, Subsea Accumulator Module.
Hydraulic Power Unit, Master Control Station and Topside
Umbilical Termination Unit.
This one well subsea system was designed with VHP (15,000
psi) down hole function lines for Smart Well completion
Comments
valves. This SCM was later recovered and replaced with an
Artemis system when a second well was added

Project Ranger Kyle Phase 2 Field Development


Kaeverner Oil & Gas for early stages and later Maersk
Client
Contractors and CNR directly
Completion Date 1999 and still extending
Water Depth 110 metres
Step out Distance 21 km
No. of SCMs 6
System Wellcon
Intervention Method Diver Installation and Intervention
Xmas Tree Supplier FMC
Control Method Multiplexed Electro-Hydraulic
Subsea Control Modules, Electro-Hydraulic Termination and
Distribution Units, Subsea Accumulator Modules, Subsea
Scope of Supply
Instrumentation.
Master Control Station, Hydraulic Power Unit.
Originally designed and installed for operating from the
Maersk Curlew, the Kyle system was installed with two
Comments separate drill centres at 18 km and 22.5km. This system has
since been disconnected from Curlew and controls are
currently provided from the slightly closer Ramform Banff.
Project Amerada Hess Flora & Fife Field Developments
Client Bluewater
Completion Date 1998
Water Depth 250 metres
Step Out Distance 10 km
No. of SCMs 10
System Wellcon
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
MCS, EPU, Subsea Control Modules Electro-Hydraulic
Scope of Supply
Termination and Distribution Units.
Originally the Flora and Fife SCMs were built for the Durward
and Dauntless fields. 11 SCMs were built in total. These
Comments
where later modified for the Flora field to improve the
communication over the 10 km umbilical

Project Amerada Hess Angus Field


Client Amerada Hess Limited
Completion Date 2002
Water Depth 250 metres
Step Out Distance 18 km
No. of SCMs 1
System Wellcon
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
Subsea Control Module upgrade and MCS hardware and
Scope of Supply
software changes
The Angus field was added to the already modified Flora and
Fife development for production from the Usi Gorm. Due to the
Comments longer 18km step-out the system was split into two with a
different communications transceiver used for the longer step-
out system.
Project Conoco MacCulloch
Client SLP Engineering Ltd
Completion Date 1996 and extended in 2002
Water Depth 150 metres
Step-out distance 3 & 5 km
No. of SCMs 6
System Wellcon
Intervention Method Diver (ROV to Subsea Tree Interface)
Xmas Tree Supplier Dril-Quip and Vetco
Control Method Multiplexed Electro-Hydraulic
Package Location Equipment Summary
Master Control Station, Electrical and Uninterruptible Power
Units
Scope of Supply Hydraulic Power and Umbilical Termination Units
SSIV Interface and Jumpers, Subsea Umbilical Termination
Units and Weak Links. Subsea Control and Accumulator
Modules. Instrumentation and Interface Stabplates
One of the first multi-well subsea control systems installed the
Comments MacCulloch field is still supported and continues production and
potential remaining for extension
Project Kerr McGee Janice and James
Client Kvaerner Oil and Gas
Completion Date 1998
Water Depth 150 metres
Step Out Distance 2 km
No. of SCMs 3 Subsea Data Modules
System Wellcon
Intervention Method Diver, ROV Terminations
Control Method Multiplexed Data Gathering with Direct Hydraulic Controls
Package Location Equipment Summary
Subsea PLC Master Control Station and Hydraulic Power Unit
Scope of Supply Subsea Data Aquisition Modules, Electro-Hydraulic
Distribution Units and Jumpers.
Janice utilises the same front end HMI and PLC control as a
Comments standard subsea control system. The hydraulic functions
however are topside with subsea data acquisition only.
Project Petrobras MacManifold
Client DSND Consub
Completion Date 1998
Water Depth 1000 metres design
No. of SCMs 3
Special ROVCON system based on Artemis SEM and
System
Wellcon hydraulics
Special build ROV Guidewireless Running Tool Installation
Intervention Method
and Intervention
Control Method Multiplexed Electro-Hydraulic
Master Control Station and Hyd. Power Unit.
Scope of Supply Subsea Control Module Electro-Hydraulic Termination and
Distribution Units
Large 32 function special SCMs designed for this system, with
Comments
their own running tool design. Dual SEM operated.

Diverless SCM, Running


Tool and Landing Base.
Project Petrobras P27
Client Hyundai Heavy Industries
Completion Date 1997
Water Depth N/A
Step Out Distance N/A
Intervention Method N/A
Control Method Turret Mounted Well Control Racks
Package Location Equipment Summary
Subsea Controls Hydraulic Power Unit, Surface
FPSO / Turret
Accumulator Skid, Well Control Racks for subsea wells.
Detail System Design and Manufacture
Service Factory Function Testing, Site Integration Testing, Offshore
Commissioning.

Project Petrobras P33 / P35


Client Hyundai Heavy Industries
Completion Date 1997
Water Depth N/A
Step Out Distance N/A
Intervention Method N/A
Control Method Turret Mounted Well Control Racks
Package Location Equipment Summary
Subsea Controls Hydraulic Power Unit, Surface Accumulator
FPSO / Turret Skid, Well Control Racks for 22 subsea wells, Turret Valves
Hydraulic Power Unit.
Detail System Design and Manufacture
Service Factory Function Testing, Site Integration Testing, Offshore
Commissioning.

Project Shell Gannet E & F Field Development


Client Rockwater
Completion Date 1997
Water Depth Metres
Step out Distance Km
Intervention Method Diver Installation and Intervention
Control Method Multiplexed Electro-Hydraulic
Package Location Equipment Summary
Subsea Electro-Hydraulic Termination and Distribution Units.
Detail System interface design and manufacture
Services
Factory Function / Integration Testing
Project Amerada Hess Durward and Dauntless
Client Bluewater Engineering BV
Completion Date 1996
Water Depth 100 metres
Step-out Distance 3 and 4 km + 2 km for Satellite Wells
No. of SCMs -
System Wellcon
Intervention Method Diver (ROV to SDU Isolation Valves)
Control Method Multiplexed Electro-Hydraulic
Master Control Station, Hydraulic and Electrical Power
Units, Umbilical Termination Assemblies,
Riser Base and Seabed Umbilical Termination Units +
Scope of Supply
Jumpers. Subsea Distribution Units, Subsea Control and
Accumulator Modules, Instrumentation and Interface
Stabplates
The D&D field originally had 11 SCMs. Shortly after the
Comments installation of the first phase the project was abandoned
and the SCMs later used for the Flora, Fife and Angus fields

Project Conoco Banff


Client Coflexip Stena Offshore
Completion Date 1996
Water Depth 90 metres
Step-out distance Directly above Subsea Wellhead
Intervention Method Diver
Multiplexed Electro-Hydraulic and facilities for Direct
Control Method
hydraulic operation as Back-Up
Package Location Equipment Summary
Master Control Station, Electrical and Uninterruptible Power
Control Room
Unit
Rig Floor
Hydraulic Power and Control Units
Topsides Interface Panel and Workover Control Panel
Subsea Tree
Subsea Control Module and Tree Instrumentation
Project Management
Detail System Design and Manufacture
Service
Factory Integration Testing
On and Offshore Integration Testing
Project BP Newsham
Client John Brown Engineers and Constructors
Completion Date 1995
Water Depth 35 metres
Step-out distance 6 km
No. of SCMs 2
System Wellcon
Intervention Method Diver
Control Method Multiplexed Electro-Hydraulic
Package Location Equipment Summary
Local Equipment Room Integrated Control and Fire/Gas System with Telemetry
Interface and Microwave Link to Land Base
Platform Hydraulic Power Unit and Topside Umbilical Termination
Unit
Subsea Distribution Unit
Subsea Manifold Subsea Control Modules, Instrumentation and Interface
Subsea Trees Stabplates
BP Newsham was the fist Wellcon SCM installed in 1993
Comments
and is still producing to this day
Project Emerald Extension Well & Satellite Choke Base
Client Midland and Scottish Resources Plc
Completion Date 1993
Water Depth 150 metres
Step Out Distance 2 km
Intervention Method Diver
Control Method Acoustic - Electro-Hydraulic
Package Location Equipment Summary
Upgrade of Existing Subsea Control System Computer and
Control Room Well Control Panel
Acoustic Transducer and Transponder
Subsea Tree Subsea Control Module, Subsea Battery Pack and
associated Jumper Cables
Conceptual Design
Project Management
Detail System Design and Manufacture
Service
Upgrade of Existing FPSO Equipment
Factory Integration Testing
Onshore and Offshore Integration Testing

Project Sovereign Emerald


Client Davy Offshore
Completion Date 1990
Water Depth 75 metres
Step Out Distance 0.5, 2.2 and 4.4 km
Intervention Method Diver
Control Method Direct Hydraulic
Package Location Equipment Summary
Hydraulic Power Unit and Control Panel for control of both
FPSO
Subsea Wells and Connectors
Detail System Design and Manufacture
Service
Factory Function Testing
Project Total North Alwyn Subsea Project
Client Total
Completion Date 1989
Water Depth 50 metres
Step Out Distance 4 km
Intervention Method Diver
Control Method Multiplexed – Hydraulic
Package Location Equipment Summary
Hydraulic Test Panel
Platform
Subsea Control Module – Hydraulic Components, SCM
Subsea Tree
Teststand
Project Management
Service Detail Design and Manufacture
Factory Function Testing

The Total North AlwynSCM under FAT prior to delivery.


Project Placid L10-S1
Client Placid
Completion Date 1988
Water Depth 50 metres
Step Out Distance 4 km
Intervention Method Diver
Control Method Pilot Hydraulic
Package Location Equipment Summary
Hydraulic Control Panel
Platform
Subsea Control Module, Diver Intervention Panel and
Subsea Tree
Interface Stabplates
Project Management
Detail System Design and Manufacture
Service
Factory Function Testing
Offshore Integration Testing