Activity Progress
Activity Progress
Activity Progress
2017)
PLUMBING
1 BELOW GROUND PIPING WORKS 10% 40% %20
7 SANITARYWARES FIXING 0% 4% %0
9 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 2% 4% 2%
3 FHC installation 0% 0% 0%
4 Sprinkler Installation 0% %4 0%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 0% %4 %0
4 GRILL/DIFUSER INSTALLATION 0% %4 %0
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% %4 %0
ELECTRICAL
1 Slab Conduiting %20 %20 %20
4 Conduit piping 5% 5% 5%
PLUMBING
1 BELOW GROUND PIPING WORKS %60 60% 60%
2 BLOCKWALL CHASING & MARKING 10% 10% %10
3 HIGHER LEVEL DRAINAGE PIPEWORKS 10% 10% 10%
4 CONCEALED DRAINAGE PIPE WORKS 10% 10% %10
5 H/L WATER SUPPLY PIPE WORKS 10% 10% %10
6 CONCEALED WATER SUPPLY PIPEWORKS 10% 10% %10
7 SANITARYWARES FIXING 0% 4% %0
8 PUMPROOM & WATER TANK AREA S.N %10 S.N
9 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 8% 8% 8%
2 Below Ground HDPE piping 70% 70% 70%
3 FHC installation 0% 0% 0%
4 Sprinkler Installation 0% %4 0%
5 Fire Pump Installation & Testing 0% 0% 0%
6 Conduting works for Fire Alarm systems 60% 60% 60%
7 Cabling works for Fire Alarm systems 20% 20% 20%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 10% 10% 10%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% 0% 0%
ELECTRICAL
1 Slab Conduiting %50 %50 %50
5 Distribution Board & back boxes (I.G) Fixing 10% 10% %10
PLUMBING
1 BELOW GROUND PIPING WORKS %30 80% 70%
2 BLOCKWALL CHASING & MARKING 2% 6% %4
3 HIGHER LEVEL DRAINAGE PIPEWORKS 4% 10% 10%
4 CONCEALED DRAINAGE PIPE WORKS 2% 6% %4
5 H/L WATER SUPPLY PIPE WORKS 0% 4% %0
6 CONCEALED WATER SUPPLY PIPEWORKS 0% 4% %0
7 SANITARYWARES FIXING 0% 4% %0
8 PUMPROOM & WATER TANK AREA S.N %2 S.N
9 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 8% 8% 8%
2 Below Ground HDPE piping 70% 70% 70%
3 FHC installation 0% 0% 0%
4 Sprinkler Installation 0% %4 0%
5 Fire Pump Installation & Testing 0% 0% 0%
6 Conduting works for Fire Alarm systems 60% 60% 60%
7 Cabling works for Fire Alarm systems 20% 20% 20%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 10% %15 %10
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 10% %15 %10
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 10% %4 %10
ELECTRICAL
1 Slab Conduiting %40 %40 %40
2 Marking on Blockwall %40 %40 %40
3 Cutting & Chasing works 20% 20% 20%
4 Conduit piping 18% 18% 18%
5 Distribution Board & back boxes (I.G) Fixing 15% 15% %15
PLUMBING
1 BELOW GROUND PIPING WORKS %60 100% 100%
2 BLOCKWALL CHASING & MARKING 15% 15% 15%
3 HIGHER LEVEL DRAINAGE PIPEWORKS 30% 30% 30%
4 CONCEALED DRAINAGE PIPEWORKS 20% 20% 20%
5 H/L WATER SUPPLY PIPE WORKS 20% 20% 20%
6 CONCEALED WATER SUPPLY PIPEWORKS 20% 20% 20%
7 SANITARYWARES FIXING 0% 4% 0%
8 PUMPROOM & WATER TANK AREA S.N %2 S.N
9 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 20% 20% 20%
2 Below Ground HDPE piping 100% 100% 100%
3 FHC installation 0% 0% 0%
4 Sprinkler Installation 0% %4 0%
5 Fire Pump Installation & Testing 0% 0% 0%
6 Conduting works for Fire Alarm systems 70% 70% 70%
7 Cabling works for Fire Alarm systems 30% 30% 30%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 25% 25% 25%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 25% 25% 25%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 20% 4% 20%
ELECTRICAL
1 Slab Conduiting %50 %50 %50
2 Marking on Blockwall %50 %50 %50
3 Cutting & Chasing works %50 %50 %50
4 Conduit piping 30% 30% 30%
5 Distribution Board & back boxes (I.G) Fixing 25% 25% 25%
PLUMBING
1 BELOW GROUND PIPING WORKS %100 100% 100%
2 BLOCKWALL CHASING & MARKING 30% 30% 30%
3 HIGHER LEVEL DRAINAGE PIPEWORKS 15% 15% 15%
4 CONCEALED DRAINAGE PIPE WORKS 10% 10% 10%
5 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
6 CONCEALED WATER SUPPLY PIPEWORKS 10% 10% 10%
7 SANITARYWARES FIXING 0% 4% 0%
8 PUMPROOM & WATER TANK AREA S.N %2 S.N
9 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 10% 10% 10%
2 Below Ground HDPE piping 100% 100% 100%
3 FHC installation 0% 0% 0%
4 Sprinkler Installation 0% %4 0%
5 Fire Pump Installation & Testing 0% 0% 0%
6 Conduting works for Fire Alarm systems 70% 70% 70%
7 Cabling works for Fire Alarm systems 25% 25% 25%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 15% 15% 15%
CHILLED WATER PIPES INSTALLTION,INSULATION &
2
TESTING
15% 15% 15%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %50 %50 %50
2 Marking on Blockwall %40 %40 %50
3 Cutting & Chasing works %40 %40 %40
4 Conduit piping 25% 25% 25%
5 Distribution Board & back boxes (I.G) Fixing 20% 20% 20%
PLUMBING
1 BLOCKWALL CHASING & MARKING 40% 40% 40%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 20% 20% 20%
3 CONCEALED DRAINAGE PIPE WORKS 15% 15% 15%
4 H/L WATER SUPPLY PIPE WORKS 10% 4% 10%
5 CONCEALED WATER SUPPLY PIPEWORKS 15% 15% 15%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 15% 15% 15%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 80% 80% 80%
6 Cabling works for Fire Alarm systems 30% 30% 30%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 20% 20% 20%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 20% 20% 20%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %60 %60 %60
2 Marking on Blockwall %50 %50 %50
3 Cutting & Chasing works %50 %50 %50
4 Conduit piping 30% 30% 30%
5 Distribution Board & back boxes (I.G) Fixing 25% 25% 25%
PLUMBING
1 BLOCKWALL CHASING & MARKING 35% 35% 35%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 18% 18% 18%
3 CONCEALED DRAINAGE PIPE WORKS 12% 12% 12%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 12% 12% 12%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 12% 12% 12%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 75% 75% 75%
6 Cabling works for Fire Alarm systems 28% 28% 28%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 18% 18% 18%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 18% 18% 18%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %60 %60 %60
2 Marking on Blockwall %50 %50 %50
3 Cutting & Chasing works %50 %50 %50
4 Conduit piping 30% 30% 30%
5 Distribution Board & back boxes (I.G) Fixing 25% 25% 25%
PLUMBING
1 BLOCKWALL CHASING & MARKING 40% 40% 40%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 25% 25% 25%
3 CONCEALED DRAINAGE PIPE WORKS 15% 15% 15%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 15% 15% 15%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 15% 15% 15%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 85% 85% 85%
6 Cabling works for Fire Alarm systems 35% 35% 35%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 25% 25% 25%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 25% 25% 25%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %70 %70 %70
2 Marking on Blockwall %60 %60 %60
3 Cutting & Chasing works %60 %60 %60
4 Conduit piping 40% 40% 40%
5 Distribution Board & back boxes (I.G) Fixing 30% 30% 30%
PLUMBING
1 BLOCKWALL CHASING & MARKING 38% 38% 38%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 22% 22% 22%
3 CONCEALED DRAINAGE PIPE WORKS 15% 15% 15%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 15% 15% 15%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 15% 15% 15%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 80% 80% 80%
6 Cabling works for Fire Alarm systems 32% 32% 32%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 22% 22% 22%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 22% 22% 22%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %70 %70 %70
2 Marking on Blockwall %55 %55 %55
3 Cutting & Chasing works %55 %55 %55
4 Conduit piping 35% 35% 35%
5 Distribution Board & back boxes (I.G) Fixing 30% 30% 30%
PLUMBING
1 BLOCKWALL CHASING & MARKING 50% 50% 50%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 30% 30% 30%
3 CONCEALED DRAINAGE PIPE WORKS 20% 20% 20%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 20% 20% 20%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 20% 20% 20%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 40% 40% 40%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 30% 30% 30%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 30% 30% 30%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %80 %80 %80
2 Marking on Blockwall %65 %65 %65
3 Cutting & Chasing works %65 %65 %65
4 Conduit piping 50% 50% 50%
5 Distribution Board & back boxes (I.G) Fixing 35% 35% 35%
PLUMBING
1 BLOCKWALL CHASING & MARKING 42% 42% 42%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 30% 30% 30%
3 CONCEALED DRAINAGE PIPE WORKS 20% 20% 20%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 20% 20% 20%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 20% 20% 20%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 85% 85% 85%
6 Cabling works for Fire Alarm systems 36% 36% 36%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 28% 28% 28%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 28% 28% 28%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %75 %75 %75
2 Marking on Blockwall %60 %60 %60
3 Cutting & Chasing works %60 %60 %60
4 Conduit piping 45% 45% 45%
5 Distribution Board & back boxes (I.G) Fixing 35% 35% 35%
PLUMBING
1 BLOCKWALL CHASING & MARKING 60% 60% 60%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 40% 40% 40%
3 CONCEALED DRAINAGE PIPE WORKS 30% 30% 30%
4 H/L WATER SUPPLY PIPE WORKS 5% 5% 5%
5 CONCEALED WATER SUPPLY PIPEWORKS 30% 30% 30%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 30% 30% 30%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 50% 50% 50%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 40% 40% 40%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 40% 40% 40%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %90 %90 %90
2 Marking on Blockwall %75 %75 %75
3 Cutting & Chasing works %75 %75 %75
4 Conduit piping 60% 60% 60%
5 Distribution Board & back boxes (I.G) Fixing 45% 45% 45%
PLUMBING
1 BLOCKWALL CHASING & MARKING 52% 52% 52%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 35% 35% 35%
3 CONCEALED DRAINAGE PIPE WORKS 30% 30% 30%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 30% 30% 30%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 25% 25% 25%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 45% 45% 45%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 35% 35% 35%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 35% 35% 35%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %80 %80 %80
2 Marking on Blockwall %70 %70 %70
3 Cutting & Chasing works %70 %70 %70
4 Conduit piping 55% 55% 55%
5 Distribution Board & back boxes (I.G) Fixing 40% 40% 40%
PLUMBING
1 BLOCKWALL CHASING & MARKING 70% 70% 70%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 50% 50% 50%
3 CONCEALED DRAINAGE PIPE WORKS 40% 40% 40%
4 H/L WATER SUPPLY PIPE WORKS 5% 5% 5%
5 CONCEALED WATER SUPPLY PIPEWORKS 35% 35% 35%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 40% 40% 40%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 60% 60% 60%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 50% 50% 50%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 50% 50% 50%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %90 %90 %90
2 Marking on Blockwall %75 %75 %75
3 Cutting & Chasing works %75 %75 %75
4 Conduit piping 70% 70% 70%
5 Distribution Board & back boxes (I.G) Fixing 60% 60% 60%
PLUMBING
1 BLOCKWALL CHASING & MARKING 60% 60% 60%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 45% 45% 45%
3 CONCEALED DRAINAGE PIPE WORKS 40% 40% 40%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 35% 35% 35%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 35% 35% 35%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 50% 50% 50%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 40% 40% 40%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 40% 40% 40%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %85 %85 %85
2 Marking on Blockwall %70 %70 %70
3 Cutting & Chasing works %70 %70 %70
4 Conduit piping 65% 65% 65%
5 Distribution Board & back boxes (I.G) Fixing 50% 50% 50%
Activities Planned for the Week (20.04.17 to 26.04.17)
PLUMBING
1 BLOCKWALL CHASING & MARKING 75% 75% 75%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 55% 55% 55%
3 CONCEALED DRAINAGE PIPE WORKS 45% 45% 45%
4 H/L WATER SUPPLY PIPE WORKS 10% 10% 10%
5 CONCEALED WATER SUPPLY PIPEWORKS 40% 40% 40%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 45% 45% 45%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 65% 65% 65%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 55% 55% 55%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 55% 55% 55%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %90 %90 %90
2 Marking on Blockwall %80 %80 %80
3 Cutting & Chasing works %80 %80 %80
4 Conduit piping %80 %80 %80
5 Distribution Board & back boxes (I.G) Fixing 70% 70% 70%
PLUMBING
1 BLOCKWALL CHASING & MARKING 65% 65% 65%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 50% 50% 50%
3 CONCEALED DRAINAGE PIPE WORKS 45% 45% 45%
4 H/L WATER SUPPLY PIPE WORKS 0% 4% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 40% 40% 40%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 40% 40% 40%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 60% 60% 60%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 50% 50% 50%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 50% 50% 50%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %85 %85 %85
2 Marking on Blockwall %75 %75 %75
3 Cutting & Chasing works %75 %75 %75
4 Conduit piping 70% 70% 70%
5 Distribution Board & back boxes (I.G) Fixing 55% 55% 55%
PLUMBING
1 BLOCKWALL CHASING & MARKING 75% 75% 75%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 55% 55% 55%
3 CONCEALED DRAINAGE PIPE WORKS 50% 50% 50%
4 H/L WATER SUPPLY PIPE WORKS 10% 10% 10%
5 CONCEALED WATER SUPPLY PIPEWORKS 45% 45% 45%
6 SANITARYWARES FIXING 0% 4% 0%
7 PUMPROOM & WATER TANK AREA S.N %2 S.N
8 ROOF @WORKS 0% 0% %0
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 45% 45% 45%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% %4 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 65% 65% 65%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 55% 55% 55%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 55% 55% 55%
3 FLEXBILE DUCT INSTALLATION 0% 4% 0%
4 GRILL/DIFUSER INSTALLATION 0% 4% 0%
5 FCU INSTALLATIONS 0% %0 %0
6 THERMOSTAT FIXING 0% 4% 0%
ELECTRICAL
1 Slab Conduiting %90 %90 %90
2 Marking on Blockwall %80 %80 %80
3 Cutting & Chasing works %80 %80 %80
4 Conduit piping %80 %80 %80
5 Distribution Board & back boxes (I.G) Fixing 70% 70% 70%
PLUMBING
1 BLOCKWALL CHASING & MARKING 70% 70% 70%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 55% 55% 55%
3 CONCEALED DRAINAGE PIPE WORKS 50% 50% 50%
4 H/L WATER SUPPLY PIPE WORKS 0% 0% 0%
5 CONCEALED WATER SUPPLY PIPEWORKS 45% 45% 45%
6 SANITARYWARES FIXING 0% 0% 0%
7 PUMPROOM & WATER TANK AREA S.N S.N S.N
8 ROOF @WORKS 0% 0% 0%
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 50% 50% 50%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% 0% 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 65% 65% 65%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 60% 60% 60%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 60% 60% 60%
3 FLEXBILE DUCT INSTALLATION 0% 0% 0%
4 GRILL/DIFUSER INSTALLATION 0% 0% 0%
5 FCU INSTALLATIONS 0% 0% 0%
6 THERMOSTAT FIXING 0% 0% 0%
ELECTRICAL
1 Slab Conduiting %85 %85 %85
2 Marking on Blockwall %85 %85 %85
3 Cutting & Chasing works %80 %80 %80
4 Conduit piping 75% 75% 75%
5 Distribution Board & back boxes (I.G) Fixing 65% 65% 65%
PLUMBING
1 BLOCKWALL CHASING & MARKING 75% 75% 75%
2 HIGHER LEVEL DRAINAGE PIPEWORKS 60% 60% 60%
3 CONCEALED DRAINAGE PIPE WORKS 55% 55% 55%
4 H/L WATER SUPPLY PIPE WORKS 15% 15% 15%
5 CONCEALED WATER SUPPLY PIPEWORKS 50% 50% 50%
6 SANITARYWARES FIXING 0% 0% 0%
7 PUMPROOM & WATER TANK AREA S.N S.N S.N
8 ROOF @WORKS 0% 0% 0%
FIRE FIGHTING
1 Sprinkler /Hose Reel G.I piping 60% 60% 60%
2 FHC installation 0% 0% 0%
3 Sprinkler Installation 0% 0% 0%
4 Fire Pump Installation & Testing 0% 0% 0%
5 Conduting works for Fire Alarm systems 90% 90% 90%
6 Cabling works for Fire Alarm systems 75% 75% 75%
HVAC
1 DUCT WORK INSTALLATION & INSUALTION 65% 65% 65%
2 CHILLED WATER PIPES INSTALLTION,INSULATION & TESTING 65% 65% 65%
3 FLEXBILE DUCT INSTALLATION 0% 0% 0%
4 GRILL/DIFUSER INSTALLATION 0% 0% 0%
5 FCU INSTALLATIONS 0% 0% 0%
6 THERMOSTAT FIXING 0% 0% 0%
ELECTRICAL
1 Slab Conduiting %90 %90 %90
2 Marking on Blockwall %90 %80 %80
3 Cutting & Chasing works %85 %80 %80
4 Conduit piping %80 %80 %80
5 Distribution Board & back boxes (I.G) Fixing 70% 70% 70%