Checklist For Under Ground Water Piping Installation

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

PROJECT NAME & LOGOS

CHECK LIST FOR:


Form No:
INSTALLATION OF COLD WATER PIPING SYSTEM Under Ground.
Rev. No : 0
Page : 1 of 1
SUBCONTRACTOR X CONTRACTOR
SECTION OF WORK: Water Supply LOCATION:
LEVEL: WIR No.:
Checked by Checked by Date
STAGE ITEM
S/C CONT CONS.
SETTING OUT Check Layout
MEP/CIVIL Check for Services Clearances
Check for Excavation
Check for Backfilling / Compaction
INSTALLATION 1. Ensure all pipe routings, pipe sizes are in
accordance with approved drawings
2. Check materials are as per approved
material submittal.
3. Check that there are no hard protrusions and
large stones on the bedding and bedding is
acceptable to proceed with pipe lying.

4. Check that the levels and slope of installed


pipes are as per approved shop drawing.

5. Check that pipes have been tested for leaks


(1.5 working pressure – 24 hours)
6. Check that all open ends have been closed
for protection from construction debris.

7. Verify expansion requirements are provided


for at building expansion joints and where
required.
8. Check that the warning tapes (detectable
type) are approved as per approved level.

For S/C QA/QC: Date: FOR CONTRACTOR Date: For CONS. Rep.: Date:
QA/QC:

Name: Sign: Name: Sign: Name: Sign: