Talking Points for Lender’s Conference

(January 18, 2019)


 Earliest project completion is our priority
 Simple cycle operational before summer is also our priority
 Govt. of Punjab commits to extend full support to this project including but not limited to the
following:
a) Additional equity, if required (2 billion)
b) Working capital 20% part (6 billion)
c) Standby Letter of Credit (SBLC) guarantee of 20% (7.6 billion)
d) Up to financial close by March 2019 LC retirements (10 billion)
 Support of entities from Federal Government stands available:
a) Sui Northern Gas Pipelines Limited (SNGPL)
 Gas Supply Agreement (GSA) with SNGPL in final stage
 Gas pipeline construction completion March-April 2019
 Temporary gas pipeline connection by end February 2019
 Banks concerns on SBLC issue of three 3 RLNG (QATPL and NPPMCL) projects
has been taken up with concerned (Ministry of Energy and SNGPL) for amicable
solution
b) Central Power Purchase Agency (CPPA)
 Power Purchase Agreement (PPA) with CPPA in final stage
 Reimbursement Agreement (RA) with SNGPL being processed
 Installation of metering system, witnessing of tests etc. by NTDC in hand
 Banks concerns on CPPA outstanding payments for QATPL is being taken care
and in coming day better releases will be witnessed
 CPPA ensures that capacity payments for QATPL will be ensured without any
default
c) Irrigation department is helping in canal intake/outfall structures construction
d) Security department is fully engaged for foolproof security
 We expect banks should fully and expeditiously move forward for financial close by end of
February/March 2019 for PTPL as well as to extend financial support towards additional
working capital and SBLC provisions for QATPL