Topic 2 Testing-And-Commissioning-In-Plumbing
Topic 2 Testing-And-Commissioning-In-Plumbing
Topic 2 Testing-And-Commissioning-In-Plumbing
TESTING AND
COMMISSIONIN
G IN PLUMBING
K EY TO PIC S
WHAT IS TESTING 03
AND
COMMISSIONING IN
• PLUMBING?
It is the report to be issued by an independent
Third party (Consultant) nominated by the
Employer or Project Owner for verifying the
satisfactory execution of installation, testing &
commissioning.
• It is also a diligent process of performing all
necessary quality control of Plumbing
installation.
12
BASIC REQUIREMENTS PRIOR TO
COMMISSIONING
1.Approved Material Submittal
2.Approved Material Inspection w/ material delivery
3.Approved Shop Drawing
4.Approved Method Statement of Installation
5.Approved Material Installation & Testing (Drainage/Water Line)
04
What is Commissioning
CheckList?
USED TO ENSURE THE SAFETY AND
FUNCTIONALITY OF A NEW PLUMBING
SYSTEM. IT ALSO VA L I D AT E S THE
PERFORMANCE OF PUMP AND PIPING
S Y S T E M . I T I S A L S O U S E D T O C A R E F U L LY
EXAMINE THE PIPING SYSTEM IN A
FA C I L I T Y AND PROVE IT WORKS
ACCORDING TO ITS DESIGN.
COMMISSIONING
14
CHECK LIST:General
• Is the work area clean, and orderly, with no leftover materials or
scattered debris?
• Is safety hazard addressed: sharp edges, low head clearance,
missing equipment, guards, etc.?
• Are name tags, nameplates, and serial numbers attached to the
equipment?
• Are instrument gauges/meter labeling correct and operating in the
normal range?
• Are valves labeled according to standard?
• Are equipment and components labeled according to standards?
14
COMMISSIONING
CHECK LIST:General
• Are walls and floor penetration through fire rated construction have
applied fire stop sealant?
• Are walls and ceiling penetration repaired and painted with equivalent
materials?
• Does the installation meet the code compliance requirements?
• Has unapproved equipment and piping materials and accessories
removed from services?
• Does equipment meet requirements for work space clearance?
• Is manufacturer installation, operation and start-up documents
complete and verified (Operation and Maintenance Manual)?
08
DO C U M ENTATION
• Is an equipment operation manual and
specification submitted to the
consultant and approved?
• Are as-built drawing such as Red
mark/Line drawing are submitted to the
consultant?
08
PLUM B ING
• Are all piping materials installed has been
submitted and approved by the consultant?
• Are installed types of pipes labeled in
compliance to the standard, including
direction of flow?
• Are all drainage/sanitary piping sloped a
minimum of 2% drop per linear meter as
specified in the plumbing code?
PLUM B ING 08
AREA OF
APPLICATION:
FOR W ET A R EA S LIK E TO ILETS,
B ATHR OO M S, K ITC H EN S, ETC .
RESPONSIBILITIES 19
SAFETY
14
• During installation and testing, all safety
precautions shall be as per established project
Safety plan. Secure work safety permit before
commencing of work.
• All personnel shall wear proper PPE at all times
and used proper tools in a safe manner.
• The work place shall be clean, safe to work and
have proper access and egress routes.
• Ensure work areas have adequate light. Provide
additional lights if necessary.
• Provide Fire Extinguisher and pail of Sand during
hot works. Fire watchman shall be at work place
at all time.
• Electric Power tools using Octopus connection is
strictly prohibited.
MATERI AL RECEI PT A N D STO RA GE
15
• Only approved makes of pipes and fittings shall be used.
• When off-loading, pipes shall be lowered carefully and
should not be dropped to the ground to avoid from
damage.
• Pipes shall be adequately supported at all times and shall
be stacked on a flat surface free from any sharp objects.
• Pipes shall be stacked in layers and classified according to
its size as per manufacturer’s recommendation.
• All open ends of the pipes must be suitably plugged to
prevent the ingress of debris or dust.
• All materials delivered on site must have an approved
material submittal and shall submit material inspection
request upon delivery and prior to installation.
03
PREPARATION
• Ensure that the shop drawings to be used
are marked approved and coordinated
with other services.
• The area must be properly clean and safe
ready for piping installation.
• Ensure work safety permit has been
prepared, inspected and approved by the
safety department.
• Power tools to be used must be properly
checked and in good condition to prevent
any accident.
INSTALLATION 03
• Water tests are to be conducted to ensure and prove the tightness of joints and to
ensure that there are no leaks in the piping system.
• The pipes to be tested shall be joined, plugged, and shall have been in position for
at least 24hrs before the test is carried out.
• Pressure gauges shall be installed with isolating valve at the extremities of the
piping circuit to be tested.
• The piping shall be tested for line, gradient, and water tightness.
• Close the valves one at a time and fill the pipe with fresh clean water, leaving all
the high points open to allow purging of air.
TESTING 06
DOMESTIC WATER
PIPELINE SYSTEM
The disinfection process for the pipe network of the domestic water
system shall be implemented through the following steps:
GENERAL DESCRIPTION
All process steps will be achieved properly by
the followings:
• Detailed process step description
• Process schedule
• Risk assessment
• Responsibility matrix
09
MATERIAL USED
• C ALC IUM HYPOC HL OR I T E
– DOSAGE 0 .2 KGM
C HEMIC ALS / 1 .0 C U.M .
WATER
• Po t a b l e wa t e r q u a l i t y
22
COMMENCEMENT
TIME OF THE
FLUSHING
PROCESS
TH E CH E MIC A L FL U SH IN G
SH A LL B E STA RT E D A S TH E
PRO JEC T SC H E D U L E B U T TH E
FO LLO W I N G PR E - C A U TIO N
SH O U LD B E TA K E N I N TO
C O N SID E R AT IO N .
20
• The chemical flushing process shall commence immediately after the system hydro
testing, and shall be reflected in the Commissioning Plan and commissioning
schedule. The maximum amount of time that a loop can be untreated or loaded
without water is 48 hours. If cleaning and flushing of the system cannot be
accomplished immediately after the hydro-test, the water used for hydro-testing shall
be charged with the pre-treatment/ Passivation chemicals to avoid corrosion.
• Any installation or maintenance works shouldn’t be done during or after the
treatment process to avoid contaminations or losing of treated water.
• It is highly recommended to flush whole water distribution network as one circuit to
avoid contamination or loss of treated water during reconnection.
PRELIMINARY PREPARATION
06
Purpose
Disinfection
Steps
• Fill all storage facility with potable water. 12
• Add the disinfectant solution to get free chlorine not less than 50mg/lit and samples
shall be taken from different points of the storage facility to ensure that free chlorine is
more than 50 ppm in all samples.
• Let the transfer pump run, pumping water through all the piping system to ensure that
the water with the disinfection solution reaches the internal surface of the piping
system. By getting samples from different points and allowing water to run until the
heavy concentration of the disinfection solution 50 ppm free chlorine reaches all
openings, especially the ones at the end of each line.
• After getting 50 ppm min. free chlorine in all storage facilities and in all open outlets,
the level of the water in all storage facilities must be up to Min 5% close to outlets,
keeping it in the same condition for a period of 24 hrs. During this period all valves in
lines must be open and closed to be internally disinfected.
12
• Measuring the free chlorine after 24 hours, this value shall be 10 ppm of
free chlorine min. In all outlet.
• Then lowering the chlorine content by flushing with fresh water (or let
the chlorinated water for 4-5 days) and adding chlorinating agent until
getting free chlorine of max 1 ppm.
• After the disinfection procedure is completed and before the system is
placed in service, samples for bacteriological analysis shall be collected
and tested for coli form organisms.
• If the test for coli form bacteria organism is negative, then the system
may be placed in service.
• Then disinfection certificate shall be issued.
05
TESTING AND
COMMISSIONING
OF PUMP
Pre-commissioning
check
P R I O R TO START- UP
• Check and inspect the installation of water pump is complete, verify the 12
TESTING &
COMMISSIONING
PROCEDURE
12
TESTING &
COMMISSIONING
OF PUMP SET
Confirm that the system is completely filled with 12
water:
• Tighten the foundation bolts properly. Check the
suction line connection in order to avoid drawing
of air into the pump.
• Open the suction valve slowly, and start the pump
by opening the discharge valve. Observe any
leakage in the pump.
• After a few minutes of operation note the pressure
reading at both suction and discharge sides.
• Measure the RPM / speed of the pump motor using
the tachometer.
12
RESULTS
If specified equipment performance is not
verified, the General Contractor shall see that
corrections are made and reschedule functional
performance test as soon as possible after
corrective work is completed.
04
Reports
S U B M I T R E P O RT O F F I N A L F U N C T I O N A L
P E R F O R M A N C E T E S T F O R A C C E P TA N C E B Y
T H E C O N S U LTA N T E N G I N E E R .
04
THANK YOU!