Basics of Paralleling
Basics of Paralleling
Basics of Paralleling
T, w
E
L
Generator Set
Skid
Engine
Alternator
Cooling
Control
Power System
Utility
Backup Power
Loads
Paralleling
Synchronous operation of two or more generator sets connected together
on a paralleling bus in order to provide power to common loads
Electronic
Governor
Pump
Fuel
T, w
Automatic Voltage Regulator (AVR)
DC Current
v
AVR
Output
0 t
Exciter Rotor
& Stator
𝛿𝑩
𝜵×𝑬=− (𝐹𝑎𝑟𝑎𝑑𝑎𝑦 ′ 𝑠 𝐿𝑎𝑤)
Rectifier 𝛿𝑡
Magnetic
Main Stator Flux Field
Synchronizer
AC Network:
480 VAC, 60 Hz, 3Ø
Synchronizing: Phase and Frequency
Source-1
Adjusting the governor fuel set point Source-2
Ø
Offset (t)
v
Setpoint
1800 RPM + ω(t)
+ -
0 90 180 270 360
Deg
Electronic
Governor
Speed f1
Sensor f2
Fuel Fuel v
Actuator
Shaft 0 t1 t2 t3 t4 t
Prime
Mover
Synchronizing: Voltage Amplitude
Adjusting the field excitation
Offset (t)
Setpoint
4.16kV +
+ - Source-1
v Source-2
Voltage
Regulator
Voltage
Sensor
0 t
Excitation
System
Electric
Generator
V(t)
Output
Rotor Position and Output Voltage
v
One Wave Cycle
N SHAFT N
0 90 180 270 360 90 180 270 360 Deg
S
Alternator Shaft Position
(Degrees)
Offset Offset
Setpoint Setpoint
1800 RPM + ω(t) 4.16kV +
+ - + -
Electronic Voltage
Governor Regulator
Speed Voltage
Sensor Sensor
Fuel Fuel Excitation
Actuator System
Ready to Load
2 MW
1 MW 1 MW
1 MW 0.5 MW 0.5 MW
2MW Load
Load Sharing
The kW load sharing is achieved by increasing or decreasing fuel to the
engines
The kVAR load sharing is achieved by increasing or decreasing the field
excitation to the alternators
Peak Shave
Base Load
Requirements
Power
Power
User Supplied Power Utility Supplied Power
Time Time
Connecting to the Grid
Base load, peak shave, extended paralleling
Cannot change the grid voltage and frequency
Drive generator sets to match the grid
Grid Synchronizer
Infinite Match kW Load
Source: Grid Govern Lines
kVAR Load
Frequency Govern Lines
Phase
GOV GOV
Voltage
AVR AVR
Grid Connecting Example
Peak Shave Mode - Extended Paralleling
Grid
Controller
kW Load
Read Power Govern Lines
kVAR Load
Govern Lines
GOV GOV
Utility Import Setpoint: AVR AVR
e.g. 0.5 MW
0.5 MW
2 MW 2 MW
1 MW 1 MW
2.5 MW Load
Typical Generator Protection Elements
15 – Synchronizer
24 – Volts/Hertz
25 – Synch Check
27 – Undervoltage
32 – Directional Power
40 – Loss of Excitation/Reverse kVAR
46 – Phase Balance Current
47 – Phase Sequence Voltage
50 – Instantaneous overcurrent
51 – Time Overcurrent Reverse kVAR Reverse kW
59 – Overvoltage
81U/O – Under/Over Frequency
Paralleling Control
Grid
Load Load
Master Control
Is required when:
– Synchronizing multiple generator sets with the utility or multiple utility feeds
– Load and capacity management
– System monitoring and control
– Complex sequence of operation
Master Control
Grid
Synchronize
Governor and AVR are the basic functions on every genset and the
synchronizer, load share and load govern simply adjust the reference
point to them
Paralleling enhances the overall system reliability, performance and
flexibility
Distributed logic architecture in a paralleling system improves the overall
reliability by eliminating single points of failure
Thank You!
Match generating capacity to the load to optimize fuel efficiency and prolong
generator set life Capacity: 5MW
1 MW 1 MW 1 MW 1 MW 1 MW
CB CB CB CB CB
Load: 4.75
0.5 MW
1.5
3.0
3.5 MW
Reference Material:
Load Demand
The load demand feature is used to match generating capacity to the
load to optimize fuel efficiency and prolong generator set life while
maintaining correct reserve capacity for the customer’s application
Shutdown sequence can either be a fixed sequence or can be based on
running hours
– Fixed sequence: the sequence can be changed while the system is in operation
– Running hours: attempts to equalize generator set hours over time by exchanging
stopped and running generator sets
To protect system integrity, load demand will restart all generator sets
whenever an overload condition is detected
The minimum amount of capacity to maintain online is adjustable