Substation Grounding Grid Design Using Alternative Transients Program-ATP and ASPIX
Substation Grounding Grid Design Using Alternative Transients Program-ATP and ASPIX
PAGE 1
Substation grounding grid design using Alternative Transients Program-ATP and ASPIX
This example shows the method for designing a grounding grid following the standard IEEE 80 safety criteria. It shows the procedure for designing the grounding grid of a substation with voltage levels of 115 kV and 34.5 kV.
1 Software
This example of the design was developed with the aid of the following software: Alternative Transients Program (ATP): Licensing to use ATP is free of all charges for all who are not engaged in EMTP commerce. For information on the licensing and user groups, visit the website: http://www.emtp.org/ Aspix: You may obtain a trial version for 30 days. This version allows you to run simulations and observe the results; however, you cannot save or generate reports. You can request a 30-day free license without functionality limitations. The program can be downloaded from the following website: http://www.spartalightning.com/products/aspix Aspix Resistivity Analyzer: It is an Excel spreadsheet that allows the processing of the resistivity measurements to obtain a two-layer model. This spreadsheet sheet is available for free and can be downloaded from the website: http://www.spartalightning.com/download
2 Design method
The method for designing the grounding grids includes the following steps: 1. 2. 3. 4. 5. 6. 7. Measuring and analyzing the soil resistivity. Plotting the grounding grid layout. Calculating the grounding grid resistance with the initial design. Calculating the earth current distribution. Calculating the touch and step voltages. Verifying the touch and step voltages. Redesign of the grounding grid when the calculated touch and step voltages are higher than the tolerated values; the procedure is repeated from point 2.
3 Input information
The following information is required for designing the grounding grid: Single line diagram of the power system Short-circuit levels Parameters of the power transformers Substation plan view Measurements of the soil resistivity
http://www.spartalightning.com/
PAGE 2
115 kV
Single circuit line 58 km 115 kV 25 MVA Dyn5 Z1 = 12% Z0= 12% Load 2 substation 25 MVA Dyn5 Z1 = 12% Z0= 12%
Load 1 substation
34,5 kV
34,5 kV
The substation is composed of three line bays of 115 kV, one 25 MVA transformer, one 115 kV transformer bay, and four 34.5 kV bays (three for the distribution circuits and one for the power transformer), as shown in Figure 2.
http://www.spartalightning.com/
PAGE 3
The substation has a layer of crushed rock of 20 cm thickness and with a resistivity of 2500 m. The maximum time of fault clearance is 500 ms. The cables of the mesh have a depth of burial of 50 cm.
5 Resistivity measurements
The measurements are obtained using the Wenner method for a separation of the electrodes of up to 8 m and using the Schlumberger-Palmer method for a separation of the voltage electrodes of up to 32 m. The soil resistivity measurement data are summarized in Table 1.
http://www.spartalightning.com/
PAGE 4
Schlumberger-Palmer Method
c(m) a (m) c(m)
The Aspix Resistivity Analyzer is used for processing the resistivity measurements and to obtain the two-layer model. This processor is an Excel spreadsheet that generates a curve of resistivity with a probability of non-exceedance of 70%. From this curve, Aspix Resistivity Analyzer tries to find the values of the upper-layer resistivity, bottom-layer resistivity, and depth of the top layer that best suit to the obtained measurements. This tool displays a graph where the user can observe the resistivity measurements and the values calculated by the analyzer, allowing comparison of the model with the measurements. Table 2 summarizes the processing of the resistivity measurements in Table 1.
Table 2. Earth resistivity measurement processing
Resistivity Analyzer
Equally Spaced - Wenner Method Profile 2 P1 (Ohm_m) P2 (Ohm_m) P3 (Ohm_m) P4 (Ohm_m) P5 (Ohm_m) P6 (Ohm_m) P7 (Ohm_m) P8 (Ohm_m) P9 (Ohm_m) P10 (Ohm_m) Average Std Dev Resistivity_70% 207.1 164.7 131.6 33.82 24.47 42.3 223.6 177.4 150.4 156.175 45.334 177.134 165.02 123.55 62.518 145.573 162.309 0 0 5 4
a (m)
8 185 84
16
32
250
193.1 168.5 139.6 167.7 185.3 245.2 175.6 222.3 129.5 117.9
200
150
100
50
35
Estimated 2 layer soil parameters Upper Limit Lower Limit 1 (Ohm_m) 256.14 10000.00 1.00 2 (Ohm_m) 136.35 10000.00 1.00 k H(m)
I V
c c a Schulumberger-Palmer Method
-0.31 1.82
0.99 20.00
-0.99 0.10
The resistivity analyzer provides the following parameters for the two-layer model: Resistivity of the upper layer (1) = 256.14 m Resistivity of the bottom layer (2) = 136.35 m Depth of the top layer (H) = 1.82 m
http://www.spartalightning.com/
PAGE 5
6 Initial design
6.1 Grounding grid layout
The design of the grounding grid must be such that it ensures the safety of persons against failures, and requires the minimum amount of materials and work. In the design method, initially a mesh is drawn on the substation layout covering all the substation equipment. This first layout of the grounding grid must take into account the following: All the substation equipment require at least one ground pigtail for their structures. When the substation has a metallic fence, a ground conductor can be buried outside the fence in order to control the touch voltages. Normally, it is a cable installed 1 m outside the fence, buried at 50-cm depth. This cable must be interconnected with the internal grounding grid every 20-50 m, depending on the soil resistivity. A cable around the transformers, outside the transformer foundation. A cable outside the gantry foundations. The minimum number of cables required to facilitate grounding of all the equipment and their structures are drawn. In the case of the above example, the fence is a brick wall; therefore, it is not necessary to install a buried cable outside the fence. Figure 3 shows the plan view of the substation and the grounding grid drawn according to the above mentioned criteria.
http://www.spartalightning.com/
PAGE 6
Below is the analysis of the grounding grid to know whether this first design meets the safety requirements or whether it is necessary to improve it.
http://www.spartalightning.com/
PAGE 7
Aspix parameter
Upper layer resistivity (m) Lower layer resistivity (m) Upper layer thickness (m) Crushed rock resistivity (m) Thickness crushed rock surfacing (m) Fault duration (s) Maximum grid current (A)
Value
256.14 136.35 1.82 2500 0.2 0.5 1000
These parameters are entered in the Aspix program using the Simulation option in the Simulation Settings menu. Figure 4 shows the parameters entered in the program.
The next step is to enter the physical data of the grounding grid in the program. For this, the wires and rods that make up the mesh of the grounding are added. In this example, the mesh of the grounding is composed only of horizontal conductors, which are added by right-clicking on Horizontal Conductors and then clicking on New Conductor. Figure 5 shows the data that must be entered by each conductor.
http://www.spartalightning.com/
PAGE 8
Once the conductor details are entered, the user can observe the plan view of the grounding grid. The plan view is displayed with the Grid Plan View option in the View menu, and it appears as shown in Figure 6.
The simulation is run using the Run option in the Simulation menu. The results are displayed using the Results option in the Simulations Results menu. The program displays a window with the results table as shown in Figure 7.
http://www.spartalightning.com/
PAGE 9
Thus far, only the grounding grid resistance value (2.267 ) has been calculated. The touch and step voltages have not yet been calculated given that the value of the current passing through the grounding grid is required.
http://www.spartalightning.com/
PAGE 10
By assumed an average span of 300 m and a tower footing resistance of 30 , the 20 sections of the line closest to the substation (6 km) are modeled in detail, and the remaining part is modeled as a single section. Figure 8 shows the network modeled using the ATP program.
Source substation Load 1 substation
Load 2 substation
A single phase and two phases to the ground faults are simulated, at the levels of 115 kV and 34.5 kV. The case in which more current passes through the grounding grid corresponds to a two-phase ground fault on a 34.5-kV circuit at a point very close to the substation, by assuming that the 34.5-kV circuits do not have a ground wire. Figure 9 shows the distribution of the ground fault current.
http://www.spartalightning.com/
PAGE 11
115 kV
Ground wire
34.5 kV
2720 A 875 A Towers footing resistances Grounding in the fault point Substation grounding grid 1121 A 815 A Ground wire 2720 A
The currents cannot be added arithmetically because there is an angle of deviation between them mainly caused by the inductive component of the ground wires; this lag can be observed in Figure 10.
4000 [A] 3000 2000 1000 0 -1000 -2000 -3000 -4000 0.00
Fault ground current and transformer neutral current Substation grounding grid current Lines ground wires current
0.02
0.04
c: -MALL
0.06
c:CG1 -MALL
0.08
c:CG2 -MALL
[s]
0.10
The maximum current value through the grounding grid is 1121 A, and it is the value that is used to calculate the touch and step voltages.
http://www.spartalightning.com/
PAGE 12
The effect of the direct current component of the short-circuit current is negligible given that the X/R relationship of the system in the substation analyzed is less than 10 and the fault duration is 500 ms.
The areas that can be defined using the Aspix program are rectangular in shape and are defined by the coordinates of the starting point (x, y), number of points in the X and Y directions, and distance between the points or resolution. For the case that is being analyzed, the five areas that are shown in Figure 12 can be defined.
http://www.spartalightning.com/
PAGE 13
Area 5
Area 4
Area 3 Area 2
Area 1
Once the chart areas for simulation are defined, the simulation is run with the Run option from the Simulation menu. Further, the results are observed using the Simulations Results option of the Results menu, and the results table is shown in Figure 13. The results table displays a summary of the simulation; we can observe the values of the grounding resistance and the calculated maximum touch and step voltages values in the defined chart areas. In addition, we can observe the tolerable touch and step voltages for people of 50 kg and 70 kg of weight in accordance with the standard IEEE 80. In this example, the safety criterion is not to exceed the tolerable touch and step voltages for persons of 50 kg of weight. Aspix also generates the touch and step voltages charts for all the configured areas. These charts can be twodimensional or three-dimensional and can be displayed using the options Touch Voltage 3D Chart, Step Voltage 3D Chart, Touch Voltage Chart 2D, and Step Voltage Chart 2D in the Results menu. These charts are shown in Figure 14, Figure 15, Figure 16, and Figure 17, respectively.
http://www.spartalightning.com/
PAGE 14
http://www.spartalightning.com/
PAGE 15
http://www.spartalightning.com/
PAGE 16
As can be observed in the results table shown in Figure 13, the tolerable touch voltage for a 50-kg person is 677.8 V, and this value is exceeded by the calculated touch voltage of 914.2 V. The step tolerable voltage is
http://www.spartalightning.com/
PAGE 17
2219.1 V and is above the calculated step voltage of 406.5 V. In summary, with this initial design, the tolerable touch voltage is exceeded, i.e., the design does not meet the safety criteria and should therefore be modified.
7 Modified design
7.1 Grounding grid layout
The modifications to the initial design must be oriented to the reduction in the touch voltages, for which there are different alternatives such as follows: The ground potential rise (GPR) is decreased, for which the alternatives are as follows: reduce the grounding grid resistance or decrease maximum current through the grounding grid. The space between the parallel conductors is reduced by adding conductors on the inside of the grid of the initial design. The first option is to attempt to decrease the touch voltage by reducing the space between the parallel conductors. This requires identifying the points where the tolerable touch voltage is exceeded. The regions where the tolerable touch voltage is exceeded appear circled as shown in Figure 18, and the modification of the design consists of adding cables in these regions. Figure 19 shows the modified design.
http://www.spartalightning.com/
PAGE 18
http://www.spartalightning.com/
PAGE 19
http://www.spartalightning.com/
PAGE 20
115 kV
Ground wire
34.5 kV
2732 A
The maximum current value through the grounding grid is 1188 A, and it is the value that is used to calculate the touch and step voltages.
http://www.spartalightning.com/
PAGE 21
Figure 23 and Figure 24 and Figure 25 and Figure 26 show the charts of the calculated touch and step voltages in two dimensions and three dimensions. As can be observed in Figure 22, the tolerable touch voltage for a 50-kg person is 677.8 V. This value is greater than the calculated touch voltage in the grid, which is 657.1 V. The tolerable step voltage is 2219.1 V, and it is greater than the calculated step voltage of 396.1 V. This modified design controls touch and step voltages, rendering them lower than the tolerable values, i.e., it meets the safety criteria and can be considered as the final design.
http://www.spartalightning.com/
PAGE 22
http://www.spartalightning.com/
PAGE 23
http://www.spartalightning.com/