Circuit Breaker Testing SWP: 1 Purpose AND Scope
Circuit Breaker Testing SWP: 1 Purpose AND Scope
Circuit Breaker Testing SWP: 1 Purpose AND Scope
Additional Training Course Code 4445 4440 4430 Course Description Switching Operator and Authorised Switching Operator Assistant and Authorised Safe Entry to High Voltage Enclosures and Authorised
STAFFING RESOURCES
a) b) EFM competent in the use of test equipment. Safety Observer (required for all live work as defined in the ESO Code of Practice for Electrical Work).
Both are required to be trained in switchboard rescue and resuscitation and manual handling techniques. have appropriate Switching and Access authorisations for the roles they are required to perform and have the ability to assess and maintain relevant exclusion zones from exposed live electrical apparatus. hold current licences for any vehicles and equipment they may be required to operate.
DOCUMENTATION
CS000501F115. Daily / Task Risk Management Plan ES000901R102. Health and Safety Risk Control Guide SP0509R01 Circuit Breaker Testing Job Safety Analysis SP0509C01 Circuit Breaker Test Report SP0509C01R01 Circuit Breaker Sample Test Report SP0509C02 Circuit Breaker HV Withstand Test Report. SP0509C03 Circuit Breaker Testing Competency Assessment SP0506 Substation Primary Plant and Secondary Systems Field Testing SWP AS 1931 1996 High Voltage Test Techniques Parts 1 and 2 AS 2006 1986 High Voltage A.C. Switchgear and Controlgear Circuit Breakers for Rated Voltages Above 1,000V AS 2650 1986 High Voltage A.C. Switchgear and Controlgear Common Requirements
Required Training and Certificates Regulatory Training Course Code 2120 2130 2140 2160 Course Description Cardio-Pulmonary Resuscitation Low Voltage/Switchboard Rescue Pole Top Rescue (if required) EWP Rescue and Escape (if required)
Page 1 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
5.3. Record identification details. Manufacturers name, manufacturers type description and manufacturers serial number: Plant number; Description, ie. dead tank, live tank etc; Rated voltage and insulation level; Rated nominal and short-circuit current and duration; Rated operating sequence; Interrupting medium; Specialised requirements such as:
Standard Work Practice SP0509 Ver 2
TASK STEPS
5.1. Carry out an on site risk assessment Prior to performing this activity any hazards associated with prerequisite tasks at the worksite shall be identified and assessed with appropriate control measures implemented and documented in accordance with the Daily/Task Risk Management Plan CS000501F115 and using reference document Health and Safety Risk Control Guide ES000901R102. If any risks cannot be managed or reduced to an acceptable level, do not proceed with the task and seek assistance from your Supervisor.
Page 2 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
With the circuit breaker in the open position: A to Earth and all other terminals B to Earth and all other terminals C to Earth and all other terminals a to Earth and all other terminals b to Earth and all other terminals c to Earth and all other terminals
Page 3 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
specifies that a 90% power frequency withstand test be carried out on site after erection. The level of high voltage testing to be applied is therefore: a) Where no HV testing has been carried out at the manufacturers works 100%. b) Where HV testing has been carried out at the manufacturers works but subsequent assembly of the HV chamber / bushings is required on site 90%. c) Where HV testing has been carried out at the manufacturers works and no on-site assembly is required No HV withstand test. d) If the circuit breaker is aged or refurbished 75%. Where Um<=66kV the value of voltage applied shall be as per AS 2650-1986 as listed in the table below. Where Um>66kV the value of test voltage shall be in accordance with AS 2650-1986. Note that the test voltage used may be limited by the output capability of the test equipment. In this case a reduced test voltage for an extended duration as specified in Table 11.1 of AS 2067 1984 may be used. The requirements of the test are satisfied if no disruptive discharge occurs. An insulation resistance test is to be repeated after the HV withstand test to confirm that insulation degradation has occurred. Application of a 1 minute power frequency withstand test is to be in accordance with AS1931 Part 1 between the load and line terminals of the circuit breaker as detailed below. Note that these connection arrangements have been specified for consistency with AS2650 and AS2006 (Clause 7.1).
Standard Work Practice SP0509 Ver 2
With the circuit breaker in the open position. A, B and C to Earth and all other terminals a, b and c to Earth and all other terminals
Auxiliary and Control Circuit Voltage Withstand Insulation Resistance Resistance Of Main Circuit Timing Time Travel
On-site test required if circuit breaker wiring has been substantially modified On-site test required On-site test required
On-site test required Required for transmission CBs or CBs assembled on site
On-site test required Required for transmission CBs or CBs assembled on site
*otherwise review manufacturers results only DDF and capacitance measurement of the CB insulation may be required at the request of the client, particularly if DLA test equipment is available on site at the time of commissioning.
Page 5 of 6
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
v) w) x) y)
Check operation of interlocks; Check operation of all alarms; Check control switches in service position; Check operational nameplate and labels are in place.