End Block Design Aid
End Block Design Aid
End Block Design Aid
|
\ .
Place within the frst
h
/
2
(2)
A
s2
=
2
0.67
1200
300*
P
P h
h
| |
|
\ .
Place within the last
h
/
2
(3)
Where:
A
s1
, A
s2
= Minimum vertical reinforcement to be extended a distance h in front of the
diaphragm. Concentrate
2
/
3
of this reinforcement in the frst h/2 (A
s1
) and
1
/
3
in the latter half (A
s2
). (in.
2
per ft)
h = Cross section depth (ft)
P = P
jack
per girder (kips) (consider the allowable fnal force variation between
girders)
MeMo to Designers 11-25 october 2012
11-25 Anchorage Zone Design 3
LRFD
The designer should frst establish the stirrup schedule for the girders considering all
other loads. The stirrup schedule should then be checked using the equations above. The
requirement for stirrups in the webs within the general zone due to prestressing forces should
not be considered additive to other loads.
Girder Stem Thickness
The webs shall be designed to resist the longitudinal compressive forces. The girder thickness
at the face of diaphragm, t
w
, shall be designed so that:
(t
w
)
REQUIRED
>
( )
*1000
1 *18 3 12 *0.7
1200
d ci
P
P
T f
( | |
+
|
(
\ .
Where:
t
w
= web thickness (in)
T
d
= End diaphragm thickness (in)
= 0.57 in.
2
/ft
d) Modify the stirrup schedule as follows:
Stirrups within the frst h/2:
Use #5 @ 6, A
s
= 1.24 in.
2
/ft > 1.14 in.
2
/ft
Stirrups within the second h/2:
Use #5 @ 9, A
s
= 0.83 in.
2
/ft > 0.57 in.
2
/ft, as originally designed
3) Check web thickness for compression
(t
w
)
REQUIRED
=
( )
2710*1000
2710
1 *18 3 39 12 *0.7*0.7*3500
1200
( | |
+
|
(
\ .
= 15.25
(t
w
)
PROVIDED
= 12 < 15.25
MeMo to Designers 11-25 october 2012
11-25 Anchorage Zone Design 5
LRFD
Increase the web thickness for interior girders to 16 at the anchorages and fare to 12 over
16 feet. Exterior girders are typically fared to 18 near the anchorages to make room for the
prestressing trumpets and spiral reinforcement. Therefore, the exterior girders are adequate
as designed for compression.
4) Example details:
39 43.5
#5@6
43.5
#5@9
Longitudinal Section
16-0
16
18
18
12
Girder Layout
MeMo to Designers 11-25 october 2012
11-25 Anchorage Zone Design 6
LRFD
References
Nonlinear Finite Element Analysis of Prestressed Anchorage Zones, Task Order No. 2,
Contract No. 59A0603, Project No. CALT00590202, David Evans and Associates (2011)
Barton J. Newton
State Bridge Engineer
Deputy Division Chief, Structure Policy & Innovation
Division of Engineering Services
Original signed by Barton J. Newton