7.LT Panel
7.LT Panel
7.LT Panel
1. Check all the CT secondary wires are 1. Don’t touch any cables and the kit
isolated when it is in running condition.
2. Check the calibration due of the test 2. Don’t touch any bushing while
equipment doing the tests
3. Breaker should be in open condition 3. Don’t keep the breaker in service
and in test position. and on position
4. Ensure zero resistance when line 4. Don’t test with damaged cables and
and earth are shorted and switched improper clips
on to know the zero value for the 5. Don’t work in wet (rainy) conditions
proper working of kit. 6. Don’t lose your concentration while
5. Keep some distance while doing the testing.
test.
6. After Insulation resistance test
completion, note down the values
and discharge the CT terminals and
remove the test cables
7. Ambient temperature must be
noted.
4.3.6 Polarity test for CT:
1. Connect the secondary S1 terminal to galvanometer positive terminal
and S2 to the negative terminal
2. Touch the battery positive terminal to P1 in and negative terminal to
the P2 terminal at the CT primary winding Terminals
3. Check the deflection in the galvanometer
4. It must be in clock-wise direction
DO’S DONT’S
1. Check the connections as per the 1. Don’t use low batteries for testing
diagram. 2. Don’t apply the charge continuously
2. Check the CT secondary cable (apply single pulse).
continuity from CT secondary to CT
terminal block.
3. Check whether the battery is
charged or not
4. Verify the galvanometer in good
condition
4.3.7 Ratio test for CT
DO’S DONT’S
1. Apply the voltage in the primary 1. Don’t apply voltage across the
terminals only secondary terminal
2. Secondary side should be kept
open
4.3.14 Winding resistance test for PT:
1. Connect the multimeter leads to the CVT secondary winding
Terminals
2. Note down the winding resistance value
3. Repeat the above procedure for remaining cores
DO’S DON’Ts
1. Measure with calibrated 1. Measure the VT winding resistance
multimeters for individual cores
2. Note the ambient temperature 2. Primary winding resistance should
3. Remove the secondary terminals not be measured (Only the
to isolate the VT secondary)
4. Clean the secondary terminals 3. Loose connections should be
and measure the resistance avoided in the VT secondary
terminals.
4. Don’t measure the terminals with
dust in VT secondary terminals
4.3.15 Continuity test for PT:
1. Connect the multimeter leads to the CVT secondary
winding Terminals
2. Observe the beep sound in multimeter
3. Repeat the above procedure for remaining cores
Do’s Don’ts
1. Personal Protective equipment 1. Unauthorized persons should not
(PPE) should be used while testing enter the testing premises.
2. Ensure the zero energy condition 2. Don’t change the kit probe in on
3. All the testing equipment must be condition. Switch off the kit after
connected to the proper earth line one each test
4. Ensure the all connections are in 3. Avoid contact with energized
tight after testing electrical circuits
5. Ensure all the supply is dead 4. Do not use the twisted testing
6. Before doing testing, discharge the cables
respective terminals 5. Never bypass fuses and circuit
7. Test equipment's to ensure zero breakers.
energy state before beginning the 6. Don’t use the joint cables while
work testing.
7. Avoid testing during rainy season.
8. Do not make connection changes
while testing
4.4 Control Measures
1. OCP for LT Panel is available with testing engineers
2. Ensure PTW system in place for the particular Panel
3. Ensure all supply to the equipment is dead
4. Unauthorized persons should not be allowed to
enter Testing area
5. Above 2mtr height Use proper plat form or ladder
for height work and wear safety belt
6. Barricade the testing area with warning tape
7. Proper supervision, conduct job specific toolbox
meeting and barricading the entire area
8. Calibrated equipment shall be used
9. Insulated hand tools shall be used
10. Avoid joints for power cable and supply has to be
taken via ELCB
11. Avoid Lone working
12. Use appropriate insulated hand gloves
5.0 Final Checks & Restoration of work area after
completion of work:
1. Disconnect the temporary supply and remove the
barricading tapes
2. Ensure no loose materials / tools are kept in and
around the area
3. Leave the place by keeping it tidy and clean