Bongabon 2 Storey
Bongabon 2 Storey
Bongabon 2 Storey
Title:
BOQ
IT ITEM DESCRIPTION QTY UNIT
E
I. SITE WORKS
Scope of Work:
1. Includes clearing, layout, and excavation
a. Wall Footings 4.80 cu.m
b. Column Footings 41.00 cu.m
c. Septic Tank 13.95 cu.m
Labor:
Excavation works 59.75 cu.m
Materials:
Assorted Form Lumber 800.00 bd.ft
Assorted CW Nails 6.00 kgs
Nylon Chord 5.00 rolls
Material Cost
Labor Cost
Total Cost
II. EMBANKMENT WORKS
Scope of Work:
1. Embankment for buildable areas
2. Backfilling Works
Materials:
Filling Materials - to elevate the buildable area by 0.20m 90.00 cu.m
Material Cost
Labor Cost
Total Cost
III. REINFORCED CONCRETE WORKS
Scope of Work:
1. Construction of reinforced concrete works system with deformed bars
and specification, includes the following:
a. Column Footings
b. Column
C. Floor Slab on grade
Slab thickness shall be 0.15m with temperature bars spaced 0.40m
bothways on top of gravel bed throughout.
d.Roof beam
e. Lavatory Counter
f. Lintel beam
NOTE: Use Grade 60 Reinforcing Steel and 28 days curing period for
concrete.
Materials:
Portland Cement 120.00 cu.m
Sand 48.00 cu.m
Gravel 62.00 cu.m
GI Tie Wire #16 50.00 kgs
Deformed Bar 10mmØ x 6m 720.00 lgths
Deformed Bar 12mmØ x 6m 320.00 lgths
Deformed Bar 16mmØ x 6m 380.00 lgths
14" Cut- Off Blade 50.00 pcs
Material Cost
Labor Cost
Total Cost
IV. STEEL TRUSS, ROOF FRAMING & ROOFING
Materials:
2" x 2" x 6mm THK. Angle Bar 20.00 pcs
1-1/2" x 1-1/2" x 6mm THK. Angle Bar 15.00 pcs
2" x 4" x 1.50mm THK. C- Purlin 40.00 pcs
2" x 6" x 1.50mm THK. C- Purlin 8.00 pcs
10mm Round Bar 25.00 pcs
Welding Rod Special 30.00 kgs
Epoxy Primer- Gray 4.00 gals
Lacquer Thinner 10.00 bottles
Baby Roller 10.00 pcs
2" Paint Brush 8.00 pcs
3" Paint Brush 10.00 pcs
2" x 2" x 1.50mm THK. Tubular, B.I 25.00 pcs
1-1/2" x 1-1/2" x 1.50mm THK. Tubular, BI 50.00 pcs
Welding Rod Special 15.00 kgs
Grinding Disc for Metal 30.00 pcs
UNIT AMOUNT
PRICE
450.00 26,887.50
21.00 16,800.00
80.00 480.00
50.00 250.00
250.00 22,500.00
1300.00 26,000.00
950.00 14,250.00
450.00 18,000.00
550.00 4,400.00
180.00 4,500.00
190.00 5,700.00
750.00 3,000.00
450.00 4,500.00
65.00 650.00
45.00 360.00
55.00 550.00
750.00 18,750.00
600.00 30,000.00
190.00 2,850.00
250.00 7,500.00
490.00 76,440.00
550.00 3,300.00
550.00 11,000.00
2.50 3,750.00
150.00 450.00
420.00 1,260.00
Material Cost 237,210.00
Labor Cost 94,884.00
Total Cost 332,094.00
V. MASONRY WORKS
Scope of Work:
1. Construction of wall/zocallo footing with deformed bars
a. Wall Footing - 0.40m x 0.15m x 40 lin.m
Materials:
Portland Cement 68.00 sq.m
Mix Sand (Mortar) 10.00 cu.m
Fine Sand (Paste) 12.00 cu.m
GI Tie Wire #16 10.00 kgs
Deformed Bar 10mmØ x 6m 150.00 lgths
Deformed Bar 12mmØ x 6m 42.00 lgths
Hacksaw Blade 10.00 pcs
Concrete Hollow Block 4" x 8" x 16" 600.00 pcs
Material Cost
Labor Cost
Total Cost
VI. CARPENTRY WORKS
Scope of Work:
1. Installation of Interior Ceilings
2. Formworks and Scaffoldings
Materials:
Materials:
DOORS
D1 - (0.70m x 2.10m) PVC Door With Fix Louver (with 2.00 sets
WINDOWS
W2 -Sliding Window with powder coated frame 2.00 sets
(0.60 x 0.60m)
Material Cost
Total Cost
VIII. TILE WORKS
Scope of Work:
1. Tiling of Comfort Room
2. Tiling of Lavatory Counters
3. Tiling of 2nd Floor
Materials:
Materials:
Portland Cement 12.00 cu.m
Sand 2.50 cu.m
Gravel 2.00 cu.m
GI Tie Wire #16 4.00 kgs
Deformed Bar 10mmØ x 6m 10.00 pcs
Deformed Bar 12mmØ x 6m 12.00 pcs
Hacksaw Blade 1.00 pc
Material Cost
Labor Cost
Total Cost
235.00 15,980.00
900.00 9,000.00
1,100.00 13,200.00
67.00 670.00
147.00 22,050.00
212.00 8,904.00
55.00 550.00
13.00 7,800.00
Material Cost 78,154.00
Labor Cost 31,261.60
Total Cost 109,415.60
480.00 38,400.00
125.00 18,750.00
135.00 10,800.00
65.00 3,250.00
5.00 3,750.00
55.00 825.00
420.00 4,200.00
60.00 180.00
250.00 7,500.00
250.00 7,500.00
2.00 500.00
480.00 36,000.00
21.00 16,800.00
21.00 18,900.00
70.00 140.00
70.00 140.00
70.00 140.00
70.00 140.00
Material Cost 167,915.00
2,400.00 4,800.00
2,100.00 4,200.00
125.00 3,125.00
55.00 3,300.00
150.00 22,500.00
950.00 7,600.00
1,100.00 3,300.00
40.00 200.00
250.00 5,000.00
25.00 250.00
Material Cost 45,275.00
Labor Cost 18,110.00
Total Cost 63,385.00
e water-
950.00 11,400.00
900.00 2,250.00
900.00 1,800.00
58.00 232.00
147.00 1,470.00
212.00 2,544.00
55.00 55.00
Material Cost 19,751.00
TOTAL
51,429.50
31,500.00
795,102.00
332,094.00
109,415.60
235,081.00
9,000.00
63,385.00
27,651.40
104,641.60
57,789.20
23,266.60
1,840,355.90
1,840,355.90