Bill of Quantity
Bill of Quantity
Bill of Quantity
2 CONCRETE WORK
2.1 5cm thick lean concrete class C-5, under footing
2
and masonry foundation wall M 333.33 90.00 29,999.25
2.2 10cm thick reinforced concrete ground floor slab
in C-15 with minimum cement content of 280
2
kg/m3 well spread and leveled M 56.77 330.00 18,732.48
2.3 Reinforced concrete class C-30, with minimum
cement content of 360kg/m3 filled into form
work and vibrated around rod reinforcement.
Steel and form work measured separately.
a. In footings 3
M 212.23 2,300.00 488,138.20
b. In foundation column 3
M 9.60 2,300.00 22,080.00
c. In grade beam M3 54.58 2,300.00 125,534.00
2.4 Provide cut and fix in position sawn zigba wood
form work
a. To footing 2
M 398.58 240.00 95,659.20
b. To footing column 2
M 96.00 240.00 23,040.00
c. To grade beam 2
M 280.40 240.00 67,296.12
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
2.5 Reinforcement steel bars according to structural
drawings. Price includes cutting, bending,
placing in position & trying wires.
Diameter 8mm deformed bars kg 814.67 29.00 23,625.36
Diameter 10mm deformed bars kg 251.23 29.00 7,285.67
Diameter 12mm deformed bars kg 263.74 29.00 7,648.34
Diameter 16mm deformed bars kg 1,810.60 29.00 52,507.32
Diameter 20mm deformed bars kg 308.20 29.00 8,937.80
Diameter 24mm deformed bars kg 1,722.96 29.00 49,965.84
Diameter 28mm deformed bars kg 152.00 29.00 4,408.00
Total Carried to summary Birr ……………………………………………………………... 970,483.75
3 MASONRY WORK
3.1 50cm thick hard trachytic or equivalent stone
masonry foundation wall bedded in cement
3
mortar mix 1:3 M 27.84 760.00 21,154.60
Total Carried to summary Birr ……………………………………………………………... 21,154.60
Total (A)………………………………………………………
1,192,536.87 =
B. SUPER STRUCTURE
1 CONCRETE WORK
1.1 Reinforced concrete class C-30, with minimum
cement content of 360kg/m3 filled into form
work and vibrated around rod reinforcement.
a. In elevation column M3 88.18 2,300.00 202,823.17
b. In lintel, floor, and top tie beams 3
M 0.00 2,300.00 -
c. In stair case M3 0.00 2,300.00 -
1.2 Provide cut and fix in position sawn zigba wood
form work
a. To elevation column 2
M 1,442.46 240.00 346,189.62
b. To lintel, suspended, and top tie beams 2
M 2,260.20 240.00 542,447.40
c. To stair case 2
M 1,587.05 240.00 380,891.66
1.3 Reinforcement steel bars according to structural
drawings. Price includes cutting, bending,
placing in position & tying wires
Diameter 10mm deformed bars kg 1,722.01 29.00 49,938.26
Diameter 12mm deformed bars kg 1,853.90 29.00 53,763.02
Diameter 16mm deformed bars kg 2,124.95 29.00 61,623.48
Diameter 20mm deformed bars kg 4,135.78 29.00 119,937.62
Diameter 24mm deformed bars kg 34,526.28 29.00 1,001,262.12
Diameter 28mm deformed bars kg 156.36 29.00 4,534.44
Total Carried to Summary Birr …………………………….……………………….. 2,763,410.80
Total (B)………………………………………………………
13,789,785.61 =
A+B………………. 14,982,322.47