Is 4091 1979
Is 4091 1979
Is 4091 1979
Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.
1 +, 1 +
01 ' 5
Jawaharlal Nehru
! $ ' +-
Satyanarayan Gangaram Pitroda
! > 0 B
BharthariNtiatakam
(Reaffirmed 2010)
IS:4091-1979
Indian
Standard
( Reaffirmed 2006 )
First Revision)
UDC
624.159.11.04:006.76:621.315.66
@ Cojyiht
BUREAU
1980
OFINDIAN
STANDARDS
Cr5
Jdy
1980
IS : 4091- 1979
Indian Standard
CODE OF PRACTICE FOR
DESIGN AND CONSTRUCTION OF
FOUNDATIONS FOR TRANSMISSIdN LINE
TOWERS AND POLES
(
First Revision )
Representing
Cent;Lorfe_$ding
PROPDINESHMOHAN
Research
Institute ( CSIR ),
Members
DR
R . IL BHANDARI
Centraaogezding
SHRI I. G. CHACKO
SHRI S. GUHA ( Alterrzate )
SHRI K. N. DADINA
Research
Institute
( CSIR ),
SHRI M. G. DANDAVATE
of India, Bombay
SHRI N. C. DUGGAL ( Alternate )
SHRI R. K. DAS GUPTA
Simplex Concrete Piles ( I ) Pvt Ltd, Calcutta
SHRI H. GUHA BISWAS( Alternafe)
SHRI A. G. DASTIDAR
In personal capacity
( 5, Hungerford Court, 121
Hungerford Street, Calcutta )
SI~RIV. C. DESHPAN~E
Pressure Piling Co ( India ) Pvt Ltd, Bombay
DIRGCTOR ( CSMRS )
Central Water Commission, New Delhi
DEPUTY DIRECTOR( CSMRS ) ( Alternate )
SHRI A. H. DIVANJI
Asia Foundation and Construction Pvt Ltd, Bombay
SHRI A. N. JANGLE (Alternate)
SHRI A. GHOSHAL
Braithwaite Burn & Jessop Construction Co Ltd,
Calcutta
SHRI N. E. A. RAGHAVAN ( Alternate)
DR SHASHI K. GULHATI
Indian Institute of Technology, New Delhi
SHRI A. VARADARAJAN ( Alternate )
SHRI M. IYENCAR
Engineers India Ltd, New Delhi
DR R. K. M. BHANDARI( AIlcmok 1
SHRI G. S. JAIN
G. S. Jain & Associates, Roorkee
( Continued on page 2 )
@ Copyright
1980
OF INDL4N STANDARDS
This publication is protected under the Indian Copyrighr Act ( XIV of 1957 ) and
reproduction in whole or in part by any means except with written permission of the
publisher shall be deemed to be an infringement of copyright under the said Act.
BURl3U
--.--~.-.- ..____..
__ __.~
Is :4091-1979
( Continuedjlom page 1 )
Representing
Members
IS : 4091- 1979
Indian Standard
CODE OF PRACTICE FOR
DESIGN AND-CONSTRUCTION OF
FOUNDATIONS FOR TRANSMISSION LINE
TOWERS AND POLES
( First Revision )
0.
F 0 R EW 0 R D
0.1 This Indian Standard ( First Revision) was adopted by the Indian
Standards Institution on IQ August 1979, after the draft finalized by the
Foundation Engineering Sectional Committee had been approved by the
Civil Engineering Division Council.
0.2 Transmission line towers and poles are subjected to large horizontal
forces at the top,.thereby causing overturning and/or uplifting of foundation. The design of foundations.for such structures involves special problems
and this standard has been prepared with a view to providing guidance to
the designer. Often well foundations are used in river beds for which IS :
39551967 may bc referred. This standard was first published in 1967.
The revision has been done to bring in line with latest practice.
0.3 In the formulation of this standard due weightage leas been given to
international co-ordination among the standards and practices prevailing
in different countries in addition to relating it to the practices in this field in
the country.
0.4 For the purpose of deciding whether a particular reyuircment of this
standard is complied with, the final value, observed or calculated, expressing
the result of a test or analysis, shall be rounded off in accordance with IS :
2-19607. The number of significant places retained in the rounded off value
should be the same as that of the specified value in this standard.
1. SCOPE
1.1 This standard covers the design and construction of concrete foundations including anchor bolts grouted into rock for transn?ission-lint towers
and poles.
*Code
tRules
IS : 4091- 1979
1.2 Grillage, brick and masonry footings and anchor plates are not covered
in this code. The design and construction of prestressed concrete foundations are also not covered.
2. TERMlNOLOGY
2.0 For the purpose of this standard, the following definitions shall apply.
2.1 Broken Wire Conditions (BWC) - This is a condition when one or
more of the wires on one side or both sides of the tower or pole are broken
causing an unbalanced pull or a twisting moment on the tower or pole.
2.2 Footings - Foundations are normally constructed by making open excavations, they may have enlarged base provided either in the open excavation or by under-cutting the soil by suitable devices.
2.3 FoundationsThat part .of the structure which is in direct contact
with soil and transmits the loads to the ground.
2.4 Highest Flood Level ( HFL ) - Highest flood level of a river or stream
is the level of the highest flood ever recorded or the calculated level for the
highest possible flood.
2.5 Low Water Level (LWL) - Low water level or a river of stream is the
level of the water surface obtained generally in the dry weather.
2.6 Normal Condition ( NC ) - This is a condition when the wires on either
side of the transmission tower are intact.
2.7 Ordinary Flood Level ( OFL ) - Ordinary flood level of a river or stream
is the average level of a high flood which is expected to occur normally every
year.
2.8 Pile ( Concrete ) - A particular type of cast in-situ or precast foundation
normally provided by driving or boring, and having uniform, bulbed, tapered or corrugated section along its length.
2.9 Rock - Foundation. supporting material other than soil which is possible to exca.vate, in the case of soft rocks with pick axe and shovels, and in
case of hard rocks by special methods like blasting.
2.10 Soil, Black Cotton - Clayey soil, not necessarily black in colour,
which shrinks when dry and swells when wet, resulting in differential movement of ground. In deep deposits of these soil generally there is no appreciable ground movement due to seasonal moisture changes beyond 3.5 m
[see IS : 2720 ( Part XL )-1977* 1.
*Methods
of-free swellklex
of soils.
IS : 4091- 1979
3. NECESSARY
INFORMATION
3.1 For the design and construction of foundation the following information shall be supplied:
4 Route map showing the proposed Iay-out of the towers with the
for earthquake
resistant
design of structures
( third revision ).
IS : 409141979
2) The nature of the surface soil in bed and banks with trial pit or
3)
4)
5)
6)
bore hole sections showing the levels and nature of the various
strata down to the stratum suitable for founding the towers;
The ordinary flood level;
Low water level;
The highest flood level and years in which it occurred. State
if the flood level is effected by back water
or tidal effect and, if
.
so, give details; and
The estimated depth of scour or of the scour depth has been
observed, the depth of scour so observed.
for ordinary
and rapid-hardening
Portland cement.
**Specification for mild steel and medium tensile steel bars and hard drawn steel wire
for concrete reinforcement:
Part I Mild steel and medium tensile steel bars ( second revision).
Part II Hard-drawn
ttSpecification for hot rolled mild steel, medium tensile steel and high yield strength
steel deformed bars for concrete reinforcement ( revised).
$$Specific.ation for cold-twisted steel bars for concrete reinforcement
@Code of practice for plain and reinforced concrete ( third revision).
( second revision ).
Is : 4091- 1979
IA
Conventional
Assumption
IB
Actual
Action
Without
Under-Cut
IC
Actual
Action
with
Under-Cut
FIG. 1 SOILRESISTANCE
TO UPLIFT
8
IS : 4091- 1979
5.1.6 Depending upon the relative magnitude of upward or downward
vertical loads, lateral load and overturning moment, footings in soil shall
be as classified in Table 1 according to their suitability.
51.7 Bored piles with enlarged bases usually provide an economical type
of footing in many soils where under-reaming is possible. In expansive type
of soils such as black cotton soils, they have to be carried down to a depth
of 3.5 m in deep layers of these soils to counteract the effect of upthrust due
to swelling pressure introduced in the soil. Normal type of independent
spread footing carried down to shallow depths will not be suitable in such
soils,
5.1.8 Different types of piles can be used depending upon the location
and in case of heavy uplift forces and moments multiple under-reamed piles
or anchors may be used. In case of loose to medium sandy Soils bored compaction under-reamed piles may be used.
5.1.9 The piles in uplift should be designed by the usual considerations
of the friction on stem and bearings on the annular projections. A factor
of safety of 3 may be applied for safe uplift.
5.1.10 The load carrying capacity of an under-reamed pile may bc determined from a load test as given in IS : 2911 (Part IV) - 1979*.
In the absence of actual tests, the safe loads allowed on piles under-reamed to
2.5 times the shaft diameter may be taken as given in Table 2.
5.1.10.1 The safe loads given in Table 2 apply to both medium compact sandy soils and clayey soils of medium consistency. For dense sandy
( N> 30 ) and stiff clayey ( N> 8 ) soils the loads may be increased by 25
percent. However, the values of lateral thrust should not be increased
unless stability of top soil ( strata to a depth of about three times the stem
diameter ) is, ascertained. On the other hand a 25 percent reduction should
be made in case of loose sandy ( N( 10 ) and soft clayey ( N94 ) soils.
NOTE-For
determining
the average
N valuei ( the standard
penetration
test
values ) a-weighted
average shall bc taken and correction for fineness under water table
shall be applied where applicable.
of practice
of pile foundations:
Part IV Load
test on
IS : 4091- 1979
No - bearing capacity factor usually taken as 9;
CP = cohesion of the soil around the toe, in kgf/cma;
A a = x/4 (Da-. D2 ) where Dn and D ire the under-reamed
bblb and the &em diameter respectively, in cm;
C.a - average cohesion of soil around the under-reamed bulbs,
in kgf/cm2;
Als = surface area of th& cylinder circumscribing the underreams, in cm2;
OS= reduction factor (usually 0.95 for clays );
cs = av;;fynThesion
of the soil along the pile stem, in kgf/
I
A8 = surface area of the stem, in cm2.
The expression given in 5.1.10.2 holds and for the usual vertical spacing between under-reamed bulbs riot greater than 1.5 times
the diameter of the under-reamed bulb.
b) In case of sandy soils the ultimate load carrying capacity of an
under-reamed pile may also be worked out by the following cxpression:
Qa=;@-
0) [
r-n
dDunYNy+yNaXdr
r=l
where
DU = diameter of under-reamed bulb, in cm;
D = diameter of stem in cm;
n = number of under-reamed bulbs;
y = average field density of soil in kg/cmS;
Ny and Nq = bearing capacity faetors depending on the angle of intcrnal friction [ for values Ny see IS : 6403-1971* and N,-,,
see IS : 2911 ( Part III )-1980t 1;
n, = depth of the centre of different under-ream bulbs in cm;
4ir = total depth of pile in cm;
K = earth pressure constant ( usually 1.75 for sandy soils);
8 = angle of wall friction;
CI,= depth of the centre of the first under-ream bulb in cm; and
4, = depth of the centre of last under-ream bulb in cm.
*Code of practice for determination of allowable bearing pressure on shallow foundation.
*Code of practice for design and construction of pile foundations: Part III Underreamed piles (first revision ) .
10
IS:4091-1979
5.1.10.3 In case of piles resting on rock the bearing component will
be obtained by multiplying the safe capacity of rock with the bearing area
of pile stem plus the bearing provided by the under-ream portion.
5.2 Allowable Bearing Pressure - The allowable bearing pressure of the soil
where the towers or poles are founded shall be based on adequate subsoil
exploration and. testing carried out in accordance with IS : 188%1971*,
IS : 1892-1979t and IS : 1904-1978:.
The permissible bearing pressure so arrived may be exceeded at the
edges of footings by 25 percent when variation in the intensity of the reaction
caused by the transmission of moments to the footing is taken into account.
5.3 Permissible Stresses in Concrete and Reinforcement- Where stresses
due to wind, temperature and shrinkage. effects are combined with those
due to dead, live and impact loads, stresses specified in IS : 456-1978s for
these conditions should be used in the design.
5.4 Structural Safety
5.4.1 For the structural safety against sliding, overturning and for the
footings at different levels provisions laid down in IS : 19&l-1978$ shall
apply.
5.4.2 The depth of footings shall conform to the provisions laid down
in the relevant Indian Standards depending on the type of foundation [ see
IS : 1080-198011,IS tlS04-1978$, IS : 2911 (Part I/Set I)-19797, IS : 2911
( Part I/Set 2 )-I9797 and IS : 2911 ( Part T/Set 3 )-19791 1.
5.5 Footing on Rock
5.5.1 A rock footing, for uplift and horizontal loads, may be considered
to develop strength by the dead load of the concrete and. the strength of
bar anchorage ( the pull-out value of anchor bars grouted in drill holes or
the failure strength of rock engaged by bars).
5.5.2 The depth of embedment of the bars below the bottom of the footing should not be less than the following:
*Method
tCode
-___-
D=45d
jfirstrevision ).
15
Is:4091~1979
where
D A the minimum depth of embedment in mm, and
n = diameter of anchor bar in mm.
5.5.3 The spacing of embedded bars 1should normally be one-haIf of the
normal depth of embedment- as given in 5.5.2.
5.5.4 The size of the bar shall be governed by the criterion that combined stresses do not exceed the permissible limits.
5.6 Concrete Piles-In
case concrete piles ( other than under-reamed )
the provisions of IS : 2911 ( Part I/Set l )-1979*, IS : 2911 ( Part ISec 2 )1979* and 1s : 2911 ( Part 1,Bec 3 )-1979* shall apply.
5.7 Special Cokiderations
5.7.1 Footings in Seismic Zones - In designing footings in seismic zones,
the provisions of IS : 1893-1979t shah apply.
5.7.2 Footings in Sdphate Bearing Clays - Suitable precautions as laid
down in IS : 1080-19621 shall be taken in the case of footings in sulphate
bearing clays.
5.7.3 In the case of river crossing, the horizontal pressure due to forces
of water current shall be considered in the design.
NOTE
ing debris.
Towers located in river are likely to be subjected to shock loads,due to floatThe towers should be suitably protected against such shocks.
5.7.4 Excavations, Drillilzg and Blasting- These operations shall conform to IS : 3764-1966$, and IS : 4081-196711.
5.7.5 In case the footings under the same tower structure happen to rest
such thatsome of them are in soil and the rest on rock then the consideration
shall be given for differential settlement and the structural safety.
5.7.6 In case of deviations in the alignment of the Iine, modifications
should be made in the design of foundations for towers. No special provisions may be necessary for deviations up to 2.
5.8 Concreting - Concreting shall be done in accordance with the relevant
requirements given in IS : 456-19787.
*Code of practice for design and construction of pile foundations:
Section 1 Driven cast in-situ piles.
Section 2 Bored cast in-situ piles.
Section 3 Driven precast piles.
iCriteria
( third reuision).
16
IS : 4091- 1979
6. STAY SETS
6.1 The stay set may be provided by burying a 30 x 30 cm and 5 mm
thick mildsteel plate having a 18 x 18 mm hole in the centre through which
n 16 mm diameter bolt passes.
6.2 As an alternative to the steel plate in 6.1, cleats formed by two 30 cm
long pieces of angle iron of size 50 x 50 x 15 mm buried in a concrete
pad of 15 cm can also be provided.
7. POLES
7.1 The foundation for poles is provided by a certain length of the pole
buried into the ground. The bearing capacity in compression is mainly
derived by the skin friction on the surface of the poles and to a smaller
extent by the base area. Under the action of wind the lateral loading introduces moments and lateral thrust on the foundation.
7.2 Depth of embedment of the pole for the purpose of foundation should
not bc less than one-sixth of the total length of the pole above ground level.
7.3 A protective collar providing a concrete cover of not less than 10 cm
around the pole shall be provided. The depth of the concrete collar below
the ground level should not be less then 45 cm and it should be atleast 15 cm
above the ground level.
17
BUREAU
OF
INDIAN
STANDARDS
Headquarters:
Telegrams: Manaksanstha
( Common to all Offices)
Offices:
TeJepbone
331 01 31
331 13 75
36 24 99
21643
I 3 1641
41 24 42
Southern : C. I. T. Campus, MADRAS 600113
41 25 19
I 41 2916
TWestern : Manakalaya, E9 MIDC, Marol, Andheri ( East ), 6 32 92 95
BOMBAY 400093
Branch Offices:
/nspection
Approach,
2 51 71
5 24 35
P. 0. Princep 27 68 00
is at
Novelty
Chambers,
Grant
Road,
89 66 28
Square, 22 36 71