Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Circuit Breaker Testing SWP: 1 Purpose AND Scope

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

CIRCUIT BREAKER TESTING SWP

1 PURPOSE AND SCOPE


Provide guidelines for testing of circuit breakers. Details of specialised circuit breaker tests are not included in this SWP. Course Code 3131 Course Description Pole Testing for Safe Access (if required)

Additional Training Course Code 4445 4440 4430 Course Description Switching Operator and Authorised Switching Operator Assistant and Authorised Safe Entry to High Voltage Enclosures and Authorised

STAFFING RESOURCES
a) b) EFM competent in the use of test equipment. Safety Observer (required for all live work as defined in the ESO Code of Practice for Electrical Work).

Both are required to be trained in switchboard rescue and resuscitation and manual handling techniques. have appropriate Switching and Access authorisations for the roles they are required to perform and have the ability to assess and maintain relevant exclusion zones from exposed live electrical apparatus. hold current licences for any vehicles and equipment they may be required to operate.

DOCUMENTATION
CS000501F115. Daily / Task Risk Management Plan ES000901R102. Health and Safety Risk Control Guide SP0509R01 Circuit Breaker Testing Job Safety Analysis SP0509C01 Circuit Breaker Test Report SP0509C01R01 Circuit Breaker Sample Test Report SP0509C02 Circuit Breaker HV Withstand Test Report. SP0509C03 Circuit Breaker Testing Competency Assessment SP0506 Substation Primary Plant and Secondary Systems Field Testing SWP AS 1931 1996 High Voltage Test Techniques Parts 1 and 2 AS 2006 1986 High Voltage A.C. Switchgear and Controlgear Circuit Breakers for Rated Voltages Above 1,000V AS 2650 1986 High Voltage A.C. Switchgear and Controlgear Common Requirements

Required Training and Certificates Regulatory Training Course Code 2120 2130 2140 2160 Course Description Cardio-Pulmonary Resuscitation Low Voltage/Switchboard Rescue Pole Top Rescue (if required) EWP Rescue and Escape (if required)
Page 1 of 6

Check this is the latest Process Zone version before use.

Standard Work Practice SP0509 Ver 2

Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

CIRCUIT BREAKER TESTING SWP


AS 2467 1981 Maintenance of Electrical Switchgear Test Equipment Manual Circuit breaker Manual / Manufacturers Drawings 5.2. All work to be done with circuit breaker de-energised All of the tests described in this SWP should be carried out with the CB de-energised and appropriate control measures in place (eg barriers, matting) to prevent inadvertent contact with adjacent live plant or breaching exclusion zones. Furthermore, the P53 Operate the Network Process is applicable at all times for isolation and earthing. As described in Carry Out Field Testing SWP SP0506, particular safety risks applicable to Circuit Breakers include: Contact with high voltage at CB primary connections. High fault current at CB primary connections. Stored energy (eg charged spring) in the closing and tripping mechanism Initiation of other protection or control functions by change in state of circuit breaker auxiliary contacts

KEY TOOLS AND EQUIPMENT


Test Equipment within calibration date, tested and tagged Safety Barriers HVIA Operating Equipment PEDs, Live Line Tester, Class 0 gloves. All equipment to be inspected and confirmed within test date prior to use PPE including full-length protective cotton clothing, safety footwear, helmet. Additional PPE as required: brim for safety helmet, leather work gloves, class 00 gloves, hearing protection, safety eyewear, high visibility clothing when working on or near roadways. All PPE to be inspected and confirmed within test date (where applicable) prior to use Sun protection to be used when working outdoors

5.3. Record identification details. Manufacturers name, manufacturers type description and manufacturers serial number: Plant number; Description, ie. dead tank, live tank etc; Rated voltage and insulation level; Rated nominal and short-circuit current and duration; Rated operating sequence; Interrupting medium; Specialised requirements such as:
Standard Work Practice SP0509 Ver 2

TASK STEPS
5.1. Carry out an on site risk assessment Prior to performing this activity any hazards associated with prerequisite tasks at the worksite shall be identified and assessed with appropriate control measures implemented and documented in accordance with the Daily/Task Risk Management Plan CS000501F115 and using reference document Health and Safety Risk Control Guide ES000901R102. If any risks cannot be managed or reduced to an acceptable level, do not proceed with the task and seek assistance from your Supervisor.

Check this is the latest Process Zone version before use.

Page 2 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

CIRCUIT BREAKER TESTING SWP


Rated Transitional Recovery Voltage envelope, Rated Out of Phase Breaking Current, Rated Cable Charging Breaking Current, Rated Capacitor Bank Breaking and Inrush Making Currents, Rated Small Inductive Breaking Current. 5.4. Visual inspection of Circuit Breaker condition. Inspect the circuit breaker for any sign of damage or leaks both externally and in the circuit breaker marshalling box. Confirm that the interrupting medium level/pressure is correct before commencing tests and that assembly is complete and no transport bracing has been left in place. Inspect the external surfaces and ensure the circuit breaker is clean and dry. Check all connections for adequate labelling. The connections should be unambiguous, legibly and adequately marked. 5.5. Auxiliary and Control Circuit Voltage Withstand. The circuit breakers auxiliary and control circuitry shall be subjected to a 1 minute power frequency withstand test at 2kV to confirm insulation integrity. The circuitry shall be considered to have passed if no disruptive discharge occurs during the test. Consideration shall be given where electronic components are used in the auxiliary and control circuitry. Different testing procedures and values maybe adopted subject to agreement by the Commissioning Engineer. 5.6. Measure Resistance of the Main Circuit. Measurement shall be made using D.C. current of at least 50A and less than the nominal current rating of the circuit breaker. The test shall be conducted as close as practical to ambient temperature. A four wire ductor should be used for measuring the resistance of the main contacts. Measure Insulation Resistance. DC insulation tests are to be carried out between terminals of the circuit breaker as detailed below. Note that these connection arrangements have been specified for consistency with AS2650 and to allow for future insulation condition diagnostic assessment. The voltage applied will be as per Table 1 for a duration of 1 minute. With the circuit breaker in the closed position: A or a to Earth and all other terminals B or b to Earth and all other terminals C or c to Earth and all other terminals

With the circuit breaker in the open position: A to Earth and all other terminals B to Earth and all other terminals C to Earth and all other terminals a to Earth and all other terminals b to Earth and all other terminals c to Earth and all other terminals

Check this is the latest Process Zone version before use.

Page 3 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Standard Work Practice SP0509 Ver 2

CIRCUIT BREAKER TESTING SWP


A, B and C refer to one set of CB high voltage terminals (eg fixed contact top of CB) and a, b, and c refer to the other set of terminals (eg moving contact middle of CB) Minimum acceptance value for new plant is 1,000M. Table 1. Applied Voltages for IR Tests Primary Voltage Rating Up to 1kV Above 1kV to 3.6kV Above 3.6kV to 12kV Above 12kV Measure Timing. The time taken for the circuit breaker to complete an operation shall be measured for both opening or closing. Timing should be started by the application of voltage to the trip/close coil and stopped by operation of the main contacts. For both single and three pole CBs, each pole is timed independently as per clause HH2.4.2.1 of AS2006 - 1986 Note test both trip coils. Time travel measurement is required for 110 kV and above CBs or any CBs assembled on site. Measure spring charge time following close operation. 5.7. Carry out HV Testing. AS 2006 1986 specifies that normally no dielectric tests are performed at site on the main circuit, however AS 2067 1984
Check this is the latest Process Zone version before use. Page 4 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

specifies that a 90% power frequency withstand test be carried out on site after erection. The level of high voltage testing to be applied is therefore: a) Where no HV testing has been carried out at the manufacturers works 100%. b) Where HV testing has been carried out at the manufacturers works but subsequent assembly of the HV chamber / bushings is required on site 90%. c) Where HV testing has been carried out at the manufacturers works and no on-site assembly is required No HV withstand test. d) If the circuit breaker is aged or refurbished 75%. Where Um<=66kV the value of voltage applied shall be as per AS 2650-1986 as listed in the table below. Where Um>66kV the value of test voltage shall be in accordance with AS 2650-1986. Note that the test voltage used may be limited by the output capability of the test equipment. In this case a reduced test voltage for an extended duration as specified in Table 11.1 of AS 2067 1984 may be used. The requirements of the test are satisfied if no disruptive discharge occurs. An insulation resistance test is to be repeated after the HV withstand test to confirm that insulation degradation has occurred. Application of a 1 minute power frequency withstand test is to be in accordance with AS1931 Part 1 between the load and line terminals of the circuit breaker as detailed below. Note that these connection arrangements have been specified for consistency with AS2650 and AS2006 (Clause 7.1).
Standard Work Practice SP0509 Ver 2

Test Voltage in kV (D.C.) 1 2 5 10

CIRCUIT BREAKER TESTING SWP


With the circuit breaker in the closed position: A/a and C/c to Earth and all other terminals B/b to Earth and all other terminals Schedule of Tests The table below details the circumstances in which different tests are carried out: Test High Voltage Withstand New Circuit Breaker Workshop or on-site test required at discretion of Commissioning Engineer *. Review manufacturers test result only Aged or refurbished Circuit Breaker Workshop or on-site test required. Reduced values apply.

With the circuit breaker in the open position. A, B and C to Earth and all other terminals a, b and c to Earth and all other terminals

Nominal voltage of system (Un) kV r.m.s. 3.3 6.6 11 22 33 66

Highest Voltage for equipment (Um) kV r.m.s. 3.6 7.2 12 24 36 72.5

Rated Short term Power-frequency withstand voltage (PFWV) KV r.m.s. 10 20 28 50 70 140

Auxiliary and Control Circuit Voltage Withstand Insulation Resistance Resistance Of Main Circuit Timing Time Travel

On-site test required if circuit breaker wiring has been substantially modified On-site test required On-site test required

On-site test required On-site test required

On-site test required Required for transmission CBs or CBs assembled on site

On-site test required Required for transmission CBs or CBs assembled on site

*otherwise review manufacturers results only DDF and capacitance measurement of the CB insulation may be required at the request of the client, particularly if DLA test equipment is available on site at the time of commissioning.

Check this is the latest Process Zone version before use.

Page 5 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Standard Work Practice SP0509 Ver 2

CIRCUIT BREAKER TESTING SWP


5.8. Complete Pre-commissioning Checklist Circuit breakers being placed in service for the first time or after refurbishment require that the following items are checked prior to energisation: a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) p) q) r) s) t) u) Check closing with 85% normal supply volts; Check closing with 85% normal air pressure; Check tripping with 70% normal supply volts (85% if AC); Check insulation medium/pressure; Check gas pressure alarm; Check gas pressure trip/lockout; Check fuses and links in service position; Check main earth on cabinet and support structure; Check motor overload/excess run timer set; Check local trip operation, including operation with both trip coils in parallel; Check local close operation; Check remote trip operation; Check remote close operation; Check SCADA trip operation; Check SCADA close operation; Check protection trip operation; Check protection reclose operation; Function test all Local/Remote/Maintenance switch; Check operation of pole discrepancy protection (if fitted); Check anti-pumping relay operation ie apply a close command and then a trip command while the close is maintained; Apply a latched trip command and then a close command while the trip is maintained;
Page 6 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

v) w) x) y)

Check operation of interlocks; Check operation of all alarms; Check control switches in service position; Check operational nameplate and labels are in place.

Check this is the latest Process Zone version before use.

Standard Work Practice SP0509 Ver 2

You might also like