NEW CHILLER INSTALLATION HMI


Risk Assessment
PROJECT No :
COOLING TOWER INSTALLATION Date: Rev- 0

Loading &
Work Activity Location: All Assessment Team: Safety Team & Construction Team Approved by Project Mangers
Transportation

RISK RATING
TASK HAZARD CONTROLS Risk Rating After Control

Likely hood

Likely hood
Severity

Severity
Person in Danger Controls Measures and/or Recovery Measures

Risk

Risk
Risk Level
Step Hazard Description & Effect
Description of Task Step Low
No: Medium
High

1 Working with May cause cutting of


cutting tools fingers or injury to hand Personnel Proper use of PPE’s (hand glove,
3 1 1 goggle, ear plug, safety shoe, 3 1 1 Low
of the personnel
helmet) required
2 Defective
Fall injury / fatality
scaffolding Personnel 3 4 1 Erection/dismantling of scaffold to be 3 1 1 Low
property done under supervision of experienced
Scaffolding Supervisor and Inspector
should inspect before start the work.
3 Improper use of Fall injury / fatality Personnel 3 4 3
scaffolding property Daily inspection and certification 3 2 1 Low
●Substandard by a competent person.
materials Site supervision to prevent
● Faulty erection overload.
● Defective access
devices Indicate the use of green and red
● Overload scaffolding tag.

Low: 1&2, Medium: 3&4, High: 6&9, Risk Rating: Severity X Likely Hood Page 1 /2
                                                                                                                                                                                                           

NEW CHILLER INSTALLATION HMI


Risk Assessment
PROJECT No :
COOLING TOWER INSTALLATION Date: Rev- 0

Loading &
Work Activity Location: All Assessment Team: Safety Team & Construction Team Approved by Project Mangers
Transportation

RISK RATING
TASK HAZARD CONTROLS Risk Rating After Control

Likely hood

Likely hood
Severity

Severity
Person in Danger Controls Measures and/or Recovery Measures

Risk

Risk
Risk Level
Step Hazard Description & Effect
Description of Task Step Low
No: Medium
High

4 vertigo while Dizziness and fall Personnel 2 2 4 Confirm non – attack of vertigo in 1 2 2 Low
working at height injury / fatality the past before allowing to work at
heights

Accompany the workers for the 1st


time to check up and ensure that he
does not suffer from vertigo.

Leaning / Fall / injury Personnel 2 2 4 Training and instructions 1 1 1 Low


5 overstretching at Close supervision
heights to reach the Provide safety harness if platform
pipe/bolt/instrument or ladder has no safe access to such
ahead. job
Do not work on ladder

Low: 1&2, Medium: 3&4, High: 6&9, Risk Rating: Severity X Likely Hood Page 2 /2
                                                                                                                                                                                                           

NEW CHILLER INSTALLATION HMI


Risk Assessment
PROJECT No :
COOLING TOWER INSTALLATION Date: Rev- 0

Loading &
Work Activity Location: All Assessment Team: Safety Team & Construction Team Approved by Project Mangers
Transportation

RISK RATING
TASK HAZARD CONTROLS Risk Rating After Control

Likely hood

Likely hood
Severity

Severity
Person in Danger Controls Measures and/or Recovery Measures

Risk

Risk
Risk Level
Step Hazard Description & Effect
Description of Task Step Low
No: Medium
High

6 Heavy wind speed Fall of person, fall of Personnel Avoid working in the wind speed
at height material, deviation of more than 20 km/hr. at any time of
material and working day.
platform Take adequate precaution to hold
the material from flying.
Hard barricading and use of safety
harness with double lanyard.
Use of adequate equipment catering
for average wind speed.

Faulty mounting of Injury by trip / slip and Personnel Provide ladder on firm footing at
7 the ladder fall appropriate inclination and fasten
on top

Low: 1&2, Medium: 3&4, High: 6&9, Risk Rating: Severity X Likely Hood Page 3 /2
                                                                                                                                                                                                           

NEW CHILLER INSTALLATION HMI


Risk Assessment
PROJECT No :
COOLING TOWER INSTALLATION Date: Rev- 0

Loading &
Work Activity Location: All Assessment Team: Safety Team & Construction Team Approved by Project Mangers
Transportation

RISK RATING
TASK HAZARD CONTROLS Risk Rating After Control

Likely hood

Likely hood
Severity

Severity
Person in Danger Controls Measures and/or Recovery Measures

Risk

Risk
Risk Level
Step Hazard Description & Effect
Description of Task Step Low
No: Medium
High

General Notes:

1. Safety is everyone’s responsibility, PM, CM, Safety Team and Site Engineer are to ensure all control measures are in place before any activity can
commence.
2. All hazards identified in this RISK ASSESMENT must be communicated to all personnel involved in the activities through Toolbox Talks.
3. This Risk Assessment must be reviewed and revised if necessary every six months or change of site or change of work procedure
4. In case of any Emergency follow our emergency evacuation procedure.

Prepared By: Reviewed By: Approved By:

Project Safety Manager Project Manager

Low: 1&2, Medium: 3&4, High: 6&9, Risk Rating: Severity X Likely Hood Page 4 /2