A Bansod Maintenance Manual For Kwu Turbine
A Bansod Maintenance Manual For Kwu Turbine
A Bansod Maintenance Manual For Kwu Turbine
1
14) Wooden blank flanges to fit inside the opening of the pipes, cylinders or
pedestals must be put and tied in position to prevent ingress of any foreign
material.
15) Stands for keeping the HP, IP and LP rotors must be available and checked
before using the same.
16) Care should be taken to avoid oil spillage on the floor or area around the
equipment.
17) Firefighting equipment and first aid boxes should be available near the
work site.
18) Temporary office along with telephone facilities on job site should be
installed to avoid delays in communication.
19) A cleaning gang should continuously work to keep TG floor area free to
dust, dirt, rags, paper etc.
2
CHAPTER I - OPERATING
PARAMETERS OF 210/250/500
MW KWU TURBINE
3
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
5. MS flow TPH
6. CRH steam pressure Kg/cm2
7. CRH steam temperature C
0
4
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
2. IV Ti/Tm C
0
5. HP Shaft Ti/Tm C
0
6. IP Shaft Ti/Tm C
0
5
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
1. Hotwell temperature 0
C
6
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
7
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
TL TR BL BR
Bearing no. 1 0
C
Bearing no. 2 0
C
Thrust bearing 0
C
Bottom Front Bottom Rear
Bearing no. 3 0
C
Bearing no. 4 0
C
Bearing no. 5 0
C
Bearing no. 6 0
C
Bearing no. 7 0
C
8
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
9
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
HPCV 1 / 2 position %
IPCV 1 / 2 position %
10
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
Rotor temperature 0C
Generator Current 0C
Generator Voltage KV
Hydrogen purity %
11
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
12
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
Bearing No. 6
1) Foundation Bolts – 95 mm hammering Spanner.
2) Pedestal Parting Plane – 75 mm Hammering Spanner.
13
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
LP Casing
1) LP Outer Casing P/P Bolts -65 & 36 mm Hammering Spanner.
2) LPT Exhaust Diaphragm 24/26 Ring Spanner.
3) LP Sole Plane to Foundation – 85 mm Hammering Spanner.
4) IP Inner Casing P/P bolts -41 mm Hammering Spanner.
5) LP Casing Inner Outer Jack Bolts (For Roll Check) – 41 mm Hammering Spanner.
6) LP Outer Cover Jack Bolts M-36-41 mm Hammering Spanner.
IP Casing
1) IP Outer Casing Cap Nut -75, 85 and 95 mm Hammering Spanner.
2) IP Inner Casing Cap Nut -105 and 120 mm.
3) IP Casing Jack Bolts (for Roll Check ) M64- 50 MM Hammering spanner.
4) IP Inner Casing Jack Bolts (For Roll check) M-36 – 50 MM.
HP Casing`
1) HP Casing gland box (R) – 41 mm Hammering spanner.
2) HP Casing gland box (L) – 27 mm Ring Spanner.
3) HP Exhaust Elbow Flange – 65 mm Hammering Spanner.
4) HP Inner Casing P/P – 75 mm Hammering spanner.
5) HP Casing insert – 50 mm Hammering spanner.
6) HP Casing Jack Bolts (For Roll Check) M -64 – 56 mm
7) HP Inner Casing P/P Jack bolts M-36 – 41 mm Hammering Spanner.
8) HP/IP Coupling – 65 mm Box Spanner.
9) LP/IP Coupling – 70 mm.
10) LP / GEN – 55 mm.
11) Pedestal No. 1 Jack Bolts M-50 – 65 mm Hammering Spanner.
12) Pedestal No. 2 jack Bolts M- 65 – 55 MM.
13) Coupling jack bolts 50 & 46 mm.
14) Jacking Oil line – 36 / 32 , 41 mm – Single Head.
14
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
15
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
1) Oxygen Cylinders.
2) Acetylene.
3) Sleeper 25 x 250 x 2000.
4) Kerosene/Diesel.
5) Cotton waste.
6) Gland Packing ( Graphs, asbestos, Metalic)
7) Emery Paper 200 x 300 mm (36, 60 and 80, 100, 120, 180).
8) Hacksaw Blades (Size ½” and 1”)
9) Holdite
10) Rubber gasket (3 mm, 5mm )
11) Rustoline.
12) Oil sealent
13) Wooden Planks.
14) Diamond Lapping Paste (Medium).
15) Oil Paper (0.5 mm)
16) Prussian Blue.
16
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
17
OPERATING PARAMETERS OF 210/250/500 MW KWU TURBINE
1. Incharge 1 76 days
2. Engineer 1 76 days
3. Supervisors 3 76 days
18
CHAPTER II - SCOPE OF WORK
IN ANNUAL AND CAPITAL
OVERHAUL
19
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
20
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
22. Barring gear nozzle inspection, repair / replacement of fins and resetting as per requirement.
23. Box up of all bearings and pedestals. Cleaning of rack filters and basket strainers during oil flushing as per
requirement. During Oil flushing will be as per quality of the oil in the circuit.
24. Assistance during commissioning.
25. Checking, adjustment and minor repair of all MS & HRH lines, CRH lines hangers.
26. Fitting of turbine cladding removed for O/H.
21
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
22. Placement of top half on bottom half and checking of parting plane gap and ovality before and after
heat tightening the studs.
23. Checking of inner casing centering w.r.t. barrel with dummy shaft and finalizing radial key sizes.
24. Place HPT Rotor over the inverted upper half casing and record all axial and radial clearance.
25. Fixing of sealing segments and placement of HPT Rotor.
26. Recording flow path reading and assembly with upper half inner casing. Repeat with bottom half.
27. Heat tightening of inner casing parting plane studs.
28. Roll check and bump check of HP Rotor with inner casing and centering.
29. Locking of inner casing with rotor.
30. Insertion of HP Rotor with inner casing into barrel.
31. Fitting of casing keys, threaded ring or lock ring as applicable.
32. Making HPT Module Horizontal.
33. Fixing of gland box and seal segments, recording roll check and bump check at every stage.
34. Lifting of HPT Module land placement on TG Pedestal & subsequent loading to bearings.
35. HPT Roll check and Bump check.
36. HPT horn drop checking and correction.
37. HPT inlet breech nuts & exhaust elbows connection along with associated pipe lines.
1. Removal of complete insulation of IP Turbine and dismantling of associated and required piping. Checking
of axial and radial clearances in the assembled condition after noting down the control dimensions.
2. Removal of gland box seals on both sides, checking of axial and radial clearances and repair/replacement
of any components of gland boxes, as per requirement. Loosening of outer casing parting plane bolts and
removal of the top half casing. For this Induction heating machine shall be arranged by BHEL. However,
the subcontractor shall provide
3. All assistance from loading/unloading of the equipment, opening of casings and closing, etc.
4. All manpower required for the same including rigging gangs and helpers and T&P shall be provided by the
subcontractor.
5. Rolling test and float test of IP rotor with respect to inner casing after centering the casing.
6. Loosening of inner casing parting plane bolts and removal of top half of casing. For this, Induction heating
machine shall be arranged by BHEL. However, the subcontractor shall provide all assistance from
loading/unloading of the equipment, opening of casings and closing, etc.
7. All manpower required for the same including rigging gangs and helpers and T&P shall be provided by the
subcontractor.
22
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
8. Measurement of flow path clearances, and necessary replacement/repair of fins of rotor and casing as per
requirement.
9. Measurements of parting plane stud lengths, testing and replacement as per requirement.
10. Removal of Rotor.
11. Facial run out checks on HP coupling half, IP coupling halves and LP coupling halves and necessary
scraping / matching to the extent possible as required.
12. Casing parting plane ovality check and necessary correction on casing parting plane for minimum contact
of 10 mm from the stud hole.
13. Removal of inner bottom casing if required.
14. Cleaning by alumina /sand blasting of inner casing and Rotor, inspection of seal strips of the inner casings
and repair / replacement of fins, as per requirement.
15. Placement of top half of inner casing / outer casing (without rotor ) on bottom half for checking ovality of
casing after tightening of the parting plane studs. Ensure that L-Rings are made free.
16. Removal of casing top half after checking the ovality of the casing.
17. Placement of rotor in the ZERO position in the inner casing and necessary grinding/machining of casing
and rotor fins etc. and adjustment in keys, packers etc. as per requirement during checking of axial /radial
clearances of blades/fins.
18. Final box up of inner casing after thorough cleaning, checking for minimum axial and radial clearances by
rolling checks, bump check, horn drop check of inner casing and necessary rectification as per
requirement.
19. Checking for axial and radial clearances of seal strips of sealing segments of the outer casing (both top and
bottom half) and necessary adjustment/grinding as per requirement.
20. Placing of top half of IP outer casing on the bottom half after cleaning and boxing up of the outer casing.
21. Checking of the axial / radial clearances of seal strips and boxing up of gland boxes after necessary
grinding etc. as per requirement.
22. Final checking of axial / radial clearances in the assembled condition and necessary rectification as per
requirement.
23. Final connection of associated piping etc.
24. Assistance for removal and replacement of IPT thermocouples and putting new ones as per instruction
and requirement of C&I.
23
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
24
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
HP STOP & CONTROL VALVES, IP STOP & CONTROL VALVES ,LP BYPASS STOP & CONTROL VALVES, LP BYPASS
WATER INJECTION VALVES:
1. Before dismantling of the stop and control valve governing characteristics of stop/control valves should
be taken and any discrepancy on the valve side should be attended during overhaul.
2. Erect scaffolding at valves as required and remove insulation.
3. Removal of measuring instruments. Take reference dimensions.
4. Drain actuator housing. Remove oil lines and steam leak off line.
5. Heat and remove valve body cover bolts.
6. Disassemble valve completely.
7. Open coupling between valve and servomotor.
a. Detach actuator housing from valve body cover.
b. Dismantling of servomotor internals and cleaning of all internals.
c. Carry out DPT as per requirement.
d. Disassemble actuator and valve completely.
8. Complete revision of the servomotor, replacement/repair of components, as required.
9. Determine condition of valve and decide on maintenance work to be attended. Carry out DP Test of valve
internals (body, seat, disc., spindle etc.) as per requirement.
10. Clean and de-scale component parts.
11. Inspect valve stem and pilot disc. Check stem for run out. Carry out DP test of valve internals (body, seat,
disc, spindle etc.) as per requirement. Inspect sealing faces at the valve seat and disc. Lap up if necessary.
12. Check clearances and install the actuator and valve body.
13. Inspect pistons springs, discs and sealing faces.
14. Reseal and assemble actuator.
15. Attach actuator and valve body cover to valve body and heat bolts. Connect up stem.
16. Associate with BHEL/CUSTOMER during installation of measuring instruments and indicators of the valves.
Start oil pumps and check valves for leak and proper functioning. Attend the defects.
17. After completion of the job governing characteristics should be set as per standard values in association
with BHEL/CUSTOMER.
18. Do hot tightening of valve flanges, glands and bonnets at part load and full load of machine.
25
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
26
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
2.8 - OH OF GENERATOR
27
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
18. Inspection of stator and slot wedge, checking for tighten sand tightening of loose wedges by dewedging
and re-wedging by using suitable packers below the wedges, tightness mapping chart to be prepared
before and after carrying out actual wedge tightening work. Checking of looseness of braiding in overhang
portion.
19. Replacement of winding RTD’s as required.
20. Hydraulic testing of stator winding as per BHEL protocol and attending any leakages thereby in Teflon
tubes or copper pipes. In case of it requires removal of putty boxes, re-assembly of the boxes to be done.
21. Pneumatic testing of stator winding as per BHEL protocol.
22. Draining of stator water from the windings.
23. Assistance in Carrying out ELCID Test on the stator core & RSO test on rotor.
24. Measurement of PI value of stator and bringing it to a value more than 2 by Hot air blowing, as required.
25. Assistance in Tan Delta and Partial discharge test on the Generator to be carried out.
26. Carrying out Rotor Purge Test. Die Penetration test and UT of Rotor retaining rings after removal of Paint
in the retaining rings.
27. Die Penetration test of the Fan blades after removal of paint. DPT and UT of seal rings.
28. Conducting DP and Ultrasonic test of Bearing no. 5 and 6.
29. Heating the stator suitably, glue injector in the winding overhang portions as required.
30. Varnishing of stator winding after completion of work and drying out of varnish.
31. Blue matching of Bearing no.6 pedestal with foundation.
32. Blue matching of Bearing no.6 with pedestal and then with shaft journal.
33. Pedestal insulation checking and rectification if found less. Adjustment of oil catcher and deflector plate
as per BHEL protocol and replacement of fins of oil catcher as required. Cleaning of all lub oil and seal oil
pipe lines and seal body. DP test to be done on all welding joints of pipe lines. Air tightness test of Rotor
as per BHEL Protocol and if leakage is there rectification of the same by opening CC Bolts.
34. Taking rotor IR value and rectification of the same if found less. Replacement of CC bolt to be done as
required. Insertion of TG rotor inside stator.
35. Assembly of end shields and fan shields.
36. Assembly of seal rings, seal cover and seal body.
37. Assembly of bearing no.6 and its pedestal.
38. Assembly of seal oil and Lub oil lines at both ends after slope checking.
39. Alignment of LP-Generator and coupling of LP-Gen.
40. Assisting in assembly of Brush Gear and alignment of Brush Gear as per BHEL Protocol. Brush holder
adjustment.
41. Assisting in Brush Gear cable termination.
42. Assembly of Gas coolers.
43. Disconnection of Phase and neutral links from GT.
28
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
29
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
16. Inspection & Replacement of all Terminal bushings along with gaskets. (6 Nos.)
17. UT check of Generator seal rings and replacement as required.
18. Dismantling/cleaning of H2 coolers ,exciter coolers, Hydraulic Test & attending leakage by plugging of
tubes
19. Glue injection and varnishing of stator wdg.
20. Varnishing of Gen. Rotor
21. Insertion of Generator Rotor and Boxing up of Generator.
22. Air tightness test of Generator casing at 4 kg/cm2 for 24 hrs.
23. Color matching of Generator bearing.
24. Replacement of oil catcher fins as necessary.
25. Replacement of any of defective components of Generator & Exciter and varnishing of same.
26. Checking of the Generator stator palms for any feeler gap.
27. Matching of exciter pedestal with the exciter base frame and revisioning of exciter bearing including
replacement as required. Re-matching of Exciter anchor plate and tightening of anchor bolts to required
elongation.
28. Revisioning of PMG Assembly, Varnishing and assembly
29. Assistance during the N.F.T of Generator end winding. & checking of terminal nose joint
30. Removal of Exciter dome, Stator top half & removal of rotor & complete overhauling
31. Revisioning of Exciter/PMG Assy. Assistance during testing, cleaning & varnishing
32. Swing check of exciter and necessary correction
30
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
2.9 - ASSISTANCE DURING MPI & NFT OF LPT ROTOR FREE STANDING
BLADES 2X2 STAGES (OPTIONAL WORK)
1. Cutting of welding of locking plates of both sides of LPT Rotor free standing blades.
2. Removal of locking plates of both sides of blades.
3. Removal of all clamping pieces.
4. Removal of blades with proper marking.
5. Thorough cleaning of blades and their grooves in the rotor by suitable means so as to remove corrosion
products, if any.
6. Inspection of blades roots and their grooves in the rotor.
7. Crack detection of all blades by MPI (Coil method) -100%
8. Fitting of all blades (cleared by MPI) in the position with technological pieces.
9. Fitting of technological pieces in place of clamping pieces.
10. Measurement & recording of Natural Frequency of blades.
11. Removal of technological pieces.
12. Replacement of technological pieces by new clamping pieces.
13. Fitting of locking pieces in position.
14. Welding of locking plates as per drawing.
NOTE: If any defect is observed in blades then it is to be replaced by new one. If the natural frequency of any of the
blades is found to be beyond permissible range & it cannot be improved upon even after proper cleaning of the
blade root & its groove in the rotor, then the blade has to be replaced by new one.
31
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
GENERATOR STATOR :
1. IR & PI Test with 5 KV megger.
2. DC winding resistance measurement.
3. Tan Delta/Power Factor/Capacitance test.
4. Computerized Digital ELCID test.
5. Partial Discharge probe test OR Offline PD Analysis.
6. DC leakage current/Step Voltage test.
7. Stator Slot wedge system check (wedge tightness mapping)
i) By Wedge deflection test if ripple springs are installed)
ii) By wedge knocking test.
8. RTD elements check.
9. IR with 1000V DC source and amp. Meter
GENERATOR ROTOR :
1. IR & PI
2. Digital RSO Test
3. AC Impedance measurement.
4. DC winding resistance measurement.
5. Diode wheel check.
6. Voltage balance test.
EXCITER :
1. IR & PI
2. DC winding resistance measurement.
3. Pole impedance test
4. Pole drop test.
GENERATOR :
1. NFT of Generator End Winding.
32
SCOPE OF WORK IN ANNUAL AND CAPITAL OVERHAUL
TURBINE :
1. Natural frequency test on LP turbine rotor free standing blades of 120/200/210 & 250 MW sets.
2. Natural frequency test on LP turbine rotor free standing blades of 500 MW sets.
3. MPI of LP rotor blade roots, rotor grooves, rotor discs, rotor shaft etc.
33
CHAPTER III - SYSTEMATIC
PROCEDURE OF TURBINE
OVERHAULING
34
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
PROCEDURE :
1) Before overhauling of turbine record all turbovisory parameters for reference.
2) Before stopping barring gear at HPC 350° temp., start removal of insulation from HP/IP module &
complete it till stopping of barring gear.
3) Note down governing & LPBP characteristics from rack with the help of starting and load limiting device.
4) Stop barring gear, stop AOP & JOP.
5) Start opening of all pedestals parting plane bolts.
6) Record seal bore readings at each pedestal, record yoke key clearances & removal yokes.
7) Record all reference readings of rotor with respect to pedestal, remove top half of bearings and note
down side oil, top oil clearances of all bearings.
8) Note down coupled run out of rotor at each journal & couplings with the help of dial gauge by mounting
dial on pedestal and pointer on journal and coupling.
9) Decouple LP / Generator coupling as per procedure & separate Generator from Turbine.
10) Carry out roll check, Bump Check, Horn drop check of casings as per set procedure & note down
readings for future correction.
11) Decouple HP/IP, IP/LP coupling as per procedure.
12) Open HP, IP, LP casing.
13) Measure the float of rotor with pads assembled in thrust bearing.
14) Before dismantling of bearings check bearing oil catcher clearances.
15) Ensure JOP operation from local, as it is required frequently for number of checks of turbine. If JOP is
not available ensure sufficient stock of thick oil for lubrication of rotor & pins required for rotor rotation
at all couplings.
35
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
3) Immediately after cutting the pipelines close the open part of it with gaskets /wooden flange or polythene
sheet. This should not be neglected, as there is possibility that some body may put some foreign material
inside it & which will finally damage the turbine complete.
4) Before cutting of dismantling pipelines, these are to be locked with beam to avoid abnormal loading on
hangers. The locking is must for HP inlet & exhaust pipes.
1) Before decoupling put JOP in service, unscrew all 16 Nos. of HP/IP coupling bolts. Take out four no of
opposite coupling bolts & replace it with loose (clearance) coupling bolts. One by one take out all bolts,
the bolts should come out with little tapping of copper bar.
2) The nuts and bolts should be stored carefully, protect it from damage on threads.
3) Put IP front rotor lifting device in position, load the device remove the loose coupling bolts.
4) Put guide pins in coupling holes to hold IP rotor in position to avoid sudden unloading of rotor from spigot.
5) HP Rotor is jacked towards front & removed from spigot.
6) Rotor is axially positioned on the basis of available reference reading of rotor thrust collar to casing spigot.
7) After positioning, rotor is locked axially with the help of axial lock.
8) Now once the rotor is lock axially, there are two alternatives to lock rotor radially. One is to support rotor
on HP front & rear rotor lifting device and another is to put radial lock plates in position before removal of
bottom bearings.
36
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1) Before breach nut opening check the heating device for any sort of chocking of nozzles. This can be
removed with induction heater.
2) Check whether the gas regulators & gas supply pipes are in good working condition.
3) Make arrangement of two LPG cylinders per nut.
4) Assemble the device on Breach nut, with the help of jackscrew maintain equal gap between nozzle &
breach nut body face. Industrial gas torch can be used for heating if nozzle arrangement is not available.
5) Light up gas & slowly increase gas pressure with regulator. The pressure of both cylinders should be
increased equally so that uniform heating is obtained all over the face of nut.
6) Heat the nut up the temperature of 2000 C the required temperature can be checked by thermal chalk or
leaser thermometer. After attaining the temp close the gas supply & removal the device.
7) Put the nut rotating pin inside the hole provided on nut & rotate the nut in anti clockwise direction by
taking load on crane with the help of sling. Rotate the nut till it become free for manual rotation.
8) Take out nut & support it on wooden slippers, remove U-Seal ring & properly protect it from damage.
9) Removal of HP exhaust elbows where there are two exhaust pipes. In case of single exhaust HP turbine,
open exhaust flange provided at bottom of the casing.
1) Before lifting the module ensure that all four pedestal clamps of HP casing are removed.
2) Check the availability of sling 2 Nos. 12 Mtr. x 60 mm.
3) Take out all radials & axial keys of casing, check that pipes below & above casing are cut & removed.
4) Lift the casing with the help of main hoist & check the level (by putting sprit level on journal).
5) Make the level of casing, lift it & place it on stands assembled in unloading bay.
37
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
3) After putting these locks in position the front shaft lifting device can be removed. Now it is easy to
remove casing gland box covers. The gland box covers should be removed carefully without damaging
sealing segments & rotary seals. With the help supplied fixture.
4) Couple the casing turning device to rotor at rear end with Allen bolts M-30.
5) Assembly another support stand on base frame at casing rear end to support the rotor lifting device
assemble on casing turning device.
6) Temporarily shift the load of rotor on crane shift the rotor lifting device on coupled casing turning device
& remove rear- casing top & bottom gland box cover. After removal of rear gland box cover a radial lock
ring is put in position. Before putting this ring, rotor is centered axially as per reference readings.
7) After fixing radial lock ring in position, final axial lock- ring is fitted on this ring & rear shaft lifting device is
removed.
1) For removal of these seals, manufacturer supplies a special fixture. The stationary bush is assembled on
journal no I & the rotary bush type turning fixture are assembled on stationary bush. There should be
sufficient clearance between stationary & rotary bush so that easy turning of rotary bush is possible.(not
applicable where gland bush complete is provided.)
2) Check tie rods for its threading, counter check with threading of seal segments. The threaded end is fitted
in segments & another end is locked in rotary bush.
3) Before removal of sealing segments, remove segment window cover. Put sufficient antirust liquid in seals
for easy removal.
4) Assemble the fixture & take out the seal segment by rotating rotary bush on fix / stationary bush with tie
rods. Move the segment in such a way that the compression spring comes in window, remove the spring
with special tool provided by manufacturer. Similarly remove all springs & finally take out the segment.
Repeat the same procedure for all three rows of sealing segments, (6 segments per row).
1) Before making module vertical ensure that outer casing supports are assembled properly in their
respective position to support outer casing on four places at front end.
2) With the help of main hoist and special D- shackle provided by manufacturer, make the casing vertical on
stand at its front end, lift it shift it to outer casing support stand.
3) Tight casing on stand with bolts size M-36 X 50.
38
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1) Remove threaded ring locks when the casing was horizontal on stand.
2) Assemble the beams 2 Nos. on casing rear top with the help of special long bolts (12 Nos) for pressing
inner casing down so that compression of U-seal is released & thread ring /sealing segments can be taken
out easily by rotating in anticlockwise direction.
3) Put two no hydraulic jack below the beam & press inner casing against outer cases about 0.1 to 0.3 mm.
4) Put the striker pieces in the slots provided on threaded ring, hammer the striker pieces at a time with two
persons in position till the ring is free to rotate in threads. Remove the beams & with the help of crane
rotate the threaded ring, lift it & place it on wooden slipper.
5) The next step is to remove radial keys provided for locking of inner to outer casing ( 8 from rear & 4 from
front). Before removing front keys remove lock plates & grub screws. The keys can be removed with the
help of puller and knocking ring arrangement.
6) Assemble the rotor guide bush on outer casing at front end to guide rotor while removing inner casing
from outer casing.
7) Before lifting inner casing change the fixture layout of base plat & put inner casing support stand &
journal support stand in position.
1) Put two no of hydraulic jack below inner casing inside outer casing jack inner casing against outer casing
equally to release inner casing from I. seal ring. Mount dial gauge at top pointer on inner casing & base on
outer casting. Note the upward displacement of casing. Take load on crane & continue jacking till the
inner casing is free from I seal ring.
2) Lift the inner casing, take out from outer casing, and Put the pin (100 mm dia, 500 mm long) inside the
dummy assembled to the rear end. There is sufficient clearance in between pin & bush of assembled
dummy at rear end.
3) Rest the pin on stand & slowly make the casing horizontal, assemble the roller stand below journal No. 1,
2 & finally remove all radial, axial locks of casing & rotor.
4) Leveled the casing with the help of spirit level, center the rotor with respect to casing or casing with
respect to rotor by checking front exhaust side radial gap between rotor blades and casing.
5) After centering carry out roll check of inner casing. The rotor can be moved left / right, top / bottom with
the help of roller stand. Take all readings & start dismantling P/P bolts with the help of heating device or
induction heater provided by manufacturer.
39
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
6) Remove the top half of the casing, inspect rotor & casing for any damage, measure the flow path
clearance with the help of filler gauge & outside micrometer. Measure the axial gap between rotary &
stationary sealing strips with the help of taper wedge.
7) If necessary measure rotor inter stage run out (if high vibrations are reported), for the measurement of
run out special dial gauge with spoke is used.
8) Lifting rotor & placing it on stand. The rotor is lifted with the help of rotor lifting beam, which has facility
to level the rotor in horizontal plane.
9) Clean the casing as well as all casing components completely. Assemble the top & bottom half & measure
the P/P(parting plane) gap & casing ovality. If required, remove the high spots of P/P with the help of
parallel block, again assemble the casing by hand tightening & measure the gap. The characteristics of gap
should be like this …that it is open inside & close towards outside from center of casing.
10) Repair of damage sealing segments: Removing damage strips, replacing with new strip & square wire can
be carried out to repair the segments. Replace the seal segment compression springs if necessary.
1) Assemble the seals in top & bottom half of inner casing, (Rear side) place rotor in position with journal
on roller support. Apply jointing compound on parting plane & place top half in position & box up the
casing with hot tightening. Before hot tightening measure the length of each stud for final
measurement of elongation after tightening.
2) The tightening toque is applied as per degree of rotation given in drawing. The same degree is marked
on circumference of the nut, then it is heated to particular temperature & cap nut is turned through as
per the marked distance. This gives correct tightening & required elongation of P/P studs. After cooling
measure the length of each stud to work out elongation. Elongation is nothing but it is difference
between cold stud length before hot tightening & length after hot tightening.
3) Align the rotor with roll & bump check: Assemble the radial & axial locks on casing, make it vertical &
insert it in outer casing. Before insertion check that the outer casing is properly cleaned & dress for
any damage place U – seal ring in position. Assemble threaded ring/sealing segments, make the casing
horizontal & place it on stand.
4) Box up front & rear seals & gland box. Align rotor with roll & bump check, put axial & radial locks in
position.
5) Lift the module & place it in position.
40
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1) Removal of insulation.
2) Before removal of any pipeline carry out Roll check & centering readings of casing.
3) Cutting of extraction pipe lines.
4) Removal of IP inlet pipe: Open both flange joints, if required use heating for opening of bolts. With the
help of auxiliary hoist of EOT crane & chain pulley block, perfectly balance the pipeline, lift the pipe line &
place it horizontally on wooden sleeper, protect insert from damage to its mating face.
5) Removal of seal steam inlet & leak off pipe lines.
6) Before opening P/P bolts of casing load the casing on jack bolts at all Four Corners of casing.
7) Removal of P/P Bolts with the help of heating device supplied with machine by manufacturer or by
induction heater. Number all studs & cap nuts & give same numbers to P/P holes so that the same stud
will go to its original position. Protect stud & cap nut from any damage.
8) Removal of top half of casing: Before removal of top half of casing tension both exhaust pipe lines with
the help of chain pulley block for easy removal of casing. Lift outer casing place it on wooden slipper.
9) Inspect the casing, remove eccentric bush from bottom side & carry out roll check & bump check with
inner casing.
10) Opening of P/P Cap nuts of inner casing with the help of heating device supplied with machine or
induction heater.
11) Removal of top half of inner casing & measurement of flow path readings, radial clearance between
stationary seals & rotor blades, measurement of axial clearance between stationary & rotary seals.
12) Removal of IP rotor : For removal of IP rotor, use rotor lifting device, level the rotor in zero-zero position
(parallel to axis of rotation) lift it slowly, avoid any jerk while lifting the rotor, place it on stand.
13) Inspect rotor & casing both for any damage. Clean rotor & casing both with cleaning agent & smooth
emery paper clean studs cap nut & other components of casing.
If inner casing bottom half is not lifted, then immediately cover the space in between inner &
outer casing with wooden covers, also cover extractions holes with dummies in order to protect entry of
foreign material inside the casing.
14) Replacement of damage sealing segments from stationary seal by new square wire, check the
compression of all springs, replace the spring with new spring if necessary.
15) Box up of casing :
a) Before box up removal all extraction covers & cover placed in between inner & outer casing, check for any
foreign material inside casing. Lift the rotor clean it with air & place it in position slowly, avoid jerk while
placing the rotor in order to avoid damage.
41
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
b) Lift the top half of casing, clean the P/P with cleaning agent, slowly place it in the position, before placing
completely apply jointing compound (Stag.-B) in between parting plane. Place it completely & tighten it
with heat tightening device or induction heater, measure the elongation.
c) Carry out roll & bump check of inner casing, note down readings.
d) Lift outer casing, clean the P/P with cleaning agent, tension the cross around pipe lines with chain pulley,
and place the casing in position, see that the casing should seat easily without application of external
force. Put jointing compound in between P/P of outer casing. Put all four dowel pins in position, all studs
& cap nuts in position. Tighten the casing with heating device.
e) Assemble the inlet pipeline, tighten it properly. Re-weld the extraction pipe lines. Assemble leak off & seal
steam lines, replace joints (Gaskets) of all these lines including cross around lines. Remove the locks of
bellow of cross around pipelines & tighten the joints.
f) Measure the elongation of all studs, carry out roll & bump check of complete IP casing. Take the centering
reading and prepare the final radial & axial keys.
1) Removal of LP top cover & putting checker plates on opened part of condenser.
2) Carry out roll check of complete casing.
3) Lift top half of LP inner outer, inner-inner casing & gland box. Before lifting inner outer casting open the
inspection windows & take out locks & eccentric bush.
4) Check flow path clearances with feeler gauge & outside micrometer.
5) Put LP rotor Compensator support fixture in position or both ends LP front & rear, as these are lifted with rotor.
6) Lift the rotor with rotor lifting device & place it on stand.
7) Inspect the casing internally, check rotor for any damage or serious erosion. Clean the casing & rotor
mechanically with emery paper.
8) If necessary carry out fins cutting & grinding wherever clearances are reduced as per readings obtained in roll
check of inner-outer & inner-inner casing.
Box up of casing:
A) Clean the rotor fully with sand blasting, check the coupling holes for any burr. Check the coupling bolt
locking pins, for its good condition, if necessary replace the same with new pin. Before placing rotor in
position place LP rear bearing in position. Prepare shaft seal compensator along with gasket (front & rear)
& position them on LP rotor with the help of fixtures or support. Lift rotor with supplied device, leveled it
in zero-zero position & placed slowly in position.
42
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
B) Lift top half of inner – inner casing clean it & place it in position. Apply jointing compound before box up
of casing. Similarly put inner outer casing in position, tighten it & carry out roll check of inner outer-casing.
Adjust the casing by machining packers & radial keys.
C) Centering of front & rear gland boxes of LP Casing, adjust the clearances with keys if necessary.
D) Inspect all extraction bellows & clean the condenser, remove checker plates & ladder put inside
condenser for inspection of bellow, lift outer cover & place it in position with O ring, apply jointing
compound before box up & tighten the casing.
1) Clean all coupling faces before alignment, align all rotors radially, axially & shift them in spigot provided on
couplings.
2) During alignment achieve left & right movement of rotors with the help of radial keys of pedestal, if the
correction is very less than it can be carried out through torous provided on the bottom of the bearing. The
up & down movement, of rotor is to be achieved with the help of adding or subtracting shims in the
cylindrical or spherical seat of bearing.
3) Avoid any adjustment of shims more than 0.3 mm in torous or spherical piece of bearing during the alignment.
Insure that during alignment the catenary of the rotor is maintained.
4) Put four no of loose bolts in HP/IP, IP/LP coupling, hand tight the loose bolts by keeping gap of about 0.20 to
0.25 mm in coupling face.
5) Rotate the rotor & record the coupling gap at 900 intervals on left right & top position. Ensure that loose bolts,
are remain free while recording the gap of coupling for alignment purpose. Note down the readings, measure
deviation & correct it, try to achieve left right, top-bottom deviation within 0.03 to 0.05 mm.
6) Ensure all coupling bolts are fitted within 0.02 to 0.03 mm clearance & bolts are to be ground within accuracy
of 0.05 mm.
43
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
DETAILED EXPLANATION :
The couplings of turbine shaft are generally rigid couplings; the basic function of any coupling is to
connect two or more shafts together to form a single shaft assembly. The radial and axial alignment of shafts are
to be completed before their coupling and alignment are to be done in such way that the entire shaft assembly
follow the continuous deflection curve given log sheet. The alignment checks determines both the radial and axial
position of two adjacent coupling flanges relative to one another The radial measurement is perform on
circumference of the coupling and axial measurement is performed on gap created in between the two coupling
flanges.
In any turbine generator erection or in overhauling the rotating shafts of the machine are aligned first &
the stationary parts like casings, seals, glands etc. are aligned later. It is necessary to align turbine generator rotors
because of following reasons.
The coupling connecting the shaft assemblies should be free of stresses & moments.
The objective is to avoid cyclic bending stress in the coupling planes, when coupled shafts are rotating in
the bearings, otherwise it would cause crank like moments
Obviously the undesired effect first mentioned, namely that of cyclic bending stresses, can lead to
malfunctions particularly in case where shrunk fit coupling flanges have been used. If the cyclic bending stress
constantly exceeds permissible levels, the coupling flange may get loosen and result in to failure. The second
undesired effects mentioned, namely crank like movement of shaft, and would result in additional dynamic load on
the adjacent journal bearings. The excessive misalignment will result into extra dynamic forces on the bearings
than permissible limits and will result into heavy vibrations of bearings as well as shafts.
A shaft which is supported at each end will have a certain degree of sag owning to its dead weight .The
extent of sag is essentially determined by the weight, the diameter & the distance between the bearing supporting
the shaft. The center line of shaft supported in such a manner can therefore no longer be regarded as a true
straight line but will assume more or less curve shape relative to the theoretical center line depending upon the
weight of shafts & the distance between two bearings. The actual center line is termed as shaft deflection curve
(catenary of the machine). It is the fact that this deflection curve remains the same even when the turbine is in
running, which in turn means that allowance must be made for shape of the deflection curves during erection &
overhauls of the machine.
44
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
This is the natural result of the weight factor. Obviously when shaft sag stresses are produced & the restoring
forces originating from these stresses limit the shaft sag. In turbine generator units these natural stresses are
accepted as inevitable. Additional stresses as a result of misalignment, must however, be avoided at all costs. To
satisfy this requirement during erection & overhaul of turbine generator units coupling checks must be employed
to assume optimum alignment of shafts relative to each other.
With the aid of coupling check, it is possible to align the journal bearings so that the deflection curve of a
shaft assembly is continuous. One major precondition in performing the coupling checks is that the bearings
supporting the shafts to be spaces in same way as in later operation. Without doubt, the optimum method of
achieving this is to place the shafts in their intended bearings
The standard coupling check covers firstly the radial position and secondly the axial position of two
adjacent coupling flanges relative to each other. Normally the measurement is taken radially on the circumference
of the adjacent coupling flanges, with the axial measurement being taken on outermost diameter of the inner axial
45
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
surfaces of the coupling. The measurement itself is taken with the aid of dial gauges or micrometer, or else with a
measuring jig firmly mounted on coupling flange & using a feeler gauge or slip gauge.
To eliminate as far as possible the influence of any axial or radial runouts present in the coupling plane, it
is imperative that the two shafts be turned in same direction and by same amount when the measurement is taken.
Since a measurement is normally taken in the two main planes, vertically and horizontally, at the top and the
bottom as well as on the left and right hand sides in each case, this should be also be turned through 90 degree in
each case.
Draw the meticulously cleaned coupling flanges together using three auxiliary fitting bolts, tight until only a slight
measuring gap is left
Set the measuring jigs in the top position on the coupling of the shaft assembly which are to be measured.
Using marker pen, mark this position with a line on both coupling flanges as “top” and proceeding in clockwise
direction mark “right” & “left position. It is not possible to measure to measure the gap at bottom position of the
coupling, so the bottom gap is calculated from the relation (left gap+ right gap = top gap + bottom gap).
Radial measurement is performed once at each measuring point, axial measurement is performed at
three points (left, right, and top) to compensate slight axial displacement, which are revealed when the shafts are
turned. The precise axial measurement is calculated from the arithmetic mean of the measurements taken at that
point
In detail the procedure is as follows
Perform radial measurement using measuring jig(dial gauge may also be used) with filler gauge at the top of
the coupling
Perform axial measurement using feeler gauge (if gap is wide use block gauge also) at right, left and top
coupling flanges.
Start up jacking oil pump and turn shaft assembly through 90 degree in the direction in which it will rotate in
service, shut down pump (auxiliary coupling bolts must be loose).
Perform radial measurement at the left of the coupling.
Perform axial measurement at left, right & top between coupling flanges.
Rotate the coupling in 180°, 270° & 360°, obtain axial & radial measurements as described above. Calculate
bottom gap from above mentioned relation, and also calculate arithmetic mean of measured gap at each
measurement points.
Radial correction is applied ½ of the deviation obtained during check and axial correction is applied as it is
obtained during check.
46
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
After coupling, adjacent shaft ends must be subjected to a final check for concentricity. An additional
measurement has to be taken at the journal area adjacent to the coupling to detect any runout.
Using firmly attached dial gauge; any runout present at journal & coupling areas can be measured by
carefully turning the coupled line of shafting.
If these checks revel runout of more than 0.03 mm, the couplings have not connected properly. It should
be pointed out here that a radial runout at shaft journal of only 0.03 mm is enough to produce an inherent
imbalance of 30 m in later operation.
The cause of the irregularities mentioned above can be due to unevenly tightened couplings, misaligned
centering and lack of parallelism between the couplings. It is imperative in all cases to locate the cause of the
improper connection and eliminate them by appropriate measure.
3.19 - COUPLING
1) Insert all coupling bolts in coupling bolts in coupling holes as per hole number punch on bolt.
2) Ensure freeness of bolts within 0.02 to 0.03 mm, tight four opposite bolts with prescribed elongation &
then check run out at coupling and journal, if the run out is within the limits tight another four bolts with
prescribed elongation. (0.33 to 0. 34 MM) & check run out at coupling & journal.
3) If it is found that run out at particular bolt or coupling & journal is going out of limit, use indifferent
method of tightening to control excess run out at journal & coupling.
4) Coupling bolts are not to be hammered in coupling holes & these are to be fitted with thumb pressure
only.
5) Balancing of coupling bolts by weight.
6) The question of balancing of coupling bolts arises only when the reaming & honing operations are carried
out in overhauling. The coupling bolts are to be balance within 5 gm accuracy.
7) Final balancing of coupling bolts is to be done along with individual bolt. If all coupling holes are of same
size before & after honing & reaming then all the bolts are kept of equal weight. If necessary adjust the
weight of bolts by machining the metal from bolt head or add weight by welding electrode.
47
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1. Before removal of bearing measure float of rotor. Measurement of float is necessary before dismantling
of thrust pad, as it is pad thickness deciding factor.
2. Remove the top half, load the rotor on lifting tackle, remove JOP connection & take out bottom half of
bearing. Remove spherical seats & take it out. Assemble the bearing out side & check spherical seat &
spherical support contact. The contact should be full throughout length & area of the spherical seat, no
contact around 25 to 30 mm area from both ends of spherical seat may be accepted.
3. Check the feeler tightness of spherical seat & support, the seat should be feeler tight, check it by inserting
0.03 mm feeler gauge in between gap of spherical seat & support. Check bearing shell parting plane feeler
tightness & pinch of bearing liner. Also check feeler tightness of bearing shell & liner. After tightening
bearing P/P bolts there should not be any gap in between bearing shell & liner.
4. Ensure proper color contract between spherical seat of bearing & pedestal, if required color matching
may be carried out for full contract.
5. Preparation of thrust pads: The thrust pads are dismantle from bearing by taking out holding pins of pads.
The working area of pad is blue matched & the spring elements are removed. Adding or subtracting shims
in between spring element & thrust pad can change the thickness of pad. The float is the thickness
deciding factor for thrust pads, accordingly add shims in between pad & spring element, increase the
thickness & reduce the float of rotor with required value. Take the bearing bottom shell contract with
rotor by placing it on rotor, the contract should be 20 to 30 mm wide & throughout length of liner, this
should be carried out for all bearings & if required corrections are made by hand work.
Check the side contract faces of bearing shell on which the axial keys rests, similarly check
pedestal side contact faces where axial keys rests if any pitting is observed, remove it by hand work
(scrapping). The mating faces of key & block should be surface ground & must have good contact with
pedestal & bearing shell.
The axial keys are prepared after checking parallelism of bearing with pedestal, its axial
positioning & Measurement of side oil clearances. Ensure that the bearing is fully rest on spherical seat
axially.
It should not be assembled in shifted condition from spherical seat. Check the self-aligning
property of bearing by disturbing bearing axially with 0.03 mm & rotating rotor for three to four times &
rechecking its axial position. The bearing should come to its original position (parallel to pedestal) with
the disturbed shift value i.e. 0.03 mm.
Make the bearing parallel with pedestal & measure the axial key gap at all four sides & prepare
the thickness of keys according to measurement. The thickness of keys should be made in such a way that
the keys should go hand tight.\, inside the gap 0.03 mm feeler tight key can be accepted.
48
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1) Before removal of pedestal top, ensure that all insulation removal work completed.
2) Remove cover & record seal bore readings at all pedestal (front and rear) with the help of inside
micrometer. Put dummy gasket on oil inlet hole of bearing pedestal, at its parting plane.
3) Measure the yoke key clearances take out the keys & remove the yoke.
4) Measure bearing oil – guard clearances & remove it. Remove top half of bearing & measure side oil
clearances with feeler gauge, compare it with available drawing readings, if variation is noticed correct it
from side keys. The correction should be carried out only when it is necessary. Measure the top oil
clearance with the help of lead wire. Place the wire on journal along its axis put top half in position tight it
fully, again remove top half & take out the lead wire & measure the thickness without side micrometer.
The thickness will give the top oil clearance.
5) Put rotor lifting device in position take the load of rotor on device, take out JOP connection & remove the
bottom half of bearing. Take out bearing seat & check the bearing seat contact. Assemble the bearing
check feeler tightness of liner with shell. The liner & shell should be 0.03 mm feeler tight. Inspect bottom
& top half for any damage on babbit. Carry out DPT & ultrasonic of bearing liner to identify any cracks or
babbit looseness.
6) Put the seat in position tight it put little oil for lubrication & place in position. Do not take out two
bearings of same shaft at the same time.
7) For Bearing No. 3, 4 & 5, ensure color contact between cylindrical seat of bearings & pedestal, if required
it by hand work (scrapping). Ensure contact between torous piece of bearing & cylindrical seat of pedestal,
the contract should be line contact through out the seat of width not more than 20 mm. If the contact is
disturb the machine may cause problem while in operation like jamming of bearing gear, heavy pedestal
vibration etc. In case of any variation, it is required to send the same to works for machining the seat
faces. As per recommendations & instructions of M/s BHEL, it is not allowed to achieve contact with hand
machining.
49
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
1) Before oil finishing clean the pedestal completely & remove bearing inlet throttle (for Bearing No. 1, 2, 3,
4, 5 ) & put bearing oil flushing dummies in all throttle, for bearing No. 6 & 7 shock circuit the inlet / outlet
pipe with special pipe connection.
2) Before oil flushing ensure that the insulation work is completed & pedestal oil guard rings are fitted in
position with required clearances. If during operation any pedestal oil leakage noticed, change the brass
fins & machine it with desired clearances. Set it on pedestal with respect to rotor.
3) Ensure that pedestal parting plane is feeler tight after tightening all parting plane bolts. If required color
matching may be carried out by scrapping. The cutting is to be carried out on upper half of the pedestal
cover, Box up all bearings remove gasket dummy from oil inlet at P/P of pedestal & assemble the yoke.
50
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
Prepare top / bottom yoke keys, by keeping 0.05 to 0.06 mm clearance. Apply jointing compound in
between P/P & box up the pedestal top cover after.
4) Start the oil pump & check the complete oil system for oil leakages. Slowly raise the temperature of oil to
normal working level is 42 0C, run the oil pump for 24 hours, clean the MOT bucket strainer & restart the
pump. Again stop the pump after 24 hours clean the bucket strainer. Remove top covers of all pedestals,
take out dummies from inlet & refit bearing inlet throttle in position. Complete instrumentation and
calibration. Take bearing No. 6 & 7 pedestal in oil circuit by removing shock circuit pipe connection.
Start AOP, now the bearings are taken in oil flushing again the system is checked for leakage, dirt
in MOT strainer is observed is the percentage of dirt is decreasing then put thrust bearing filters in service
& observer the choking rate before putting machine on barring. The thrust bearing filter should stand for
at least 16 hours, conclude the oil flushing & give clearance to barring.
Before box up of pedestal measure final seal bore readings & all other control readings. The
pedestal packers are to be removed, cleaned & contact of each should be checked. The axial keys are
removed, cleaned, lubricated & put back in position. Put machine on barring, observe for oil leakage &
rubbing sound.
51
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
Horn drop test is carried out for measuring the loading of casing on each corner of pedestal. The horn
drop readings are important in the HP & IP casings & may cause serious problems in operation of machine like high
vibrations in machine, failure of barring in hot or cold machine, obstruction during expansion of machine etc.
In horn drop test a drop is measured at an individual corner of the casing with the help of dial indicator by
removing support / packer of individual corner & then it is compared with opposite corner to record indifferent,
loading of casing.
Preparation & Procedure:
1) Ensure availability of four no of hydraulic jacks having capacity of 50 tons each.
2) Ensure four no of jackscrews of size M-60.
3) Place four jacks below Four Corners casing.
4) While recording the horn drop readings the casing must be absolutely free & even the radial or axial keys
of front & rear end of casing either to be removed or made free.
5) A dial gauge is also to be installed on each corner of casing to measure drop.
6) By lifting individual corner with jack the load of casing is supported on hydraulic jack or jacking screw,
then removes the individual packer.
Now gradually the jack is released in support of jacking screw to avoid jack failure or sudden release of
jack due to manual operation (may cause damage to seals). This is carried out at all Four Corners of HP & IP casings
& the drop readings are recorded on dial gauge.
If the corner is lifted by (+) 0.1 mm & packer is removed, then it is allowed to come down (-) 0.1 mm, this
is the zero position of the corner. Further drop from this position will be the drop of the particular corner
accordingly carried out for all Four Corners of casing.
This check is carried out in KWU machine for measurement of minimum radial clearance in HP, IP & LP
casing. It is measured by actual movement of casing from right to left & top to bottom, while rotating the rotor by
hand.
The variation in the readings may cause vibrations, obstruction to barring gear & reduced efficiency of
machine. The roll check should be carried out along with checking of centering of casing with respect to rotor. As
per roll check readings, casing centering should be carried out & same readings should be recorded for reference.
The roll check should be carried out in cold machine only.
PROCEDURE :
1) Alignment & coupling of HP, IP & LP rotors to be completed before starting the rolling test of the casing.
52
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
2) Centering readings should be recorded before carrying out the check, as to place casing in its original
position after the check if no corrections are required.
3) Install all jacking screws of HP & IP casing at all four corners along with dial gauges for monitoring up
down & left right movement of casing.
4) Place four hydraulic jacks of 50 T capacities below four corners of casing.
5) Before starting roll check, it should be ensure that rotor is totally free on hand barring, otherwise make it
free by adjusting the lift of rotor at each journal (normally 0.1 to 0.11 mm).
6) Measure the lift of rotor at corresponding journal by starting JOP; usually it is adjusted to 0.1 mm by
throttling jacking oil inlet valve. (Corresponding journal means, for HP casing J-1 & J-2 for IP J-2 & J-3 for
LP J-3 & J-4).
7) Lift the casing at all four corners in step of 0.05 mm to 0.1 mm with the help of hydraulic jack in support of
jacking screws. The rotor is also kept rotating manually side by side with the lifting of casing.
The rotation of rotor & lifting of casing continued till it becomes slightly tight at the seals of casing. After
this lowers the casing by 0.05 mm at all Four Corners & the rotor is rotated again. If the rotor is not completely
free, then 0.05 mm again lowers the casing till the rotor is completely free. After ensuring freeness of rotor it is
again rotated & the casing is lifted on its front end till the rotor rotation becomes tight on seal portion of front end.
As soon as the shaft become tight the lifting of casing & rotation of rotor is stopped, dial readings on front end left
right recorded. The lift on front end of casing gives bottom clearance of front end of casing.
After this the casing is lowered in step of 0.05 mm on front end to achieve freeness of rotor. The rear end
of casing is then lifted in steps of 0.05 mm by keeping rotor in motion. The lifting is continued till rotor become
tight on its seal. The corresponding dial reading on left & right corner of rear end of casing will give bottom
clearance on rear end of casing.
After recording the bottom clearances of front & rear end of individual casings, the casing is lowered back
to its original zero-zero position with hydraulic jack in support of jack screws.
Similar procedure is to be repeated for deciding top clearances of the casing. This may be decided by
lowering casing by removing packers below the corners of the casing, with the help of hydraulic jack in support of
jacking screws. The casing is lowered in step of 0.05 mm to 0.1 mm keeping rotor in motion till it become tight, on
its seals. Front & rear clearance is obtained as started in above procedure & casing is moved back to its original
position.
After recording the top & bottom clearances, the radial keys of casing are removed and again rolling test
for left & right directions are done similar to top / bottom. The procedure is same as that of top / bottom, only the
difference is dial gauges are installed on left & right corners for measurement of left / right clearances. After this
check the casing is brought back to its original position.
53
SYSTEMATIC PROCEDURE OF TURBINE OVERHAULING
After completion of the rolling test, casing clearances are adjusted as required in radial direction with the
help of radial keys & packers below the horns of casing. Final corresponding centering reading is recorded with
respect to roll check correction.
Swing check is the measurement of radial throw, caused due to coupling face run out of two coupled
rotors. This is measured on opposite end of coupling at journal where the weight of shaft is less as compared to
other end.
The higher swing check values may cause higher shaft vibration, higher Babbit metal temperature etc. The
value of swing check depends upon axial run out of coupling faces, the diameter of coupling & length of rotor. It is
recommended to keep minimum swing check value for better performance during operation of machine. In
tandem compounding turbine it is essential to measure swing check value on extreme end & where the weight of
rotors is light. In 210/250/500 MW KWU machine it is measure on HP rotor front.
Any variation in the swing check value may be corrected by inter changing the coupling face position or by
correcting the coupling faces with scrapping.
Face run out of all couplings is to be checked for concavity / convexity. This can be checked with the help
light wt straight edge. No. convexity is permitted; concavity of about 0.04 to 0.05 is permitted.
While recording the swing check readings of HP rotor front end is to be supported on lifting device & front
bearing bottom is removed. During swing check the lifting device are to fit properly, the tie rods of lifting device
should be seen for correct, fitting of its spherical bearings etc. The spherical bearings should not obstruct the
movement of shaft radially during checking of swing check.
IT can be carried out in other way by shifting load of rotor on dummy bearing and hanging it to EOT crane
with long sling. Ensure that the rotor is not disturbed radially due to fitting of dummy bearing.
During checking of swing check readings measure radial movement of rotor on parting plane & rotate the
rotor either on jacking oil with hand barring. Avoid jerk during rotation of rotor while recording the swing check
readings.
The final swing check value of HP rotor is to be measured after fitting & elongation of all coupling bolts of
HP-IP & IP-LP rotors. During tightening of coupling bolts the indifferent tightening of bolts may be avoided for
improvement of swing check & sequential tightening may be followed.
During checking of swing check readings the initial few rotations are given to the rotor to avoid initial sag
due to stationary position and then only the readings are to be recorded.
54
CHAPTER IV - TURBINE
COMMISSIONING
55
TURBINE COMMISSIONING
TURBINE COMMISSIONING:
It is set of activities required to carry out for rolling of turbine at rated speed safely.
These activities are performed in specific sequence, which is called as commissioning procedure.
The activities are carried out for individual systems and then combined for achieving goal i.e. turbine
commissioning.
• If the dirt, welding slag is carried over with oil there is every chance of damage to bearings.
PROCEDURE
• Trial run of vapor extraction fans should be completed and bearings are kept by passed by putting
dummies in oil inlet.
• First charging of oil system is done by starting EOP to avoid leakages and proper venting as disch. Pr.is less
than AOP.
• Once the system is completely filled AOP to be run for further flushing.
56
TURBINE COMMISSIONING
• Heating is to be stopped & oil is cooled by opening the CW valves to coolers till the temp. of oil goes down
to min. possible value.
• Continue this thermal shock method along with manual tapping of oil lines on its complete length.
• After initial flushing like this, bearings are included in flushing operation.
• Oil sample at inlet of COP should be free from moisture and mechanical impurities.
• Duplex oil filter/MOT filter should be free from impurities; no chocking of filters should be experienced in
duration of 24 hours.
• Charge the governing rack by opening manual isolating valves provided on rack.
• Ensure that turbine trip solenoid supply is made off.EHC is to be kept isolated.
• Close trip oil valves to ESV servomotor & Secondary oil valves in HPCV, IPCVs.
• Open starting device and ensure oil pressure in trip oil, secondary oil ckt.
57
TURBINE COMMISSIONING
• Close the starting device and open all valves previously closed.
• Open starting device gradually, ensuring speeder gear to its max. position.
• From 50% onwards control valves start open. Ensure that at 2.5Kg/cm2 of HPSO HPCV starts opening. at
2.5Kg/cm2 of IPSO IPCV starts opening. HPCV will open first followed by IPCV.
• Record the characteristics of valves .i.e valve lift verses secondary oil pressure.
58
TURBINE COMMISSIONING
• Ensure that oil pipe lines connected to valve servo motor are tightened properly in order to prevent high
oil pressure leakage.
• Operate the individual servo motor block valve from local & ensure full opening of each valve, main as
well as spray valve.
• Bypass low vacuum, Low injection water pressure protection and Bypass limiter.
• Operate controller & check signal oil pressure to its fullest value.
59
TURBINE COMMISSIONING
• Bring back to controller at zero position and start recording characteristic of valve verses signal oil
pressure.
b) Stop valve open to full opening at 2 Kg/Cm2 of signal oil followed by.
• Ensure that IOT & SOT float isolating valves are in open condition.
• Start SOP from local & check for oil leakage. Ensure Seal oil pressure and differential pressure.
• Checked hydrogen side & air side return flow from seal assembly. Kept liquid in generator valve opened.
• Start vacuum pump for venting purpose. If the system is normal shift control to remote.
• Complete the different trial from control room & give clearance for air filling in the generator stator.
• Gradually increased the air pressure & observed the DP. Keep eye on liquid in generator protection.
• Increase the pressure to rated pressure in step of 0.5 Kg/cm2. Observed the air pressure in casing.
• If the drop in pressure is 0.3 Kg/cm2. in 24 hours. Then conclude the test & give clearance for hydrogen
filling.
60
TURBINE COMMISSIONING
61
TURBINE COMMISSIONING
20. Reset the LPBP tripping. Once the HRH pressure is > 2 Kg/cm2, open LPBP spray valve first and then LPBP
stop and control valves. While opening the LPBP spray valves ensure that the CEP discharge header
pressure should not reduce < 20 Kg/cm2.
21. Open HPBP, raise the boiler parameter to 40-50 Kg/cm2 , and temp 350-375 deg C and HRH parameter -4-
12 Kg/cm2 @300 Deg C. by opening the LPBP control valves.
22. Ensure that condenser vacuum is <-0.85 Kg/cm2.
23. Ensure there is no hold up from Generator / bo8iler end for turbine rolling.
24. Ensure that all ESV, IPSV and HP & IP control valves are closed and control fluid lines to governing rack
and control valves are lined up.
62
TURBINE COMMISSIONING
16. Ensure that generator H2 cooler and exciter cooler are charged from cooling waterside.
17. Ensure that no parameters are above the alarm limits.
a) Bearing vibration < 84 Microns.
e) Diff. Expansion +2 mm
18. Open start up device very slowly. Turbine speed will rise. At around 2500-2800 rpm the speed will try to
stabilize, this is called governor take over speed. With starting device full open the speed will not
increased beyond this value. Ensure the primary oil pressure in the local gauge is around 1.8-2.0 Kg/cm2,
to increase speed further, we need to increased the speeder gear. From 0%
19. Now open the starting device full. Speed will not increase beyond take over speed of governor.
20. Slowly raise the speeder gear from 0%.
Adjust the speeder gear position such that the speed is maintained at 3000 rpm. At about 2950 rpm MOP
will take over and running AOP will be cut off on auto.
21. Ensure that the lub oil temp after cooler is not increasing beyond set value (45 0C). Allow soaking of
turbine at rated speed and wait for thermal stabilization of turbine casings. Observe for any abnormality
for any of the above parameters and bearing metal temps and vibrations.
22. Ensure that sufficient TSE margin (>30 deg K) and X7 criteria are available.
23. Give clearance for synchronization of unit.
63
TURBINE COMMISSIONING
64
TURBINE COMMISSIONING
65
TURBINE COMMISSIONING
66
TURBINE COMMISSIONING
67
TURBINE COMMISSIONING
68
TURBINE COMMISSIONING
69
CHAPTER V - HP TURBINE
PHOTOGRAPHS
70
HP TURBINE PHOTOGRAPHS
71
HP TURBINE PHOTOGRAPHS
72
HP TURBINE PHOTOGRAPHS
73
HP TURBINE PHOTOGRAPHS
74
HP TURBINE PHOTOGRAPHS
75
HP TURBINE PHOTOGRAPHS
76
HP TURBINE PHOTOGRAPHS
77
HP TURBINE PHOTOGRAPHS
78
HP TURBINE PHOTOGRAPHS
5.18 - VALVES
79
HP TURBINE PHOTOGRAPHS
80
HP TURBINE PHOTOGRAPHS
81
HP TURBINE PHOTOGRAPHS
82
HP TURBINE PHOTOGRAPHS
83
HP TURBINE PHOTOGRAPHS
84
HP TURBINE PHOTOGRAPHS
85
HP TURBINE PHOTOGRAPHS
5.24 - INTERNALS
86
HP TURBINE PHOTOGRAPHS
87
HP TURBINE PHOTOGRAPHS
88
HP MODULE DOCUMENTS
CHAPTER VI - HP MODULE
DOCUMENTS
89
HP MODULE DOCUMENTS
90
HP MODULE DOCUMENTS
NORMAL POSITION
DIMENSION CONDITION
DIA 1 2 3 4 5
Loosely Seated
Tightened Cold
a
Tightened
Warm
Loosely Seated
Tightened Cold
b
Tightened
Warm
Loosely Seated
Tightened Cold
c
Tightened
Warm
NOTE : 1. Joint gap and ovality measurement should preferably be done together
2. Parting plane studs may be tightened up to +60% to minimize joint gap.
3. If joint gap is 1.5 mm or less with top half being loosely seated and nominal
4. If joint gap is 1.5 mm or less with top half being loosely seated and also b is less than c, no further joint
gap measurement need be done.dia does not fall below 1 mm max., no further ovality measurement need be done.
91
HP MODULE DOCUMENTS
92
HP MODULE DOCUMENTS
NOTE : The seals shall be numbered beginning from Turbine side for each stage.
SEAL SEAL SEAL
STAGE LEFT RIGHT STAGE LEFT RIGHT STAGE LEFT RIGHT
NO. NO. NO.
25 1 16 1 7 1
2 2 2
3 3 3
24 1 15 1 6 1
2 2 2
3 3 3
23 1 14 1 5 1
2 2 2
3 3 3
22 1 13 1 4 1
2 2 2
3 3 3
21 1 12 1 3 1
2 2 2
3 3 3
20 1 11 1 2 1
2 2 2
3 3 3
19 1 10 1 1 1
2 2 2
3 3 3
18 1 9 1 1
2 2 2
3 3 3
17 1 8 1 1
2 2 2
3 3 3
93
HP MODULE DOCUMENTS
UPPER HALF
(DURING DISMANTLING / AFTER FINAL ASSEMBLY)
CASING CASING
+5.5 b b
+
3 a 2 a 1 a +5.5
+
ROTOR ROTOR
94
HP MODULE DOCUMENTS
LOWER HALF
(DURING DISMANTLING / AFTER FINAL ASSEMBLY)
CASING CASING
+5.5 b b
+
3 a 2 a 1 a
+5.5
+
ROTOR ROTOR
95
HP MODULE DOCUMENTS
STAGE NO
DR DR DR DR
SEALING
SEALING
LE RIG LE RIG LE RIG LE RIG
G FT HT G FT HT G FT HT G FT HT
NO
NO
2 1 5.9 - - - 25 1 5.9 - - -
5 2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 24 1 5.9 4.5 - -
4 2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 23 1 5.9 4.5 - -
3 2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 22 1 5.9 4.5 - -
2 2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 21 1 5.9 4.5 - -
1 2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 20 1 5.9 4.5 - -
0 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 19 1 5.9 4.5 - -
9 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 18 1 5.9 4.5 - -
8 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 17 1 5.9 4.5 - -
7 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 16 1 5.9 4.5 - -
6 2 - - - 4.5 2 - - - 4.5
96
HP MODULE DOCUMENTS
STAGE NO
SEALING
SEALING
DR LE RIG DR DR LE RIG DR LE RIG
G FT HT G G FT HT G FT HT
NO
NO
1 1 5.9 - - - 15 1 5.9 - - -
5 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 14 1 5.9 4.5 - -
4 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 13 1 5.9 4.5 - -
3 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 12 1 5.9 4.5 - -
2 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 11 1 5.9 4.5 - -
1 2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 10 1 5.9 4.5 - -
0 2 5.9 - - 4.5 2 5.9 - - 4.5
9 1 5.9 4.5 - - 9 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
8 1 5.9 4.5 - - 8 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
7 1 5.9 4.5 - - 7 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
6 1 5.9 4.5 - - 6 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
5 1 5.9 4.5 - - 5 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
4 1 5.9 4.5 - - 4 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
3 1 5.9 4.5 - - 3 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
2 1 5.9 4.5 - - 2 1 5.9 4.5 - -
2 5.9 - - 4.5 2 5.9 - - 4.5
1 1 5.9 4.5 - - 1 1 5.9 4.5 - -
2 - - 4.5 2 - - 4.5
97
HP MODULE DOCUMENTS
STAGE NO
PER OBSERVED PER OBSERVED PER OBSERVED PER OBSERVED
SEALING
SEALING
DRG LE RIG DRG DRG LE RIG DRG LE RIG
FT HT FT HT FT HT
NO
NO
25 1 6.4 5.0 6.4 5.0
24 1 6.4 5.0 6.4 5.0
23 1 6.4 5.0 6.4 5.0
22 1 6.4 5.0 6.4 5.0
21 1 6.4 5.0 6.4 5.0
20 1 6.4 5.0 6.4 5.0
19 1 6.4 5.0 6.4 5.0
18 1 6.4 5.0 6.4 5.0
17 1 5.0 4.4 5.0 4.4
16 1 5.0 4.4 5.0 4.4
15 1 5.0 4.4 5.0 4.4
14 1 5.0 4.4 5.0 4.4
13 1 5.0 4.4 5.0 4.4
12 1 5.0 4.4 5.0 4.4
11 1 6.4 5.0 6.4 5.0
10 1 6.4 5.0 6.4 5.0
9 1 6.4 5.0 6.4 5.0
8 1 6.4 5.0 6.4 5.0
7 1 6.4 5.0 6.4 5.0
6 1 6.4 5.0 6.4 5.0
5 1 6.4 5.0 6.4 5.0
4 1 6.4 5.0 6.4 5.0
3 1 6.4 5.0 6.4 5.0
2 1 6.4 5.0 6.4 5.0
1 1
98
HP MODULE DOCUMENTS
NOTE : The sealing strips shall be numbered successively beginning at turbine side
RADIAL CLEARANCE “d” AXIAL CLEARANCES TOL: 0.5
AS PER AS AS PER + DIRECTION (b) AS PER - DIRECTION
DRG OBSERVED DRG DRG (a)
STRIP NO.
SEALING
A 1 0.6 - - - -
2 0.6 3.65 3.65
3 0.6 3.65 - - 3.65 - -
4 0.6 3.65 3.65
5 0.6 3.65 - - 3.65 - -
6 0.6 3.65 3.65
7 0.6 3.65 - - 3.65 - -
8 0.6 3.65 3.65
9 0.6 3.65 - - 3.65 - -
10 0.6 3.65 3.65
11 0.6 3.65 - - 3.65 - -
12 0.6 3.65 3.65
13 0.6 3.65 - - 3.65 - -
14 0.6 3.65 3.65
99
HP MODULE DOCUMENTS
B 15 0.6
16 0.6 3.65 3.65
17 0.6 3.65 3.65
18 0.6 3.65 3.65
19 0.6 3.65 3.65
20 0.6 3.65 3.65
21 0.6 3.65 3.65
22 0.6 3.65 3.65
23 0.6 3.65 3.65
24 0.6 3.65 3.65
25 0.6 3.65 3.65
26 0.6 3.65 3.65
27 0.6 3.65 3.65
28 0.6 3.65 3.65
C 29 0.6
30 0.6 3.65 3.65
31 0.6 3.65 3.65
32 0.6 3.65 3.65
33 0.6 3.65 3.65
34 0.6 3.65 3.65
35 0.6 3.65 3.65
36 0.6 3.65 3.65
37 0.6 3.65 3.65
38 0.6 3.65 3.65
39 0.6 3.65 3.65
40 0.6 3.65 3.65
41 0.6 3.65 3.65
42 0.6 3.65 3.65
D 43 0.6
44 0.6 3.65 3.65
45 0.6 3.65 3.65
46 0.6 3.65 3.65
47 0.6 3.65 3.65
48 0.6 3.65 3.65
100
HP MODULE DOCUMENTS
101
HP MODULE DOCUMENTS
102
HP MODULE DOCUMENTS
DETAIL - II
NOTE : The seals strips shall be numbered successively beginning at Turbine Side.
RADIAL CLEARANCE “d” AXIAL CLEARANCES TOL: 0.5
AS PER AS AS PER + DIRECTION (a) AS PER - DIRECTION (b)
DRG calculated DRG DRG
STRIP NO.
SEALING
M
1 0.40 - - - -
2 0.40 6.4 4.4
3 0.40 6.4 - - 4.4 - -
4 0.40 6.4 4.4
5 0.40 6.4 - - 4.4 - -
6 0.40 6.4 4.4
7 0.40 6.4 - - 4.4 - -
8 0.40 6.4 4.4
9 0.40 6.4 - - 4.4 - -
10 0.40 6.4 4.4
L
11 0.40 - - - -
12 0.40 6.4 4.4
13 0.40 6.4 - - 4.4 - -
14 0.40 6.4 4.4
15 0.40 6.4 - - 4.4 - -
16 0.40 6.4 4.4
17 0.40 6.4 - - 4.4 - -
18 0.40 6.4 4.4
19 0.40 6.4 - - - -
20 0.40 6.4 - - -
103
HP MODULE DOCUMENTS
NOTE : The seals strips shall be numbered successively beginning at Turbine Side.
K
21 0.40 - - - -
22 0.40 6.4 4.4
23 0.40 6.4 - - 4.4 - -
24 0.40 6.4 4.4
25 0.40 6.4 - - 4.4 - -
26 0.40 6.4 4.4
27 0.40 6.4 - - 4.4 - -
28 0.40 6.4 4.4
29 0.40 6.4 - - 4.4 - -
30 0.40 6.4 4.4
31 0.40 - - 4.4 - -
32 0.40 6.4 4.4
33 0.40 6.4 - - 4.4 - -
34 0.40 6.4 4.4
35 0.40 6.4 - - - - -
36 0.40 6.4 - - -
J
37 0.40 - - - -
38 0.40 6.4 4.4
39 0.40 6.4 - - 4.4 - -
40 0.40 6.4 4.4
41 0.40 6.4 - - 4.4 - -
42 0.40 6.4 4.4
43 0.40 6.4 - - 4.4 - -
44 0.40 6.4 4.4
45 0.40 6.4 - - 4.4 - -
46 0.40 6.4 4.4 - -
104
HP MODULE DOCUMENTS
TEST LOAD
DETAIL - I
SEALING NO. a b c
AS PER DRAWING
O 0.1-0.2 -
AS OBSERVED
FRONT LEFT RIGHT LEFT RIGHT LEFT RIGHT
A
B
C
D
E
F
G
H
REAR
M
L
105
HP MODULE DOCUMENTS
SEALING RING NO a b c d
AS PER DRAWIG
0.2 – 0.3 0.20 0.5 5.0
AS OBSERVED
K
106
HP MODULE DOCUMENTS
GUIDE BLADES
MOVING BLADES
GUIDE BLADES (a) 0.6 mm MOVING BLADES (b) 0.6 mm TOTAL (a+b) 1.20 mm
ALIGNMENT
TS GS
TS GS
107
HP MODULE DOCUMENTS
+VE -VE
TOLERANCE = +-0.7 mm
108
HP MODULE DOCUMENTS
OBSERVED VALUES
109
HP MODULE DOCUMENTS
110
HP MODULE DOCUMENTS
DETAIL - I (SH.NO.1)
DETAIL - II
111
HP MODULE DOCUMENTS
HP CASING ASSEMBLY
DETAIL - X VIEW - M
112
HP MODULE DOCUMENTS
HP CASING ASSEMBLY
SECTION - KK
AS AS OBSERVED
MEA-
PER FITTING KYEY NO.
SURE
DRG. 1 2 3 4 5 6 7 8 9 10 11 12
A 0.04-0.05 - - - - - - - -
B 0.08-0.10 - - - - - - - - - - -
C 0.08-0.10 - - - - - - - - - - -
D - - - - -
E - - - - - - - - -
F - - - - -
113
HP MODULE DOCUMENTS
114
HP MODULE DOCUMENTS
U1 e
115
HP MODULE DOCUMENTS
c
d 2 + 0.5
e NON STRESSED (X) MEASURED
PRE STRESSED (Y) CALCULATED REFER SHEET- 5
PRESTRESSED 1.0 TO 1.13 CALCULATED (X-Y)
116
HP MODULE DOCUMENTS
2.0 TIGHTNESS OF BREACH-NUT : Tightness of Breach-nut should be 32 mm after closing the joint surface
117
CHAPTER VII - IP MODULE
ASSEMBLY DOCUMENTS
118
IP MODULE ASSEMBLY DOCUMENTS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
119
IP MODULE ASSEMBLY DOCUMENTS
120
IP MODULE ASSEMBLY DOCUMENTS
STAGE 1 – 11 = 0.9 mm
STAGE 12-20 = 1.0 mm
NOTE : The seal shall be numbered beginning from Turbine side for each stage
STAGE SEAL LEFT RIGHT STAGE SEAL LEFT RIGHT STAGE SEAL LEFT RIGHT
NO NO NO
20 1 13 1 6 1
2 2 2
3 3 3
19 1 12 1 5 1
2 2 2
3 3 3
18 1 11 1 4 1
2 2 2
3 3 3
17 1 10 1 3 1
2 2 2
3 3 3
16 1 9 1 2 1
2 2 2
3 3 3
15 1 8 1 1 1
2 2 2
3 3 3
14 1 7 1
2 2
3 3
121
IP MODULE ASSEMBLY DOCUMENTS
STAGE 1 – 11 = 0.9 mm
STAGE 12-20 = 1.0 mm
NOTE : The seal shall be numbered beginning from Turbine side for each stage
STAGE SEAL NO LEFT RIGHT STAGE SEAL NO LEFT RIGHT STAGE SEAL NO LEFT RIGHT
1 1 8 1 15 1
2 2 2
3 3 3
2 1 9 1 16 1
2 2 2
3 3 3
3 1 10 1 17 1
2 2 2
3 3 3
4 1 11 1 18 1
2 2 2
3 3 3
5 1 12 1 19 1
2 2 2
3 3 3
6 1 13 1 20 1
2 2 2
3 3 3
7 1 14 1
2 2
3 3
122
IP MODULE ASSEMBLY DOCUMENTS
CASING
CASING
3 2 1
b b
a a
ROTOR
ROTOR
123
IP MODULE ASSEMBLY DOCUMENTS
CASING
CASING
a a
b b
1 2 3
ROTOR ROTOR
124
IP MODULE ASSEMBLY DOCUMENTS
TOL : +- 0.8
125
IP MODULE ASSEMBLY DOCUMENTS
TOL : +- 0.8
126
IP MODULE ASSEMBLY DOCUMENTS
NOTE : The sealing strips shall be numbered successively beginning at turbine side:
127
IP MODULE ASSEMBLY DOCUMENTS
3 29 0.50 3.9 - - -
30 0.50 3.9 - - - - -
31 0.50 3.9 3.4
32 0.50 3.9 - - 3.4 - -
33 0.50 3.9 3.4
34 0.50 3.9 - - 3.4 - -
35 0.50 3.9 3.4
36 0.50 3.9 - - 3.4 - -
37 0.50 3.9 3.4
38 0.50 3.9 - - 3.4 - -
39 0.50 3.9 3.4
40 0.50 3.9 - - 3.4 - -
41 0.50 3.9 3.4
42 0.50 - - - - - -
128
IP MODULE ASSEMBLY DOCUMENTS
129
IP MODULE ASSEMBLY DOCUMENTS
130
IP MODULE ASSEMBLY DOCUMENTS
131
IP MODULE ASSEMBLY DOCUMENTS
132
IP MODULE ASSEMBLY DOCUMENTS
TEST LOAD
DETAIL - I
AS PER A B C
DRG. 0 0.1 – 0.2 -
SEALING AS OBSERVED
NO. LEFT RIGHT LEFT RIGHT LEFT RIGHT
5
4
3
2
1
7
8
9
10
133
IP MODULE ASSEMBLY DOCUMENTS
GUIDE BLADES
MOVING BLADES
ALIGNMENT
TS GS
TS GS
134
IP MODULE ASSEMBLY DOCUMENTS
+VE -VE
TOLERANCE = 0.7 mm
135
IP MODULE ASSEMBLY DOCUMENTS
136
IP MODULE ASSEMBLY DOCUMENTS
137
IP MODULE ASSEMBLY DOCUMENTS
h
c
e f
138
IP MODULE ASSEMBLY DOCUMENTS
k
a
h f g h b
e
i i
d d
F F
C C
139
IP MODULE ASSEMBLY DOCUMENTS
NOTE : THESE READINGS ARE REQUIRED IN CASE OF REPLACEMENT OF INNER OR OUTER CASING
140
CHAPTER VIII - DOCUMENTS
FOR GENERAL OVERHAUL
141
DOCUMENTS FOR GENERAL OVERHAUL
STATIONARY BLADE
STEAM FLOW
MOVING BLADE
TURBINE SIDE
AXIAL CLEARANCE BETWEEN BLADES
a b
AS PER
STAGE AS PER LEFT RIGHT DRG LEFT RIGHT
NO. DRG
DIS ASSY DIS ASSY DIS ASSY DIS ASSY
1 - 27
2 7 27
3 7 27
4 14 27
5 7 27
6 13.5 33.5
7 13.5 33.5
8 13 33
GENERATOR SIDE
AXIAL CLEARANCE BETWEEN BLADES
a b
AS PER
STAGE AS PER LEFT RIGHT DRG LEFT RIGHT
NO. DRG
DIS ASSY DIS ASSY DIS ASSY DIS ASSY
1 - 7
2 27 7
3 27 7
4 34 7
5 27 7
6 33.5 13.5
7 33.5 13.5
8 33 13
142
DOCUMENTS FOR GENERAL OVERHAUL
note: readings recorded are as measured before roll check,need not be repeated after roll check.
TURBINE SIDE
GENERATOR SIDE
143
DOCUMENTS FOR GENERAL OVERHAUL
L R
HPR
IPF
IPR
LPF
LPR
144
DOCUMENTS FOR GENERAL OVERHAUL
LEFT RIGHT
LOCATION Dismantling Assembly Dismantling Assembly
FRONT
REAR
145
DOCUMENTS FOR GENERAL OVERHAUL
2 3
1 4
8 5
7 6
b b
146
DOCUMENTS FOR GENERAL OVERHAUL
NOMINAL ACTUAL
MEAS. MIN. CLEARANCE MAX. CLEARANCE CLEARANCE
a. FRONT BRG 0.060 0.110
b. IMP W.RING (F) 0.145 0.210
c. IMP W.RING (R) 0.145 0.210
d. THRT BRG FLT 0.180 0.221
e. THRT BRG CLR 0.060 0.110
f. GOP W.RING (F) 0.120 0.177
g. GOP W.RING (R) 0.120 0.177
h. P0.50
i. P0.50
j.
k.
l.
m.
n.
o.
p.
q.
2 3 4 5 6 7
1
8 9
10 11
147
DOCUMENTS FOR GENERAL OVERHAUL
148
DOCUMENTS FOR GENERAL OVERHAUL
II
I e b
C
a
a
DETAIL I
b
DETAIL II
ACTUAL
DIMENSION NOMINAL
DISMANTL ASSY
a. 3± 0.2
b. 0.30
c. 14 ± 0.50
d. 5 ± 0.50
e. 14 ± 0.50
149
DOCUMENTS FOR GENERAL OVERHAUL
DIS ASSY
HPF
HPR IPF
IPR LPF
DIS ASSY
LPR
150
DOCUMENTS FOR GENERAL OVERHAUL
BEARIN ASS
G NO. DIS ASSY DIS Y
1
FRONT REAR
ASS
DIS ASSY DIS Y
2 FRONT REAR
ASS
DIS ASSY DIS Y
3
FRONT REAR
ASS
DIS ASSY DIS Y
4
FRONT REAR
ASS
DIS ASSY DIS Y
5
FRONT REAR
151
DOCUMENTS FOR GENERAL OVERHAUL
THRUST FLO AT
f f O
e e
b
c c
B C e f a
D
DRAWINGS
(TOC)
BRG NO
A
g D
C
RIGHT
LEFT
A R
T
DRG C L R L R L R L R G
T
0.34 0.42
28
D 1 TO TO
0
I 0.41 0.45
S 0.35 0.43
29
M 2 TO TO
0
A 0.41 0.46
N 0.54 0.36
45
T 3 TO TO
0
L 0.62 0.40
I
N 0.48 0.32
40
G 4 TO TO
0
0.54 0.36
0.34 0.42
28
A 1 TO TO
0
S 0.41 0.45
S 0.35 0.43
29
0.3 ±
E 2 TO TO
0
0.1
M 0.41 0.46
B 0.54 0.36
45
L 3 TO TO
0
Y 0.62 0.40
0.48 0.32
40
4 TO TO
0
0.54 0.36
152
DOCUMENTS FOR GENERAL OVERHAUL
BEARING
AXIAL KEY
A B
OS TS
TS OS
D1
E F
LEFT RIGHT
A
B
E
F
PADN 1 2 3 4 5 6 7 8 9 10 11 12 13 14
O.
TK
PADN 1 2 3 4 5 6 7 8 9 10 11 12 13 14
O.
TK
153
DOCUMENTS FOR GENERAL OVERHAUL
DISMANTLING ASSEMBLY
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
R/O
Note:
1) Readings are to be recorded after elongation of all coupling bolts of HP/IP and HP/LP
coupling.
2) Dial Indicator on Journal no. 1 is mounted on Parting Plane
3) Position of Hole(Left/Right) ,dial gauge position on Parting Plane (Left/Right) is to be
recorded.
4) JOP is to be stopped before each reading.
154
DOCUMENTS FOR GENERAL OVERHAUL
8.14 - ALIGNMENT
RADIAL AXIAL
MOP TOL : T-B= ± 0.02 mm
JOURNAL
L-R=± 0.02 mm RUN OUT
DISMANTLING ASSY.
AXIAL 1
HPR-IPR AXIAL 2
IPR-LPR AXIAL 3
LP-GEN
RADIAL AXIAL 4
155
DOCUMENTS FOR GENERAL OVERHAUL
HP COUPLING
BOLT NO. HP JOURNAL J2 IP COUPLING J1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
R/O
156
DOCUMENTS FOR GENERAL OVERHAUL
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
R/O
157
DOCUMENTS FOR GENERAL OVERHAUL
J4 LPC GEN C J5
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
R/O
158
DOCUMENTS FOR GENERAL OVERHAUL
5. 4 4
0.31
6. TO 5
5
0.34 6
7. 6
0.4 1
8. 7
7 TO 0.43
9. 0.43 8
8 TO
10. 9
0.47
11. 9 10
12. 10 11
13. 12
11
14. 13
12
15. 14
13 15
16.
14 16
17
18
159
DOCUMENTS FOR GENERAL OVERHAUL
D
C
CENTEREING OF CASING
ASS
DIS ASSY DIS
Y
FRONT REAR
ASS
DIS ASSY DIS
Y
FRONT REAR
160
DOCUMENTS FOR GENERAL OVERHAUL
C D
CENTERING OF CASING
C D
ASS
DIS ASSY DIS
Y
FRONT REAR
ASS
DIS ASSY DIS
Y
FRONT REAR
161
DOCUMENTS FOR GENERAL OVERHAUL
C D
C D
ASS
DIS ASSY DIS
Y
FRONT REAR
ASS
DIS ASSY DIS
Y
FRONT REAR
162
DOCUMENTS FOR GENERAL OVERHAUL
HP CYLINDER
HP FRONT LEFT
HP FRONT RIGHT
HP REAR LEFT
HP REAR RIGHT
IP CYLINDER
IP FRONT LEFT
IP FRONT RIGHT
IP REAR LEFT
IP REAR RIGHT
163
DOCUMENTS FOR GENERAL OVERHAUL
CLEARANCE ‘C’
CLAMPING PLATE
CLEARANCES - C
LOCATION AS PER DRG ACTUAL
HP FRONT RIGHT 0.1-0.15
164
DOCUMENTS FOR GENERAL OVERHAUL
J1 S1 S2
BOLT NO J S1 S2
R/O
165
DOCUMENTS FOR GENERAL OVERHAUL
HP IP LP GEN
B1 B2 B3 B4 B5 B6
B1
B2
B3
B4
B5
B6
166
DOCUMENTS FOR GENERAL OVERHAUL
FRONT HP-IP
PEDESTAL PEDESTAL
MEASUREMENT A B C
AS PER DRG 56 50.6 0.50
RIGHT
LEFT
LOCATION
AS PER DRG 0.1 TO 0.15 0.1 TO 0.15
FRONT LEFT -
FRONT RIGHT -
REAR LEFT
REAR RIGHT
C
A B
DETAIL- I
A- UN TIGHTENED
B- TIGHTENED
167
DOCUMENTS FOR GENERAL OVERHAUL
TOP
MEASUREMENT
DISMANTLE ASSEMBLY
HP FRONT
HP REAR
168
DOCUMENTS FOR GENERAL OVERHAUL
IP CYLINDER
B
IP ROTOR
GS
TOP
MEASUREMENT
DISMANTLE ASSEMBLY
HP FRONT
HP REAR
169
DOCUMENTS FOR GENERAL OVERHAUL
LINK I
SHAFT POSITION MONITOR TS GS
ACTUAL
LINK II
TS GS
ACTUAL
LINK I
NOMINAL 2± 0.2 mm
ACTUAL
LINK II
NOMINAL 2± 0.2 mm
ACTUAL
EMERGENCY GOVERNOR
170
DOCUMENTS FOR GENERAL OVERHAUL
R/O
171
DOCUMENTS FOR GENERAL OVERHAUL
HP IP LP GEN
B1 B2 B3 B4 B5 B6
172
DOCUMENTS FOR GENERAL OVERHAUL
FREE CONDITION
TS GS
STAGE NO.
AA BB CC AA BB CC
TS GS
STAGE NO.
AA BB CC AA BB CC
173
CHAPTER IX - VALVES AND
GOVERNING
174
VALVES AND GOVERNING
NOMINAL CLEARANCES
HP CV CONE BUSH 0.16 TO 0.195 MM
HP STOP VALVE
VALVE CONE CUSH VALVE SPINDAL BUSH
SPINDAL BUSH CLR SPINDA BU CLR
L SH
A
SV1 B
C
AV
A
SV2 B
C
AV
HP U- RING COMPRESSION
CV1
CV2
SV1
SV2
175
VALVES AND GOVERNING
NOMINAL CLEARANCES
HP CV CONE BUSH 0.16 TO 0.195 MM
IP CONTROL VALVE
VALVE CONE BUSH VALVE SPINDAL BUSH
SPINDAL BUSH CLR SPINDAL BUSH CLR
A
CV1 B
C
AV
A
CV2 B
C
AV
NOMINAL CLEARANCES
CONE BUSH (BOTH CV AND SV) 0.60 TO 00.68
176
VALVES AND GOVERNING
177
REFERENCES