Reliability Considerations in Simple Paralleling Applications
Reliability Considerations in Simple Paralleling Applications
Reliability Considerations in Simple Paralleling Applications
TM
Reliability in power generation systems, defined as the probability that power will be available at any point in time, is the primary reason standby generator sets are purchased. Using paralleled redundant generator sets is one method commonly used to enhance system reliability. Redundancy traditionally has been a requirement only in critical applications such as data centers and hospitals where an extended loss of power could result in loss of life or a substantial financial loss, as these were the only scenarios where the cost of a redundant generator and the associated paralleling switchgear could be justified. The availability of lower cost power transfer devices and paralleling control systems have in recent years made redundant paralleled generators an attractive option in less critical standby power applications.
A standby generator set from a reputable manufacturer that has been maintained properly and tested periodically according to manufacturers recommendations is a very reliable solution. Adding a redundant generator with the inherent complexity of a paralleling system isnt necessarily going to make the system more reliable. Investing in a reliable generator set and a robust maintenance program so the generator doesnt fail is often a better investment than installing a more complex system to compensate for a failed generator set.
future as demand increases rather than installing a single larger generator that is oversized for the load. This will need to be balanced against the future investment required to add generators and switchgear and other required facility modifications.
Paralleling Systems
When a decision has been made to parallel generator sets there are several concerns that need to be addressed to ensure that the system is as reliable as possible.
Control System
A robust control system is critical to having a reliable paralleling system. A control system needs to minimize single points of failure and have fault tolerance measures built in. Key factors in a paralleling control include the following
www.cumminspower.com
2012 Cummins Power Generation
Genset 1
Genset 2
Synchronizing and closing to a live bus Generator sets synchronize reliably and quickly when there is no other control in the loop. External controls adjusting bias lines or otherwise interfering with the synchronizing algorithm introduce unnecessary complexity into the system.
be taken off line so that there will be sufficient capacity to serve the critical loads. Most paralleling generator set controls have a load shed or load dump output which can be connected to the load shed input of the transfer switches that serve the non-emergency loads (see figure 2). This will take the non-emergency loads off line in the event that the generator sets are overloaded. Note that to properly shed load transfer switches must be three position switches with centeroff positions.
Genset 1
Genset 2
Product Standards
Consulting engineers in the US consistently specify that paralleling switchgear must be rated to UL 891 or UL 1558. These standards ensure that industry safety guidelines are being followed and that the power transfer and protective devices and bussing have all been appropriately evaluated as a system for safety under fault conditions. Power transfer devices must also be rated appropriately for the paralleling application. UL 891 and UL 1558 specify circuit breakers listed to UL 489 (in the case of UL 891) or UL 1066 (in the case of UL 1558) for overcurrent protection and the breakers are typically used for power transfer as well as for protection. Draw out breakers are specified in critical applications such as hospitals and data centers, allowing operators to isolate faults and facilitate inspection and testing of breakers and easily replace breakers if necessary. Contactors that are not listed to a standard for paralleling equipment may not be suitable for a paralleling application as they may not have been evaluated for safety when subjected to the higher levels of fault currents present in a system with paralleled sources. Contactors that are components in UL 1008 listed transfer switches may not be suitable as a power transfer device in a paralleling application. UL 1008 recognizes and lists the entire switch mechanism, not the individual contactor. The individual contactor has not been type-tested according to the UL requirements and does not carry the UL listing separate from the transfer switch mechanism. In addition, UL 1008 lists switches that transfer loads between sources but does not test or recognize devices that parallel between two live sources. Because of these two factors it is not appropriate to apply the UL 1008 standard to contactors that are used to parallel between two live sources.
Installation Considerations
Installing and commissioning paralleled generator sets is not a simple process. A qualified manufacturer will have experience with protective relaying, system grounding, and other paralleling issues beyond the generator set functionality. Working with a manufacturer who has substantial paralleling experience over a wide range of applications and will assume responsibility for a correct installation is a key to a successful project even in the most basic paralleling application. There are several considerations that an experienced installer will address.
paralleling bus by separate breakers in separate compartments or sections in the switchgear line up.
Selective Coordination
The National Electrical Code requires selective coordination for emergency and legally required loads. Any downstream breakers must coordinate with upstream overcurrent protection such as paralleling breakers or a genset mounted breaker. Coordinating with a generator set mounted Molded Case Circuit Breaker (MCCB) with an instantaneous trip will be very difficult and will require in most cases that the downstream breakers are supplied from the same breaker manufacturer as the genset mounted MCCB. It is much easier to coordinate with a power breaker as is most often used in paralleling switchgear as they are typically equipped with programmable trip unit specifically for the purpose of coordination. When the generator control includes integral, UL listed overcurrent protection, coordination between the genset and the paralleling breaker is simplified because the overcurrent trip curve is optimized to allow the maximum permissible time delay while still protecting the alternator.
Separation of Circuits
The National Electrical Code requires that Emergency, Legally Required and Optional loads are separated from each other. With paralleled generator sets that means that the Emergency, Legally Required and Optional loads must be fed from the generator
Distribution Panel G
G
Figure 3: Distribution panel with no incoming breaker
Scalability
Paralleling systems are frequently expanded after they are put into service to accommodate increasing power demands. The ability to add a generator set and the associated switchgear in the future should always be considered. The system should have the flexibility to allow generator sets from a different manufacturer to be added in the future. Being locked in to a certain manufacturer limits flexibility for future expansions. Additional question to ask concerning expansion include Are the generators properly isolated so that new generators can be added without taking the facility off line? What is involved in modifying the control for expansion? If a different manufacturers generators are used for the expansion what will be required for the generators to parallel properly? Does the manufacturer have experience implementing field expansions, including expansions that include generators from other manufacturers. How can the system be modified to support utility paralleling if that is required in the future?
Conclusions
The decision on whether to provide backup power with a single generator set or with redundant paralleled generator sets will be based on reliability and cost. The key question is does the redundancy coupled with the added complexity of a paralleling system increase the system reliability enough to justify the additional cost? When a decision has been made to parallel generator sets there are several considerations that need to be addressed to maximize the reliability of the system. The control system should be designed with critical functions distributed to the individual generator controls to minimize single points of failure The controls should have fault tolerance provisions such as load shed and manual operating modes. The installation must meet code requirements for coordination, separation of circuits and ten second service to emergency loads and must allow proper isolation of the generator sets. The system must be supported by an organization with a proven track record for servicing complete paralleling systems.
www.cumminspower.com
2012 Cummins Power Generation Inc. All right reserved. Cummins Power Generation and Cummins are registered trademarks of Cummins Inc. The Power of One and Our energy working for you. are a trademarks of Cummins Power. GLPT-5590-EN (10/12)