13044-QSH-PP-023 Testing Precommissioning Rev.55

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

□ E NYS

Method Statement
13044-QSH-PP-023

Testing & Precommissioning

DENYS ENGINEERS E CONTRACTOf· t> l3V


Avenida 25 de Seternbro
IVl I\ 1- U V ...
I UIJ;-10071 0885
.... �•po,,.

5 20/09/2017 Test sections TJ and filling point are changed BVLI � RALD

4 14/07/2017 Details of cock valves, equipment and filh"ng are added BVLI DDS/'1 RALD

3 24/05/2017 Revision of test pressures and test set up BVLI DDS/'1 RALD

2 26/01/2017 Alternative structure for PS1 and VVTP to fill the pipe BVLI DDS/'1 DDS/'1

1 12/12/2016 Changed Test pressures - added information about counter pressure BVL/ DDS/'1 DDS/'1

0 01/09/2016 First issue BVL/ DDS/'1

Rev. Date Description Prepared Checked Approval PM

STATUS (Concept/Final/Deleted):

Distribution:
□ENVS
Project 13044 - FIPAG - Maputo

Reference 13044-QSH-PP-023
Testing & Precommissioning Revision ROS

The Contractor is responsible for providing all material and equipment required fo,- pipeline pressure
tests, including pumping equipment and its set-up.

5. Test Sections and Test Pressure

5.1. Test Sections and Test Pressure of main pipeline


The test pressures are determined from the d1·awings 40089-FD-PPL-A-001 to A-004. The test
pressure is calculated as the System Test Pressure elevation subtracted by the lowest point in the test
section. The test pressures are presented in Table 1.
The test sections are determined using the section valves present in the pipeline. These sections are
visualized in the following drawings, which can be found in the appendix:
13044-ENG-TES-T1&T2 rev. 1
13044-ENG-TES-TJ-part 1 rev. 2
13044-ENG-TES-T3-part 2 rev. 2
13044-ENG-TES-T4&MACHAVA-part 1 rev. 2
13044-ENG-TES-T4&MACHAVA-part 2 rev. 2

T.able 1 0 verv,ewo rr,es tsecrtons, w,·th th e tes·t pressures and Iengths.


Test sections Tl
Section From To DP {bar) TP {bar) L (mtr)
1 Chamber A Chamber D 4,3 6,3 192
2 Chamber D Blind Flange (KP 0.28) 4,3 7,2 258

Test sections T2
Section From To DP (bar) TP {bar) L (mtr)
1 Blind Flange (KP 0) SV 2.1 (KP 7.01) 5,8 9,4 7011
2 SV 2.1 (KP 7.01) Blind Flange (KP 10.93) 4,2 7,6 3828

Test sections T3
Section From To DP (bar) TP (bar) L (mtr)
1 Blind Flange (l<P 0) SV 3.1 (KP 3.50) 13,2 15 3500
2 SV 3.1 (KP 3.50) SV 3.2 (KP 14.635) 12,8 15,6 11130
3 SV 3.2 (KP 14.635) AV 3.28 (KP 26+386) 8,9 14,2 11751
4 AV 3.28 (KP 26+386) lncomati River (KP 34+329) 7,4 11,1 7943
5 SV3.3 (KP 33+647) SV 3.4 (KP 41+486) 7,4 10 7839
6 SV 3.4 (KP 41+486) SV 3.5 (KP 46+978) 5,2 7,9 5492

4
DENYS
Project 13044 - FIPAG - Maputo

Reference 13044-QSH-PP-023
Testing & Precommissioning Revision ROS

e i I .-. I ·""' I .-i

Missing Construction

c:,. ---·-

l �l�-

Figure 1: Drawing 40089-GEN-A-007 - General Flow diagram with marked items: Green: part 1 of the Contract, Red: part 2
of the Contract, for detail see appendix.

Since at this stage the Contractor of Part 2 has not yet started, the pump station and the water
treatment plant are not ready.

Filling Stretch T2
At the pumping station area, a basin will be used as a buffer for the pump. A container will be placed
in the grnund and directly connected to the valve on the reduction fiange at the end of T1. A 1 O"
pump will be used to pump the water to Stretch T2, see Figure 2. Ductile iron pipe or HDPE pipe
will be used to connect the outlet of the pump to the start of Stretch T2.

6
Project 13044- FIPAG - Maputo
DENYS Reference 13044-QSH-PP-023
Testing & Precommissioning Revision ROS

6. Process

6.1. Starting situation


Due to the danger of an open trench, testing and commissioning will be done with having the pipe
backfilled, but if possible, the flange connections near the chambers will not be backfilled.

6.2. General testing procedure


The tests will be done following the steps as shown in Figure 7.

Select length to be tested

Test preparation

Repair the
Pipe lilling
main

YES

Empty the Purge the air


main

Pressurize

find the
fault(s)
NEGATIVE

Check all the external bolts

Put into service

Figure 7: Scheme of testing procedure