Masjid Al-Furqan - Phase 2 - Cost Estimate No.1a
Masjid Al-Furqan - Phase 2 - Cost Estimate No.1a
Masjid Al-Furqan - Phase 2 - Cost Estimate No.1a
1
Project: MASJID AL-FURQAN - PHASE 2
Date: 17-Nov-21
2.0 Structural
2.1 Demolition Works LS 1.00 6,000.00 6,000.00
2.10 Waterproofing c/w 50mm thk Protective Screed m2 23.80 150.00 3,570.00
Anti-Termite m2 29.98 35.00 1,049.30
Damp Proof Membrane m2 29.98 20.00 599.60
RWDP System LS 1.00 1,200.00 1,200.00
SUB-TOTAL (2.0) 37,753.00
Note:
1 The Structural Works will be Design and Build by the Contractor. We have made our own assumption for cost estimate purposes.
2 EXCLUDES the Loose Furniture and White Board. Will be procured by the Client.
2.0 Structural
2.1 Demolition Works LS 1.00 6,000.00 6,000.00
2.10 Waterproofing c/w 50mm thk Protective Screed m2 23.80 150.00 3,570.00
Anti-Termite m2 29.98 35.00 1,049.30
Damp Proof Membrane m2 29.98 20.00 599.60
RWDP System LS 1.00 1,200.00 1,200.00
SUB-TOTAL (2.0) 37,753.00
Prepared by SCQS Page 3of 4
COST ESTIMATE NO.1A
Project: MASJID AL-FURQAN - PHASE 2
Date: 18-Nov-21
3.0 Architectural
3.1 Wall
a. External Wall; 115mm thick Cement Sand Brick wall m2 24.00 120.00 2,880.00
b. Internal Wall; 115mm thick Cement Sand Brick wall (Seal Off) m2 5.00 150.00 750.00
Note:
1 The Structural Works will be Design and Build by the Contractor. We have made our own assumption for cost estimate purposes.
2 EXCLUDES the Loose Furniture and White Board. Will be procured by the Client.