Introduction:
M/s. Total Environment Building Systems Pvt Ltd, Proposed construction
of Residential Villas at survey nos. 226/2, 227/1, 227/2, 228/1, 228/2,
228/3,229,230/1,230/2,230/3,230/4,230/5,230/6, 231/3,231/2,239/2B,
240/1,240/2,241,242/1,242/2, 244/2,245/1,245/2,246(P),353, 354/1A,
354/1B, 354/2 and 355(P) of Bettahalasur village, Jala Hobli, Bangalore
North Taluk, of Bettahalasur, Village Jala Hobli, Bangalore North Talluk,
Karnataka with a view to conserve fresh water resources and adopt re-
use measures. They propose to set up a water pollution control and re-
use system for the wastewater generated from Development. The only
sources of wastewaters are from toilets, kitchen etc., in the complex
and therefore domestic in nature.
Water demands for above facilities are derived based on the per
capita demand, specified in National Building Code of India-Part IX.
Accordingly, the overall water demand works out to be 142 cum/day,
95% of which is generated as sewage. Hence, the overall sewage
generated shall be 145 cum/day (142 cum + 3 cum shock load). The
breakup of the water demand is as enlisted in the below table.
2
Process Description:
SBR systems have five steps in common that are carried out in
sequence as follows
- Fill
- React (aeration)
- Settle (sedimentation/clarification)
- Draw (decant)
- Idle
This report details the following from the proposed facility. Collection,
Treatment and reuse of Domestic Effluents;
3
Water Demand Calculation
STP
Capacity 142 KLD
Shock load 3 KLD
145 KLD
Say 145 KLD
5
Irrigation Water Demand Zone 1
6
3 Villas-Roof
a V30D 175.68
b V30A 176.95
c V30B 181.31
d V30C 185.66
e V50A 243.14
160457.44
4 Common area landscape
a Block 1 1614.00
b Block 2 606.00
c Block 3 1198.00
d Block 4 538.00
e Block 5 644.00
f Block 6 1178.00
g Block 7 287.00
h Block 8 344.00
i Block 9 684.00
j Block 10 568.00
k Block 11 148.00
l Block 12 163.00
m Block 13 0.00
n Block 21 208.00
7
p Block 15 296.00
r BLOCK 31 1092.00
s PARK & OPEN SPACE 7110.00
83390.00
Landscape area-
5 311296 46694 357991
Residential units
8
Water Balance Chart - Residential Block Zone 1
9
QUALITY OF RAW & TREATED DOMESTIC SEWAGE
BOD5 : 250-350mg/L
COD : 600-800mg/L
SS : 400 mg/L
E coli : 10MPN
PH : 6.5 – 9.0
TSS : < 20 mg /L
10
SBR TECHNOLOGY
11
Design Details of Sewage Treatment Plant:
Total quantity of raw effluent = 145 m3/day = 6.04 m3/hr
Standard conditions: BOD5 @ 270 C = 250 mg / L
Expected BOD5 reduction:
1. Avg. Influent BOD5 = 200 mg/L
2. BOD5 reduction in SBR =95 %
Therefore BOD5 at the outlet of secondary treatment =15 mg/L
3. BOD5 reduction with tertiary treatment like Coagulation, filtration and
disinfection = < 10 mg/L
12
Equalization Tank / Collection Tank
The flow from the bar screen chamber is let into the equalization tank. In
order to homogenize the quality of wastewater, as well as to feed
wastewater at a uniform rate to the rest of the treatment plant, an
equalization tank is proposed. In order to mix the contents, as well as to
provide a degree of preparation, diffused aeration by means of membranes
and blowers are proposed.
13
Considered following design data
•
Inlet BOD= 350 mg/L
• Outlet BOD= < 10
•
BOD removed= 335 mg/L
O2 for N removal:
15
Kg O2 required for NH3-N removed = 14.007 kg/d
2.86 kg O2 released during de-nitrification (standard)
16
Standard oxygen tranfer efficiency
• of diffuser per meter depth = 5.60% per m
• Liquid level of aeration basin = 6 m
• Height at which diffuser are kept = 0.4 m
• Effective aeration depth = 5.6 m
SOTE(Standard oxygen transfer
efficiency) the above aeration
• depth = 31.36
• Fraction of O2 in air = 23.2 %
• Specific gravity of air = 1.204
• Air required at field condition per basin (consider 4 basin)
= 21.1 kg
= 240.546 Nm3 /hr/basin
Hours of aeration time per basin per
• day = 12 hrs/d/basin
• Air required per hours per basin = 20.05 Nm3 /hr/basin
Number of operating blower any Nm3
• time in Basin-2 = 10.02 /hr
Air Blowers:
BOD load sequencing /Aeration
tank = 50750 mg/L
= 50.75 Kg/day
(2kgs of oxygen is required for every Kg of BOD removal)
Oxygen is required in kg/day = 101.5 Kg/day
Volume of air required:
Assumption:
15% of oxygen transfer efficiency of aeration equipment (for Diffuser)
Factor of safety 2.0 is taken to determine the actual design for
sizing the blowers air contains 23.20% of O2 by weight & density
of air is 1.2
Total air requirement:
TAR = (O2 X 2 )/(1.2*0.232)
= 729.2 m3 /day
Actual air requirement for diffuser:
AAR = (TAR/0.15) m3 /day
AAR = 4861.1 m3 /day
Blower capacity = 210.00 m3 /hr
Consider 20% excess assuming for air requirement in the equalization tank
= 252 m3 /hr
17
= 252 250
Provide Air Blowers capacity 252 2W & 1 S
Pre-Filtration tank:
Pre-Filtration Tank is also provided to hold water, before filtration process.
Tank Volume (Around 20 %) = 29 Cum
Size:
(E.D+FB
Assume depth: 2.5 m 0.5m)
Area 11.60 m2
Assume Length: 5.0 m
Size of the Pre-filtration tank 5.00 2.32 2.50
Hence, required Volume of the
Tank= 5m X 3m X 2.5m (E.D+FB 0.5m)
The wastewater after biological treatment still contains some solids, colour, odour and
harmful micro-organisms. The pressure sand filter and activated carbon filter are used
to remove the solids and colour. The disinfection process is used to remove the micro-
organisms and odour.
Pressure sand filter with various grades of pebbles and sand media help in the
removal of residual suspended solids. The filter will be operating in the pressure range
of 3-3.5 kg/cm2.
18
Activated Carbon Filter
Chlorinator
Sodium Hypochlorite is used as disinfectant for treated water. This is available in solution
form with 12% to 15% of chlorine. Contact period of 15 to 30 min is specified with chlorine
residual to be minimum to keep the coliform count under control.
Hence provide 100 - 200 L Tank with 4 - 10 LPH dosing Pump and required dosing can be
adjusted as per requirement.
Final Treated Water Tank is also provided to hold Filtered water, before pumping to
gardens, and toilet flushing purpose. Online chlorination shall be done before pumping for
end use.
Tank Volume (One day storage) = 145 Cum
Size:
Assume depth: 3 m (FB 0.3E.D)
Area 48.33 m2
Assume Length: 15.0 m
Size of the Final Treated water tank 15.00 3.22 3.00
15m X 4m X 3m (FB
Hence, required Volume of the Tank= 0.3E.D)
19
Pumps
1. Sewage transfer pump -2nos
Capacity: 20klh @ 15m head
Solid handling Size: up to 20 mm
Duty: to Pump the Sewage from the equalization tank to SBR tank
2. Sludge transfer pump- 2 nos
Capacity: 10klh @ 35m head
Solid handling Size: up to 20 mm
Duty: to pump the sludge from the SBR tank to sludge holding tank and from there dried
using mechanical filter press.
3. Filter feed pump -2 nos
Capacity: 20 klh @ 35m head
Solid handling Size: up to 5 mm
Duty: to Pump the Pre-filter water from Pre-filter tank to PSF & ACF.
List of Structures:
Sl.No. Description Qty Dimension
1.0 m X 1.0 m X 0.6 m+F.B. 0.3m
Bar Screen
1 Chamber 1
2 Equalization Tank 1 5m X 2.9m X 2.5m (E.D)
5m X 2m X 2.5m (E.D+FB 0.5m)
Sequential Batch
3 Reactor 1
3m X 2m X 3m (E.D)
20
Flow diagram of Sewage Treatment Plant (SBR) of 145 KLD Capacity
Equalization
Tank
SBR Tank
To PSF
Filter Press
Disposal
ACF
Disinfectant
21
Detailed Feasibility Report
On
For
for
1
Introduction:
M/s. Total Environment Building Systems Pvt Ltd, Proposed construction
of Residential Villas and Clubhouse at survey nos. 226/2, 227/1, 227/2,
228/1,228/2,228/3, 229,230/1,230/2, 230/3,230/4, 230/5, 230/6, 231/3,
231/2, 239/2B, 240/1, 240/2, 241, 242/1, 242/2, 244/2, 245/1, 245/2,
246(P), 353, 354/1A, 354/1B, 354/2 and 355(P) of Bettahalasur village,
Jala Hobli, Bangalore North Taluk, Karnataka with a view to conserve
fresh water resources and adopt re-use measures. They propose to set
up a water pollution control and re-use system for the wastewater
generated from Development. The only sources of wastewaters are
from toilets, kitchen etc., in the complex and therefore domestic in
nature.
Water demands for above facilities are derived based on the per
capita demand, specified in National Building Code of India-Part IX.
Accordingly, the overall water demand works out to be 92 cum/day,
95% of which is generated as sewage. Hence, the overall sewage
generated shall be 95 cum/day (93 cum + 2 cum shock load). The
breakup of the water demand is as enlisted in the below table.
2
SBR operation the processes are carried out sequentially in the same
tank.
Process Description:
SBR systems have five steps in common that are carried out in
sequence as follows
- Fill
- React (aeration)
- Settle (sedimentation/clarification)
- Draw (decant)
- Idle
This report details the following from the proposed facility. Collection,
Treatment and reuse of Domestic Effluents;
3
RESIDENTIAL BLOCK ZONE 2 + Clubhouse
Sewage
No. of Per Capita
Sr. No. of Flushing Domestic Total Water Generated in L
Description persons Population Demand
No. Units Demand Demand Demand (95% of total water
per villa (LPCD)
demand )
CLUBHOUSE
Sewage
Generated
Per Capita
Sr. Flushing Domestic Total Water in L
Area in Sq. m Population Demand
No. Demand Demand Demand (95% of total
(LPCD)
water
demand )
5
Irrigation Water Requirement for Zone 2
2 Villas-Terrace
gardens
a V30D 0.00
b V30A 0.00
c V30B 0.00
d V30C 0.00
e V50A 9.46
1371.85
3 Villas-Roof
a V30D 175.68
b V30A 176.95
c V30B 181.31
d V30C 185.66
e V50A 243.14
106095.16
4 Common area
landscape
6
Block 16 504.00
Block 17 745.00
Block 18 451.00
Block 19 582.00
Block 20 350.00
Block 23 1565.00
Block 24 530.00
Block 25 980.00
Block 26 812.00
Block 27 465.00
Block 28 0.00
Block 29 0.00
Block 30 979.00
BLOCK 32 540.00
PARK & OPEN 11041.91
SPACE
CA 9075.46
11041.91 143101.85
5520.955
Landscape area-
5 296219 44433 340651
Residential units
and Clubhouse
7
Water Balance Chart - Residential Block Zone 2 & Clubhouse
8
QUALITY OF RAW & TREATED DOMESTIC SEWAGE
BOD5 : 250-350mg/L
COD : 600-800mg/L
SS : 400 mg/L
E coli : 10MPN
PH : 6.5 – 9.0
TSS : < 20 mg /L
9
SBR TECHNOLOGY
10
Design Details of Sewage Treatment Plant:
11
Equalization Tank / Collection Tank
The flow from the bar screen chamber is let into the equalization tank. In
order to homogenize the quality of wastewater, as well as to feed
wastewater at a uniform rate to the rest of the treatment plant, an
equalization tank is proposed. In order to mix the contents, as well as to
provide a degree of preparation, diffused aeration by means of membranes
and blowers are proposed.
Flow : 95 cum
20 hours
Average flow: 4.75 cum/hr
Peak factor: 2.5
Peak flow: 11.875 cum/hr
Provide holding capacity of Min. 2 hours
Capacity : 23.75 cum
Size:
Assume depth: 2.5 m (E.D)
Area 9.5 m2
Aeration: Coarse Bubble Diffusers
Assume Length: 5.0 m
Size of the Equalization Tank: 5.0 1.9 2.5
5m X 1.9m X 2.5m
Hence, required Volume of the Tank= (E.D)
Provide tank of 23.75cum capacity
12
Considered following design data
13
Q= V / T
Q= 14/13
Q= 1.1 m3 /hr
Providing recirculation ratio (Qr) of 25 % of
flow rate
Flow rate to anoxic zone to Q+
each basin= Qr
= 1.1+(0.25 X1.1)
= 1.3 m3
14
Determination of O2 required at given flow condition
O2 for BOD removal
• 1.2 kg O2/kg BOD
• Inlet BOD= 350 mg/L
• Outlet BOD= < 10
• BOD removed= 335 mg/L
O2 for N removal:
15
2.86 Kg O2 released during
denitrification = 1.6 kg/d
16
Standard oxygen transfer efficiency
of diffuser per meter depth = 5.60% per m
Liquid level of aeration basin = 6 m
Height at which diffuser are kept = 0.4 m
Effective aeration depth = 5.6 m
SOTE(Standard oxygen transfer
efficiency) the above aeration
depth = 31.36
Fraction of O2 in air = 23.2 %
Specific gravity of air = 1.204
Air required at field condition per basin (consider 4 basin)
= 13.9 kg
= 158.898 Nm3 /hr/basin
Hours of aeration time per basin per
day = 12 hrs/d/basin
Air required per hours per basin = 13.24 Nm3 /hr/basin
Number of operating blower any Nm3
time in Basin-2 = 6.62 /hr
Air Blowers
BOD load sequencing /Aeration
tank = 33250 mg/L
= 33.25 Kg/day
(2kgs of oxygen is required for every Kg of BOD removal)
Oxygen is required in kg/day = 66.5 Kg/day
Volume of air required:
Assumption:
15% of oxygen transfer efficiency of aeration equipment (for Diffuser)
Factor of safety 2.0 is taken to determine the actual design for
sizing the blowers air contains 23.20% of O2 by weight & density
of air is 1.2
Total air
requirement:
TAR = (O2 X 2 )/(1.2*0.232)
= 477.7 m3 /day
Actual air requirement for diffuser:
AAR = (TAR/0.15) m3 /day
AAR = 3184.9 m3 /day
Blower capacity = 140.00 m3 /hr
Consider 20% excess assuming for air requirement in the equalization tank
= 168 m3 /hr
17
= 56
Provide Air Blowers capacity 100 2W & 1 S
Pre-Filtration Tank:
The wastewater after biological treatment still contains some solids, colour,
odour and harmful micro-organisms. The pressure sand filter and activated
carbon filter are used to remove the solids and colour. The disinfection
process is used to remove the micro-organisms and odour.
Pressure sand filter with various grades of pebbles and sand media help in the
removal of residual suspended solids. The filter will be operating in the
pressure range of 3-3.5 kg/cm2.
18
Activated Carbon Filter
The recommended ACF dimension is 1.3 m dia and height 1.5 m. Suitable
designed backwashing system is adopted.
Chlorinator
Hence provide 100 - 200 L Tank with 4 - 10 LPH dosing Pump and required
dosing can be adjusted as per requirement.
Final Treated Water Tank is also provided to hold Filtered water, before
pumping to gardens, and toilet flushing purpose. Online chlorination shall be
done before pumping for end use.
Sludge Holding
19
Tank Volume = 9.5 Cum
Size:
Assume depth: 3 m (E.D)
Area 3.17 m2
Assume Length: 3.0 m
Size of the Sludge Holding tank 3.00 1.06 3.00
Hence, required Volume of the Tank= 3m X 1m X 3m (E.D)
Pumps
1. Sewage transfer pump -2nos
Capacity: 20klh @ 15m head
Solid handling Size: up to 20 mm
Duty: to Pump the Sewage from the equalization tank to SBR tank
2. Sludge transfer pump- 2 nos
Capacity: 10klh @ 35m head
Solid handling Size: up to 20 mm
Duty: to pump the sludge from the SBR tank to sludge holding tank and
from there dried using mechanical filter press.
3. Filter feed pump -2 nos
Capacity: 20 klh @ 35m head
Solid handling Size: up to 5 mm
Duty: to Pump the Pre-filter water from Pre-filter tank to PSF & ACF.
List of Structures
20
Flow diagram of Sewage Treatment Plant (SBR) of 95 KLD Capacity
Equalization
Tank
SBR Tank
To PSF
Filter Press
Disposal
ACF
Disinfectant
21