The document outlines the engineering tasks and estimated man-hours for a FEED (Front End Engineering Design) project. It lists 13 engineering disciplines with codes T3 to T13. Under each discipline are the engineering tasks like diagrams, studies, schedules and lists, specifications and drawings. Descriptions are provided for each task explaining the engineering work.
The document outlines the engineering tasks and estimated man-hours for a FEED (Front End Engineering Design) project. It lists 13 engineering disciplines with codes T3 to T13. Under each discipline are the engineering tasks like diagrams, studies, schedules and lists, specifications and drawings. Descriptions are provided for each task explaining the engineering work.
The document outlines the engineering tasks and estimated man-hours for a FEED (Front End Engineering Design) project. It lists 13 engineering disciplines with codes T3 to T13. Under each discipline are the engineering tasks like diagrams, studies, schedules and lists, specifications and drawings. Descriptions are provided for each task explaining the engineering work.
The document outlines the engineering tasks and estimated man-hours for a FEED (Front End Engineering Design) project. It lists 13 engineering disciplines with codes T3 to T13. Under each discipline are the engineering tasks like diagrams, studies, schedules and lists, specifications and drawings. Descriptions are provided for each task explaining the engineering work.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 8
FEED Engineering Man-hour 산정 기준
설계 구분 Code 공종 Task (대분류)
FEED Engineering T3 General Familiarization FEED Engineering T3 General Familiarization FEED Engineering T3 General Familiarization FEED Engineering T3 General Departmental reporting FEED Engineering T3 General Departmental reporting FEED Engineering T3 General Departmental reporting FEED Engineering T3 General Authorities FEED Engineering T3 General Meetings & Site visits FEED Engineering T3 General Meetings & Site visits FEED Engineering T3 General Tender preparation FEED Engineering T3 General Personnel FEED Engineering T3 General Estimate development FEED Engineering T4 Process Diagrams FEED Engineering T4 Process Diagrams FEED Engineering T4 Process Diagrams FEED Engineering T4 Process Studies FEED Engineering T4 Process Studies FEED Engineering T4 Process Studies FEED Engineering T4 Process Equipment FEED Engineering T4 Process Schedules& Lists FEED Engineering T4 Process Schedules& Lists FEED Engineering T4 Process Schedules& Lists FEED Engineering T5 Mechanical Schedules & Lists FEED Engineering T5 Mechanical Schedules & Lists FEED Engineering T5 Mechanical Equipment FEED Engineering T6 Piping Diagrams FEED Engineering T6 Piping Diagrams FEED Engineering T6 Piping Diagrams FEED Engineering T6 Piping Studies FEED Engineering T6 Piping Studies FEED Engineering T6 Piping Studies FEED Engineering T6 Piping Schedules & Lists FEED Engineering T6 Piping Schedules & Lists FEED Engineering T6 Piping Schedules & Lists FEED Engineering T6 Piping Specification(Design) FEED Engineering T6 Piping Specification(Design) FEED Engineering T6 Piping Specification(Design) FEED Engineering T6 Piping Specification(Design) FEED Engineering T7 Civil Specification(Design) FEED Engineering T7 Civil Detail Drawings FEED Engineering T7 Civil Detail Drawings FEED Engineering T7 Civil Detail Drawings FEED Engineering T7 Civil Detail Drawings FEED Engineering T7 Civil Lay-outs & Plot plans FEED Engineering T7 Civil Lay-outs & Plot plans FEED Engineering T7 Civil Lay-outs & Plot plans FEED Engineering T8 Instrumentation Configuration & Specification FEED Engineering T8 Instrumentation Configuration & Specification FEED Engineering T8 Instrumentation Configuration & Specification FEED Engineering T8 Instrumentation Design Specification FEED Engineering T8 Instrumentation Design Specification FEED Engineering T8 Instrumentation Studies FEED Engineering T8 Instrumentation Studies FEED Engineering T8 Instrumentation Studies FEED Engineering T8 Instrumentation Studies FEED Engineering T8 Instrumentation Schedules & Lists FEED Engineering T8 Instrumentation Schedules & Lists FEED Engineering T8 Instrumentation Schedules & Lists FEED Engineering T8 Instrumentation Diagrams FEED Engineering T8 Instrumentation Diagrams FEED Engineering T8 Instrumentation Diagrams FEED Engineering T8 Instrumentation Diagrams FEED Engineering T8 Instrumentation Lay-outs & Plot plans FEED Engineering T8 Instrumentation Lay-outs & Plot plans FEED Engineering T8 Instrumentation Lay-outs & Plot plans FEED Engineering T9 Electrical Diagrams FEED Engineering T9 Electrical Diagrams FEED Engineering T9 Electrical Diagrams FEED Engineering T9 Electrical Diagrams FEED Engineering T9 Electrical Diagrams FEED Engineering T9 Electrical Lay-outs & Plot plans FEED Engineering T9 Electrical Lay-outs & Plot plans FEED Engineering T9 Electrical Lay-outs & Plot plans FEED Engineering T9 Electrical Lay-outs & Plot plans FEED Engineering T10 Procurement Studies FEED Engineering T10 Procurement Studies FEED Engineering T10 Procurement Studies FEED Engineering T11 Construction Man Contract Documents FEED Engineering T11 Construction Man Contract Documents FEED Engineering T11 Construction Man Contract Documents FEED Engineering T12 Project ManagemeReports FEED Engineering T12 Project ManagemeReports FEED Engineering T12 Project ManagemeQuality FEED Engineering T12 Project ManagemeDepartmental Control FEED Engineering T12 Project ManagemeDepartmental Control FEED Engineering T12 Project ManagemeDepartmental Control FEED Engineering T12 Project ManagemeSpecial FEL Tasks FEED Engineering T13 Safety Inventory FEED Engineering T13 Safety Ergonomics FEED Engineering T13 Safety Ergonomics FEED Engineering T13 Safety Health, Safety,Environment FEED Engineering T13 Safety Health, Safety,Environment FEED Engineering T13 Safety Health, Safety,Environment FEED Engineering T13 Safety Health, Safety,Environment Descriptions Data retrieval, meetings, read scope, etc. Data retrieval, meetings, read scope, etc. Data retrieval, meetings, read scope, etc. Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc. Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc. Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc. Labor inspection, local laws, inspection procedures, etc. Meetings with clients and vendors, surveys, site visits, etc. Meetings with clients and vendors, surveys, site visits, etc. Write tender at the end of basic engineering (depends on contract strategy) Extra personnel needed on the project Input to 30% (basic), 20% (basic) and 10% (detail) estimate PFD, P&ID, UFD, ESD. Need to be set-up PFD, P&ID, UFD, ESD. Need to be set-up PFD, P&ID, UFD, ESD. Need to be set-up All equipment items require studies.General studies refers to studies like HAZOP, Design conditions All equipment items require studies.General studies refers to studies like HAZOP, Design conditions All equipment items require studies.General studies refers to studies like HAZOP, Design conditions Preparation of datasheets per piece of equipment type. Equipment list, Data sheets instrumentation, Line destination table. Equipment list, Data sheets instrumentation, Line destination table. Equipment list, Data sheets instrumentation, Line destination table. Equipment & Insulation input to process, spare parts list, etc. Equipment & Insulation input to process, spare parts list, etc. Preparation of datasheets as well as the requisition and handling of this document It represents the time needed to add to each diagram defined by process. It represents the time needed to add to each diagram defined by process. It represents the time needed to add to each diagram defined by process. Stress analysis, Site & plot plans, Piping route study Stress analysis, Site & plot plans, Piping route study Stress analysis, Site & plot plans, Piping route study Tie-in list, Drawing list, Line list etc. Tie-in list, Drawing list, Line list etc. Tie-in list, Drawing list, Line list etc. For piping, erection, ewlding, painting, etc. For piping, erection, ewlding, painting, etc. For piping, erection, ewlding, painting, etc. For piping, erection, ewlding, painting, etc. Update owner specifications to the current project, e.g. for paving, painting, etc. Drawings for structural, construction, architectural and underground Drawings for structural, construction, architectural and underground Drawings for structural, construction, architectural and underground Drawings for structural, construction, architectural and underground Paving drawings (new or update), Soil Report, Draingae lay-outs, etc. Paving drawings (new or update), Soil Report, Draingae lay-outs, etc. Paving drawings (new or update), Soil Report, Draingae lay-outs, etc. Software specifications, I/O configurations, control system, etc. Software specifications, I/O configurations, control system, etc. Software specifications, I/O configurations, control system, etc. E.g. Fire & gas detection spec, plant automation spec E.g. Fire & gas detection spec, plant automation spec Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc. Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc. Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc. Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc. Cable schedules, drawing lists, process data sheets (input to process). One list of each is required Cable schedules, drawing lists, process data sheets (input to process). One list of each is required Cable schedules, drawing lists, process data sheets (input to process). One list of each is required Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha Input to lay-outs & plot plans need to be made. For control rooms, cables, etc. one Inputdrawing needs to lay-outs to beplans & plot prepared need to be made. For control rooms, cables, etc. one drawing needs to be prepared Input to lay-outs & plot plans need to be made. For control rooms, cables, etc. one drawing needs to be prepared A number of diagrams need to be setup once, and require minimum 1 update e.g. logic, key on line, panel A number of diagrams need to be setup once, and require minimum 2 update e.g. logic, key on line, panel A number of diagrams need to be setup once, and require minimum 3 update e.g. logic, key on line, panel A number of diagrams need to be setup once, and require minimum 4 update e.g. logic, key on line, panel A number of diagrams need to be setup once, and require minimum 5 update e.g. logic, key on line, panel Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons For example, Value Improvement Processes report, Project basis of design For example, Value Improvement Processes report, Project basis of design Quality audit plan need to be set up which describes when and how quality audits will be held All kind of procedures are made, e.g. control, progress and planning procedures. All kind of procedures are made, e.g. control, progress and planning procedures. All kind of procedures are made, e.g. control, progress and planning procedures. ITBs for contract need to be made and send out to contractors An inventory of all necessary safety activities must be made Reviews are needed to check if design applies to ergonomic standards. Also, a checklist must be set up Reviews are needed to check if design applies to ergonomic standards. Also, a checklist must be set up HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review Man-hour Metrics Man-hour Metrics Task (중분류) (Min.) (Max.) Unit Data retrieval 9 24 hrs/department Meetings 1 1 meeing/month Read scope 1 week ACC & DCC update of ACC & DCC, progress control 1 1 a week progress planning meeting 1 1 a month Collect information of what's needed at the projec Site visit 1 1 day/visit Meetings Tender preparation 2 3 weeks/discipline Define per discipline the extra personnel needed
PFD(5 equipm./PFD) 3 5 days/PFD
P&ID (4 equipm/P&ID) 14 20 hrs/P&ID UFD (3 equipm./UFD) 18 24 hrs/UFD 1 study/equipment 15 25 hr/study 1 HAZOP study 200 300 hr Design conditions 60 100 hrs depending on complexity of equipment 5 20 hr/equipment Equipment list 2 3 hrs/equipment Data sheets 2 4 hrs/control or relief valve Line dest. Table 0.5 1 hrs/line number Equipment & Insulation input Spare parts list depending on type of equipment and complexity 20 100 hrs/equipment type 12 18 hrs/PFD 26 34 hrs/P&ID 20 24 hrs/UFD Stress analysis 28 36 hrs/stress isometric Site & plot plans 22 30 hrs/unit or on-site plan Piping route study 38 46 hrs/main equipment and main pipe rack Tie-in list: 20 tie-ins/sheet 36 40 hrs/sheet Drawing list: 24/sheet 14 18 hrs/sheet Line list 60 70 hrs Piping 20 24 piping class Erection 16 20 specification Welding 8 12 hrs/welding class Painting 8 12 hrs/specification 8 12 hrs/specification Structure plan 70 80 hrs/plan Construction plan: e.g. foundation location plan 40 50 hrs/plan Architectural: e.g. elevation plan 30 40 hrs/plan Underground: e.g. drainage details 40 45 hrs/drawing paving 65 75 hrs/drawing Soil report 120 140 hrs/report Drainage lay-outs 18 25 hrs/drawing Software specification 10 15 hrs/specification I/O configuration 20 30 hrs/configuration Control system 35 40 hrs/specification Fire & detection spec 75 85 hrs Plant auotmation spec 20 28 hrs Per piece of equipment 18 25 hrs/study Analyzers 14 20 hrs/study Temperature 6 10 hrs/study Level 6 10 hrs/study Cable schedules 28 35 hrs/schedule Drawing list 15 20 hrs/list Process data sheets 5 10 hrs/data sheet Input to PFD/P&ID 8 12 hrs/diagram Cause & effect chart 40 50 hrs/chart I/O index 60 70 hrs Cable routing 30 40 hrs/diagram Input to lay-outs & plot plans 80 100 hrs/lay-out & plot plan Control room 20 25 hrs Cable drawing 25 30 hrs Logic diagram 50 60 hrs Key one line diagram 60 70 hrs Panel wiring diagram 70 80 hrs Interconnection diagram 70 80 hrs Updates require 20 30 hrs less Input to lay-outs & plot plans 70 80 hrs/lay-out Lighting lay-out 10 15 hrs/lay-out Earthing lay-out 50 60 hrs/lay-out Power lay-out 10 15 hrs/lay-out Procurement plan 100 120 hrs Purchase procedure 100 120 hrs Subcontract procedure 80 100 hrs Constructibility procedure 60 75 hrs Subcontracting plan 60 75 hrs Temporary site facilities plan 35 50 hrs VIP report 200 240 hrs Project basis of design 70 100 hrs Quality audit plan 30 45 hrs Project control procedure 40 60 hrs Progress procedure 40 60 hrs Planning procedure 30 45 hrs Setting up and sending out ITBS 200 300 hrs Inventory of safety activities 18 25 hrs Reviews at 30%, 60%, 90% of (model) progress 80 120 hrs/review Checklist 70 90 hrs Noise allocation report 100 130 hrs Fire & gas review 30 40 hrs Fire fighting study 50 60 hrs Escape routing review 30 40 hrs Man-hour Metrics (기타)