Testing and Commissioning On Transformer
Testing and Commissioning On Transformer
230/ 34.5/13.8 kV
100/133
YNyn0(d5)
12.24 @ 100 MVA BASE.
= HV side Voltage
= 230 1000 = 916 Ohms
HV side full load current
251
HV side Impedence/ Phase = HV side Impedence X % Impedence = 916 X 12.24 = 112 Ohms
100
HV side current / Phase
3.288<121.5 23.573<299.34
21.985
22.226
22.265
Polarity of
the neutral BCT was reversed at the protection panel to simulate the unstable
condition.