Professional Documents
Culture Documents
Case Study EM April 2022
Case Study EM April 2022
of the Month
1. Introduction: For the last few months, the response of the readers to side. (Refer Fig 2.1.1)
the case studies on various incidents is overwhelming. Hence this month we
are again choosing the write up on similar kind of studies for developing
the synchronization of practical observation to the theoretical concepts.
The analysis of each incident being supported by actual observations
had been described during the situation to add awareness amongst the
operation, testing and commissioning engineers to know the cause of
problems and be helpful for easy rectification of the problems. This can
also help to develop economic schemes for the smooth running of the
operation and control system in the Grid Sub-Station.
2.1. Issues on High Impedance Fault: With one 33Kv feeder, snapping of 4. The protection system did not actuate, resulted with burning of
conductor and getting connected to Earth on Load connected side. ground shrubs due to laying of the wire from supply side.
w w w. e l e c t r i c a l m i r r o r. n e t
B. Fault on 11Kv side of the Delta Star transformer:
Any fault on the load connected side on 11 KV system. The
associated protection system should have to act upon to clear
the fault. But due to earth integrity, the related fault gets
converted to impedance kind of fault and causes delay action
on the tripping relays. The relays at different locations in the
upstream shall be actuating to clear the fault. But best solution
is to make use of ground return wire. Refer fig 2.2.2
C. Fault on Delta Transformer:
Delta winding of the transformer and fault on this system. In
2. But in the case of multi-used supply transformers (More practice transformer protection shall be actuating the fault in
than one), the current magnitude shall be less or may this situation and clears the same. In case of any deviation/
not be sufficient to result actuation of the SEF (Sensitive non-actuation, the upstream relays act to clear the fault.
Earth Fault) Relay. Recommendations:
3. So, the feeder that used for feeding this system should So, EARTH plays the important role for circulation of fault
accordingly be used with special Logic for actuation of current. So earth continuity to be confirmed in every system
Earth Fault relay and tripping of the feeder. 2.3: Actuation of OSR of transformer: It was found with the
2.2. Some Other Technical Solution to the HIGH IMPEDANCE actuation of OSR during a rainy day at one of the 132/33KV
FAULT in 33KV and 11 KV System. Grid Sub-station.
Different situations: Observations:
A. Fault on the Supply connected side: 1. It was reported by the grid in-charges regarding tripping
Snapping of Conductor for the 33Kv feeder towards supply end of the 20MVA Power transformer on OSR during the
side and touching to ground: rainy day.
2. Accordingly, it was asked for the checking of the OSR,
For this situation, if proper earth loop gets maintained, then
might be causing the ingress of moisture/ rain water and
the relay at supply end shall only actuate and trip the system.
causing the contact closure and tripping of the breaker.
The fault loop current flow is seen in the Fig 2.2.1. But in
case of any earth issues in the system, impedance fault shall 3. The transformer was taken shutdown for detail checking.
be developing and may not cause tripping, which may result 4. It was found with no any abnormality at the OSR on
with serious concern to the system due to delay in tripping external checking. The gland face was covered with
action. So, using of guard wire to get proper return current adhesive putty and cover plate was applied with suitable
Fig 2.3.1
6. The moist part and sulphation contacts were cleaned
properly and then cover was put to the OSR with
application of adhesive putty.
7. The problem was rectified and transformer was charged
Case Study