Operation of Price Adjustment
Operation of Price Adjustment
Operation of Price Adjustment
ABSTRACT
The construction industry always faces problems on price fluctuation and adjustment of the price to
compensate the cost fluctuation becomes necessary. There is dilemma on which formula of price
adjustment to use in construction contracts. Price adjustment affects all the stakeholders i.e. client,
consultant and contractor. This research has revealed about the trend of the cost of components of
construction i.e. labor, material, fuel, equipment, etc. and compare the different formulas of price
adjustment Ten contracts commencing within 2010 A.D to 2019 A.D have been chosen. The formula
used in the contracts has been compared with other formulas under same circumstance that original
formula was used. The cost of fuel and bitumen cannot be predicted as it is fluctuating with respect
to time. PPMO formula for Price Adjustment use NRB index of labor, material and equipment or
fuel. Labor index has increased by 44.86 % during June 2015 to June 2019. Material index is
fluctuating and has increased by 20.66% and Equipment index by 31.54%. Comparing the price
adjustment factor using different formulas it is seen that the value of price adjustment factor using
different formulas are different and change with course of time. Thus, it cannot be generalized that
which formula could give minimum value of price adjustment. It depends upon condition such as
time, index and cost.
Keywords: Trend, Price adjustment, Index, Initial completion date, Formulas
1. INTRODUCTION:
Price fluctuations are the outcome of different forces i.e. both national and international bazzar forces, along
with components of the development sector that mainly causes it vulnerable to average cost fluctuation and
bank economic report (Riggs, 2006) [1]. Price fluctuation has become a very obvious trend in current economic
scenario, all over the world. It particularly gets very important in the developing countries due to the
dependency of the country on external factors (MCCartney, 2011) [2]. Market price fluctuations all levels
directly affect contractors. Besides the contractor, the client and the beneficiaries of construction project also
are affected by price fluctuation. Inflation has become an ongoing issue whose impacts saturate the whole
development industry. Contractual workers are confronted with extreme vulnerability in offering and financing
chips away at ventures. Efficiency is influenced on the grounds that contractual worker can't precisely estimate
long haul returns on their ventures and are needed to redirect important funding to meet asset costs (Mishra
and Regmi, 2017) [3]. It is therefore a major concern to know how the price of different components of
construction is fluctuating during various time of a construction project and know the trend so that we can
predict the risk in a more accurate way.
For addressing the adverse effect of price fluctuation price adjustment provision is introduced in most of the
contracts with duration greater than 12 months. According to ‘Price Adjustment Guidance on Procurement
2018’, there is no single price adjustment formula that encompasses every situation. Different formulas are
applied in contracts of different sizes and for different components. A contract may comprise one or more
currencies of payment. For a contract with price adjustment provisions, at least one price adjustment formula
should be given for each currency of payment. Agreements for major and complex works and plant may
likewise contain a few areas, every one of which can be recognized commonly, area, access, timing, or
whatever other exceptional attributes which may cause various strategies for development, staging of the
Where "Pn" is the change multiplier to be applied to the assessed agreement esteem in the important money of
the work did in period "n," this period being a month, except if in any case expressed in the agreement
information. "a" (default esteem is set at 0.15) is a fixed coefficient, expressed in the applicable table of change
information, speaking to the nonadjustable segment in legally binding installments. "b", "c", "d", … are
coefficients speaking to the assessed extent of each cost component identified with the execution of the works,
as expressed in the pertinent table of change information. Such classified cost components might be
characteristic of assets, for example, work, gear, and materials. (a + b + c + d + … = 1) "Ln", "En", "Mn", …
are the current expense records or reference costs for period "n," communicated in the significant cash of
installment, every one of which is pertinent to the important organized cost component on the date 49 days
preceding the most recent day of the period (to which the installment declaration relates). "Lo", "Eo", "Mo",
… are the base expense files or reference costs, communicated in the important cash of installment, every one
of which is appropriate to the applicable arranged cost component on the base date.
Where, Pc is the change factor for the bit of the agreement value payable in a particular cash "c." Ac and Bc
are coefficients determined in the specific states of agreement, speaking to the nonadjustable (normally 0.10
to 0.20) and movable segments, separately, of the agreement value payable in that particular money "c." Ac +
Bc = 1. Imc is a merged record winning toward the month's end being invoiced and Ioc is a similar united file
winning 28 days before offer opening for inputs payable; both in the particular money "c." PPMO uses price
adjustment formula as shown in table ‘Table 3’ below :
Where, Pn is the change factor for the bit of the agreement value for the work carried out in the period "n".
"A" "is a constant or the non-adjustable portion of price adjustment factor to be specified in Appendix- to bid,
representing the non-adjustable portion of the contract price"
"b, c, d " " are coefficients or weightages of the order 0.xx (i.e.., fractions having two significant digits) for
each specified element of adjustment in the contract. The sum of a, b, c, d, etc shall be one"
"Lo, Mo, Eo" "are the base date indices for specified (adjustable) elements"
"Ln, Mn, En - " are the current date records of the predetermined (customizable components for the period "n".
Regularly following wellspring of list is applied. Public Entity will pick material Index for everything.
(a) Labor: "Public Salary and Wage Rate Index"- "Development Labor" of Nepal Rastra Bank or rate fixed by
District Rate Fixation Committee
(b) Material: "National Wholesale Price Index" - Construction Materials" of Nepal Rastra Bank
(c) Equipment use: "Public Wholesale Price Index" - "Transport Vehicles and Machinery Goods" of Nepal
Rastra Bank or Fuel Price fixed by Nepal Oil Corporation.
The base costs of the development materials are taken of 30 days before the cutoff time for accommodation of
the offer as cited by the bidder and checked by the business. With the end goal of count of value change, the
ex-manufacturing plant cost of a similar source will be mulled over. HTMA (2010) [7] are found to be referred
by experience engineer for modification in private contract. Hiyassant (2000) [8] has concluded bid evaluation
is significant for price fluctuation decision. Jennings (1996) [9] also highlighted prequalification and M.T.
Banki (2008) [10] focuses on bidding strategy of Iranian construction industry.
Labor cost trend
450
400
350
300
250
Labor cost
200
150
100
50
0
18‐Oct‐12
23‐Oct‐15
06‐May‐13
22‐Nov‐13
06‐Apr‐15
10‐May‐16
26‐Nov‐16
10‐Jul‐12
14‐Aug‐13
15‐Jul‐15
18‐Aug‐16
02‐Mar‐14
06‐Mar‐17
27‐Dec‐14
26‐Jan‐13
10‐Jun‐14
18‐Sep‐14
31‐Jan‐16
14‐Jun‐17
22‐Sep‐17
Date of IPC
Similarly, by analyzing the all 4 contracts, it can be seen that the labor cost has increased with respective to
time in every contract. Labor cost has increased by 33.33 % in Nepalgunj-Kohalpur Road Package-1, 21.67%
in Nepalgunj-Kohalpur Road Package-2, 29.21%in construction of Prestressed Bridge over Tinau River and
18.17% in Bhairahawa-Lumbini-Taulihawa Road project up to the last IPC date.
Fuel cost trend
120000
100000
Fuel cost/KL
80000
60000
40000
20000
0
22‐Nov‐13
26‐Nov‐16
26‐Jan‐13
14‐Aug‐13
31‐Jan‐16
18‐Aug‐16
06‐May‐13
02‐Mar‐14
10‐Jul‐12
18‐Oct‐12
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
06‐Apr‐15
06‐Mar‐17
15‐Jul‐15
23‐Oct‐15
10‐May‐16
14‐Jun‐17
22‐Sep‐17
Date of IPC
Fig. 2: Fuel Cost trend of Nepalgunj Kohalpur Road Package-1
Similarly, by observing the all 4 contracts, it can be seen that the fuel cost has fluctuated more with respect to
time. In Nepalgunj-Kohalpur Road Package-1, it can be seen that base value of fuel was 95500/KL in October
2012 and cost has increased up to 109000/KL in April 2014 and again went on decreasing to 77500/KL in May
2017.The cost of fuel has reduced by 23.22% up to last IPC. In Nepalgunj Road Kohalpur Package-2, the cost
of fuel has increased by 4.71% up to last IPC. In construction of Prestressed RCC bridge over Tinau River, the
cost of fuel has reduced by 5.81% up to last IPC date. In Bhairahawa-Lumbini-Taulihawa Road Project the
cost of fuel has increased by 34.93% up to last IPC date. So, it cannot be predicted accurately whether the fuel
cost increase or decrease in a contract over time.
Bitumen cost Trend
120000
100000
80000
Bitumen Cost
60000
40000
20000
0
22‐Nov‐13
26‐Nov‐16
06‐Apr‐15
27‐Dec‐14
26‐Jan‐13
18‐Oct‐12
06‐May‐13
14‐Aug‐13
02‐Mar‐14
31‐Jan‐16
10‐Jun‐14
18‐Sep‐14
23‐Oct‐15
10‐May‐16
18‐Aug‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
10‐Jul‐12
15‐Jul‐15
Date of IPC
Fig. 3: Bitumen Cost trend of Nepalgunj Kohalpur Road Package-1
Similarly, it can be seen that the bitumen cost has fluctuated with respect to time. In Nepalgunj Road Kohalpur
Package-1, base value of bitumen is Rs 81350, peak value is 96400 and value at last date of IPC is 77900. The
cost of bitumen has reduced by 4.24 % up to last IPC. Similarly, in Nepalgunj Road Kohalpur Package-2, the
cost of bitumen has reduced by 7.8 % up to last IPC date. In Bhairahawa-Lumbini-Taulihawa Road Project the
Labor Index Trend
600.0
500.0
400.0
Labor Index
300.0
200.0
100.0
0.0
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
Month
Labor Index Linear (Labor Index)
From the figure 4; it can be seen that labor index has increased every month from June-2015 to June-2019.
Labor index has increased by 44.86 % during four years.
Material index trend
400
350
300
Material Index
250
200
150
100
50
0
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
Month
Material Index Linear (Material Index)
Fig. 5: Material Index Trend
From the figure 5, it can be seen that material index has increased from month from June-2015 with value
291.6 to March 2016 with value 299.9 and decreasing up to October 2016 with value 285.9 and then increased
to June-2019 with value 359.47. Material index has increased by 20.66 % during four years.
Equipment index trend
300
250
200
Axis Title
150
100
50
0
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
Month
Equipment Index Linear (Equipment Index) Linear (Equipment Index)
A B C D
0.30 to 0.20 to
0.15 0.15 to 0.25 0.40 0.30
By application of FIDIC formula the price adjustment has increased by 8.9% up to last IPC, Small works
formula has shown increment up to 25.4%. PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has
shown increment up to 16.1%, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown
increment up to 13.4%, PPMO formula using coefficients Lmax, Mmin, Emax (Pp3) has shown increment up
to 15.5%.
Comparison of Price Adjustment factor using different
1.3 formulas
1.25 1.254
Price adjustment factor
1.2
1.161
1.15 1.155
1.134
1.1
1.089
1.05
0.95
06‐May‐13
10‐May‐16
22‐Nov‐13
06‐Apr‐15
26‐Nov‐16
18‐Oct‐12
23‐Oct‐15
02‐Mar‐14
06‐Mar‐17
14‐Aug‐13
10‐Jul‐12
26‐Jan‐13
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
18‐Aug‐16
15‐Jul‐15
31‐Jan‐16
14‐Jun‐17
22‐Sep‐17
Fidic formula Small works Formula PPMO formula Pp1
PPMO formula Pp2 PPMO formula Pp3
Fig 7: Comparison of Price adjustment factor using different formulas in Nepalgunj Kohalpur Road
Package-1
From the figure 7, it can be seen that Price adjustment factor has fluctuated more during time in FIDIC formula.
The reason behind this is the fluctuation in cost of fuel and bitumen.
Ln, Cn, Rn, Gn, Fn, Bn are the current cost of unskilled labor, cement, reinforcement, gabion, fuel, and others
index consumer price index) 30 days before each IPC. Lo, Co, Ro, Go, Fo, Bo are the cost of base date. The
value of b, c, d has been chosen with three combinations and calculate the price adjustment factor using PPMO
formula.
Table 5: Comparison of Price adjustment factor of Prestressed RCC Tinau River Bridge
Small
FIDIC works
Formula formula PPMO formula
Date of
IPC Pf Ps Pp1 Pp2 Pp3
Base
value 5-Jul-15 1.0000 1.0000 1.0000 1.0000 1.0000
23-Mar-
IPC 1 16 1.0681 1.0672 1.0449 1.0427 1.0493
IPC 2 29-Jun-16 1.0773 1.0941 1.0497 1.0502 1.0616
30-Sep-
IPC 3 16 1.0908 1.1201 1.0760 1.0679 1.0928
IPC 4 28-Jan-17 1.1092 1.1067 1.1009 1.0987 1.1213
28-Mar-
IPC 5 17 1.1066 1.0941 1.1031 1.1009 1.1230
19-May-
IPC 6 17 1.1400 1.1176 1.1081 1.1050 1.1279
IPC 7 10-Jul-17 1.1395 1.1235 1.1099 1.1059 1.1298
IPC 8 13-Oct-17 1.1545 1.1512 1.1261 1.1245 1.1456
29-Apr-
IPC 9 18 1.2177 1.1453 1.1879 1.1801 1.1995
IPC 10 5-Jul-18 1.2177 1.1453 1.1879 1.1801 1.1995
IPC 11 2-Jan-19 1.2177 1.1453 1.1879 1.1801 1.1995
28-Apr-
IPC 12 19 1.2177 1.1453 1.1879 1.1801 1.1995
By application of FIDIC formula the price adjustment has increased by 21.77% up to last IPC from base value,
Small works formula has shown increment of 14.53% up to last IPC. PPMO formula using coefficients Lmax,
Mmax, Emin (Pp1) has shown increment of 18.79% from base value, PPMO formula using coefficients Lmin,
Mmax, Emax (Pp2) has shown increment of 18.01%, PPMO formula using coefficients Lmax, Mmin, Emax
(Pp3) has shown increment of 19.95%.
Comparison of Price adjustment factor using different
1.2 formulas
1.18 1.1862
1.1781
1.16 1.172
1.1498
1.14
Price adjustment factor
1.12
1.1
1.08
1.06
1.04
1.02
1
0.98
10‐May‐16
15‐May‐19
23‐Oct‐15
27‐Oct‐18
06‐Apr‐15
26‐Nov‐16
10‐Apr‐18
15‐Jul‐15
19‐Jul‐18
27‐Dec‐14
18‐Aug‐16
06‐Mar‐17
04‐Feb‐19
23‐Aug‐19
31‐Jan‐16
14‐Jun‐17
22‐Sep‐17
31‐Dec‐17
Date of IPC
Small works formula PPMO formula Poriginal PPMO formula Pp1
PPMO formula Pp2 PPMO formula Pp3
Fig.8: Comparison of Price adjustment factor in Midhill Highway Project Gauri Khola Bridge along Sisapur
Bhawanipur Road in Rupandehi District
Original formula “Poriginal” has been calculated using coefficients b=0.25, c=0.30, d=0.30 which is
combination of (Lmax, Mmin, Emax). These coefficients have been proposed by contractor of this project.
PPMO formula has been compared using different combinations.
Anjay Kumar Mishra, et al. (2020); www.srinivaspublication.com PAGE 243
PAGE n
International Journal of Case Studies in Business, IT, and Education SRINIVAS
(IJCSBE), ISSN: 2581-6942, Vol. 4, No. 2, November 2020 PUBLICATION
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax, Emin)
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
PPMO formula has been compared with small works formula.
Table 6: Comparison of Price adjustment factor in Construction of Bridge over Gauri Khola
Small
works PPMO formula
formula
Date of IPC Ps Poriginal Pp1 Pp2
Base value 12-Mar-17 1.0000 1.0000 1.0000 1.0000
IPC 1 8-May-18 1.0537 1.0835 1.0939 1.0892
IPC 2 30-Jun-18 1.0597 1.0941 1.1077 1.1032
IPC 3 1-Jan-19 1.0870 1.1172 1.1270 1.1206
IPC 4 19-Apr-19 1.0938 1.1219 1.1307 1.1221
IPC 5 24-May-19 1.1051 1.1272 1.1371 1.1283
IPC 6 5-Jul-19 1.1157 1.1272 1.1371 1.1283
By the PPMO formula using original coefficients (Lmax, Mmin, Emax) the increment of price adjustment
factors up to last IPC is 12.72%. PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has shown
increment of 13.71% from base value, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown
increment of 12.83%. By using Small Works formula, the increment of price adjustment factors up to Last IPC
is 11.57%.
Original formula “Poriginal” has been calculated using coefficients b=0.20, c=0.40, d=0.25. These coefficients
were proposed by contractor of this project. PPMO formula has been compared using different combinations.
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax, Emin)
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(iii) Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
PPMO formula has been compared with small works formula.
5.16 Inguriya River Bridge along Sainamaina-11 Palpa Laugha Pani Road in Rupandehi District:
Base Date: 12-March-2017
Original formula used is PPMO formula. PPMO formula is taken as Pp=a+b*(Ln/Lo) +c*(Mn/Mo)
+d*(En/Eo) where Ln, Mn, En are the NRB index of labor, material and equipment respectively taken 30 days
before IPC date and Lo, Mo, Eo are the base index of Labor, Material and Equipment respectively. Apart from
this, the coefficient of b, c and d are not known in this study. The limits have been set by the project for the
value of b, c and d as
A B C d
0.30 to 0.20 to
0.15 0.15 to 0.25 0.40 0.30
Original formula “Poriginal” was calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax, Emin)
These coefficients are proposed by contractor of this project. PPMO formula was compared using different
combinations.
(i) Pp1 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(ii) Pp2 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
PPMO formula has been compared with small works formula.
Table 8: Comparison of Price adjustment factor in Construction of Bridge over Inguriya River
Small
works PPMO formula
Formula
Date of IPC Ps Poriginal Pp1 Pp2
Base value 12-Mar-17 1.0000 1.0000 1.0000 1.0000
IPC 1 18-Dec-17 1.0507 1.0332 1.0359 1.0349
IPC 2 11-May-18 1.0567 1.0970 1.0973 1.0906
IPC 3 11-Jul-18 1.0537 1.0939 1.0892 1.0835
IPC 4 17-Jan-19 1.0597 1.1270 1.1206 1.1172
IPC 5 18-Mar-19 1.0870 1.1331 1.1243 1.1233
IPC 6 13-Jul-19 1.0885 1.1371 1.1283 1.1272
By the PPMO formula using original coefficients Lmax, Mmax, Emin the increment of price adjustment
factorup to last IPC is 13.71%. PPMO formula using coefficients Lmin, Mmax, Emax (Pp1) has shown
increment of 12.83% from base value, PPMO formula using coefficients Lmax, Mmin, Emax (Pp2) has shown
increment of 12.72%. and using coefficients Lmax, Mmin, Emax (Pp3) has shown increment of 12.23%. By
using Small Works formula, the increment of price adjustment factors up to Last IPC is8.85%.
Comparison of P.A factor using different formulas
1.2500
1.2257
1.2000 1.2166
Price adjustment factor
1.1500 1.1422
1.1000
1.0500
1.0000
0.9500
0.9000
0.8500
0.8000
26‐Nov‐16
22‐Sep‐17
04‐Feb‐19
31‐Jan‐16
18‐Aug‐16
23‐Aug‐19
10‐May‐16
06‐Mar‐17
10‐Apr‐18
14‐Jun‐17
31‐Dec‐17
19‐Jul‐18
27‐Oct‐18
15‐May‐19
01‐Dec‐19
Date of IPC
Small works formula PPMO formula Poriginal
Fig.9: Comparison of Price adjustment factor at Rapti Nadi Bridge, Sisniya Chainpur Khadbari Road Project
Base date: 10-May-2011, Original Formula used is Small Works formula as Ps=Ac+Bc*(Lmc/Lmo). Where
Ac=0.15 and Bc=0.85 Lmc is consolidated consumer price index at current IPC and Lmo is consolidated
consumer price index at base date. From NRB economic bulletin the value of Lmo for the base date and Lmc
for 30 days before IPC date has been taken. Small works formula has been compared with PPMO formula
given by Pp=a+b*(Ln/Lo) +c*(Mn/Mo) +d*(En/Eo).
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 where coefficient of labor is
maximum, material maximum and equipment is minimum. In simpler form combination can be denoted as
Lmax, Mmax, Emin
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
Anjay Kumar Mishra, et al. (2020); www.srinivaspublication.com PAGE 246
PAGE n
International Journal of Case Studies in Business, IT, and Education SRINIVAS
(IJCSBE), ISSN: 2581-6942, Vol. 4, No. 2, November 2020 PUBLICATION
(iii) Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
By using Small Works formula, the increment of price adjustment factors up to Last IPC is 31.85%. By the
PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has shown increment of 25% from base value,
PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown increment of 19.8%, PPMO formula
using coefficients Lmax, Mmin, Emax (Pp3) has shown increment of 23.9%.
From the table 9, It is seen that the contracts whose base date is before 2015, The price adjustment factor
calculated by FIDIC formula is lowest, followed by PPMO formulas and Price adjustment factor obtained by
small works formula is highest. And in the contracts whose base date is after 2015, the price adjustment factor
calculated by FIDIC formula is highest, followed by PPMO formulas and Price adjustment factor obtained by
small works formula is lowest. Thus, it cannot actually be defined which formula gives more value of price
adjustment factor. It depends upon the condition such as time, index and cost.
In PPMO formula if the coefficients are set by the client, the price adjustment factor using coefficients of labor
“Lmax’’is more likely to give higher value of Price Adjustment factor than using “Lmin’’.
6. CONCLUSION:
There are different formulas used in different contracts. In contracts using FIDIC formula, the cost of labor is
increasing with respect to time and it is more predictable that labor cost will increase in future. The cost of
bitumen and fuel are unpredictable as the cost is fluctuating more with respect to time. In contracts using
PPMO formula the index of Labor, Material and Equipment is used. The index of labor increase with time and
it is more predictable than Material and Equipment index as they are fluctuating with respect to time.
Comparing the price adjustment factor using different formulas it can be seen that the value of price adjustment
factor using different formulas are different. Also, it can be seen that during the course of time the price
adjustment factor calculated using different formulas is different. Thus, it cannot be generalized that which
formula could give minimum value of price adjustment. It depends upon the condition such as time, index and
cost. As most of the respondents in our study preferred to use PPMO formula so it is suggested to use PPMO
formula in the construction contracts. In PPMO formula under the limits set by the client, if the coefficient of
labor is chosen maximum it is likely that the price adjustment factor would be more.
REFERENCES:
[1] Riggs, J., (2006). Material price escalation. Construction briefing.
[2] McCartney, M., (2011). Pakistan Growth, Dependency and crisis. The Lahore Journal of Economics, 16(1),
71-94.
[3] Mishra, A. & Regmi, U., (2017). Effects of Price Fluctuation on the Financial Capacity of "Class A"
Contractors. International Journal of Creative Research Thoughts (IJCRT), 5(4), 1920-1938.
[4] ADB, (2018). Price Adjustment Guidance Note on procurement, s.l.: ADB.