Flow Chart Template Monitoring
Flow Chart Template Monitoring
Flow Chart Template Monitoring
Issue
Date:
Doc. Code:
Revision
No.:
Page No.:
00
1 of 4
1.0 Purpose
Responsible
Details
START
Receiving of Project
Status Reports
Administrative
Staff
The
Administrative
Staff
receives the Project Status
Reports with the attached
routing slip of all on-going
projects from its respective
Project Engineers / Regional
Offices / District Offices,
record the documents in the
logbook and forward it to the
Engineer-in-charge
for
Monitoring, copy furnished
to
Project
Manager
Engineer II /
Engineer III
A
Department of Public Works and Highways
Unified Project Management Office
Bridges Management Cluster (UPMO BMC)
Issue
Date:
Doc. Code:
Revision
No.:
Page No.:
Responsible
00
2 of 4
Details
A
Engineer II /
Engineer III /
Project Manager /
Project Director
Engineer
II /
Engineer III
The
information,
i.e.
Percentage
of
Accomplishments,
Ongoing
Activities,
Time
Variation Requests among
others, stipulated in each
Project Status Reports are
reviewed by the Engineer
II/ Engineer III.
Engineer II /
Engineer III /
Project
Manager/
Project Director
Issue
Date:
Doc. Code:
Revision
No.:
Page No.:
00
3 of 4
B
Process Flow
Responsible
Details
Engineer II /
Engineer III /
Project Manager /
Project Director
The
Engineer
II
/
Engineer III prepares the
Monthly Progress Report
as the summary of the
status of all on-going
bridges including the ongoing activities, issues
and concerns of each
projects
and
project
accomplishments.
The
Monthly Status Report is
then
reviewed
and
initialed by the Project
Manager assigned to the
Project and is further
approved by the Project
Director.
Administrative
Staff
Issue
Date:
Doc. Code:
Revision
No.:
Page No.:
00
4 of 4
4.0 References
DPWH Quality Manual
DO 134, Series 2004
Report
DO 183, Series 1996
DO 102, Series 1988
DO 142, Series 1989
DO 202, Series 1993
Contract
5.0 Records
Monthly Progress Report
Electronic Files/Copies of Individual Project Status Report
Prepared by:
Reviewed by:
KRISTOFFER T. CRUZ
Engineer III
Approved by: