Note:
1. Amount of labour and materials for usage for MDL +6 foundation in Type A soil is same as MDL + 0 foundation in Type A soil as per the
standard CEB foundation drawing. This payment is paid as per the contractors claim in Interim Bill No.02. Invoice No. GSE-1980
2. Amount of labour and materials for usage for MDM +3 foundation in Type C soil is same as MDM + 0 foundation in Type C soil as per the
standard CEB foundation drawing. This payment is inculded in the Sub Total - Foundation Work of this payment certificate.
3. Overall financial impact of this variation is negligible from the original bid value because new rate is equal to an already approve rate.
Therefore the earlier MPC approved total bid value of Rs. 75,927,970.00 is not exceeded.
I recommend the payment of Rs. ……………………….…………. to the contractor as the Interim Payment No.3 of
bid no. CE(P&HM)DD1/T/SC/2016/01. (Job No. 596/1481/MV/2017/01)
…………………………..
Chief Engineer (Line Construction & Maintenance) DD1
…………………………..