API Closed Book (2011) by SC Kim
API Closed Book (2011) by SC Kim
API Closed Book (2011) by SC Kim
1. 000 .
Solution: API 570-8.1.4.1
Temporary repairs should be removed and replaced with a suitable permanent repair at the next available
Maintenance opportunity. Temporary repairs may remain in place for a longer period of time only if approved
and documented by the piping engineer.
3. 000 .
Where
API Closed Book (2011) by SC Kim
5. PQR ?
Solution: ASME SEC. 9-QW-200.2
(a) Procedure Qualification Record (PQR). The PQR is a record of variables recorded during the welding of the
test coupons. It also contains the test results of the tested specimens. Recorded variables normally fall within a
small range of the actual variables that will be used in production welding.
(b) Contents of the PQR. The completed PQR shall document all essential and, when required, supplementary
essential variables of QW-250 through QW280 for each welding process used during the welding of the test
coupon.
6. When the MAWP is recalculated for the continued use of a piping system, what wall thickness is used?
Answer: c) actual thickness minus twice the estimated corrosion loss before the next inspection
Solution: API 570-7.2
7. Thickness measurement location (TML) readings on a piping system indicate that the corrosion rate has
increase. The inspectors most appropriate response is to:
Answer: a) recalculate the inspection interval of the system.
Solution: API 570-5.6.2
9. PMI ?
Solution: API 578-4.3
If the owner/user elects to prioritize piping systems for the material verification program or needs to
determine whether PMI testing is needed at all, the owner/user should consider the following.
a) Likelihood of a material mix-up during previous project and maintenance activities. A key factor is the
effectiveness of the material verification program at the time of these activities.
b) Consequences of a failure. Some factors to be considered include flammability, fire potential, toxicity,
proximity to other equipment or community, temperature, pressure, mode of failure, and size of release.
c) Reason for alloy specification (i.e. corrosion resistance or product purity).
d) Historical data relating to inadvertent material substitutions. This may be related to previous experience with
material nonconformities in the process unit or within the operating plant.
10. ?
Solution: API 570-8.2.7
Pressure tests with longer hold times and observations of pressure gauges can be substituted for
insulation stripping when the risks associated with leak under the insulation are acceptable.
API Closed Book (2011) by SC Kim
11. A piping system was installed in February 1989 with initial thickness of 0.29 thickness measured 0.20 in
August 1999 and 0.17 in February 2001. The piping retirement thickness is 0.13. The remaining life of the
component is:
Answer: b) 2 years
Solution: API 570-7.1.1
ST= 0.20-0.17/1.5= 0.02
LT= 0.29-0.17/12= 0.01
RL= 0.17-0.13/0.02= 2 years
14. ?
API Closed Book (2011) by SC Kim
15. 000 .
Solution: API 570-8.2.2
The repair organization shall use welders and welding procedures qualified in accordance with ASME B31.3 or
the code to which the piping was built.
17. When a piping inspector notices deformation of a pressure vessel wall in the vicinity of a pipe attachment,
which of the following is the most appropriate action to take?
Answer: c) check for piping misalignment
Solution: API 574-10.1.3.b)
Piping should be inspected for misalignment, which can be indicated by the following conditions:
a) piping dislodged from one or more supports so that its weight is not being properly distributed on the
remaining hangers or saddles;
b) the deformation of a vessel or tank wall in the vicinity of a piping attachment;
c) piping supports forced out of plumb by expansion or contraction of the piping;
d) excessive replacement or repair of bearings, impellers, and turbine wheels of centrifugal pumps,
compressors, and turbine seals to which piping is connected;
e) the shifting of a base plate, breaking of a foundation, or shearing of foundation bolts of mechanical
equipment to which piping is attached;
f) cracks in connecting flanges or the cases of pumps or turbines to which piping is attached;
g) expansion joints that are excessively deformed or not performing properly.
18. ?
Solution: ASME SEC. 5-T-283-1
Radiography shall be performed with a technique of sufficient sensitivity to display the designated hole-type
IQI image and the essential hole, or the essential wire of a wire-type IQI. The radiographs shall also display the
IQI identifying numbers and letters.
API Closed Book (2011) by SC Kim
19. 11 ?
Solution: API 570-7.1.1
ST= 0.20-0.17/1.5= 0.02
LT= 0.29-0.17/12= 0.01
RL= 0.17-trequired/0.02= 2 years
20. A piping systems carrying a flammable petroleum process can be categorized as a Class 3 system if it
contains which of the following?
Answer: a) A finished product being pumped at a remote booster station.
Solution: API 570-6.3.4.4
Services that are flammable but do not significantly vaporize when they leak and are not located in high-
activity areas are in Class 3. Services that are potentially harmful to human tissue but are located in remote
areas may be included in this class.
24. CML ?
Solution: API 570-5.7.1
When ultrasonic measurements are taken above 150 F (65 C), instruments, couplants, and procedures should
be used that will result in accurate measurements at the higher temperatures. If the procedure does not
compensate for higher temperatures, measurements should be adjusted by the appropriate temperature
correction factor.
25. The owner of a newly installed piping system does not have any data on piping systems in the same or a
similar service. After the system has been put into service, when must the initial thickness measurements be
made?
Answer: b) after no more than three months of service
Solution: API 570-7.1.2 c)
27. Which of the following materials requires hydrostatic testing with potable water or stem condensate?
Answer: c) 300 series stainless steel
Solution: API 570-5.8.1
28. An imperfection of a type or magnitude exceeding the acceptable criteria is known as an:
Answer: b) defect
Solution:
1) Indication: a response or evidence resulting from the application of a non-destructive evaluation technique.
2) Defect: An imperfection of a type or magnitude exceeding the acceptable criteria.
3) Discontinuity: an interruption of the typical structure of material, such as a lack of homogeneity in its
mechanical, metallurgical or physical characteristics. A discontinuity is not necessarily a defect.
4) Imperfections: flaw or other discontinuities noted during inspection that may be subject to acceptance
criteria during an engineering and inspection analysis.
29. During radiographic examination of a weld, the wire image quality indicator shall be placed:
Answer: c) on the weld so that the length of the wire is perpendicular to the weld
Solution: ASME SEC. 5-T-277.1 [c]
30. ?
Solution: API 570-8.2.3.3
Local PWHT may be substituted for 360 banding on local repairs on all materials, provided the following
precautions and requirements are applied.
a) The application is reviewed, and a procedure is developed by the piping engineer.
API Closed Book (2011) by SC Kim
b) In evaluating the suitability of a procedure, consideration shall be given to applicable factors, such as base
metal thickness, thermal gradients, material properties, changes resulting from PWHT, the need for full-
penetration welds, and surface and volumetric examinations after PWHT. Additionally, the overall and local
strains and distortions resulting from the heating of a local restrained area of the piping wall shall be
considered in developing and evaluating PWHT procedures.
c) A preheat of 300 F (150 C), or higher as specified by specific welding procedures, is maintained while
welding.
d) The required PWHT temperature shall be maintained for a distance of not less than two times the base
metal thickness measured from the weld. The PWHT temperature shall be monitored by a suitable number of
thermocouples (a minimum of two) based on the size and shape of the area being heat treated.
e) Controlled heat also shall be applied to any branch connection or other attachment within the PWHT area.
f) The PWHT is performed for code compliance and not for environmental cracking resistance.
31. Undercut?
Solution: API 577-3.1.70
A groove melted into the base metal adjacent to the weld toe or weld root and left unfilled by weld metal.
32. New connections installed on existing piping systems shall always be:
Answer: c) designed per the applicable code
Solution: API 570-8.2.4
35. ?
Solution: API 570-9.3.6
The external condition of buried piping that is not cathodically protected should be determined by either
pigging, which can measure wall thickness, or by excavating according to the frequency given in Table 5.
Significant external corrosion detected by pigging or by other means may require excavation and evaluation
even if the piping is cathodically protected. Piping inspected periodically by excavation shall be inspected in
lengths of 6 ft to 8 ft (2.0 m to 2.5 m) at one or more locations judged to be most susceptible to corrosion.
API Closed Book (2011) by SC Kim
Excavated piping should be inspected full circumference for the type and extent of corrosion (pitting or
general) and the condition of the coating.
36. ?
Solution: API 570-5.5.8
thermography to check for hot spots in refractory lined systems
37. ?
Solution: API 570-5.12
Flanged joints that have been clamped and pumped with sealant should be checked for leakage at the bolts.
Fasteners subjected to such leakage may corrode or crack (e.g. caustic cracking). If re-pumping is
contemplated, affected fasteners should be renewed first. Flange fasteners should be examined visually for
corrosion and thread engagement. Fasteners should be fully engaged. Any fastener failing to do so is
considered acceptably engaged if the lack of complete engagement is not more than one thread.
38. / ?
Solution: API 570-5.9
The owner/user shall assess the need for and extent of application of a material verification program
consistent with API 578 addressing inadvertent material substitution in existing alloy piping systems.
39. Measurements from an inspection of a Class 3 pipe reveal an actual metal thickness of 0.35. The
calculated minimum thickness is 0.25. With a corrosion rate of 2.4mils per year, when should the next
thickness measurement inspection be scheduled?
Answer: c) 10 years
Solution:
1) RL= 0.35-0.25/0.0024= 41.6 year/2= 20.8 years
2) Class 3= 10 years
40. welder ?
Solution: ASME SEC. 9-QW-461.9
Groove: 1G, 2G, 5G, 6G, 2G & 5G, Special Positions
Fillet: 1F, 2F, 2FR, 4F, 5F, Special Positions
43. ?
Solution: API 570-9.3.7
An alternative or supplement to inspection is leak testing with liquid at a pressure at least 10 % greater than
maximum operating pressure at intervals one-half the length of those shown in Table 5 for piping not
cathodically protected and at the same intervals as shown in Table 5 for cathodically protected piping.
48. ?
Solution: API 570-6.2.2
If the service conditions of the piping system are changed, i.e. will exceed the current operating envelope (e.g.
process contents, maximum operating pressure, and the maximum and minimum operating temperature),
inspection intervals shall be established for the new service conditions.
If both the ownership and the location of the piping are changed, the piping shall be inspected before it is
reused. Also, the allowable service conditions and the inspection interval shall be established for the new
service.
49. When may temporary repairs be allowed to remain in service beyond the next maintenance opportunity?
Answer: a) when approved by a piping engineer and properly documented
Solution: API 570 8.1.4.1
API Closed Book (2011) by SC Kim
52. ASNT Recommended Practice SNT-TC-1A is which of the following type of document?
Answer: b) a document covering NDE personnel qualifications
Solution: ASME SEC. 5-T-120
54. When inaccessibility prevents placing the image quality indicator(s) (IQI) manually on the source side of a
weld being radiographe, what identification is placed on the radiograph to indicate that film side IQI(s) were
used.
Answer: c) F
Solution: ASME SEC. 5-T-277.1 [b]
55. Vertical supports constructed of pipe components should be checked to determine if they are filled with
water, because water inside a support may cause:
Answer: a) internal corrosion of the support
Solution: API 570-5.5.4
Vertical support dummy legs also shall be checked to confirm that they have not filled with water that is
causing external corrosion of the pressure piping or internal corrosion of the support leg.
56. Evaluation of data from the inspection of an injection point yields a remaining life of 16 years. When
should the next set of thickness measurements be performed?
Answer: a) three years
Solution: API 570-Table 2, API 570-6.3.3
API Closed Book (2011) by SC Kim
57. ?
Solution: API 570-7.8
Results of external piping system inspections shall be documented. A narrative or checklist format is
recommended when documenting inspection results. The location of CUI inspections, either by insulation
removal or NDE, should be identified. The location may be identified by establishing a CML on the appropriate
inspection ISO or with marked-up construction ISOs and narrative reports.
58. ?
Solution: API 570-6.6.3
Threaded connections associated with machinery and subject to fatigue damage should be periodically
assessed and considered for possible renewal with a thicker wall or upgrading to welded components.
The schedule for such renewal will depend on several issues,
59. Environmental cracking noted during an in-service examination of welds should be assessed by the:
Answer: a) piping engineer
Solution: API 570-5.11
Environmental cracking shall be assessed by an engineer in accordance with API 579-1/ASME
FFS-1 and/or corrosion specialist.
60. What is the cause for rejection of the B image on a film due to excessive backscatter?
Answer: c) A light image
Solution: ASME SEC.5-T-284
If a light image of the B, as described in T-223, appears on a darker background of the radiograph,
protection from backscatter is insufficient and the radiograph shall be considered unacceptable.
A dark image of the B on a lighter background is not cause for rejection.
61. Which inspection method is most appropriate for detecting external chloride stress corrosion cracking is
austenitic stainless steel piping systems?
Answer: b) Liquid penetrant
Solution: API 574-7.4.4
62. ?
Solution: API 570-5.7.1
Factors that can contribute to reduced accuracy of ultrasonic measurements include the following:
a) improper instrument calibration;
b) external coatings or scale;
c) significant surface roughness;
d) rocking of the probe (on the curved surface);
e) subsurface material flaws, such as laminations;
f) temperature effects [at temperatures above 150 F (65 C)];
g) improper resolution on the detector screens;
API Closed Book (2011) by SC Kim
h) thicknesses of less than 1/8 in. (3.2 mm) for typical digital thickness gauges;
i) improper coupling of probe to the surface (too much or too little couplant).
65. In-service UT measurements indicate thinning in the HAZ of an elbow-to-weld neck flange on a 30 vapor
line. What is the best method to determine the extent of deterioration during the next scheduled downtime?
Answer: a) internal inspection
Solution: API 570-5.5.1
Internal visual inspections are not normally performed on piping. When possible and practical, internal visual
inspections may be scheduled for systems such as large-diameter transfer lines, ducts, catalyst lines, or other
large diameter piping systems.
66. An inspection reveals that the pipe shoes on a line have moved off the primary supports and are hanging
on the beams, preventing the line from returning to its cold position. What is the most appropriate action for
the inspector to take?
Answer: a) consult a piping engineer to evaluate the stress on the pipe.
Solution: API 570-7.5
67. ?
Answer: SNT-TC-1A
Solution: ASME SEC. 5-T-120
(1) SNT-TC-1A, Personnel Qualification and Certification in Nondestructive Testing
(2) ANSI/ASNT CP-189, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel
68. 000 .
Solution: API 570-8.2.6
Acceptance of a welded repair or alteration shall include NDE in accordance with the applicable code and the
owner/users specification, unless otherwise specified in API 570.
69. What is the threshold temperature above which special ultrasonic testing instruments and procedures are
recommended?
Answer: b) 150
Solution: API 570-5.7.1 f)
72. RT ?
Solution: API 570-5.7.1
Radiographic profile techniques are preferred for pipe diameters of NPS 1 and smaller. Ultrasonic
thickness measurements taken on small bore pipe smaller (NPS 2 and below) may require specialized
equipment (e.g. miniature transducers and/or curved shoes as well as diameter specific calibration blocks).
Radiographic profile techniques may be used for locating areas to be measured, particularly in insulated
systems or where non-uniform or localized corrosion is suspected. Where practical, UT can then be used to
obtain the actual thickness of the areas to be recorded. Following ultrasonic readings at CMLs, proper repair of
insulation and insulation weather coating is recommended to reduce the potential for CUI. Radiographic profile
techniques, which do not require removing insulation, may be considered as an alternative
73. Surface conditions of buried pipeline paths should be visually surveyed approximately every:
Answer: a) 6 months
Solution: API 5709.3.1
74. What is the most common form of corrosion under insulation on carbon steel pipe?
Answer: b) localized corrosion
Solution: API 574 7.4.4
The two forms of CUI are localized corrosion of carbon steel and chloride SCC of austenitic stainless steels.
e) carbon steel piping systems, including ones insulated for personnel protection, operating between 10 F (
12 C) and 350 F (175 C); CUI is particularly aggressive where operating temperatures cause frequent or
continuous condensation and re-evaporation of atmospheric moisture;
h) austenitic stainless steel piping systems operating between 120 F (60 C) and 400 F (205 C) (susceptible
to chloride SCC);
76. / ?
Solution: API 570 6.3.3
The owner/user or the inspector shall establish inspection intervals for thickness measurements and external
visual inspections and, where applicable, for internal and supplemental inspections.
79. ?
Answer: Arc Length
Solution: API 577-3.1.5
The distance from the tip of the welding electrode to the adjacent surface of the weld pool.
80. 1 RBI / ?
Answer: 5 years (thickness measurement, visual inspection)
Solution: API 570-6.3.2
These RBI assessments shall be reviewed and approved by a piping engineer and authorized piping
inspector at intervals not to exceed the respective limits in Table 2, or more often if warranted by process,
equipment, or consequence changes.
82. RBI ?
Solution: API 570-6.3.3
If RBI is not being used, the interval between piping inspections shall be established and maintained using the
following criteria:
a) corrosion rate and remaining life calculations;
b) piping service classification (see 6.3.4);
c) applicable jurisdictional requirements;
d) judgment of the inspector, the piping engineer, the piping engineer supervisor, or a materials specialist,
based on operating conditions, previous inspection history, current inspection results, and conditions that may
warrant supplemental inspections covered in 5.5.6.
API Closed Book (2011) by SC Kim
The owner/user or the inspector shall establish inspection intervals for thickness measurements and external
visual inspections and, where applicable, for internal and supplemental inspections.
85. ?
Solution: API 574-4.2.16.5
4.2.16.5 Appearance or Morphology of Damage
a) The signature mark of a fatigue failure is a clam shell type fingerprint that has concentric rings
called beach marks emanating from the crack initiation site (Figure 4-50 and Figure 4-51). This
signature pattern results from the waves of crack propagation that occur during cycles above the
threshold loading.
87.
88.
Where
D is the inside diameter in inches (millimeters);
t is the minimum required thickness of the fillet-welded patch in inches (millimeters).
For minor leaks, properly designed enclosures may be welded over the leak while the piping system is in-
service, provided the inspector is satisfied that adequate thickness remains in the vicinity of the weld and the
piping component can withstand welding without the likelihood of further material damage, such as from
caustic service. Temporary repairs should be removed and replaced with a suitable permanent repair at the
next available maintenance opportunity. Temporary repairs may remain in place for a longer period of time
only if approved and documented by the piping engineer.
92. The owner of a newly installed piping system does not have any data on piping systems in the same or
similar service. After the system has been put into service, when must the initial thickness measurements be
made?
Answer: b) after no more than 3 months of service
Solution: API 570-7.1.2 c)
93. ?
Solution: API 570-5.9
This material verification program should be consistent with API 578. Using risk assessment procedures,
the owner/user can make this assessment by 100 % verification, A material verification program consistent with
API 578 may include procedures for prioritization and risk ranking of piping circuits.
API Closed Book (2011) by SC Kim
95. ?
97. MT YOKE ?
Solution: API 577-9.4.1
The yoke is placed parallel on the weld to detect discontinuities transverse to the weld.