1 Mobilization 2 Camping: Cacale
1 Mobilization 2 Camping: Cacale
1 Mobilization 2 Camping: Cacale
Supply and Constract barbed wire fencing fixed to 2.5 m long of all seasened
8.8.1 ecylaptuos poles spaced every 1.5m and 30cm wire spacing including all necessary m 19.80
materials and incidental works as per the drawing[pm=2(5.5+4.4)=19.8m]
266.62 5,279.08
8.8.2 Supply and fix Corregated iron sheet gate 2.1*1.2 m with lock and latch No 1.00 2,322.86 2,322.86
Total for one water point 77,972.40
9 pipe Line (from pond to water point and cattle trough)
9.1 Earth Work
9.1.1 Route selection, surveying and installation of permanent bench mark Ls By Zone office
9.1.2 Trench Excavation to depth of 80 cm and 60 cm width M3 By community
9.2 Supply and Installation of HDPE Pipes and Fittings with necessary accessories
a OD 63mm (PN 16) m 120 178.20 21,384.00
9.3 HDPE Fittings -
9.3.1 HDPE-GS Female Adapter (PN16) -
a OD63mmX2 1/2 '' Pcs 3 433.71 1,301.13
9.3.2 HDPE-GS Male Adapter(PN16) -
a OD63mmX2 1/2 '' Pcs 2 433.71 867.42
9.3.3 90o compression Elbow (PN 16) -
a OD63mmX63mm Pcs 4 670.00 2,680.00
9.3.4 Compression straight coupling (PN16) -
a OD63mmX63mm Pcs 3 560.00 1,680.00
9.3.5 90o Compression Tee (PN 16) -
a OD63mmX50mmX63mm Pcs 3 980.00 2,940.00
9.3.6 HDPE Compression Reduccer(PN16) -
a OD63mmXOD50mm Pcs 3 500.00 1,500.00
9.3.7 HDPE Nipples(PN16) -
a OD 63mm Pcs 4 580.00 2,320.00
9.4 Supply and install water hose strainer filter No. 1 2,000.00 2,000.00
Construct 30cm thick masonry valve chamber with an internal dimension of
10 No. 1 5,500.00
(100L x 100 W x 80H) cm with iron sheet metal cover 5,500.00
Construct 30cm thick masonry intake chamber with an internal dimension of
11 No. 1 4,000.00
(100L x 100 W x 80H) cm with no cover 4,000.00
12 Construction of Steps(stair case)
Construction of Plain or Ordinary Concrete (1:2:4) Steps for pond interside slope
12.1 m3 12.768 4,000.00
face as per the drawing 51,072.00
12.2 Provide and fix formwork timber m2 9.6 654.14 6,279.74
Sub Total 103,524.29
TOTAL COST 6,434,716.60
Add 15% VAT 965,207.49
Grand total of the project 7,399,924.09
BILL OF QUANTITY OF GELA EARTHEN POND FOR WATER SUPPL PROJECT
Construction of Grade C- 20 concrete side wall 10 cm thick & 25 cm high wall plastered
6.2.1 m3
with cement mortar 1:3 Both face with dimention 3.0 m wide & 25 m long
6.2.2 Semi dressed stone pavement pointed with cement mortar 1:3 all round the cattle trough m2
6.2.3 Back Fill excavated area above the concrete cover over filter media with clay m3
Casting Grade C-20 with minimum cement content ,of 320kg/m3 for the Cattletrough
6.3.2 m3
Nominal reinforced Base Slab Filled into formwork
6.3.3 External and internal plastering of the body of the cattle trough m2
6.3.4 Construction of HCB wall manhole with cover having internal Plan area No
oncrete with
7.3.210mm dia reinforcement bar spaced @250mm c/c on both ways over the lean
M3 concrete and provi
7.3.3 Casting mass concrete for the edges of the washing escarpments M3
7.3.4 Supply, cut, bend and fix in position reinforcement bars Of Ф10mm Kg
7.3.5 Fixing of good quality wooden or metal form work firmly with strong M2
strutting & tight to avoid bleeding & bulking out
7.4 Finishing and miscellaneous works
4.4.1 Supply & Install all necessary pipes & fittings for drainage with all Ls
necessary accessories as per the Design Drawings
7.4.2 Apply 25mm thick cement screed mix 1:3 for floor base of washing M2
basin with 1% sloping towards the drainage.
Sub total - Carried Forward
Sub total - Brought Forward
7.4.3 Plastering the exposed faces of concrete works with three coats of M2
cement sand mortar of mix 1:3
7.4.4 Pointing the whole external face of the masonry wall with cement M2
mortar mix 1:4
7.4.5 Construction of gravel packed soak away pit to downstream of the
washing basin having 700mm dia. and 600mm depth with proper
drainage canal connection work No
7.5 Construction of 1.75m high fence of barbed wire fixed to eucalyptus
posts diameter 120mm placed 125cm c/c buried in concrete C-15 to a
depth of 30cm in 50cm dug holes with corrugated galvanized iron
sheet single leaf gate
m
Total for one Washing Basin
TOTAL COST
Add 15% VAT
Grand total of the project
QNTY UNIT PRICE TOTAL PRICE (Br)
1.8
3
16
30
1
19600 by Community
18,498.00
12,332.00
8,712.50
150 by Community
157.5
101.9
5
110
15 by Community
500
28.8
110
40
5
10
10
12
75
10
10
26
10
10.4
1
1
9.6
4.8
0.9
1.65
4.4
1.7
4.4
0.44
0.68
21
2.2
2.2
20