Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Bongabon 2 Storey

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 22

Project PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.

Title:
BOQ
IT ITEM DESCRIPTION QTY UNIT
E
I. SITE WORKS
Scope of Work:
1. Includes clearing, layout, and excavation
a. Wall Footings 4.80 cu.m
b. Column Footings 41.00 cu.m
c. Septic Tank 13.95 cu.m
Labor:
Excavation works 59.75 cu.m
Materials:
Assorted Form Lumber 800.00 bd.ft
Assorted CW Nails 6.00 kgs
Nylon Chord 5.00 rolls

Material Cost
Labor Cost
Total Cost
II. EMBANKMENT WORKS
Scope of Work:
1. Embankment for buildable areas
2. Backfilling Works

Materials:
Filling Materials - to elevate the buildable area by 0.20m 90.00 cu.m

Material Cost
Labor Cost
Total Cost
III. REINFORCED CONCRETE WORKS
Scope of Work:
1. Construction of reinforced concrete works system with deformed bars
and specification, includes the following:
a. Column Footings
b. Column
C. Floor Slab on grade
Slab thickness shall be 0.15m with temperature bars spaced 0.40m
bothways on top of gravel bed throughout.
d.Roof beam
e. Lavatory Counter
f. Lintel beam
NOTE: Use Grade 60 Reinforcing Steel and 28 days curing period for
concrete.

Materials:
Portland Cement 120.00 cu.m
Sand 48.00 cu.m
Gravel 62.00 cu.m
GI Tie Wire #16 50.00 kgs
Deformed Bar 10mmØ x 6m 720.00 lgths
Deformed Bar 12mmØ x 6m 320.00 lgths
Deformed Bar 16mmØ x 6m 380.00 lgths
14" Cut- Off Blade 50.00 pcs

Material Cost
Labor Cost
Total Cost
IV. STEEL TRUSS, ROOF FRAMING & ROOFING
Materials:
2" x 2" x 6mm THK. Angle Bar 20.00 pcs
1-1/2" x 1-1/2" x 6mm THK. Angle Bar 15.00 pcs
2" x 4" x 1.50mm THK. C- Purlin 40.00 pcs
2" x 6" x 1.50mm THK. C- Purlin 8.00 pcs
10mm Round Bar 25.00 pcs
Welding Rod Special 30.00 kgs
Epoxy Primer- Gray 4.00 gals
Lacquer Thinner 10.00 bottles
Baby Roller 10.00 pcs
2" Paint Brush 8.00 pcs
3" Paint Brush 10.00 pcs
2" x 2" x 1.50mm THK. Tubular, B.I 25.00 pcs
1-1/2" x 1-1/2" x 1.50mm THK. Tubular, BI 50.00 pcs
Welding Rod Special 15.00 kgs
Grinding Disc for Metal 30.00 pcs

Rib Type Roofing, Long Span 156.00 lm


Pre. Fab. Gutter 6.00 pcs
Pre. Fab. Flashing Gutter 20.00 pcs
2-1/2" Tekscrew 1500.00 pcs
Vulcaseal 3.00 lits
5/32 x 3/4 Blind Rivet 3.00 box
Material Cost
Labor Cost
Total Cost
LDG.

UNIT AMOUNT
PRICE

450.00 26,887.50

21.00 16,800.00
80.00 480.00
50.00 250.00

Material Cost 17,530.00


Labor Cost 33,899.50
Total Cost 51,429.50

250.00 22,500.00

Material Cost 22,500.00


Labor Cost 9,000.00
Total Cost 31,500.00
950.00 114,000.00
950.00 45,600.00
950.00 58,900.00
67.00 3,350.00
147.00 105,840.00
212.00 67,840.00
355.00 134,900.00
750.00 37,500.00

Material Cost 567,930.00


Labor Cost 227,172.00
Total Cost 795,102.00

1300.00 26,000.00
950.00 14,250.00
450.00 18,000.00
550.00 4,400.00
180.00 4,500.00
190.00 5,700.00
750.00 3,000.00
450.00 4,500.00
65.00 650.00
45.00 360.00
55.00 550.00
750.00 18,750.00
600.00 30,000.00
190.00 2,850.00
250.00 7,500.00

490.00 76,440.00
550.00 3,300.00
550.00 11,000.00
2.50 3,750.00
150.00 450.00
420.00 1,260.00
Material Cost 237,210.00
Labor Cost 94,884.00
Total Cost 332,094.00
V. MASONRY WORKS
Scope of Work:
1. Construction of wall/zocallo footing with deformed bars
a. Wall Footing - 0.40m x 0.15m x 40 lin.m

2. Erecting of CHB walls/zocallo


3. Cement-plastering smooth-finish of all exposed
NOT
Plastering and finishing of concrete surfaces includes fashioning of
E:
exterior window mouldings and window sill rabbets.

Materials:
Portland Cement 68.00 sq.m
Mix Sand (Mortar) 10.00 cu.m
Fine Sand (Paste) 12.00 cu.m
GI Tie Wire #16 10.00 kgs
Deformed Bar 10mmØ x 6m 150.00 lgths
Deformed Bar 12mmØ x 6m 42.00 lgths
Hacksaw Blade 10.00 pcs
Concrete Hollow Block 4" x 8" x 16" 600.00 pcs
Material Cost
Labor Cost
Total Cost
VI. CARPENTRY WORKS
Scope of Work:
1. Installation of Interior Ceilings
2. Formworks and Scaffoldings

Materials:

Hardiflex 3.5mm x 4' x 8' 80.00 shts


Metal Furring Double 0.400mm x 3/4" x 2" x 5m 150.00 lgths
Carrying Channel 0.400mm x 3/4" x 2" x 5m 80.00 lgths
Metal Wall Angle 0.400mm x 1" x 1" x 8' 50.00 lgths
W-Clip 750.00 pcs
Hacksaw Blade 15.00 pcs
Alum. Blind Rivets 1/8" x 3/8" 10.00 box
Concrete Nail 1" 3.00 kgs
Masonry Drill Bit 1/8" 30.00 pcs
Metal Drill Bit 1/8" 30.00 pcs
Metal Screw 1" and PVC Tox 250.00 pcs
FORMWORKS AND FALSEWORKS (for Columns,
Beams and Cover Slabs)
1/2" THK. Phenolic Board 75.00 pcs
Coco Lumber 2" x 2" x 10' 800.00 bd.ft
Coco Lumber 2" x 3" x 10' 900.00 bd.ft
CW Nail 1" 2.00 kgs
CW Nail 2-1/2" 2.00 kgs
CW Nail 4" 2.00 kgs
Concrete Nail 4" 2.00 kgs
Material Cost
Labor Cost
Total Cost
VII. DOORS AND WINDOWS

Materials:
DOORS
D1 - (0.70m x 2.10m) PVC Door With Fix Louver (with 2.00 sets
WINDOWS
W2 -Sliding Window with powder coated frame 2.00 sets
(0.60 x 0.60m)
Material Cost
Total Cost
VIII. TILE WORKS
Scope of Work:
1. Tiling of Comfort Room
2. Tiling of Lavatory Counters
3. Tiling of 2nd Floor
Materials:

Unglazed Ceramic Tiles 400mm x 400mm (for CR 25.00 pcs


Glazed Ceramic Tiles 0.30 x 0.60 (for CR Wall and 60.00 pcs
Granite Tile 60cm x 60cm 150.00 pcs
Portland Cement 8.00 cu.m
Fine Sand 3.00 cu.m
Tile Grout (2 kgs) 5.00 packs
Tile Adhesive (25 kgs) 20.00 bag
PVC Tile Trim 9mm x 8' 10.00 lghts
Material Cost
Labor Cost
Total Cost
IX SEPTIC TANK
Scope of Work:
1. Construction of Septic Tank 1.70m wide x 3.10m
Both floors of Digestive Chamber and Leaching Well shall be cemented,
Provide air space by securing the water table to be
NOT Cement for plastering of interior walls shall be mixed with adequate water-
Concrete Covers shall be reinforced with rebars spaced
Location and Positioning of septic tank must be according to
depending on actual site conditions, must be as

Materials:
Portland Cement 12.00 cu.m
Sand 2.50 cu.m
Gravel 2.00 cu.m
GI Tie Wire #16 4.00 kgs
Deformed Bar 10mmØ x 6m 10.00 pcs
Deformed Bar 12mmØ x 6m 12.00 pcs
Hacksaw Blade 1.00 pc
Material Cost
Labor Cost
Total Cost
235.00 15,980.00
900.00 9,000.00
1,100.00 13,200.00
67.00 670.00
147.00 22,050.00
212.00 8,904.00
55.00 550.00
13.00 7,800.00
Material Cost 78,154.00
Labor Cost 31,261.60
Total Cost 109,415.60

480.00 38,400.00
125.00 18,750.00
135.00 10,800.00
65.00 3,250.00
5.00 3,750.00
55.00 825.00
420.00 4,200.00
60.00 180.00
250.00 7,500.00
250.00 7,500.00
2.00 500.00

480.00 36,000.00
21.00 16,800.00
21.00 18,900.00
70.00 140.00
70.00 140.00
70.00 140.00
70.00 140.00
Material Cost 167,915.00

Labor Cost 67,166.00


Total Cost 235,081.00

2,400.00 4,800.00

2,100.00 4,200.00

Material Cost 9,000.00


Total Cost 9,000.00

125.00 3,125.00
55.00 3,300.00
150.00 22,500.00
950.00 7,600.00
1,100.00 3,300.00
40.00 200.00
250.00 5,000.00
25.00 250.00
Material Cost 45,275.00
Labor Cost 18,110.00
Total Cost 63,385.00
e water-

950.00 11,400.00
900.00 2,250.00
900.00 1,800.00
58.00 232.00
147.00 1,470.00
212.00 2,544.00
55.00 55.00
Material Cost 19,751.00

Labor Cost 7,900.40


Total Cost 27,651.40
X ELECTRICAL WORKS
Scope of Work:
1. Supply and Installation of electrical conduits, wires
2. Supply and Installation of lighting fixtures and switches
3. Supply and Installation of conv.outlets and panel
Materials:
WIRES AND CONDUCTORS
3.5 sq.mm THHN Cu. Wire (Stranded), color black 3.00 box/15
2.0 sq. mm THHN Cu. Wire (Stranded), color black 2.00 box/15
2.0 sq. mm THHN Cu. Wire (Stranded), color green 2.00 box/15
PANEL BOARD AND DISCONNECTING SWITCH
Center Main Panel Board (bolt on type)
Main : 60AT, 40AF, 240V, 2P, 14 KAIC 1.00 assy
Circuit Breakers:
14 - 20AT, 240V, 2P, 12 KAIC
LIGHTING FIXTURES AND ACCESSORIES
Circular Lamp Light 8.00 pcs
15W LED Pinlight 24.00 pcs
Vertical Downlight Case for Pinlight 4" recessed type 24.00 pcs
One Way Switch and its complete accessories 5.00 pcs
Two Way Switch and its complete accessories 5.00 pcs
Three gang Convinience Outlet 5.00 pcs
PIPES/CONDUITS AND FITTINGS
Electrical Conduit Pipe (3m x 25mm D) 25.00 lenghts
Electrical Conduit Pipe (3m x 20mm D) 15.00 lenghts
Electrical Conduit Pipe (3m x 15mm D) 15.00 lenghts
BOXES
2" x 4" PVC Utility Box [High Impact & Heat Resistant] 20.00 pcs
4" x 4" PVC Junction Box [High Impact & Heat Resistant] 25.00 pcs
CONSUMABLES
Staple Wire ½”Ø 200.00pcs.
Staple Wire ¾”Ø 30.00 pcs.
Electrical Tape, Big 3.00 rolls
PVC Tox #8 1.00 box
PVC Tox #5 1.00 box
Metal Screw [Tox #8] 1.00 gro
Metal Screw [Tox #5] 1.00 gro
S-Blue Solvent Cement 200cc 2.00 cans
G.I. Tie Wire #14 2.00 kgs.
Mica Tube ½"Ø 6.00 mtrs
Mica Tube ¼"Ø 15.00 mtrs
Concrete Nail 2" 1.00 kg
Material Cost
Labor Cost
Total Cost
4,200.00 12,600.00
2,900.00 5,800.00
2,900.00 5,800.00
0.00
0.00
8,620.00 8,620.00
0.00
0.00
0.00
1700.00 13,600.00
350.00 8,400.00
280.00 6,720.00
150.00 750.00
250.00 1,250.00
250.00 1,250.00
0.00
125.00 3,125.00
105.00 1,575.00
88.00 1,320.00
0.00
30.00 600.00
45.00 1,125.00
0.00
3.00 600.00
4.00 120.00
55.00 165.00
120.00 120.00
85.00 85.00
145.00 145.00
110.00 110.00
120.00 240.00
75.00 150.00
24.00 144.00
16.00 240.00
90.00 90.00
Material Cost 74,744.00
Labor Cost 29,897.60
Total Cost 104,641.60
XI PLUMBING WORKS
Materials:
FIXTURES AND APPURTENANCES
Water Closet, Lever-type with complete tank fittings, 1.00 set
1/2"Ø Flexible Hose
Stainless Counter Sink 0.50m x 0.80m with Sink 2.00 sets
Stainless-Chrome Faucet 1.00 pcs
Stainless Floor Drain 4"x 4" with Strainer (for CR) 2.00 pc
Soap and Tissue Holders 1.00 set
CLEAN WATER PIPELINE
PE Pipe 1/2"Ø, sched. 40 80.00 mtrs
PVC Elbow 1/2"Ø x 90 ⁰ 5.00 pcs
PVC Tee 1/2"Ø x 1/2" 5.00 pcs
PVC Coupling 1/2"Ø 5.00 pcs
End Plug 1/2"Ø 5.00 pcs
US PP Gate Valve 1/2"Ø 3.00 pc
WASTEWATER PIPELINE AND VENT-THRU-ROOF
PVC Pipe S-1000 4"Ø x 10' 10.00 pcs
PVC Pipe S-1000 2"Ø x 10' 8.00 pcs
PVC Wye 4"Ø x 4"Ø 9.00 pcs
PVC Wye 2"Ø x 2"Ø 10.00 pc
PVC Reducer 4"Ø x 2"Ø 10.00 pc
PVC Bend 4"Ø x 90° 4.00 pcs
PVC Bend 2"Ø x 90° 10.00 pcs
PVC P-Trap 4"Ø 8.00 pcs
PVC P-Trap 2"Ø 8.00 pcs
PVC Clean-Out 4"Ø w/ Cover 5.00 pcs
SEPTIC TANK
PVC Pipe S-1000 4"Ø x 10' 2.00 lgth
PVC Tee 4"Ø x 4"Ø 6.00 pcs
PVC Clean-Out 4"Ø w/ Cover 1.00 pcs
Material Cost
Labor Cost
Total Cost
XII PAINTING WORKS
Scope of Work:
1. Painting of all masonry exposed surfaces (except for
2. Application of top coat paints (at least 2 coats) on
NO Apply putty evenly throughout walls. Apply two (2) topcoat
TE: coatings to even the application on all surfaces.
Materials:
MASONRY SURFACE - application on perimeter walls and
Concrete Neutralizer 2.00 gal
Premium Acrylic Latex Primer 2.00 tins
Premium Acrylic Latex Gloss 2.00 tins
Power Putty (applied evenly throughout walls and 3.00 gals
OTHER MISCELLANEOUS ITEMS
Tinting Color Latex 2.00 pints
Tinting Color (Oil) 2.00 pints
Sand Paper #120 20.00 pcs
Paint Roller w/ Tray 10.00 sets
Paint Brush 10.00 pcs
Material Cost
Labor Cost
Total Cost
8,000.00 8,000.00
0.00
3,500.00 7,000.00
550.00 550.00
450.00 900.00
480.00 480.00
0.00
18.00 1,440.00
85.00 425.00
75.00 375.00
75.00 375.00
30.00 150.00
450.00 1,350.00
0.00
750.00 7,500.00
650.00 5,200.00
95.00 855.00
85.00 850.00
85.00 850.00
84.00 336.00
62.00 620.00
95.00 760.00
95.00 760.00
72.00 360.00
0.00
750.00 1,500.00
95.00 570.00
72.00 72.00
Material Cost 41,278.00
Labor Cost 16,511.20
Total Cost 57,789.20
450.00 900.00
2,800.00 5,600.00
3,150.00 6,300.00
453.00 1,359.00
0.00
85.00 170.00
95.00 190.00
15.00 300.00
150.00 1,500.00
30.00 300.00
Material Cost 16,619.00
Labor Cost 6,647.60
Total Cost 23,266.60
PROJECT TITLE: PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.
SUMMARY OF COST ESTIMATE
ITE PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.
ITEM DESCRIPTION MATERIAL LABOR
I SITE WORKS 17,530.00 33,899.50
II EMBANKMENT WORKS 22,500.00 9,000.00
III REINFORCED CONCRETE WORKS 567,930.00 227,172.00
IV STEEL TRUSS, ROOF FRAMING & 237,210.00 94,884.00
V MASONRY WORKS 78,154.00 31,261.60
VI CARPENTRY WORKS 167,915.00 67,166.00
VII DOORS AND WINDOWS 9,000.00
VIII TILE WORKS 45,275.00 18,110.00
IX SEPTIC TANK 19,751.00 7,900.40
X ELECTRICAL WORKS 74,744.00 29,897.60
XI PLUMBING WORKS 41,278.00 16,511.20
XII PAINTING WORKS 16,619.00 6,647.60

TOTAL PROJECT COST 1,297,906.00 542,449.90


RPOSE BLDG.

TOTAL
51,429.50
31,500.00
795,102.00
332,094.00
109,415.60
235,081.00
9,000.00
63,385.00
27,651.40
104,641.60
57,789.20
23,266.60
1,840,355.90
1,840,355.90

You might also like