Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km 24/0 to 36/4 in Nalgonda District. (Working Reach in km 24/0 to 25/8 and 32/6 to 36/4)
As per sanctioned As per work done
Sl.No. Description of item Qty. Rate Per Amount Qty. Rate Per Amount Excess Less Remarks
1 2 3 4 5 6 7 8 9 10 11 12 13
Earthwork excavation in soils upto SDR by mechanical means including trimming
bottom and side slopes in accordance with requirements of lines , grades and cross
1 sections etc., complete including seignioarge charges for finished item of work for
trench cutting as per MoRT&H specification 301(5th revision) and as directed by
the Engineer-in-Charge
Providing crack filling using slow curing type bitumen slow setting emulsion and
12 applying crusher dust of required quantity in case of cracks wider than 3 mm
including cost of all materials, T&P and labour charges for all operations
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed
stone aggregate and fine aggregate conforming to table 1000-2 of MoRT&H
including cost, conveyance of all materials to site and labour charges, centering,
machine mixing, laying,
15
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm
size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1
and fine aggregate conforming to table 1000-2) including cost,seignorage and
conveyance of all material
16
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm
size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1
and fine aggregate conforming to table 1000-2) including cost,seignorage and
conveyance of all materia
17
18
Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost, conveyance of all materials
to site and labour ch
19
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour charges
for fabrication of reinforcement including cutting, bending, binding rods, tying
grills,
20
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour charges
for fabrication of reinforcement including cutting, bending, binding rods, tying
grills,
21
22
Back filling behind Abutments with gravel including cost ,conveyance and of all
materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per
23 MoRT&H Specification No. 2200 (5th revision) and as per Drawing and technical
specification
Vibrated cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including
25 all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1600, 1700 & 2704 (5th
revision) and as directed by the Engineer-in-Charge for Approach slab.
Vibrated cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including
26 all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1600, 1700 & 2702 (5th
revision) and as directed by the Engineer-in-Charge for Wearing coat over deck
slab.
85000000 85000000
Sl.No Existing CD Work Location Total No.s Earlier proposed with Newly proposed with
25/6-8, 34/4-6, 34/8-10, 35/0-2,
1 1V-800 NP2 5 1V-1.2m span slab culvert Proposed for reconstruction with 1V-
36/0-2
1000mm dia NP3 culvert to 12.5 m
2 1V-1000 NP2 34/4-6 1 1V-1.5m span slab culvert wide
Total: 12 Nos
Detailed estimate of Widening of 8V of 1000 mm dia
S.No. Description of item Nos Measurements (metres)
L B D
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per MoRT&H specification 304(5th Revision) and as
directed by the Engineer-in-Charge
body wall foundation 1 x 2 20.20 1.60 0.90
Granular bedding 1x 2 16.00 1.50 0.30
2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to site and labour
charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th
Revision) and as directed by the Engineer-in-Charge for foundations of HP culverts
for body wall bed 1x 2 20.20 1.60 0.30
for pipe bedding 1x 2 16.00 1.50 0.30
Total:
3 Vibrated Cement Concrete M15 using 40mm, 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost (excluding seigniorage)
and conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P required etc., complete as per MoRT&H specification
1500,1700, 2200 (5th Revision) for Sub-Structure.
Body walls 1x 2 20.00 (1.4+0.5)/2 2.40
Deduct pipe portion 8 x 2 TT/4 x (1.20)2 (1.0+0.6)/2
Parapets 1x 2 20.00 0.40 0.45
4 Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia., NP-3 class for pipe culverts including
cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of 600mm/800mm/1000mm dia.
R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per
MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by
the Engineer-in-Charge for finished item of work.
8x 2 2.50
5 Back Filling behind abutments with gravel including cost ,conveyance (excluding seigniorage) of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (5th Revision) and as
per Drawing and technical specifications for finished item of work
Gravel fill between 2x 2 20.00 2 1.4
body walls
m dia
Quantity
58.18
14.40
72.58
Cum
tone aggregate and fine aggregate
of all materials to site and labour
ll other incidental and operational
ecification 1500,1700, 2100 (5th
9.70
14.40
24.10
Cum
stone aggregate (Coarse aggregate
uding cost (excluding seigniorage)
ixing, laying, vibrating, curing etc.,
mplete as per MoRT&H specification
91.20
-14.47
7.20
83.93
Cum
3 class for pipe culverts including
ng of 600mm/800mm/1000mm dia.
etc., as per drawing and as per
blication No: 13 and as directed by
40.00
Rmt
seigniorage) of all materials to site
ion No. 2200 (5th Revision) and as
112.00
112.00
Detailed Estimate of 3 V of 1000 mm dia pipe culvert for one culvert only
S.No. Description of item Nos Measurements (metres) Quantity
L B D
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per
drawing and technical specification including setting out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to the
extent required etc., complete including seignioarge charges for finished item of work as per MoRT&H
specification 304(5th Revision) and as directed by the Engineer-in-Charge
Foundations 1x 2 7.70 1.60 0.90 22.18
central portion 1x 1 7.50 6.00 1.60 72.00
Granular bedding 1x 1 10.00 5.00 0.30 15.00
109.18
2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials
to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for
foundations of HP culverts
for body wall bed 1x 1 7.70 1.60 0.30 3.70
for pipe bedding 1x 1 10.0 5.00 0.30 15.00
Total: 18.70
3 Vibrated Cement Concrete M15 using 40mm, 20mm and 10mm size HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including
cost (excluding seigniorage) and conveyance of all materials to site and labour charges, centering,
machine mixing, laying, vibrating, curing etc., including all other incidental and operational charges of all
T&P required etc., complete as per MoRT&H specification 1500,1700, 2200 (5th Revision) for Sub-
Structure.
Body walls 1x 2 7.50 (1.4+0.5)/2 2.40 34.20
Deduct pipe portion 2 x 3 TT/4 x (1.25)2 (1.0+0.6)/2 -5.89
Parapets 1x 2 7.50 0.40 0.45 2.70
31.01
Cum
4 Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia., NP-3 class for pipe culverts including
cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of 600mm/800mm/1000mm dia.
R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per
MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by
the Engineer-in-Charge for finished item of work.
3x 5 2.50 37.50
5 Back Filling behind abutments with gravel including cost ,conveyance (excluding seigniorage) of all
materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No.
2200 (5th Revision) and as per Drawing and technical specifications for finished item of work
Gravel fill between 1x 1 10.00 6 1.4 84.00
body walls
84.00
Detailed Estimate of 2 V of 1000 for one culvert only
S.No. Description of item Nos Measurements (metres) Quantity
L B D
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc.,
complete including seignioarge charges for finished item of work as per MoRT&H specification 304(5th
Revision) and as directed by the Engineer-in-Charge
body wall foundation 1 x 2 6.20 1.60 0.90 17.86
Central portion 1x 1 7.50 5.00 1.60 60.00
Granular bedding 1x 1 10.00 4.00 0.30 12.00
89.86
2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (5th Revision) and as directed by the Engineer-in-Charge for foundations of HP culverts
for body wall bed 1x 2 6.20 1.40 0.30 5.21
for pipe bedding 1x 2 10.00 4.00 0.30 24.00
Total: 29.21
3 Vibrated Cement Concrete M15 using 40mm, 20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost
(excluding seigniorage) and conveyance of all materials to site and labour charges, centering, machine mixing,
laying, vibrating, curing etc., including all other incidental and operational charges of all T&P required etc.,
complete as per MoRT&H specification 1500,1700, 2200 (5th Revision) for Sub-Structure.
Body walls 1x 2 6.00 (1.4+0.5)/2 2.40 27.36
Deduct pipe portion 2 x 2 TT/4 x (1.20)2 (1.0+0.6)/2 -3.62
Parapets 1x 2 6.00 0.40 0.45 2.16
25.90
4 Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia., NP-3 class for pipe culverts
including cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of
600mm/800mm/1000mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting
etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special
Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
2x 5 2.50 25.00
5 Back Filling behind abutments with gravel including cost ,conveyance (excluding seigniorage) of all materials to
site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (5th
Revision) and as per Drawing and technical specifications for finished item of work
Gravel fill between 1x 1 10.00 5 1.4 70.00
body walls cum
Detailed Estimate of 1V-1000mm dia for one culvert only
position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and
2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
1x 5 2.50 12.50
5 Back Filling behind abutments with gravel including cost ,conveyance (excluding seigniorage) of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (5th Revision) and as
per Drawing and technical specifications for finished item of work
Gravel fill between 1x 1 10.00 3 1.4 42.00
body walls cum
ABSTRACT ESTIMATE
CD WORKS
S.No Description of Item Quantity Rate per Amount
1 Earthwork excavation in soils upto SDR by mechanical means for
foundations of structures as per drawing and technical specification
including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing sides of bottom,
back filling the excavation earth to the extent required etc.,
complete including seignioarge charges for finished item of work
as per MoRT&H specification 304(5th Revision) and as directed by
the Engineer-in-Charge
Name of Work: Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km
24/0 to 36/4 in Nalgonda District. (Working Reach in km 24/0 to 25/8 and 32/6 to
36/4)
Ref ::- For Emulsion (Bulk) :- HINCOL Price List With Effect From Dt.
For Bulk Bitumen VG-10 (80/100), VG-30 (60/70):- HPCL Price List With Effect From
Lead from
Vizag
492.00 Kms 1476.00 1476.00 1476.00
Lead charges for Bulk @
1.50 per KM
419.00
456.00
588.00
156.00
154.00
144.00
164.00
136.00
118.00
138.00
188.00
55.00
95.00
588.00
944.00
984.00
780.00
656.00
504.00
308.00
340.00
103.00
620.00
994.00
1036.00
822.00
692.00
532.00
606.00
342.00
70.00
67.00
45.00
20.00
36.00
345.00
357.00
295.00
2575.60
3216.00
2848.50
1646.00
922.00
2678.30
1146.70
624.00
415.00
422.00
422.00
507.50
1646.00
357.00
1498.00
860.00
24171.00
2249.00
2567.00
1646.00
1283.00
1143.00
1850.00
1320.00
861.70
453.00
7.22
72.20
48.00
19550.00
ROAD METAL RATES
Widening and Strngthening of Suryapet - Nemmikal - Danthalpally
NAME OF WORK ::- road from km 24/0 to 36/4 in Nalgonda District. (Working Reach in
km 24/0 to 25/8 and 32/6 to 36/4)
Deduct
Initial cost Machine
Lead in Blasting stacking Toal Cost
Sl.No Description of Metal Kms
Conveyance less
charges
crushing
charges for per Cum
stacking charges
conveyance
Page 27
Quantity Description of Item Rate per Amount
1 Earthwork excavation in soils upto SDR by mechanical means including trimming bottom and
side slopes in accordance with requirements of lines , grades and cross sections etc., complete
including seignioarge charges for finished item of work for trench cutting as per MoRT&H
specification 301(5th revision) and as directed by the Engineer-in-Charge
Unit : Cum
Taking out put = 180 Cum Page 50 of MoRT&H SDB
(A) Labour
0.08 day Mate 345.00 day 27.60
2.00 day Mazdoor unskilled 295.00 day 590.00
617.60
(B) Machinery
180.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 2340.00
(C) charges
180.00 Cum charges 20.00 cum 3600.00
Unit = cum
Taking output = 300 cum Page 95 of MoRT&H SDB
(A) Labour
0.48 day Mate 345.00 day 165.60
2.00 day Mazdoor skilled 357.00 day 714.00
8.00 day Mazdoor unskilled 295.00 day 2360.00
Total 3239.60
(B) Machinery
6.00 hr Motor grader 3.35M Blade @50 cum/Hr 3216.00 hr 19296.00
12.00 hr Tractor with Rotavator 422.00 hr 5064.00
6.00 hr Vibratory roller 8T 2678.30 hr 16069.80
3.00 hr Water tanker 6 KL 624.00 hr 1872.00
Total 42301.80
(C) Material
Coarse graded Granular sub-base material
as per Table 400-1 of MORT&H
26.5mm-9.50 IRC & MORT&H HBG/HBT 1292.4125 173700.24
134.4 cum Chips @ 35%
9.5mm to 4.75mm @ 25% 888.35 Cum 85281.60
96.00 cum (Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm HBG M/C
metal)
2.36mm and below @40% 535.52 Cum 82255.87
153.60 cum (Rate of 2.36mm & below HBG metal)
Page 28
Quantity Description of Item Rate per Amount
Total 341237.71
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 19338.96
(E) Total of (A) + (B)+( C)+(D) 406118.07
(F) Add Contractors Profit at 10% on (E) 40611.81
Cost per 300 cum (E) + (F) 446729.88
Rate per 1 cum 1489.10
Rate to be adopted 1489.00
1 Cum
3 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (5th revision) Specn.
No.305.4.3
Unit = sqm Page 67,68 of MoRT&H SDB
Taking output = 100 sqm
(A) Labour
0.01 day Mate 345.00 day 3.45
0.25 day Mazdoor 295.00 day 73.75
Total 77.20
(B) Machinery
0.08 hr Tractor with ripper attachment @ 60 cum 422.00 hr 33.76
0.20 hr Front end loader 1 cum capacity 1646.00 hr 329.20
0.23 hr Tipper 5.50 cum capacity, 4 trips/Hour 922.00 hr 212.06
Total 575.02
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 32.61
Add Contractors Profit at 10% on (A)+(B)+© 68.48
Cost per 100 sqm 753.31
Rate per 1 sqm 7.53
Rate to be adopted 7.50
1 Sqm
4 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
macadem specification including cost,seignorage of all materials and including premixing the
material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site ,
laying in uniform layers with paver in base courses on well prepared surface and compacting
with Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-Charge
and as per MoRT&H specification.406 (5th revision) for finished item of work.
Total 5416.60
(C) Material
0.70 MT Bitumen 80/100 @ 0.20 Kgs/sqm 44825.02 MT 31377.51
Total 31377.51
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 1870.59
(E) Total of (A) + (B)+( C)+(D) 39282.30
(F) Add Contractors Profit at 10% on (E) 3928.23
Cost per 3500 sqm (E) + (F) 43210.53
Rate per 1 sqm 12.35
Rate to be adopted 12.40
1 Sqm
6 Providing and applying primer coat with Bitumen Emulsion on the prepared surface of granular
base including clearing of road surface and sparaying primer at the rate of 0.70kg/sqm using
mechanical means for finished item of work as per MoRT&H Specification 502 (5th revision) and
as directed by the Engineer-in-Charge.
unit = sqm Page 123 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos Mate 188.00 day 15.04
2.00 nos Mazdoor 146.00 day 292.00
Total 307.04
Page 30
Quantity Description of Item Rate per Amount
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250 sqm/hr. 357.00 hr 999.60
2.80 hr Air compressor 250 cfm 507.50 hr 1421.00
2.00 hr Bitumen pressure distributor @1750 sqm/hr 860.00 hr 1720.00
1.00 hr Water tanker 6 KL capacity @ 1 trip per hour 624.00 hr 624.00
Total 4764.60
(C) Material
2.45 MT Bitumen Emulsion @ 0.70 Kgs/sqm 47245.40 MT 115751.23
6.00 KL Cost of water 0.00 0.00
Total 115751.23
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 6041.14
(E) Total of (A) + (B)+( C)+(D) 126864.01
(F) Add Contractors Profit at 10% on (E) 12686.40
Cost per 3500 sqm (E) + (F) 139550.41
Rate per 1 sqm 39.87
Rate to be adopted 39.90
1 Sqm
7 Providing B.T. Patchwork for pot holes using 40mm HBG metal with required quantity of 9.5-
11.2mm size HBG key chips and 80/100 grade Bitumen including removal of the loose material in
the pot holes, trimming the edges to provide firm vertical faces, cleaning, applying tack coat,
filling the pot holeswith mix duly tamping to fill up all corners , tamping and compacting with 8t to
10t road roller and finishing including cost of all materials, T&P, and labolur charges for all
operations etc. complete.for finished item of work as directed by Engineer-In - charge
Page 31
Quantity Description of Item Rate per Amount
8 Providing and laying Dense graded bituminous macadam with 100-120 TPH batch type
HMP /40-60TPH HMP using HBG crushed aggregates of GRading-II as per table 500-10 of
MoRT&H Specification 505 (5th revision) premixed with bituminous binder of VG-30 grade @
4.5% of weight of total mixture, transporting the hot mix to work site, laid over a previously
prepared surface with mechanical paver finisher to the required grade, level and alignment, rolled
as per Clauses 501.6 and 501.7 to achive the desired compaction for finished item of work as
directed by the Engineer-In-Charge including hire and operational charges all T&P and all other
contingent charges necessary excluding cost of seiniorage charges of all materials etc.,
completes and as per MoRT&H specification No.505 (5th revision) (Excluding VAT charges)
114.60 cum IRC &MORT&H HBG M/C chips 5mm and 603.19 cum 69125.00
below @ rate
Average 20%of IRC&MoRT&H HBG M/C
metal of sizes 2.36 to 5mm and 2.36mm&
below
Page 32
Quantity Description of Item Rate per Amount
5.73 cum Filler @ 2% of weight of aggregates 535.52 cum 3068.53
Total 1189877.01
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 68459.44
(E) Total of (A) + (B)+( C)+(D) 1437648.15
(F) Add Contractors Profit at 10% on (E) 143764.82
Cost per 195 cum (E) + (F) 1581412.97
Rate per 1 cum 8109.81
Rate to be adopted 8110.00
1 Cum
Page 33
Quantity Description of Item Rate per Amount
9 Providing and Laying 30/40mm thick Bituminous concrete with 100 to 120 TPH batch type
HMP /40-60TPH hot mix plant using HBG crushed aggregates of Grading-2 as per table 500-17
of Specification 507 of MoRT&H (5th revesion), premixed with Bituminious binder VG-30 Grade
@ 5.4% of mix and filler, transporting the hot mix to work site, laying with mechanical paver
finisher to the required grade, level and alignment, rolling with smooth wheeled,vibratory and
tandem rollers to achieve the desired compaction as per MoRT&H Specification 507 (5 th
Revision) complete for finished item of work in all respects excluding seiniorage charges and as
directed by Engineer-in-charge.(Excluding VAT Charges)
122.03 cum IRC &MORT&H HBG M/C chips2.36 to 5mm, 2.36 603.19 cum 73606.67
& above
Page 34
Quantity Description of Item Rate per Amount
10 Forming shoulders with borrowed useful earth having MDD not less than 1.75 gm/cc from outside
road boundary by mechanical means upto SDR with all leads and lifts including pre-watering of
soil at borrow area, removal of top soil, excavation of soils at borrowed area, conveyance of soil,
depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table
300-2 of MoRT&H, including all hire and operational charges of T&P and (excluding
seigniorage) charges, complete for finished item of work as per MoRT&H specification 305 (5th
revision) (Payment will be made based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 345.00 day 13.80
1.00 day Mazdoor unskilled 295.00 day 295.00
308.80
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 1300.00
160.00 t.km Tipper (for 1 Km = 160x1 = 160) 72.20 t.km 11552.00
Add 10% of cost of carriage to cover cost 1155.20
of loading and unloading
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2575.60 hr 1287.80
1.00 hr Motor Grador for Grading @ 100 cum per hour 3216.00 hr 3216.00
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 345.00 day 13.80
1.00 day Mazdoor unskilled 295.00 day 295.00
308.80
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 1300.00
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2575.60 hr 1287.80
1.00 hr Motor Grador for Grading @ 100 cum per hour 0.00 hr 0.00
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 462.52 cum 2775.12
6.00 cum Cost of 40mm size IRC HBG metal 880.52 cum 5283.12
Total 8058.24
© Machinery
0.06 hr Water tanker 6 KL capacity 624.00 hr 37.44
Total 37.44
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 531.40
(E) Total of (A) + (B)+( C)+(D) 11159.48
(F) Add Contractors Profit at 10% on (E) 1115.95
Cost per 10 cum (E)+(F) 12275.43
Rate for 1 cum 1227.54
Rate to be adopted 1228.00
1 Cum
10 Back filling behind Abutments with gravel including cost ,conveyance and of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200
(5th revision) and as per Drawing and technical specifications for finished item of work
Unit = cum Page 462 of MoRT&H SDB
Taking output = 10 cum
(A) Labour
0.28 nos Mate 345.00 day 96.60
7.00 nos Mazdoor 295.00 day 2065.00
Total 2161.60
(B) Material
12.00 cum Cost of Granular material 118.77 cum 1425.24
Total 1425.24
© Machinery
2.50 hr Plate compactor/Power rammer/road roller 48.00 hr 120.00
0.05 hr Water tanker 6 KL capacity 624.00 hr 31.20
Total 151.20
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 186.90
(E) Total of (A) + (B)+( C)+(D) 3924.94
(F) Add Contractors Profit at 10% on (E) 392.49
(G) Seiniorage Charges
12.00 Gravel 22.00 Cum 264.00
Cost per 10 cum (E)+(F) 4581.43
Rate for 1 cum 458.14
Rate to be adopted 458.00
1 Cum
Page 41
Quantity Description of Item Rate per Amount
11 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including all other incidental and operational charges of all
T&P etc., complete for finished item of work as per MoRT&H specification 1500, 1700, 2100 &
2702 (5th revision) and as directed by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 345.00 day 296.70
1.50 nos Mason 357.00 day 535.50
20.00 nos Mazdoor 295.00 day 5900.00
Total 6732.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1434.60 cum 11620.26
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1078.35 cum 5823.09
6.75 cum Sand at site 624.54 cum 4215.65
6.33 MT Cement at site 6100.00 MT 38613
Total 60272
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
7888.20
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) 74892.40 Cum 2621.23
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D) 3875.68
(F) Total of (A) + (B)+( C)+(D)+(E) 81389.31
(G) Add Contractors Profit at 10% on (F) 8138.93
Cost per 15 cum (F)+(G) 89528.24
Rate for 1 cum 5968.55
Rate to be adopted 5969.00
1 Cum
12 Painting two coats after filling the surface with synthetic enamel paint in all shades on new
plastered concrete surfaces
Unit = 1 sqm
Taking output = 40 sqm Page 220 of MoRT&H SDB
(A) Labour
0.12 day Mate 345.00 day 41.40
2.00 day Painter 357.00 day 714.00
1.00 day Mazdoor 295.00 day 295.00
1050.40
(B) Material
6.00 Litres Paint Confirming to requirement of clause 803.3 146.50 Lit 879.00
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 1929.40 96.47
(D) Total of (A) + (B)+( C) 2025.87
(E) Add Contractors Profit at 10% on (D) 202.59
Cost per 40 sqm (D)+(E) 2228.46
Rate for 1 Sqm 55.71
Or say 55.70
1 Sqm
Page 42
Quantity Description of Item Rate per Amount
51 Providing weep holes in VCC Abutments, Return walls and wing walls with 100mm Diameter AC
pipe extending through the full width of the structure at 1.00m C/C in both horizontal and vertical
direction so that the weep holes in each horizontal direction is staggered from the weep holes
laying above and below lines as shown in drawing including cost and conveyance of the A.C
pipes and labour charges for cutting to required length, placing the pipe with a slope of about 1V :
20H towards stream side face etc., complete for finished item of work for weep holes as per
MoRT&H specification 2706 & 2200 (5th revision)
unit = sqm
Rate is adopted as per SSR 2008-09
Rate per 1 RM 161.00
Rate to be adopted 161.00
1 RM
11 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item
of work as per MoRT&H specification 1500,1700, 2200 (4th Revision) and as directed by the
Engineer-in-Charge for body walls
Page 46
Quantity Description of Item Rate per Amount
1 Forming embankment with earth obtained from trench cutting by mechanical means upto SDR
including pre-watering of soil , removal of top soil, excavation of soils , depositing the soils on the
embankment, spreading soil, breaking clods, sectioning , grading and consolidation with 8 to 10
Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including
all hire and operational charges of T&P and charges, complete for finished item of work as per
MoRT&H specification 305 (5th revision) .
Unit : Cum
Taking out put = 100 Cum Page 70 of MoRT&H SDB
(A) Labour
0.02 day Mate 345.00 day 6.90
0.50 day Mazdoor unskilled 295.00 day 147.50
154.40
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 1300.00
1.00 hr Motor Grador for Grading @ 100 cum per hour 0.00 hr 0.00
4.00 hr Water tanker 6 KL 624.00 hr 2496.00
1.00 hr Vibratory roller 8T 2678.30 hr 2678.30
6474.30
(C) Over head charges @5% (10%-VAT) on (A) + (B) 331.44
(D) Total of (A) + (B)+(C) 6960.14
(E) Add Contractors Profit at 10% on (E) 696.01
Cost per 100 cum (E) 7656.15
Rate per Cum 76.56
Rate per 1 cum 77.00
1 Cum
1 Construction of earthen shoulders with selective soils obtained from barrowed earth with an extra
lead of 5kms. with MDD of 17.5Kn/Cum from approved sources, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of
MoRT&H, including all hire and operational charges of T&P and charges, complete for finished
item of work as per MoRT&H specification 305(5th revision) (Payment will be made based on
level for finished item of work).
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
Page 47
Quantity Description of Item Rate per Amount
(A) Labour
0.04 day Mate 345.00 day 13.80
1.00 day Mazdoor unskilled 295.00 day 295.00
308.80
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 1300.00
160.00 t.km Tipper (for 01 Kms = 160x1 = 160) 72.20 t.km 11552.00
Add 10% of cost of carriage to cover cost 1155.20
of loading and unloading
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2575.60 hr 1287.80
1.00 hr Motor Grador for Grading @ 100 cum per hour 0.00 hr 0.00
Page 48
Quantity Description of Item Rate per Amount
(A) Labour
0.22 day Mate 345.00 day 75.90
3.00 day Mazdoor unskilled 295.00 day 885.00
960.90
(B) Machinery
180.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 87.00 cum 15660.00
11.25 hrs Tipper 5.5 cum capacity ( 4 trips for hour) 922.00 hr 10372.50
26032.50
Unit : Cum
Taking out put = 360 Cum Page 58 of MoRT&H SDB
(A) Labour
0.08 day Mate 345.00 day 27.60
2.00 day Mazdoor unskilled 295.00 day 590.00
617.60
(B) Machinery
360.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum 4680.00
Page 49
Quantity Description of Item Rate per Amount
0.00 Additional lead of 1Km (360x1.6 = 576) 4.50 t.Km 0.00
19763.92
Page 50
Quantity Description of Item Rate per Amount
15 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of
Grade - III - IRC & MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as
per Table 400-7& 9 of MoRT&H Specification 404 of 5th revision for Water Bound Macadam
specification including cost, conveyance and seignorage charges and spreading in uniform
thickness, hand packing, rolling with Power Road Roller 8- 10 Tonnes in stages to proper grade
and camber applying and brooming requisite type ' B ' screenings as per table 400-8&9 and
binding materials to fill up the interstices of coarse aggregates,watering and compacting to the
required density for finished item of work as per MoRT&H specification 404 (5th revision) and as
directed by the Engineer-in-Charge (Payment will be made based on levels for finished item of
work)
Page 51
Quantity Description of Item Rate per Amount
250.00 nos. Mazdoor 295.00 day 73750.00
Total 77941.60
(B) Machinery
12.00 hr smooth wheeled roller 8 Ton 1146.70 hr 13760.40
24.00 hr water tanker 6 KL 624.00 hr 14976.00
Total 28736.40
(C) Material
217.80 cum 63mm IRC&MoRT&H HBG metal 740.52 cum 161285.26
200.38 cum 45mm IRC&MoRT&H HBG M/C metal 1003.35 cum 201051.27
17.42 cum 22.40 mm IRC&MoRT&H HBG M/C metal 1434.60 cum 24990.73
57.60 cum Screenings 13.2mm@ 0.12cum/10sqm 997.10 cum
(Ave of 9.5-11.2 mm & 5-7 mm M/C ) 57432.96
28.80 cum Binding material @ 0.06 cum / 10sqm (Rate of 535.52 cum
2.36mm & Below) 15422.98
Total 460183.20
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 28343.06
(E) Total of (A) + (B)+( C)+(D) 595204.26
(F) Add Contractors Profit at 10% on (E) 59520.43
Cost per 360 cum (E) + (F) 654724.69
Rate per 1 cum 1818.68
Rate to be adopted per 1 cum 1819.00
Cum
17 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of
Grade - III - IRC & MoRT&H - H.B.G Machine crushed metal as per Table 400-7& 9 of MoRT&H
Specification 404 of 5th revision for Water Bound Macadam specification including cost,
conveyance and seignorage charges and spreading in uniform thickness, hand packing, rolling
with Power Road Roller 8- 10 Tonnes in stages to proper grade and camber applying and
brooming requisite type ' B ' screenings as per table 400-8&9 and binding materials to fill up the
interstices of coarse aggregates,watering and compacting to the required density for finished
item of work as per MoRT&H specification 404 (5th revision) and as directed by the Engineer-in-
Charge (Payment will be made based on levels for finished item of work)
Page 52
Quantity Description of Item Rate per Amount
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 32254.49
(E) Total of (A) + (B)+( C)+(D) 677344.23
(F) Add Contractors Profit at 10% on (E) 67734.42
Cost per 360 cum (E) + (F) 745078.65
Rate per 1 cum 2069.66
Rate to be adopted per 1 cum 2070.00
Cum
18 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of
Grade - II - IRC & MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as
per Table 400-7&9 of MoRT&H Specification 404 of 5th revision for Water Bound Macadam
specification including cost, conveyance and seignorage charges and spreading in uniform
thickness, hand packing, rolling with Vibratory Road Roller 8- 10 Tonnes in stages to proper
grade and camber applying and brooming requisite type ' A ' screenings as per table 400-8&9
and binding materials as to fill up the interstices of coarse aggregates,watering and compacting
to the required density for finished item of work as per MoRT&H specification 404 (5th revision)
and as directed by the Engineer-in-Charge (Payment will be made based on levels for finished
item of work)
Page 53
Quantity Description of Item Rate per Amount
19 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of
Grade - III - IRC & MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as
per Table 400-7& 9 of MoRT&H Specification 404 of 5th revision for Water Bound Macadam
specification including cost, conveyance and seignorage charges and spreading in uniform
thickness, hand packing, rolling with Vibratory Road Roller 8- 10 Tonnes in stages to proper
grade and camber applying and brooming requisite type ' B ' screenings as per table 400-8&9
and binding materials to fill up the interstices of coarse aggregates,watering and compacting to
the required density for finished item of work as per MoRT&H specification 404 (5th revision) and
as directed by the Engineer-in-Charge (Payment will be made based on levels for finished item of
work)
Page 55
Quantity Description of Item Rate per Amount
28.80 cum Binding material @ 0.06 cum / 10sqm (Rate of 535.52 cum
2.36mm & Below) 15422.98
Total 538411.74
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 32369.96
(E) Total of (A) + (B)+( C)+(D) 679769.10
(F) Add Contractors Profit at 10% on (E) 67976.91
Cost per 360 cum (E) + (F) 747746.01
Rate per 1 cum 2077.07
Rate to be adopted per 1 cum 2077.00
Cum
23 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine
crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @
0.75 kg / sqm including cost, and conveyance of all materials to work site and laid on prepared
surface and rolling with 8-10 T Power Road Roller etc., complete for finished item of work as per
MoRT&H Specification 510 (5th revision) and as directed by the Engineer-in-charge.
6.00 hr Tipper 10Tonne capacity for carriage of stone chips 922.00 hr 5532.00
from stock pile on road side to chip spreader
(Rate of Tipper 5 cum
6.00 hr Front end loader 1 cum bucket capacity 1646.00 hr 9876.00
6.00 hr Bitumen pressure distributor @1750 sqm/hr 1498.00 hr 8988.00
6.00 hr smooth wheeled roller 8 Ton 1146.70 h 6880.20
Total 52902.60
(C) Material
6.75 MT Bitumen 80/100 @ 0.75 Kg / sqm 44825.02 MT 302568.89
36.00 cum Crushed stone chippings 6 mm nominal 915.85 cum 32970.60
size @0.004 cum/sqm
Total 335539.49
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 19598.14
(E) Total of (A) + (B)+( C)+(D) 411561.03
(F) Add Contractors Profit at 10% on (E) 41156.10
Cost per 9000 sqm (E) + (F) 452717.13
Rate per 1 sqm 50.30
Rate to be adopted. 50.30
1 Sqm
Page 56
Quantity Description of Item Rate per Amount
24 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine
crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 60/70 grade @
0.75 kg / sqm including cost, and conveyance of all materials to work site and laid on prepared
surface and rolling with 8-10 T Power Road Roller etc., complete for finished item of work as per
MoRT&H Specification 510 (5th revision) and as directed by the Engineer-in-charge.
27 Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 20 mm
thickness by hot mix plant using hard blasted granite crushed aggregates of 13.2mm to
0.09mm (Type 'B') as per table 500-26 of specification 512 of MoRT&H (5th revision), premixed
with bituminous binder 60/70 grade @ 19 Kg per 10 Sqm area, including cost and of all
materials and transporting the hot mix to work site, laying with mechanical paver finisher to the
required grade, level and alignment, rolling with smooth wheeled roller 8 to 10 Tonnes as per
MoRT&H Specification 512 (5th revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.
Page 57
Quantity Description of Item Rate per Amount
5.00 nos. Skilled Mazdoor for checking line and levels. 357.00 day 1785.00
Total 6204.80
(B) Machinary
12.00 hr Hot mix plant 40 to 60 TPH 24171.00 hr 290052.00
6.00 hr Generator 250 KVA 1850.00 hr 11100.00
6.00 hr Front end loader 1 cum capacity 1646.00 hr 9876.00
6.00 hr Mechanical Paver finisher @ 100 TPH 2249.00 hr 13494.00
6.00 hr Smooth wheeled roller 8-10 Tonnes 1146.70 hr 6880.20
Total 331402.20
(C) Material
19.48 M.T (i) Bitumen 60/70 Grade @19 kg per 10 sqm 45758.68 MT 891379.09
(ii) Aggregate
For Type 'B'
HBG M/C aggregates 13.2mm to 0.09mm @
0.27 cum per 10 sqm
276.75 cum Average rate of IRC&MoRT&H HBG M/C metal of 888.28 cum 245832.60
sizes 12-14, 9.5-11.2, 5-7mm,2.36 - 5mm and
HBG 2.36mm&below
Total 1137211.69
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 73740.93
(E) Total of (A) + (B)+( C)+(D) 1548559.62
(F) Add Contractors Profit at 10% on (E) 154855.96
Cost per 10250 Sqm (E) + (F) 1703415.58
Rate per 1 sqm 166.19
Rate to be adopted 166.00
1 sqm
6 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using
hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of specification 508
of MoRT&H (5th revision), premixed with bituminous binder 60/70 grade @ 5% of mix and filler,
transporting the hot mix to work site, laying with hydostatic paver finisher with mechanicaL
control to the required grade, level and alignment, rolling with smooth wheeled,vibratory and
tandem rollers to achieve the desired compaction as per MoRT&H Specification 508 (5th
revision) complete for finished item of work in all respects as directed by Engineer-in-charge.
(Payment will be made based on levels for finished item of work)
5.00 nos. Skilled Mazdoor for checking line and levels. 357.00 day 1785.00
Total 6204.80
(B) Machinary
11.00 hr Hot mix plant 40 to 60 TPH 24171.00 hr 265881.00
6.00 hr Mechanical Paver finisher @ 100 TPH 2249.00 hr 13494.00
6.00 hr Generator 250 KVA 1850.00 hr 11100.00
6.00 hr Front end loader 1 cum capacity 1646.00 hr 9876.00
3.90 hr Power road roller 8 tonne for initial break down rolling 1146.70 hr 4472.13
3.90 hr Vibratory roler 8 tonne for intermediate rolling 2678.30 hr 10445.37
Page 58
Quantity Description of Item Rate per Amount
3.90 hr Finish rolling with 6-8 tonne smooth 1646.00 6419.40
wheeled tandem roller. hr
Total 321687.90
(C) Material
22.50 M.T (I) Bitumen @ 5% by weight of mix 45758.68 MT 1029570.30
(ii) Aggregate
For Grading II
162.450 cum IRC &MORT&H HBG M/C chips 9.5 to 888.35 cum 144312.46
4.75mm @ 57%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 9.5-11.2, 5-7mm,2.36 - 5mm
116.850 cum IRC &MORT&H HBG M/C chips 4.75 mm 603.19 cum 70482.17
and below @ 41%
Average rate of IRC&MoRT&H HBG M/C cum 0.00
metal of sizes 2.36 - 5mm and 2.36mm&
below
5.70 cum Filler @ 2% of weight of aggregates. 535.52 cum 3052.46
Total 1247417.39
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 78765.50
(E) Total of (A) + (B)+( C)+(D) 1654075.59
(F) Add Contractors Profit at 10% on (E) 165407.56
Cost per 195 cum (E) + (F) 1819483.15
Rate per 1 cum 9330.68
Rate to be adopted 9331.00
1 Cum
7 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an
average output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of
Grading - II as per table 500-4 of MoRT&H specificaion 504 (5th revision) premixed with
bituminous binder of 60/70 grade @ 3.3% by weight of total mixture, transported to site, laid over
a previously prepared surface with mechanical paver finisher to the required grade, level and
alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired compaction for
finished item of work as directed by the Engineer-in-Charge including hire and opeational
charges all T&P and all other contingent charges necessary including cost of charges on all
materials etc., complete and as per MoRTH specification No. 504(5th revision) .
Unit = cum
Taking out put = 205 cum (450 tonne) Page 125,126,127 of MoRT&H SDB
(A) Labour
0.84 nos. Mate 345.00 nos. 289.80
14.00 nos. Mazdoor working with HMP, mechanical broom, 295.00 nos.
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction.
4130.00
5.00 nos. Mazdoor skilled 357.00 nos. 1785.00
Total 6204.80
(B) Machinery
12.00 hr Hot Mix Plant 40 to 60 TPH 24171.00 hr 290052.00
2.20 hr Air Compressor 250 cfm 507.50 hr 1116.50
6.00 hr Mechanical Paver finisher 100 TPH 2249.00 hr 13494.00
6.00 hr Generator 250 KVA 1850.00 hr 11100.00
6.00 hr Front end loader 1 cum bucket capacity 1646.00 hr 9876.00
3.90 hr Smooth wheeled roller 8-10 tonnes for initial break 1146.70 hr 4472.13
down rolling
Page 59
Quantity Description of Item Rate per Amount
3.90 hr Vibratory roller 8 tonnes for intermediate rolling 2678.30 hr 10445.37
3.90 hr Finish rolling with 6-8 tonnes smooth wheeled 1646.00 hr 6419.40
tandem roller.
Total 346975.40
(C) Material
14.85 MT Bitumen 60/70 @ 3.3 % of weight of 45758.68 MT 679516.40
mix=205x2.2=450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
weight of bitumen - 14.85 tonnes
Weight of aggregate = 450-14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate = 290.1 cum
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
116.04 cum IRC &MORT&H HBG M/C chips 25 to 1292.41 cum 149971.55
10mm @ 40%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 25-27mm, 19-22mm, 12-
14mm, 9.5-11.2mm
116.04 cum IRC &MORT&H HBG M/C chips 10 to 5mm 997.10 cum 115703.48
@ 40%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 9.5-11.2mm, 5 to 7mm
58.02 cum IRC &MORT&H HBG M/C chips 5mm and 603.19 cum 34996.79
below @ 20%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 2.36 to 5mm and 2.36mm&
below
Total 980188.22
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 66668.42
(E) Total of (A) + (B)+( C)+(D) 1400036.84
(F) Add Contractors Profit at 10% on (E) 140003.68
Cost per 205 cum (E) + (F) 1540040.52
Rate per 1 cum 7512.39
Rate to be adopted 7512.00
1 Cum
31 Providing and laying of 100mm thick Bituminous Macadam with hot mix plant producing an
average output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of
Grading - I as per table 500-4 of MoRT&H specificaion 504 (5th revision) premixed with
bituminous binder of 80/100 grade @ 3.3% by weight of total mixture, transported to site, laid
over a previously prepared surface with mechanical paver finisher to the required grade, level
and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired compaction for
finished item of work as directed by the Engineer-in-Charge including hire and opeational
charges all T&P and all other contingent charges necessary including cost of charges on all
materials etc., complete and as per MoRTH specification No. 504(5th revision) .
ii) Aggregate
Total weight of mix = 450 tonnes
weight of bitumen - 14.85 tonnes
Weight of aggregate = 450-14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate = 290.1 cum
Grading - I
116.04 Cum of 25-10mm @ 40%
43.51 cum IRC &MORT&H HBG M/C chips 37.50 to 1209.60 cum 52629.70
25 mm
130.55 cum IRC &MORT&H HBG M/C chips 25 to 1292.41 cum 168724.45
10mm
Average@rate
40%of IRC&MoRT&H HBG M/C
metal of sizes 25-27mm, 19-22mm, 12-
14mm, 9.5-11.2mm
72.53 cum IRC &MORT&H HBG M/C chips 10 to 5mm 997.10 cum 72319.66
@ 40% rate of IRC&MoRT&H HBG M/C
Average
metal of sizes 9.5-11.2mm, 5 to 7mm
43.51 cum IRC &MORT&H HBG M/C chips 5mm and 603.19 cum 26244.58
below @ rate
Average 20%of IRC&MoRT&H HBG M/C
metal of sizes 2.36 to 5mm and 2.36mm&
below
Total 999434.79
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 67630.75
(E) Total of (A) + (B)+( C)+(D) 1420245.74
(F) Add Contractors Profit at 10% on (E) 142024.57
Cost per 205 cum (E) + (F) 1562270.31
Rate per 1 cum 7620.83
Rate to be adopted 7621.00
1 Cum
32 Construction of Gravel shoulders including cost, charges and conveyance of all materials to
work site and spreading in uniform layers by approved means, on prepared surface and
compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished
item of work as per MoRT&H Specification 401& 407 (5th revision) and as directed by the
Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Unit = cum
Page 61
Quantity Description of Item Rate per Amount
Taking output = 300 cum
(A) Labour
0.40 day Mate 345.00 day 138.00
2.00 day Mazdoor skilled 357.00 day 714.00
8.00 day Mazdoor unskilled 295.00 day 2360.00
Total 3212.00
(B) Machinery
6.00 hr Vibratory roller 8T 2678.30 hr 16069.80
3.00 hr Water tanker 6 KL 624.00 hr 1872.00
Total 17941.80
(C) Material
384.00 cum Gravel 118.77 45607.68
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 3338.07
(E) Total of (A) + (B)+( C)+(D) 70099.55
(F) Add Contractors Profit at 10% on (E) 7009.96
Cost per 300 cum 77109.51
Rate per 1 cum 257.03
Rate to be adopted 257.00
1 Cum
34 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying,
Vibrating, curing etc., including all other incidental and operational charges of all T&P etc.,
complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (4th
Revision) and as directed by the Engineer-in-Charge for base coarse below CC Pavement.
Unit = cum
Taking output = 15 cum Page331of MoRT&H SDB
(A) Labour
0.64 nos Mate 345.00 day 220.80
1.00 nos Mason 357.00 day 357.00
15.00 nos Mazdoor 295.00 day 4425.00
Total 5002.80
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1003.35 cum 13545.23
6.75 cum Sand at site 624.54 cum 4215.65
3.45 MT Cement at site 6100.00 MT 21045.00
Total 38805.88
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
2.00 hr Water tanker 6 KL 624.00 hr 1248.00
Total 9136.20
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 2647.24
(E) Total of (A) + (B)+( C)+(D) 55592.12
(F) Add Contractors Profit at 10% on (E) 5559.21
Cost per 15 cum 61151.33
Rate for 1 cum 4076.76
Rate to be adopted 4077.00
1 Cum
Page 62
Quantity Description of Item Rate per Amount
36 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H and using fly ash
(replacing cement by fly ash to the extent of 15% and sand by 10%) including cost, conveyance
of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing
etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by
the Engineer-in-Charge for base coarse below CC Pavement.
Unit = cum
Taking output = 15 cum Page 331 of MoRT&H SDB
(A) Labour
0.64 nos Mate 345.00 day 220.80
1.00 nos Mason 357.00 day 357.00
15.00 nos Mazdoor 295.00 day 4425.00
Total 5002.80
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1003.35 cum 13545.23
6.075 cum Sand at site 624.54 cum 3794.08
2.933 MT Cement at site 6100.00 MT 17891.30
1.274 MT Fly ash
Unit = cum
Taking output = 15 cum Page 345,346 of MoRT&H SDB
(A) Labour
0.86 nos Mate 345.00 day 296.70
1.50 nos Mason 357.00 day 535.50
20.00 nos Mazdoor 295.00 day 5900.00
Page 63
Quantity Description of Item Rate per Amount
Total 6732.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1434.60 cum 11620.26
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1078.35 cum 5823.09
6.08 cum Sand at site 624.54 cum 3797.2
5.381 MT Cement at site 6100.00 MT 32824.1
1.576 MT Fly ash
1.576 MT Conveyance charges of fly ash cum
Total 54064.65
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
7888.20
(A)+(B)+( C) 68685.05
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) 68685.05 Cum 2403.98
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D) 3554.45
(F) Total of (A) + (B)+( C)+(D)+(E) 74643.48
(G) Add Contractors Profit at 10% on (F) 7464.35
Cost per 15 cum (F)+(G) 82107.83
Rate for 1 cum 5473.86
Rate to be adopted 5474.00
1 Cum
38 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the
excavation earth to the extent required etc., complete including seignioarge charges for finished
item of work as per MoRT&H specification 304(5th revision) and as directed by the Engineer-in-
Charge for foundation.
(B) Material
12.00 cum Cost of Granular material 118.77 cum 1425.24
Total 1425.24
© Machinery
2.50 hr Plate compactor/Power rammer 48.00 hr 120.00
0.05 hr Water tanker 6 KL capacity 624.00 hr 31.20
Total 151.20
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C) 186.90
(E) Total of (A) + (B)+( C)+(D) 3924.94
(F) Add Contractors Profit at 10% on (E) 392.49
Cost per 10 cum (E)+(F) 4317.43
Rate for 1 cum 431.74
Rate to be adopted 432.00
1 Cum
46 Dismantling clearing away and carefully stacking materials usefulfor reuse of CC structures,
Concrete slabs, body walls etc.,
Rate is adopted as per SSR 2008-09 vide Item No.930
Rate per 1 Cum 187.00
Rate to be adopted 187.00
1 Cum
47 Providing SS Revetment 300 mm thick including cost, charges and conveyance of materials to
site and including labour charges for packing the stones for revetment etc., complete for finished
item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-
in-Charge for Pitching of slopes
Page 66
Quantity Description of Item Rate per Amount
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1434.60 cum 11620.26
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1078.35 cum 5823.09
6.75 cum Sand at site 624.54 cum 4215.65
6.05 MT Cement at site 6100.00 MT 36905.00
Total 58564.00
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
Total 7888.20
(D) Form work
2.00 % Form work @ 2% on (A)+(B)+( C) 73184.40 Cum 1463.69
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D) 3732.40
(F) Total of (A) + (B)+( C)+(D)+(E) 78380.49
(G) Add Contractors Profit at 10% on (F) 7838.05
Cost per 15 cum (F)+(G) 86218.54
Rate for 1 cum M 25 Concrete 5747.90
Rate to be adopted 5748.00
1 Cum
43 Construction of precast VRCC railing of M20 grade using HBG crushed stone aggregate of size
not exceeding 12 mm and fine aggregate conforming to table 1000-2 true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical
posts not to exceed 2000mm, leaving adequate space between vertical posts for expansion
including cost, conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all
T&P as per approved drawings and as directed during execution but excluding cost of steel and
its fabrication charges as per approved drawings and technical specifications for finished item of
work as per MoRT&H Specification 2703, 1500, 1600, 1700(5th revision)
Unit = 1 No.
Taking output = 30 Nos. Page 461,333 of MoRT&H SDB
Cement Mortor (1:3) (Out put = 1Cum)
Material
0.51 MT Cost of Cement 0.00 MT 0.00
1.05 cum Cost of Sand 624.54 cum 655.77
655.77
Labour
0.04 nos Mate 345.00 day 13.80
0.90 nos Mazdoor 295.00 day 265.50
279.30
Cement Mortor (1:3) Cost per 1 Cum 935.00
weep holes
(A) Material
31.50 RM AC pipeof 100mm Dia(including wastage 161.00 RM 5071.50
@ 5% ).
Avg length of weep hole is
taken as one metre for the purpose of
estimating.
Page 69
Quantity Description of Item Rate per Amount
10.00 nos collors for AC pipe 16.10 each 161.00
30.00 nos MS clamps 13.00 each 390.00
0.05 cum Cement mortor (1:3) 935.00 cum 46.75
5669.25
(B) Labour
0.03 nos Mate 345.00 day 10.35
0.50 nos Mason 357.00 day 178.50
0.25 nos Mazdoor 295.00 day 73.75
Total 262.60
(C) Add for Over head charges @ 5% on (A)+(B) i.e., on 5931.85 296.59
(D) Contractor's profit @ 10% on (A)+(B)+(C) i.e., on 6228.44 622.84
Cost per 30 Nos 6851.28
Rate for 1No. per 1 RM 228.38
Say Rs 228.00
1 RM
53 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
foundations of R.C.C items.
unit = sqm
Rate is adopted as per SSR 2008-09
Rate per 1 sqm 805.00
Rate to be adopted 805.00
1 Sqm
20 Sand filling in foundation including cost, seignoirage and conveyence of all materials to site and
watering, tamping etc., complete for finshed item of work as per MoRT&H specification 304 (5th
revision) and as directed by the Engineer - in - Charge.
Unit = cum
Page 71
Quantity Description of Item Rate per Amount
Taking output = 15 cum Page 335,455 of MoRT&H SDB
(A) Labour
0.86 nos Mate 345.00 day 296.70
1.50 nos Mason 357.00 day 535.50
20.00 nos Mazdoor 295.00 day 5900.00
Total 6732.20
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 1003.35 cum 8127.14
4.05 cum Cost of 20mm SS-5 HBG M/C metal 1434.60 cum 5810.13
1.35 cum Cost of 10mm SS-5 HBG M/C metal 1078.35 cum 1455.77
6.75 cum Sand at site 624.54 cum 4215.65
4.13 MT Cement at site 6100.00 MT 25193.00
Total 44801.69
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
7888.20
(D) Form work
4.00 % Form work @4% on (A)+(B)+( C) 59422.09 2376.88
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D) 3089.95
(F) Total of (A) + (B)+( C)+(D)+(E) 64888.92
(G) Add Contractors Profit at 10% on (F) 6488.89
Cost per 15 cum (F)+(G) 71377.81
Rate for 1 cum 4758.52
Rate to be adopted 4759.00
1 Cum
23 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, conveyance of all materials to site and labour charges, centering,
machine mixing, laying, vibrating, curing etc., including other incidental hire and operational
charges of all T&P as per approved drawings and as directed during execution but excluding
cost of steel and its fabrication charges for finished item as per MoRT&H specification
1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Cover
slabs over side drains
Unit = cum
Taking output = 15 cum Page 472,457 of MoRT&H SDB
(A) Labour
0.86 nos Mate 345.00 day 296.70
1.50 nos Mason 357.00 day 535.50
20.00 nos Mazdoor 295.00 day 5900.00
Total 6732.20
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1434.60 cum 11620.26
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1078.35 cum 5823.09
6.75 cum Sand at site 624.54 cum 4215.65
5.12 MT Cement at site 6100.00 MT 31232.00
Total 52891.00
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr 2718.00
6.00 hr Generator set 35 KVA 861.70 hr 5170.20
Total 7888.20
Page 72
Quantity Description of Item Rate per Amount
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 67511.40 2700.46
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D) 3510.59
(F) Total of (A) + (B)+( C)+(D)+(E) 73722.45
(G) Add Contractors Profit at 10% on (F) 7372.25
Cost per 15 cum (F)+(G) 81094.70
Rate for 1 cum 5406.31
Rate to be adopted 5406.00
1 Cum
10 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials , charges ,
labour charges , curing etc complete for finished item of work as directed by the Engineer -in-
Charge
Unit = 10 sqm
Taking output = 10 sqm Page 452 & 333 of MoRT&H SDB
(A) Labour
0.04 day Mate 345.00 day 13.80
0.50 day Mason 357.00 day 178.50
0.50 day Mazdoor 295.00 day 147.50
339.80
(B) Material
0.144 Cum Cement Mortar (1:5) 2783.37 Cum 400.80
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 740.60 37.03
(D) Total of (A) + (B)+( C) 777.63
(E) Add Contractors Profit at 10% on (D) 77.76
Cost per 10 sqm (D)+(E) 855.40
Or say 85.50
1 Sqm
Sub-Analysis
Cement Mortar (1:5)
(a) Material
0.303 MT Cement 6100.00 MT 1848.30
1.05 cum Sand for Mortar 624.54 cum 655.77
2504.07
(b) Labour
0.04 day Mate 345.00 13.80
0.90 day Mazdoor 295.00 265.50
279.30
Rate per cum 2783.37
5 Providing B.T. Patchwork for pot holes using 9.5mm to 11.2mm HBG metal with required quantity
of 80/100 grade Bitumen including removal of the loose material in the pot holes, trimming the
edges to provide firm vertical faces, cleaning, applying tack coat, filling the pot holeswith mix duly
tamping to fill up all corners , tamping and compacting with 8t to 10t road roller and finishing
including cost of all materials, T&P, and labolur charges for all operations etc. complete.for
finished item of work as directed by Engineer-In - charge
22A Providing , laying and Rolling of 75mm thick Built Up Spray Grout layer over prepared base
consisting of a two layer composite construction of compacted crushed coarse agreegates using
motor grader for aggregates .Key stone Chips spreader may be used with application of
bituminous binder after each layer, and with Key aggregates placed on top of the second layer to
serve as a base confirming to the line ,grades and cross section specified ,the compacted layer
thickness being 75mm as directed by the Engineer-in-Charge including hire and opeational
charges all T&P and all other contingent charges necessary including cost of charges on all
materials etc., complete and as per MoRTH specification No. 506(5th revision) .
RSI Items
The rates are allowed as per circular memo nos: 2/DCE®/EE(RS&PMS) /DEE1/AEE1/2005,
Dated.15-09-2005, 2/DCE®/ EE(RS&PMS)/DEE2/AEE2/2007, Dated.06-03-2007 and Road
sinages/DCE®/EE-II/DEE-7/AEE(NLG)/2013-14, Dt:-15.05.2013.
1 Supplying of hot applied thermoplastic road marking compound, 2.5mm thick including
reflectorising glass beads @ 250gms with Reflectorising Glass Beads on Bituminous Surface at
250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass bead as per
IRC: 35, the material should be of BERGER Company/ BERGER Equivalent/ Equivalent brand
and must comply with the following: a) White index for the product should be in the range of 60-
70 when measured against standard reference. The applied panel 7/8 number must be submitted
for checking up the white index in the department lab. In case the department approves the white
index of any vendor, the department engineer may carryout random checking of the applied
products at site against the approved panel. In case of any major deviation, beyond acceptance
limit, department reserve the right to cancel or reject the total supplied consignment of the said
material and will compell the vendor has to replace the full consignment by the desired material
as per approved panel at his own cost and additional demurrages may be claimed due to loss of
man days (as per the rules of the department). b) Luminance factor of the material should be in
the range of 80-85% at 45 degree centigrade as per AASTHOM 249. c) Crack resistance: The
applied panel cured for 7 days under ambient condition and then should be tested as per
BS3262, Part-1, 1989 and should pass at the range of '0' degree centigrade to '-10' degree
centigrade D) Adhesion : Strong E) Softening point: 102 degree centigrade F) Dried film finish :
Smooth and uniform G) Night Vision: High as directed by the Engineer-in-Charge and confirming
to IS: 164-1961 (1st revision reaffirmed in 1986) and clause conforming to IRC 35-1997
702.00
1 Sqm
Page 75
Quantity Description of Item Rate per Amount
2 Providing and fixing village name boards of size 900x450 mm made out of feflective sheeting of
engineering grade as per MoRTH specification No 801 &MoST circular No RW/NH-33023/31/88-
DO III dated 4.12.1995 for all backgroundin blue colour and White cut lettering and arrow marks
as per IRC 67-2001&IRC:30:1968 with engineering grade sheeting and fixed over 2 mm thick
aluminum sheet and painted back side with grey colour and fixed over back support frame of MS
angle 25x25x3 mm all round and fixing with MS angle 35x35x4 mm and mounted on two MS
angle posts of size 75x75x6 mm with clear hight of not less than 2.1 m from the ground level to
the bottem of the board as per drawing. The sign post should be painted with one coat of red
oxied paint and Two coats of Ist quality synthetic enamel paint Black & White colour with bounds
of 30 cm hight. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in the ground
by 1:2:4 concrete foundation of size 450x450x600 mm , including cost and conveyance of all
materials , equipment , machinary necessary for satisfactory completion of the work as directed
by engineer -in -charge.
3440.00
1 No
3 Providing and fixing Cautionary/Warning sign boards of size 600 mm equilateral tringle made out
of Retro feflective sheeting of type - III/IV of ASTM D4956 -01as per MoRTH specification No 801
&MoST circular No RW/NH-33023/31/88-DO III dated 4.12.1995 for all back ground of white and
letters/loags done by screen painting in back colour,borders by screen printing in red colour as
pre IRC 67-2001and fixed over 1.5 mm thick aluminum sheet (for 600 mm equilateral tringle)/2
mm thick aluminum sheet (for 900 mm equilateral tringle)and painted back side with grey colour
and fixed over back support frame of MS angle 25x25x3 mm all round with MS angle 35x35x4
mm and mounted on a MS angle posts of size 75x75x6 mm with clear hight of not less than 2.1
m from the ground level to the bottem of the board. The sign post should be painted with one
coat of red oxied paint and Two coats of Ist quality synthetic enamel paint Black & White colour
with bounds of 30 cm hight. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in
the ground by 1:2:4 concrete foundation of size 450x450x600 mm , including cost and
conveyance of all materials , equipment , machinary and lobour with all leads and lifts, loding and
unloding charges necessary for satisfactory completion of the work as directed by engineer -in -
charge.
2380.00
1 No
3 Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out
of Type – XI of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective
sheeting and confirming to IRC 67:2012 for full background of White colour and letters/logos
done by screen printing in Black colour, boarders by screen printing in Red colour and fixed over
4MM Aluminium Composite Material sheet having minimum 0.5 mm thick Aluminium skin on both
sides with back side painted grey colour and fixed over back support frame of M.S angle
25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of size
75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the
board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic
enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly
fixed with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size
450x450x600mm including cost and conveyance of all materials ,equipment, machinery and
labour with all leads and lift, loading chages necessary for satisfactory completion of the work as
directed by Engineer -in-Charge.
6226.00
each
Page 76
Quantity Description of Item Rate per Amount
4 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded
from HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene Acrylonitrite) and reflective
panels with micro prismatic lens capable of providing total internal reflection of the light entering
the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H
and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 – DO
III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 100 mm
and with minimum reflective area of 13 Sqcm on each side and the slope to the base shall be 35
+/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not
less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum
value of 700 Kgs. Fixing will be by drilling holes on the road for the twin shanks to go inside,
without nails and using epoxy resin based adhesive as per manufacturer’s recommendation and
complete as directed by the engineer for Road Studs
316.00
1 No
5 Providing and fixing Object markers 48.3mmdia.MS pipe ,keep at 50cm above ground level with
3MM Alluminium Composite Material sheet having minimum 0.30 mm thick Aluminium skin fully
covered with type XI of wide angle cube cornered micro Prismatic Retro reflective sheeting and
confirming to IRC 67:2012tro reflective sheeting fixed in to trench of 30x30x30cm filled with CC
M20 conforming to IRC-67:2012 & MORTH&H specification no 805 and approved drawing etc.,
928.00
each
6 Supply and installation of Precast RCC M15 grade roadway indicators of size 10cm x 10cm,
90cm high above ground level, painted with two coats of black and white in 15cm wide stripes,
with first quality synthetic enamel paint over one coat of appropriate primer of approved brand,
colour, and shade over the concrete surface fitted with 80x120mm rectangular/ or 75mm dia
reflectorized (front side white and back side red) panels with type III/IV fixed on 1.5mm aluminium
base sheet at the top with standard supports and burried into the ground in a trench of
size30cmx30cm, and depth 50cm depth filled with CC 1:2:4 including cost and conveyance of all
materials, equipment, machinery and labour with all leads and lifts, loading and unloading
charges necessary for successful completion of the work as directed by the Engineer-in-Charge
and conforming to IRC 79-1981 & MORTH specification no.805 and approved drawings etc.,
complete for finished item of the work
432.69
1 No
Page 77
Quantity Description of Item Rate per Amount
6 Supplying and installation of Hazard Markers/Delinators using M.S. angle of size 55x55x6mm
and 120cm high above ground level painted with two coats of black & white stripes of 15cm wide
with first quality synthetic enamel paint over one coat of appropriate primer of approved
brand,colour, with 30cm x 90cm Type – XI of ASTMD 4956-09 wide angle cube cornered micro
Prismatic Retro reflective sheeting of Yellow colour and confirming to IRC 67:2012 fixed over
3MM Alluminium Composite Material having minimum 0.30 mm thick Aluminium skin on both
sides with standard supports consisting of alternately black and Yellow with black stripes in
screen printing sloping downward at an angle of 45 degrees towards the side of the obstruction
on which the traffic is to pass and buried into the ground in a trench of size 30cm x 30cm and
50cm depth filled with CC M-20 including cost and conveyance of all materials, equipment,
machinery and labour with all leads and lifts, loading and un-loading charges necessary for
successfull completion of the work on any road in division as directed by Engineer-in-Charge
and conforming to IRC 67-2012 &MORT&H specification No.805 and approved drawings etc.,
complete for finished item of work.
4003.00
1 No
7 Providing & fixing junctin boards of size 1500 x 1200 mm made out of Type – XI of ASTMD 4956-
09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC
67:2012 for full background of Green Colour & White Letters and fixed over 4MM Alluminium
Composite Material sheet having minimum 0.5 mm thick Aluminium skin on both sides with back
side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round
and fixing with 35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear
height of not less than 2.1 m from the ground level to the bottom of the board. The signpost
should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black
and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base
angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm
including cost and conveyance of all materials ,equipment, machinery and labour with all leads
and lift, loading charges necessary for satisfactory completion of the work as directed by
Engineer -in-Charge.
26998.00
each
Providing & fixing Village Name boards of size 1200 x 450 mm made out of Type – IV of ASTMD
4956-09 High Intensity Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full
background of Green Colour & White Letters and fixed over 4MM Aluminium Composite Material
sheet having minimum 0.4 mm thick Aluminium skin on both sides with back side painted grey
colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with
35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less
than 2.1 m from the ground level the bottom of the board. The signpost should be painted with
one coat of red oxide paint and 2 coats of synthetic enamel paint Black and White colour with
bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in
to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and
conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading
charges necessary for satisfactory completion of the work as directed by Engineer -in-Charge.
8884.00
each
Page 78
Quantity Description of Item Rate per Amount
8 Providing fixing of Median Marker made of polycarbonate for impact resistance and good
weatherability. Polycarbonate used for molding the Median Marker shall have a minimum Izod
impact strength value of 600 J/m at room temperature. The impact strength of the polycarbonate
should not decrease to less than 70 % of its initial value on being subjected to UV weathering as
per ASTM G 155 for 1000 hours or exposure to 2 years of natural weathering. The body of the
median marker shall be in the form of an isosceles trapezoidal structure of length 15 cm, height
and width of 10x10 cm. The Median Marker shall have fluorescent yellow retro-reflective sheeting
conforming to type XI specifications as per ASTM D4956. Area of reflective sheeting should not
be less than 70 cm2. Edge of retro-reflective sheeting shall be concealed using a grill/ mesh/
similar mechanism to prevent vandalism and sheeting pilferage. The logo of the manufacturer
shall be embossed and printed in contrasting color on both sides of median marker for distinct
identification (even from moving vehicles).
481.00
1 Sqm
9 Providing and erecting a "W" metal beam crash barrier comprising of 3mm thick corrugated sheet
metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post,
150X75X5mm spaced 2m centre-to-centre, 1.80m high, 1.1m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all fittings to conform to IS: 1367 and IS:
1364, metal beam rail to be fixed on the vertical post with a spacer of channel section
150X75X5mm, 330mm long complete as per Clause 810.
2615.00
1 RM
Providing & fixing junction boards of size 1500 x 1050 mm made out of Type – XI of ASTMD
4956-09 wide angle cube cornered micro Prismatic Retro Retro reflective sheeting Prismatic
Retro reflective sheeting and confirming to IRC 67:2012 for full background of Green Colour &
White Letters and fixed over 4MM Alluminium Composite Material sheet having minimum 0.5
mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back
support frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a
MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground level
to the bottom of the board. The signpost should be painted with one coat of red oxide paint and
2 coats of synthetic enamel paint Black and White colour with bands of 30cm of height. The
signpost shall be firmly fixed with MS base angle 35x35x4 mm in to the ground by M-15
Concrete foundation of size 450x450x600mm including cost and conveyance of all
materials ,equipment, machinery and labour with all leads and lift, loading charges necessary for
satisfactory completion of the work as directed by Engineer -in-Charge.
23875.00
each
Supplying and installation of delineators (Roadway indicators) not less than 800mm high above
ground level. The delineator shall have a core and shell construction which shall be made of
tough, high impact resistant, injection-molded, thermoplastic outer body. The inner core shall
consist of powder coated or painted Mild steel of minimum thickness 1.0mm. The delineator
should have top retro-reflective unit consisting of white color micro prismatic non metallic retro-
reflective sheeting of minimum exposed area of 125 cm2 and bottom retro-reflective unit
consisting of red color micro prismatic non metallic retro-reflective sheeting of minimum exposed
area of 35 cm2 confirming to ASTM D4956 type XI standards. The delineators shall be fixed to
the ground by inserting the root of the delineator up to the marked portion and by firm concrete
filling as per the instructions by engineer in-charge.
1541.00
Page 79
Quantity Description of Item Rate per Amount
each
Providing and fixing Mandatory / Regulatory sign boards size 600 mm circle made out of Type –
XI of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and
confirming to IRC 67:2012 for full background of White colour and letters/logos done by screen
printing in Black colour, boarders by screen printing in Red colour and fixed over 3MM
Alluminium Composite Material sheet having minimum 0.30mm thick Aluminium skin on both
sides with back side painted grey colour and fixed over back support frame of M.S angle
25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of size
75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the
board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic
enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly
fixed with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size
450x450x600mm including cost and conveyance of all materials ,equipment, machinery and
labour with all leads and lift, loading charges necessary for satisfactory completion of the work as
directed by Engineer -in-Charge.
5169.00
each
10 This flexible prismatic sheeting shall be of 1ft width and laminated at the back with a 50 micron
thick Aluminum (Al) foil with pressure sensitive adhesive and liner. Further, this flexible prismatic
sheeting shall have screen printed arrow/slant line pattern in black color on top in a continuous
roll format. Neither AFP sheeting nor the flexible prismatic sheeting used in it shall crack when
slowly bent in 1 second time around a 1/8th inch mandrel after being conditioned for 24hrs at 0°C
and tested as per section S2.2.2. of ASTM D 4956-09. The AFP sheeting, with the liner removed,
shall be applied with a neoprene contact adhesive with Polychloroprene as base, viscosity of
200-450 cps and solid content of 20-30%. Once applied, the edges of the product shall be sealed
all around with a two-part epoxy based structural adhesive and shall be extremely resistant to
peel-off. A test report from institutes like ARAI/CRRI confirming to above mentioned flexibility and
ASTM-D4956-09 Type-VI retro reflectivity performance of the flexible prismatic sheeting used in
AFP shall be submitted by the tenderer during prequalification and supply of material.
452.00
1Sq.ft
Page 80
GOVERNMENT OF TELANGANA
Name of Work:-
Rs 857.00 Lakhs
INDEX
1 GO. Copy
2 Specification Report
3 General Abstract
4 Road - Detailed cum Abstract Estimate
5 CD Works - Abstract Estimate
6 CD Works - Detailed Estimate
7 RSI - Detailed cum Abstract Estimate
8 KM,HM stones - Detailed cum Abstract Estimate
9 Road Metal Rates
10 BT Rates
11 Lead Chart
12 Weighted Average Lead Calculation
13 Crust Design
14 Seigniorage Charges Statement
15 Road and Culvert works - Datas
16 Strip Plan
17 Road Renewal chart
18 CD Works - Inventory
19 Key Map
20 Certificates
21 Typical Crossection - Drawings
22 CD Works - Drawings
23 Earthwork Abstract Sheets
24 Video CD of the Road Go through from Km24/0 to 36/4
25 Photographs
ROAD SAFETY INTERVENTIONS
ABSTRACT CUM DETAILED ESTIMATE
Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km 24/0 to 36/4 in Nalgonda
District. (Working Reach in km 24/0 to 25/8 and 32/6 to 36/4)
Sl. Measurements
Description of item Qty. Rate Per Amount
No. L B D
Nos.
1 2 3 4 5 6 7 8 9 10
1 Providing center line marking of 300 cms length and 10 cms width with a
gap of 450 cms with thermo plastic paint including cost and conveyance of
all materials , equipment, machenary and laour with all leads and
unloading charges necessary for road and bridge works and confirming to
IRC 35-1997 etc., complete for finished item of work
NECESSITY:
As the road is a shortest connected road from Nalgonda District to Warangal District the traffic
intensity is very high with 1843 CVPD or 5518 PCUs/day. The reach from km 24/0 to 36/4 is single lane
and is very difficult to maintain single lane road in good conditions because of insufficient crust, which
is unable to meet requirements of increased traffic. The berms are getting frequently damaged in turn
leading damage of the BT edges, causing many difficulties to vehicular traffic . Further the road is
severely damaged due to floods during september and october 2013. It is taking about 3 times of
travel time to travel in this stretch of road when compared to other normal single lane road. Hence it
very necessasary to widen the road .Villagers, local leaders, Hon'ble MLA of Tungaturthy Constituency
Sri.G.Kishore Garu, Hon'ble MP Sri. B.Narsaiah Goud Garu and Hon'ble Minister for Education
Sri.G.Jagadeesh Reddy Garu are frequently representing to widen and improve the crust of central
carriage way of this road .
Administrative sanction have been accorded for Widening and strengthening of reach 24/0 -
36/4(12.4 kms) with reference of G.O.Rt.No.-1235, Dated :-02-12-2013 for an amount of Rs.850.00
Lakhs as per the proposal submitted with respect to SSR 2008-09 and using BM, SDBC. Present
estimate have been prepared with SSR 2014-15 and incorporating DBM, BC in the reach from km 24/0
to 25/8 and 32/6 to 36/4 (as the reach 25/8 to 32/6 has proposed for NH365).
Further, Keeping in view of the rapid growth of traffic as the proposed road for widening may
act as radial road for connecting the newly declared NH-365, the Pipe culverts which are proposed for
reconstruction/widening with hume pipes earlier, are now proposed for reconstruction with Slab
culverts considering suitable vent way. Also in order to strengthen the existing central carriage way in
order to cater the rapid growth of traffic, the entire reach is proposed with DBM and BC. Also the
reach from km 32/6 to 33/0 being the Maddirala junction portion and from km 35/4 to 36/0 being
village (kuntapally) portion, the reaches are proposed for widening to 10m carriage way for free flow
of traffic.
In view of above conditions of road and as per instructions of the higher officials estimate
is prepared duly providing following provisions for Rs.850.00 Lakhs:
Earthwork excavation in soils upto SDR by mechanical means including trimming bottom and side
1
slopes in accordance with requirements of lines , grades and cross sections etc.,
Construction of Granular sub-base by providing HBG material confirming to Grading - III of MoRT&H
2 Scarifying
Table theincluding
400-2 existing BT surface
cost, seigniorage charges and conveyance of all materials to work site and
3 spreading in uniform layers with motor grader or by approved means, on prepared surface mixing by
mix in place method with Rotavator / approved means at OMC and compacting with vibratory roller to
achieve the desired density etc., complete for finished item
Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
4
macadem specification
5 Providing BT patchwork with 40mm metal
6 Providing and applying Prime Coat with bitumen emulsion (Medium Setting) bulk
Providing and applying tack coat with bitumen Grade 80/100 using Bitumen pressure distributor at
7
the rate of 0.20 kgs per sqm
8 Providing
Providing and laying thick
30/40mm of 50mm thick Dense
compacted Bituminous
Bituminous Macadam
Concrete with hot
with 100-120 mixbatch
TPH planttype hot mix plant
9 /40-60 TPH hot mix plant using HBG crushed aggregates of Grading – 2 as per table 500-17 of
specification 507 of MoRT&H (5th revision), premixed with Bituminou
Forming embankment with borrowed useful earth from outside road boundary by mechanical means
10
upto SDR
11 CD works taken up as per MORTH and APDSS norms , Km&Hm stones providing
12 LS Towards VAT @ 5.00 % and Cess @ 1%
13 LS Towards Quality Control
14 L.S. towards Price Escalation for change in cost of Bitumen.and QC
15 Provision Towards Seigniorage Charges
16 Road saftey intervensions
17 LS Towards Awagahana Sadassu
The rates are adopted as per the current common S.S.R. for the year 2014-15 and the
leads taken are as per the approved quarry chart.
The work will be carried out as per the relevent specifications of MORT&H and APDSS and
other circulars issued from time to time.
Early sanction to the estimate is Solicited.
GENERAL ABSTRACT
1 2 3 4 5 6 7 8 9 10
Earthwork excavation in soils upto SDR by mechanical means including trimming bottom and side
slopes in accordance with requirements of lines , grades and cross sections etc., complete
1 including seignioarge charges for finished item of work for trench cutting as per MoRT&H
specification 301(5th revision) and as directed by the Engineer-in-Charge
2 Widening portion
From km 24/080 to 25/8 1 x 2 1720.00 1.97 0.200 1355.36
Drainage layer 1 x 2 1720.00 2.25 0.200 1548.00
From km 32/888 to 36/4 1 x 2 3512.00 1.97 0.200 2767.46
Drainage layer 1 x 2 3512.00 2.25 0.200 3160.80
For profile correction from 24/0 - 25/8 and 32/6 - 36/4 (Sheets
2000.00
Enclosed)
Or say: 10831.62 1,679.00 1.00 18186283
cum
3 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material
with all leads and lifts upto 1000 Mtrs as per MoRT&H (5th revision) Specn. No.305.4.3
4 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macadem
specification including cost,seignorage of all materials and including premixing the material with water at OMC
in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layers with paver in base
courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc., as
directed by the Engineer-in-Charge and as per MoRT&H specification.406 (5th revision) for finished item of
work.
4
From km 24/080 to 25/8 1 x 1 1720.00 7.30 0.250 3139.00
From km 32/6 to 32/888 1 x 1 288.00 7.30 0.250 525.60
From km 32/888 to 36/4 1 x 1 3512.00 7.30 0.250 6409.40
10074.00
0 say 10074.00 cum 1,985.00 1.00 19996890
0
6 Providing and applying primer coat with Bitumen Emulsion on the prepared surface of granular base including
clearing of road surface and sparaying primer at the rate of 0.70kg/sqm using mechanical means for finished item
of work as per MoRT&H Specification 502 (5th revision) and as directed by the Engineer-in-Charge.
6
6
25/080 to 25/8 1 x 1 1720.00 7.00 12040.00 sqm
32/6-32/888 1 x 1 288.00 7.00 2016.00 sqm
32/888-36/4 1 x 1 3512.00 7.00 24584.00 sqm
sqm
0 say 38640 sqm 30.80 1.00 1190112
0
7 Providing and applying tack coat with bitumen 80/100 (Medium settting) (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical
broom for finished item of work as per MoRT&H Specification 503 (5th revision) and as directed by the
Engineer-in-Charge.
For DBM
25/080 to 25/8 1 x 1 1720.00 7.00 12040.00 sqm
32/6-32/888 1 x 1 288.00 7.00 2016.00 sqm
32/888-36/4 1 x 1 3512.00 7.00 24584.00 sqm
5520.00
for BC
0
25/080 to 25/8 1 x 1 1720.00 7.00 12040.00
32/6-32/888 1 x 1 288.00 7.00 2016.00
32/888-36/4 1 x 1 3512.00 7.00 24584.00
5520.00 77280.00
0 say 77280.00 cum 10.30 1.00 795984
8 Providing and laying Dense graded bituminous macadam with 100-120 TPH batch type HMP /40-60TPH HMP
using HBG crushed aggregates of GRading-II as per table 500-10 of MoRT&H Specification 505 (5th revision)
premixed with bituminous binder of VG-30 grade @ 4.5% of weight of total mixture, transporting the hot mix to
work site, laid over a previously prepared surface with mechanical paver finisher to the required grade, level and
alignment, rolled as per Clauses 501.6 and 501.7 to achive the desired compaction for finished item of work as
directed by the Engineer-In-Charge including hire and operational charges all T&P and all other contingent
charges necessary excluding cost of seiniorage charges of all materials etc., completes and as per MoRT&H
specification No.505 (5th revision) (Excluding VAT charges)
10
Km 24/0 to 25/8 and 32/888 to 36/4 in widening
13289.20
portion (As per crossections)
Deduct T/C Quantity -4185.60
Add WMM quantity in
1x 2 5232.00 1.67 0.250 4368.72
Widening portion
In already widened portion
24/0 to 24/080 1x 2 80.00 1.50 0.300 72.00
32/6 to 32/888 1x 2 288.00 1.50 0.350 302.40
Total: 13846.72
cum
say 13846.72 cum 108.00 1.00 1495446
Forming shoulders with excavated useful earth having MDD not less than
1.75gm/cc (Table 300-1) by mechanical means up to SDR including Pre-
watering of soil , removal of top soil, excavation of soils, depositing the
soils on embankment, spreading soil, breaking clods, sectioning, grading
11 and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to
meet requirement of table 300-2 of MoRT&H, including all hire and
operational charges of T&P and (excluding seigniorage) charges, complete
for finished item of work as per MoRT&H specification 305(5th revision) .
Measurments
S.No. Description of Item Nos Quantity Rate Amount
Leangth Bearth Deapth
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical
means upto SDR with all leads and lifts including pre-watering of soil at borrow area, removal
of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soil on the
embankment, spreading soil, breaking clods, sectioning, grading and consolidation with 8 to
10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H,
including all hire and operational charges of T&P and charges, complete for finished item
of work as per MoRT&H specification 305 (5th revision)
2 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides
3 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying,
4 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all material
5 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all materia
6 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, conveyance of all materials to site and labour ch
8 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills,
9 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills,
Total : 2609593
Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km
Name of
24/0 to 36/4 in Nalgonda District. (Working Reach in km 24/0 to 25/8 and 32/6 to
Work : =
36/4)
Seigniorage Chrges
Road Work:
1) EW Excavation = 4185.60 1 22 = 92083.20
2) Forming Embankment: = 19232.32 1 22 = 423111.04
3) Granular Sub Base: = 10831.62 1.28 50 = 693223.42
4) Wet Mix Macadem: = 10074.00 1.32 50 = 664884.00
5) BT P/W = 0.00 1.313 50 = 0.00
5) DBM: = 1932.00 1.469 50 = 141905.40
6) BC: = 1160.00 1.492 50 = 86536.00
CD Work:
1) EW = 1132.64 1 22 = 24918.17
2) VCC (1:3:6): (1:4:8) = 241.25
Metal = 241.25 0.9 50 = 10856.34
Sand = 241.25 0.45 40 = 4342.54
2) VCC M15, M20, M35: = 543.60
Metal = 543.60 0.9 50 = 24461.98
Sand = 543.60 0.45 40 = 9784.79
3) Filter media = 21.60 1.200 50 = 1296.00
4) Back filling = 1032.00 1.000 22 = 22704.00
Rs: 2200106.88
Say Rs: 2200107.00
12.5m
0.45 m
0.40 0.40
0.5 0.5
2.40 m
1.2m
1.0m
0.3 m
1.40m 0.6m
0.30 m
SECTION
1.60m
Pipe Bedding
PLAN
12.5m
0.45 m
0.40 0.40
0.5 0.5
2.40 m
1.2m
1.0m
sill
0.3 m
1.2m 0.6m
0.30 m
SECTION
1.4m
PLAN
x2 3.80
32/6
6.80
25/8
x1 1.80
24/0
x1 1.8
x2 3.8
X1 = 0 + 1.8/2 = 0.9
X2 = 8.6 + 3.8/2 = 10.5
Superintending Engineer
(R&B) Circle:Nalgonda
4.6
34.6
72.8
77.7
237.7
CALCULATION OF LEAD CHART
Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km 24/0 to 36/4 in Nalgonda
District. (Working Reach in km 24/0 to 25/8 and 32/6 to 36/4)
1 Unit = cum
1 Taking output = 1 cum
1 (A) Labour
1 2.86 day Mazdoor 357.00 1 1021.02
1 1021.02
1 0.0 % Municipal Area Allowance 1021.02 0.00
1 TOTAL A= 1021.02
1 (B) Machinery
1 0.27 hour Finish rolling with 6-8 tonne 1646.00 1.00 444.42
1 smooth wheeled tandem roller.
1 TOTAL B= 444.42
1 (C) Material
1 0.042 M.T Bitumen 44825.02 1.00 1882.65
1 (ii) Aggregate
1 1.20 cum 40 - 45 mm IRC HBG m/c chips 880.52 1.00 1056.62
1 0.13 cum 9.5 to 11.2 mm IRC HBG m/c chips 1078.35 1.00 140.19
1 TOTAL C= 3079.46
1 (A + B +C) 4544.90
1 Rate per cum 4544.90
1 Rate per cum 4545.00
1
SP_65
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
ok 0
KEY MAP
Name of the work: Widening and Strngthening of Suryapet - Nemmikal - Danthalpally road from km 24/0 to 36/4 in Nalgonda District. (Working Reach
in km 24/0 to 25/8 and 32/6 to 36/4)
36/4.
28/0
Working 32/6
Reach
25/8
24/0.
70/8
71/0 10/0
km 4/4
136/2
2/8 By Pass road 138/4 of NH -9
1/0 1/0
132/8 0/0
0/2
km 4/4
Pipe Quary
1) Certified that the Leads provided in the lead statement are the shortest.
2) Certified that the Distances noted herein are correct.
3) Certified that the quarries are nearest and are having sufficient yield.
4) Certified that the routs shown are nearest.
5) Certified that the description of the variety of materials noted are correct to the
best of my knowledge.
6) Certified that the Land available for the road formation is sufficient and no land
acquisition is required